HANDBOOK of LNG Baltic Sea Ports PDF
HANDBOOK of LNG Baltic Sea Ports PDF
HANDBOOK of LNG Baltic Sea Ports PDF
The Handbook is part of the project LNG in Baltic Sea Ports. The purpose of the
handbook is to provide advice and guidance for other ports planning to establish LNG
terminals or other types of supply for the marine market.
The Handbook is based on the experiences gained from the participating ports in the
project, as well as other ports in the area with experience from establishing LNG
terminals and LNG as ship fuel.
2 (60)
3 (60)
Type
Capacity
Operator
Status
Comment
Fredriksstad/
ra, Norway
Closed
6 400
Skangass
In operation
Nynshamn,
Sweden
Closed
20 000
AGA
In operation
Redistribution
pipeline
by
truck
and
Type
Capacity
3
(m )
Operator
Comment
Lysekil/
Closed
30 000
Skangass
Brofjorden,
4 (60)
Sweden
winoujcie,
Poland
Open
320 000
Polskie
LNG
Klaipeda,
Lithuania
TBD
170 000
Klaipedas
Nafta
Regional
terminal, Gulf
of Finland
TBD
300 000
TBD
Tallin Muuga,
Estonia
Open
TBD
Vopak
/Elering
Rauma,
Finland
TBD
10 000
AGA
Pori, Finland
TBD
30 000
Gasum/
Skangass
Turku,
Finland
TBD
30 000
Gasum/
Skangass
Tornio,
Finland
Closed
50 000
ManGa
LNG
Lbeck,
Germany
TBD
TBD
TBD
Hamburg,
Germany
Closed
5 500
Bomin/Lin
de
Gvle,
Sweden
TBD
30 000
Skangass
Gvle,
Sweden
TBD
TBD
Swedegas
Sundsvall,
Sweden
TBD
5 000
TBD
Gothenburg,
Sweden
Open
30 000
Vopak
/Swedegas
Malm/
Copenhagen,
Sweden/
Denmark
TBD
10 000
TBD
5 (60)
Aarhus,
Denmark
TBD
10 000
TBD
Helsingborg,
Sweden
TBD
<15 000
TBD
Rostock,
Germany
TBD
360 000
Gazprom
Trelleborg,
Sweden
TBD
TBD
TBD
Hirtshals,
Denmark
TBD
TBD
TBD
There are several issues that need to be considered with applications for LNG bunker
operations and the establishment of LNG terminals: regulative work, technical,
financial and security and risk and safety aspects, among others.
From a regulative perspective, an LNG project can be divided into two parts: the
maritime side which is usually regulated by a national authority, and the land side that
is usually covered by a local authority (e.g. national Maritime Authorities and affected
municipalities/rescue agencies), but other authorities may/need be consulted and/or
grant permits for specific activities. Road transports are regulated by the European
Agreement Concerning the International Carriage of Dangerous Goods by Road (ADR)
applicable from 1 January 2013.
During the planning and development phase of an LNG terminal, it is necessary that
different stakeholders and responsible authorities have regular communication,
enabling a clear project outline and discussions of different alternatives, opportunities,
risks etc.
6 (60)
The illustration gives a picture of the regulations and conventions that are relevant for
each step of the supply chain.
The ports that have participated in the first phase of LNG in Baltic Sea Ports have
gained important experiences, which can assist following ports in the development of
LNG. The experiences are summarized in the list below.
As a first step, a clear distinction should be made of the roles in establishing the
LNG terminal. The port is most often the owner of the land, while the
investment in the terminal can be the responsibility of the port, the
municipality, the gas supplier and/or the operator. Determining the different
investment roles is important at project start.
The permit process takes time and can be costly for the port. One lesson
learned is that the process for LNG is often unknown to the authorities
involved, and therefore the process takes even longer time.
Risk and safety is deemed as crucial when planning for LNG, when discussing it
with the relevant authorities, and when applying for a permit. Training of staff
in risk and safety measures is necessary.
7 (60)
Land use and design: for the design of the LNG terminal, the land use and the
surrounding area must be designated. The technical equipment needed in the
terminal increases the land use significantly.
