High Voltage
High Voltage
NEW DELHI
Petition No. 220/MP/2012
Coram:
Shri V.S Verma, Member
Shri M. Deena Dayalan, Member
Date of Hearing:
Date of order:
20.6.2013
21.2.2014
In the matter of
Miscellaneous Petition for approval under Regulation 24, 111 & 113 of the Central
Electricity Regulatory Commission (Conduct of Business) Regulations, 1999 and under
section 79( c), (i) and (k) of Electricity Act, 2003 for seeking direction for implementation
of third party audit report on protection Scheme of Transmission System of Northern
Region and