8 (60)
9 (60)
Table of contents
Summary and recommendations...................................................................................... 4
1
INTRODUCTION .................................................................................................... 16
1.1
1.2
1.3
1.4
1.5
2.1
2.2
2.3
2.3.1
3.1
3.2
3.2.1
3.2.2
3.3
3.3.1
3.3.2
3.4
3.5
3.6
3.6.1
3.6.2
3.6.3
EXPERIENCES GAINED........................................................................................ 42
4.1
4.1.1
4.1.2
4.1.3
4.1.4
4.1.5
4.1.6
4.1.7
4.2
4.3
10 (60)
4.3.1
4.3.2
4.3.3
4.3.4
4.3.5
4.4
4.4.1
4.4.2
4.4.3
4.4.4
4.4.5
4.5
Regulations ........................................................................................................................................................... 49
Technical aspects ............................................................................................................................................... 49
Financial aspects................................................................................................................................................. 50
Security aspects .................................................................................................................................................. 51
Risk and safety ..................................................................................................................................................... 51
Possibilities ........................................................................................................................................................... 51
Regulations ........................................................................................................................................................... 51
Technical aspects ............................................................................................................................................... 52
Financial aspects................................................................................................................................................. 52
Security aspects .................................................................................................................................................. 52
Risk and safety ..................................................................................................................................................... 52
Conclusions of experiences gained ............................................................................................................. 53
11 (60)
Table of Figures
Figure 1. Planned and existing LNG terminals in Baltic Sea region. ............................................ 20
Figure 2. Development of LNG fuelled fleet. Confirmed projects in 2014-03-07 (DNV GL,
2014)........................................................................................................................................................................ 21
Figure 3. Estimated world LNG prices September 2014 in $US/MMBtu (Waterborne
Energy Inc, 2014). .............................................................................................................................................. 22
Figure 4. Global LNG bunker demand by 2020 (Ocane Balland DNV GL, 2014) .................. 23
Figure 5. Annual LNG demand 2020 for different sub regions of the SECA for ships being
100% of the time in SECA (DMA, 2012). .................................................................................................. 24
Figure 6. Rules and regulations process from an EU perspective. ............................................... 26
Figure 7.Interface in Denmark between maritime and shore side legislative areas, where
the Maritime authority is responsible for the left side, and the municipality is responsible
for the land side. (DMA, 2014) ..................................................................................................................... 27
Figure 8. Laws and regulations to be considered for LNG handling. ........................................... 28
Figure 9. Example of authorities and rules applicable in different links of the LNG supply
chain. ........................................................................................................................................................................ 30
Figure 10. Schematic flow diagram of terminal activities. ............................................................... 31
Figure 11. Example of semi-pressurized tanks ..................................................................................... 32
Figure 12. Example of design and dimensions for a FBT .................................................................. 32
Figure 13. Principal layout of the planned terminal in Gothenburg. ........................................... 33
Figure 14. Methods of bunkering (SSPA Sweden AB) ........................................................................ 34
Figure 15. Possible fire scenarios when LNG is spilled on water [SSPA, (Based on LuketaHanlin, 2006)]. ..................................................................................................................................................... 37
Figure 16. General structure of risk assessment approach. ............................................................ 38
Figure 17. Schematic picture over the safety zone range during bunkering and the risk
area in case of an accident. ............................................................................................................................. 39
Figure 18. Bunkering of Viking Grace in Stockholm (Source: AGA, 2014)................................ 42
Figure 19. Localization for LNG terminal in Helsingborg within the industrial area of
Industry Park Of Sweden (IPOS). ................................................................................................................ 43
Figure 20. Three localizations within the port of Malm were investigated. Alternative C
was found to be the most suitable (Source: CMP, 2013) .................................................................. 44
Figure 21. Overview of Port of Aarhus (Source: Port of Aarhus, 2013). .................................... 45
Figure 22. Overview of Muuga Harbour (Source: Port of Tallinn, 2013) .................................. 46
Figure 23. South Harbour and Katajanokka (Source: Port of Helsinki, 2013) ........................ 47
Figure 24. Proposed localization for LNG-terminal in Pansio Harbour, Port of Turku. ...... 47
12 (60)
Explanation
AIS
BLEVE
BOG
BPO
CAPEX
Capital Expenditure
CNG
DNV
dwt
ECA
EIA
FBT
FEED
FID
FOB
FSRU
GIIGNL
GHG
GT
HFO
IGC
IGF
IMO
13 (60)
Abbreviation
Explanation
ISO
ISPS
ITPS
LFL
LNG
MARPOL
MDO
MGO
MMbtu
NBP
Nm
Nautical miles
OGP
OPEX
Operating Expenditures
RPT
SECA
STS
TTS
UFL
14 (60)
15 (60)
INTRODUCTION
1.1
The project LNG in Baltic Sea Ports, partly financed by TEN-T, supports and initiates the
establishment of LNG terminals in participating ports. The ports that participate are:
Stockholm, Helsinki, Turku, Tallinn, Copenhagen-Malm, Aarhus and Helsingborg.
Some of the ports have reached far in their planning and development for supplying
LNG to ships. Stockholm, for example, has a functioning LNG supply chain for the ferry
Viking Grace. Port of Helsinki has a functioning LNG supply chain for the coast guard
vessel Turva. Other ports are planning for and acquiring permits for the establishment.
1.2
One of the main purposes of the project LNG in Baltic Sea ports is to find good
solutions and manageable ways of establishing LNG in ports, in order to supply LNG to
end users. The ports that have participated in the project have all gained experiences
and have reached far in striving towards LNG establishment.
It is also equally important to disseminate the results from the project, in order to
facilitate the establishment of LNG in other ports in the Baltic Sea area, and the rest of
Europe as well.
The experiences gained from the participating ports are therefore summarized in this
handbook, created for supporting ports in their work of planning and developing LNG.
1.3
Objective
1.4
Method
The elaboration of the LNG Handbook is based mainly on the results and findings of
the LNG projects in the participating BPO ports. Some other relevant experience from
ports in the Baltic Sea area are also included in the assessment of obstacles and
possibilities during the development and establishment of LNG as marine fuel.
The participating ports have been visited and/or interviewed, and the results and
findings have been compiled into these recommendations and guidance for other
stakeholders.
16 (60)
1.5
The handbook outline is based on the process of developing an LNG terminal, and the
phases that are connected to this process (planning, construction, production,
operation, bunkering etc).
The handbook starts with an overview of the status of LNG supply in the Baltic Sea
countries today, including future scenarios, and possible market and supply chain
development.
The general process of establishment is described, looking specifically at technical,
financial and safety aspects.
The obtained experiences from the participating ports are described and discussed.
The experiences are summarized into obstacles and possibilities for the development
of LNG, from a technical, financial and safety viewpoint, and to conclude, a checklist to
ports for LNG development is given.
17 (60)
2.1
There are a number of LNG terminal projects in the Baltic Sea Region of various
capacities. While some projects have resulted in constructed LNG terminals, other LNG
terminals are planned and/or under discussion. Of the existing terminals in the Baltic
Sea Region, listed in Table 1, there is none of large scale. Large scale terminals have a
capacity of more than 100 000 m3 LNG. Both of the existing are of the type closed,
meaning that the storage capacity is reserved by the operator of the terminal. An open
access terminals implies that independent LNG suppliers may reserve capacity in the
terminal.
Table 1. Existing terminal projects in the Baltic Sea Region.
Terminal
Type
Capacity
Operator
Status
Comment
Fredriksstad/
ra, Norway
Closed
6 400
Skangass
In operation
Nynshamn,
Sweden
Closed
20 000
AGA
In operation
The majority of terminals under discussion are medium scale terminals, approximately
larger than 10 000 m3 LNG. A few large scale terminals are under consideration in the
northeast part of the Baltic Sea Region. Table 2 gives examples of planned terminals,
but is not exhaustive as new plans are made continuously. Figure 1 shows a map of
existing and planned terminals/bunkering possibilities in the Baltic Sea Region.
Table 2. Planned terminal projects in the Baltic Sea Region. (TBD= To Be Determined)
Terminal
Type
Capacity
3
(m )
Operator
Comment
Lysekil/
Closed
30 000
Skangass
winoujcie,
Poland
Open
320 000
Polskie
LNG
Klaipeda,
Lithuania
TBD
170 000
Klaipedas
Nafta
Regional
terminal, Gulf
of Finland
TBD
300 000
TBD
Tallin Muuga,
Open
TBD
Vopak
Brofjorden,
Sweden
18 (60)
Estonia
/Elering
Rauma,
Finland
TBD
10 000
AGA
Pori, Finland
TBD
30 000
Gasum/
Skangass
Turku,
Finland
TBD
30 000
Gasum/
Skangass
Tornio,
Finland
Closed
50 000
ManGa
LNG
Lbeck,
Germany
TBD
TBD
TBD
Hamburg,
Germany
Closed
5 500
Bomin/Lin
de
Gvle,
Sweden
TBD
30 000
Skangass
Gvle,
Sweden
TBD
TBD
Swedegas
Sundsvall,
Sweden
TBD
5 000
TBD
Gothenburg,
Sweden
Open
30 000
Vopak
/Swedegas
Malm/
Copenhagen,
Sweden/
Denmark
TBD
10 000
TBD
Aarhus,
Denmark
TBD
10 000
TBD
Helsingborg,
Sweden
TBD
<15 000
TBD
Rostock,
Germany
TBD
360 000
Gazprom
Trelleborg,
Sweden
TBD
TBD
TBD
Hirtshals,
Denmark
TBD
TBD
TBD
19 (60)
Existing terminal
Existing terminal within BPO
Planned terminal
Planned terminal within BPO
Figure 1. Planned and existing LNG terminals in Baltic Sea region.
Planned terminals in the eastern parts of the Baltic Sea Region aim for an alternative
source of gas for the national gas grid infrastructure besides the marine distribution.
This increases security of supply.
2.2
Several factors will affect the development of LNG vessels. Uncertainties regarding
global trends, forces and technological development are difficult challenges. More and
more geographical areas will have emission restrictions, so called emission controlled
areas (ECA), boosting the number of LNG fuelled vessels. North America already have
ECA, while Asia, specifically Singapore and Hong Kong will have stricter restrictions
from 2020 (DNV, 2013). The stricter regulation of sulphur in Northern Europe (SECA)
will also affect the development.
20 (60)
The price of LNG, tied to global trends in global economy, and the transport demand is
one perspective. Maritime regulations and technical developments are other identified
factors.
Different studies indicate that liner traffic and vessels with regular routes initially are
the types of vessels assumed to convert to LNG propulsion. It is also reasonable to
assume that more new-buildings than retrofits will be LNG fuelled due to the fact that
it is less expensive compared to a retrofit. This makes the transition to LNG long-term
compared to other SECA compliance strategies, such as using scrubbers or switching to
MGO.
In March 2014 there were in total 101 confirmed LNG fuelled ship projects (DNV GL,
2014). Figure 2 shows the development
fuelled
Developmentofofthe
LNGLNG
fuelled
fleetfleet.
120
100
80
60
40
20
0
2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018
Year of delivery
Total In operation
Figure 2. Development of LNG fuelled fleet. Confirmed projects in 2014-03-07 (DNV GL, 2014)
The number of LNG fuelled ships through 2020 depends heavily on fuel prices. With a
LNG price 10% above heavy fuel oil (HFO), it has been estimated that 7-8% of the newbuildings between 2012 and 2020 will run on LNG. If the LNG price would go down to
30% below HFO, the uptake of LNG is expected to increase to 13% and, in the extreme
case of LNG price 70% below HFO, the LNG share of new-buildings is 30 % (DNV GL,
2014).
2.3
The availability of LNG in the North European and Baltic Sea market can be connected
to two main developments; the development of a small scale distribution network for
LNG in the North European countries, and the costs of such an infrastructure on one
hand, and the availability of LNG shipped to Europe on the other hand.
The small-scale infrastructure in the Baltic Sea region in the near future (up to 2017)
will offer different sourcing alternatives for LNG to a terminal. Depending on the size
21 (60)
of the terminal, sourcing possibilities looks different. For a medium scale terminal,
serving demand from the maritime side as well as local industrial customers and other
land based users, it might be possible to serve a medium scale terminal with a feeder
vessel. A medium size or a small size terminal could also be served by truck loads from
larger terminal establishments in the vicinity.
In the last couple of years, due to the relatively high price levels in Asia, very few spot
LNG supply vessels have been going to Europe. Possibly, this situation will change in
the near future due to American gas export permits. It is not likely though that this will
have large effects on pricing levels neither for the Asian nor the European markets.
Figure 3 shows estimated world LNG prices in September 2014 where the highest
prices were found in Asia and the lowest in North America.
Figure 3. Estimated world LNG prices September 2014 in $US/MMBtu (Waterborne Energy Inc, 2014).
When evaluating the potential market for, and the price of LNG supplied to the
maritime sector, the development of the underlying demand of LNG in combination
with availability and price is considered as the dominating factors. In a more local
perspective, factors like EU project support and governmental initiatives, such as the
Norwegian NOx Fund and the Finnish government support for small scale LNG
infrastructure, will strongly influence the development of LNG.
The FOB price, which is the price of LNG delivered as bunker fuel, consists of two main
cost components. The first is the market price of LNG, based on the HUB price of gas.
The second cost component is the supply cost that occurs when moving the LNG from
the LNG source to each specific user.
Since the HUB cost is difficult to influence, the main focus when developing a supply
chain for LNG as marine fuel is to create the most cost efficient supply chain that is
22 (60)
possible, in order to meet the demand of the client in terms of both availability and
price.
Seen in a long term perspective, the price development of LNG and NG compared to
crude oil related products such as the traditional ship fuel looks very promising,
primarily dependent on the lower consumptions to reserves ratio for NG. For crude
based products there are also a lot of less price sensitive consumers within other
industries than energy and transportation, such as plastics, lube oil etc.
2.3.1 Future market scenarios
There are many scenarios outlining probable future demand of LNG. DNV GL have
forecasted the bunker demand in 2020 to 4 -7 million tonnes globally, based on that
there will be 1000 LNG fuelled vessels. The demand in Europe and the Baltic Sea has
been forecasted to 1.4 2.2 million tonnes (DNV GL, 2014), see Figure 4.
Figure 4. Global LNG bunker demand by 2020 (Ocane Balland DNV GL, 2014)
For a scenario of 2030 while business as usual is assumed, Lloyds Register Marine &
University College London (2014) has forecasted the share of LNG as shipping fuel on a
global market to 11 %. According to an analysis by Pyry (2013), a higher share, 29 %,
is likely in the Baltic Sea region.
In a study by DMA (2012), the total demand of LNG by 2020 in SECA has been
forecasted to 4 million tonnes annual. Figure 5 is showing the forecasted demand in
different sub-regions for ships spending 100 % of their time is SECA (total demand
from these vessel types is about 2 million tonnes).
23 (60)
Figure 5. Annual LNG demand 2020 for different sub regions of the SECA for ships being 100% of the time
in SECA (DMA, 2012).
It is reasonable to believe that the land-based LNG market and the LNG maritime
market will be closely connected in the future, enabling to sign long term supply
contracts, hence securing the terminal investment. Within the BPO projects, local
market analyses have been performed for the participating ports. From these, it can be
concluded that most of the planned terminals rely on land-based demand in addition
to the expected demand from shipping. For those ports that have not identified any
land-based demand, the volumes of LNG are smaller and demand predictions are
difficult to make.
24 (60)
25 (60)
3.1
There are several issues that need to be considered with applications for LNG bunker
operations and the establishment of LNG terminals: regulative work, technical,
financial and security and risk and safety aspects, among others. This chapter give a
general overview of the process of establishing an LNG terminal, from a regulative,
technical, financial, safety and security perspective.
3.2
Regulations
When planning for an LNG terminal and associated activities, a number of rules and
regulations need to be considered to get a permit approval. The regulative process
seen from an EU perspective is illustrated in the figure below, where EU directives are
agreements between EU states regarding what rules should be included in each
nations laws.
26 (60)
From a regulative perspective, an LNG project can be divided into two parts: the
maritime side which is usually regulated by a national authority, and the land side that
is usually covered by a local authority (e.g. national Maritime Authorities and affected
municipalities/rescue agencies), but other authorities may/need be consulted and/or
grant permits for specific activities. Road transports are regulated by the European
Agreement Concerning the International Carriage of Dangerous Goods by Road (ADR)
applicable from 1 January 2013.
Figure 7.Interface in Denmark between maritime and shore side legislative areas, where the Maritime
authority is responsible for the left side, and the municipality is responsible for the land side. (DMA, 2014)
During the planning and development phase of an LNG terminal, it is necessary that
different stakeholders and responsible authorities have regular communication,
enabling a clear project outline and discussions of different alternatives, opportunities,
risks etc.
3.2.1 Permits
Once the terminal layout and the different activities have been decided upon, the
regulative/legal permit process can start and consideration must be taken to both
safety and environmental issues. Note that the permit process can start earlier, but
there is a risk that permit application details will change along the way if not discussed
thoroughly at project start, and/or that the permit application is incomplete, resulting
in longer permit process times.
Necessary permits are: Building permit, environmental permit and permit for handling
and storage of dangerous goods. If distribution is to be performed with pipelines
and/or
truck,
additional
regulations
in
accordance
with
pipeline
regulations/transportation of dangerous goods are applicable. Import by LNG carrier
requires a permit for the port. The land-use is usually regulated in a municipal local
plan (detaljplan in Sweden, lokalplan in Denmark). If the regulations in the plan do not
include handling of LNG, a process for correction of the local plan is required.
The illustration in Figure 8 shows schematically the different laws and regulations that
need to be considered for various parts of the LNG handling.
27 (60)
Step
Permitting Authority
Comment
Initial consultation
The Municipality
Feasibility study
Consultation
document
The Municipality
Occupational health
Work Environment
Authority/Municipality
Risk assessment
The Municipality
28 (60)
process
Building permit
application
Environmental permit
application
The Municipality
The Municipality/Regional
rescue services
Ministry of Environment/
Municipality/County
29 (60)
Road transports
of LNG to
Stockholm
Reloading from
truck to bunker
vessel at
Loudden
Bunker vessel
traffic and
bunkering in the
port
Figure 9. Example of authorities and rules applicable in different links of the LNG supply chain.
3.3
30 (60)
In the localization process for the terminal, several aspects need to be considered, for
example;
Characteristics of the ground and sufficient stability where the storage tank/s
are to be located
There are two different main types of storage tanks; semi-pressurised tanks, illustrated
in Figure 11, and Flat Bottom Tank (FBT), illustrated in Figure 12.
31 (60)
Both types of tanks have double walls to minimise boil-off. The better the insulation,
the lesser the boil-off, even if it can never be totally prevented. An FBT tank stores LNG
under atmospheric pressure while a semi-pressurised tank can store LNG under
pressure (approximately 12 bars). In Table 4 and in Table 5, respectively, some of the
main points in regards to evaluating site-built FBT versus vacuum-insulated semipressurized tanks are summarized.
Table 4. Pros and cons of FBT as LNG storage technique
Advantages of FBT
Disadvantages of FBT
32 (60)
The land area needed depends on the physical dimensions of the terminal and
associated activities. A full activity terminal, including areas for loading and unloading
of LNG, taking into account both berths and tank truck filling stations, areas for piping,
possible liquefaction equipment and safety distances, usually generates a total
terminal area of about 30,000 to 40,000 m2. Figure 13 shows the layout for the
planned terminal in Gothenburg with both semi-pressurised tanks and an FBT.
In addition to storage tanks, other major technical components to consider for the
terminal are:
3.3.2 Bunkering
Methods for bunkering are generally divided into:
33 (60)
Bunkering ship-to-ship requires less space since this does not cause any installation
ashore. For ports where the demand of LNG is spread out in different locations of the
harbour, this alternative might be the most favourable. This is the case for Helsinki
where the demand of LNG is assumed to be spread out in different parts of the port.
Both tank-to-ship and truck-to-ship implies fixed installations ashore which may
constrain the accessibility for some vessels.
In order to select the best suitable solution for an individual port, parameters such as
bunkering volumes, physical limitations and logistical issues need to be considered.
The total LNG volume to be handled on a yearly basis in a port is perhaps the most
important critical parameter that affects the suitable solution for LNG bunkering of
vessels. Also the bunker frequency and the size of vessels are two very central issues
when selecting appropriate method. Requirements of large bunker volumes per vessel
and also high bunkering speed, point towards STS solutions rather than TTS. However,
a high bunker frequency of smaller vessels in a port probably also require a
supplementary land-based system (ITPS) in order to be able to handle all vessels,
especially if there are physical limitations in the port basin.
A useful standard for finding what materials to use for the construction of the terminal
is the European standard EN1160 Installations and equipment for liquefied natural
gas. General characteristics of liquefied natural gas.
Special requirements for LNG facilities can be found in:
34 (60)
In addition to the European standards, local regulations, standards and guidelines may
be applicable.
3.4
Financial aspects
Similar to other infrastructure projects, the investments are very heavy for the
development and construction of an LNG terminal. It is of importance for the project
owner to find supplementary financing sources.
Important aspects to consider during the planning phase of the project are:
3.5
Security aspects
Security of the terminal implies measures for protection of the facilities. If a terminal is
to be constructed within the area of an international port, the terminal will most likely
be under the International Ship and Port Facility Security (ISPS) regulation and national
port regulations regarding port facility security. It is the obligation of the local port
administration to meet the regulations. Example of measures to enable a high security
of a terminal could be:
Only allowing authorized persons within the area. All persons moving in the
port area shall carry an identity card with photo.
35 (60)
3.6
Risk and safety aspects are composing a major part when an LNG terminal and LNG
bunkering possibilities are planned and outlined. As LNG bunkering to ships is relatively
new, available accident records cannot be used to derive accurate accident statistics
and probability figures. There are not yet any established standards for LNG bunkering
installations and procedures, however, there is a number of guidelines and
recommended practices concerning risk assessments presented by ISO and other
recognized organizations which should be considered:
Guideline for systems and installations for supply of LNG as fuel to ships OGP
Draft 118683, 2014-01-16
3.6.1 Hazards
Hazards associated with the introduction of an LNG terminal can be identified in a
number of operational phases, such as import, truck loading, railroad loading, bunker
vessel loading and LNG bunkering.
LNG hazards result mainly due to the physical and chemical properties, cryogenic
temperatures, dispersion characteristics, and flammability characteristics. If an LNG
release occurs, there is an immediate potential for a range of different outcomes and
types of consequences. Of the following identified LNG specific potential outcomes of
an accidental release of LNG, fire scenarios are found to be the ones governing for
necessary risk control measures including determination of safety distances and site
selection for bunkering facilities and operations.
delayed or immediate ignition of vapour clouds (flash fire), slow fire front
36 (60)
Vapour cloud explosion (in confined spaces and enriched with other
hydrocarbons)
Figure 15. Possible fire scenarios when LNG is spilled on water [SSPA, (Based on Luketa-Hanlin, 2006)].
The level of consequence depends on the direct receiving environment and the
behaviour of the LNG. Since the flammability range for vaporized LNG (methane) in air
is relatively narrow, 5% (LFL) 15% (UFL) compared with many other flammable gases,
it is hard to ignite. If ignited, however, the emissive power from methane is higher
than e.g. for propane. Methane is, in contrast to propane, lighter than air and
vaporized LNG from small leakages will therefore dissipate relative quickly. For a large
LNG spill, the visible white cloud of cold vaporised LNG will initially have neutral
buoyancy in air.
3.6.2 Risk assessment process
The structure of the risk assessment process includes basic components according to
the figure below.
37 (60)
Hazard identification
Possible accident scenarios, risk ranking
Risk analysis
Frequency/
probability
analysis
Consequence
analysis
Risk control
Preventive
measures
Consequence reducing
mitigating measures
analysis
Risk evaluation
Acceptance criteria, regulations, policies
Recommendations
Figure 16. General structure of risk assessment approach.
The draft guidelines from OGP (International Association of Oil and Gas Producers)
(OGP, 2013) suggest two different approaches for conducting the risk assessment.
These recommendations depend on the characteristics and complexity of the
bunkering system and facility. For the non-complex basic case, a set of 24 functional
requirements, based on internationally recognised standards and good engineering
practices, is formulated. If these 24 functional requirements are met and if there is no
cargo handling conducted in parallel with the bunkering and no passengers on board
the receiving vessel during bunkering operation, a qualitative risk assessment may be
sufficient.
If the bunkering concept deviates from the non-complex base case or if all 24
functional requirements have not been met or if cargo handling is conducted in
parallel (SIMOPS, Simultaneous Operations), a more comprehensive quantitative risk
assessment (QRA) approach should be undertaken. If passengers will be present on
board the receiving vessel during LNG bunkering, acceptance from national competent
authorities and all other stakeholders is also required.
38 (60)
Figure 17. Schematic picture over the safety zone range during bunkering and the risk area in case of an
accident.
Safety zones/ distances are not intended to provide protection from catastrophic
events or major releases but rather create an adequate separation zone around
equipment and offer a safe layout.
Corresponding safety zones may also need to be established for other LNG transfer
interfaces of the LNG supply chain, and it may also be relevant to establish additional
exclusion zones outside the safety zone where other categories and third parties must
not have access. In addition to the safety zone around the bunkering site, it may also
be necessary to establish a security zone around the bunkering facility and vessel
where ship traffic and other activities are monitored.
Zoning considerations and classifications are also important with regard to type and
location of electrical installations at the bunkering facility and standards such as the
IEC EN 60079 (IEC, 60079) and corresponding national standards.
There are two options for defining the design release scenario of adequate safety
designs. The first and simplest way is the deterministic approach, where a conservative
maximum credible accidental release is defined on the basis of the characteristics of
the bunkering system. This option takes into account such factors as hose dimension,
flow rate, pressure, temperature and ESD design. The second, and more sophisticated
way, is to apply a probabilistic approach, where the cumulative consequences of a
39 (60)
number of possible different leakage scenarios are summarised, e.g. by the use of an
event tree model.
If a quantitative risk assessment (QRA) approach needs to be applied, the zoning
considerations and definitions of safety zones are normally based on probabilistic
approaches including detailed LNG dispersion, vapour cloud modelling and fire
calculations for derivation of heat radiation and contours for individual risk around the
bunkering site and supply facility.
40 (60)
41 (60)
EXPERIENCES GAINED
This chapter gives an overview of the status in the seven project ports. Experiences
gained from on-going and implemented LNG related projects are summarized and
concluded. The main obstacles and possibilities in different aspects that have been
encountered are listed as a summary of all experiences.
The purpose of this chapter is to provide other ports with valuable information about
the process of establishing an LNG terminal.
4.1
4.1.1 Stockholm
Port of Stockholm is one of the two participating ports that have a functioning LNG
supply chain (the other being Helsinki). The ferry Viking Grace is bunkering LNG in the
port of Stockholm, using the bunker vessel Seagas for ship-to-ship bunkering.
The LNG is stored in the LNG terminal in Nynshamn, with a volume of 20 000 m3, and
is transported by truck to the port area in Stockholm, where the bunker vessel is
loaded. The bunker vessel then approaches Viking Grace on the outside, allowing for
bunkering while passengers are on-board, see Figure 18.
Within the project LNG in Baltic Sea ports, the Ports of Stockholm has developed a
safety manual that describes the risk and safety aspects of LNG bunkering, and gives
42 (60)
Figure 19. Localization for LNG terminal in Helsingborg within the industrial area of Industry Park Of
Sweden (IPOS).
The Port of Helsingborg has been the leading applicant in the LNG in Baltic Sea Ports
and will remain so even in the second phase of the project, with other participating
ports. Within the framework of the second phase of the project, Helsingborg will
43 (60)
design a multifunctional bunker ship. The multi-function ship will be able to provide
LNG bunkering, MGO bunkering and other ship supply services. When the maritime
market is ready the aim is to provide a sustainable bunker solution in the market area
of Helsingborg.
Figure 20. Three localizations within the port of Malm were investigated. Alternative C was found to be
the most suitable (Source: CMP, 2013)
44 (60)
a cluster of industrial and domestic customers which are isolated from the grids
or wish to have an alternative access to the gas supplied through the grids;
the bunkering market of the ships, which is shortly going to face a challenging
change in the emissions regulation starting from the January the 1st 2015.
45 (60)
In order to fulfil the needs of the bunkering market and, eventually, also the demand
of small commercial and domestic customers, Port of Tallinn and Vopak LNG are
investigating and preparing the possibility to develop a small facility which could be
considered as the first phase of the terminal development.
It remains the initiators ambition to develop the regional import terminal as phase II
of the project, as soon as the market conditions and the commercial demand will
require it.
46 (60)
Figure 23. South Harbour and Katajanokka (Source: Port of Helsinki, 2013)
Figure 24. Proposed localization for LNG-terminal in Pansio Harbour, Port of Turku.
47 (60)
In the project, the Port of Turku has also identified bunkering facilities of LNG in the
ports berth areas from both technical and safety perspectives, as well as set up safety
instructions for LNG bunkering. The LNG bunkering would be done with a tank truck,
and at a later stage, it will be possible to switch to bunkering with a vessel or from a
solid intermediary tank.
There is also a terminal planned in Pori (about 140 km from Turku) by the same
operator, Gasum, and the procedure of the project in Turku is partly dependent on the
project in Pori. The proposal of local detailed plan for Pansio LNG terminal area was
accepted in June 2013. The terminal was planned to be in operation in 2015 but an
appeal regarding the terminal have been made to the Turku Administrative Court and
is delaying the project.
4.2
Communication
48 (60)
4.3
Obstacles
The subsequent sections, listing some obstacles and possibilities during the
establishment of LNG in the participating ports of the project, are summaries of the
experiences gained during the implementation of the project.
4.3.1 Regulations
Lack of international standardization regarding LNG as ship fuel, especially lack of LNG bunkering related regulations. Today bunkering LNG is only allowed
with special permission. This is experienced in several of the ports. For example
Ports of Stockholm was the first port to receive a permit for bunkering and
during the permit process discussions were held with relevant authorities.
Responsible authority not always clear. Port of Aarhus have experienced that
the responsibility for bunkering permits in ports was not yet clarified in
Denmark. During the implementation of the project, new instructions and
clarifications were received from the Danish Maritime Authority, stating the
responsibility for each authority.
Finding the right dimensions and type of terminal for intended purposes is a
process. Both Copenhagen Malm and Aarhus have experienced that finding
the right size volume of the terminal is an iterative process, with decisions
along the way that are changed and corrected.
Finding suitable area for LNG activities is sometime complex. All ports have
experienced that suitable areas for LNG terminals must take risk and safety
aspects into consideration, which limits the number of suitable locations.
Lack of standardised equipment and technical solutions e.g. couplings and ESD
49 (60)
As a first step, a clear distinction should be made of the roles in establishing the
LNG terminal. The port is most often the owner of the land, while the
investment in the terminal can be the responsibility of the port, the
municipality, the gas supplier and/or the operator. Determining the different
investment roles is important at project start.
Safety distances affecting other activities require space and increase costs. Port
of Aarhus has experienced that the planned LNG terminal require more land
area than first anticipated. The technical equipment and the safety distances
strongly affect the land use in the terminal.
Additional structures
Supply of LNG to the ports is controlled by a large scale global market where
the dominating parties are found in Asia which makes it harder for smaller
importer in the Baltic Sea to be competitive
50 (60)
The enlargement of ISPS area may prevent the development of other activities
in the vicinity. This is a possible obstacle, however, it has not been experienced
by any of the participating ports.
4.4
Possibilities
Some of the possibilities presented below apply for the participating ports. Some,
however, will be available during later stages of development, during design and
building of the terminals. This will be valid for ports that chose to follow the first early
developers.
4.4.1 Regulations
New regulations and guidelines are developed, for example, ESSF LNG subgroup and PIANC 172.
51 (60)
The introduction of SGMF (The Society for Gas as a Marine Fuel) will result in
the presence of an industry body dealing with the technical and safety issues
associated with the use of LNG as ship fuel and the maintaining of high
standards across the industry.
The IGF Code is under development (seagoing vessels) and regulation for inland
waterway vessels is expected soon.
52 (60)
4.5
The safety will increase along with gained experiences from existing terminals
in operations. This will be an advantage mainly for the ports that develop LNG
as marine fuel as followers to the first ports.
The ports that have participated in the first phase of LNG in Baltic Sea Ports have
gained important experiences, which can assist following ports in the development of
LNG. The experiences are summarized in the list below.
As a first step, a clear distinction should be made of the roles in establishing the
LNG terminal. The port is most often the owner of the land, while the
investment in the terminal can be the responsibility of the port, the
municipality, the gas supplier and/or the operator. Determining the different
investment roles is important at project start.
The permit process takes time and can be costly for the port. One lesson
learned is that the process for LNG is often unknown to the authorities
involved, and therefore the process takes even longer time.
Risk and safety is deemed as crucial when planning for LNG, when discussing it
with the relevant authorities, and when applying for a permit. Training of staff
in risk and safety measures is necessary.
Land use and design: for the design of the LNG terminal, the land use and the
surrounding area must be designated. The technical equipment needed in the
terminal increases the land use significantly.
53 (60)
The actions needed when establishing an LNG terminal are summarized in Table 6. The
table aims to serve as a checklist for the procedure and the required actions. The
actions are basically listed chronologically, even though some of the work can be done
in
parallel.
54 (60)
Action
Time aspect
Authority/stakeholder
Comment
Municipality
2-6 months
Possible localizations
Expected demand of LNG
Possible technical solutions
Finding possible financial solutions
Consultation with concerned authorities and
municipality
Corrections made to municipal local/development
plan
Municipality, Maritime
authority, County administration
Municipality - Planning unit
EIA
Risk analysis
Technical specification
55 (60)
8 12 months
Investors/operators/gas
suppliers
County administrative board
(Sweden), Municipality
Environmental unit
County administrative board
(Sweden), Municipality
Environmental unit
County administrative board
(Sweden), Municipality
Environmental unit, Emergency
preparedness
Action program
Permit for transportation of dangerous goods
Permit for pipelines
Detail engineering design
Contracting costumers
Contracting gas suppliers
56 (60)
57 (60)
58 (60)
Pyry, 2012, Report on the LNG refuelling possibilities of ships in the operating
area of the Port of Helsinki, November 2012
Pyry, 2013, Feasibility study and cost-benefit analyses of liquefied natural
gas (LNG) bunkering infrastructure construction in the harbours of the port of
Tallinn, June 2013
SGMF (The Society for Gas as a Marine Fuel), 2014, http://www.socgmf.org
Sfartsstyrelsen, 2014, LNG Overview of regulations,
http://www.soefartsstyrelsen.dk/regleroglove/sider/lngsombraendstof.aspx
SSPA Sweden AB, 2013, UPDATE Feasibility Study for LNG Terminal in Port of
Aarhus, November 2013
SSPA Sweden AB, 2013, Feasibility study regarding LNG in Copenhagen Malm
Port, September 2013
SSPA Sweden AB, 2013, Strategic planning for infrastructure, localization and
ship bunkering in the ports of Stockholm, December 2013
Waterborne Energy Inc, 2014, World LNG Estimated September 2014 Landed
Prices, Updated August 2014, http://www.ferc.gov/market-oversight/mktgas/overview/ngas-ovr-lng-wld-pr-est.pdf
WPCI, 2014, LNG Fuelled vessels world map,
http://www.lngbunkering.org/lng/map/node
59 (60)
This Handbook has been prepared by SSPA Sweden AB, assigned by the Baltic
Ports Organization.
Clients reference: LNG in Baltic Sea Ports, Emil Arolski
SSPA report No: RE20136642-01-00-A
Project manager: Ulrika Roup, [email protected], Tel +46 31 772 90 60
60 (60)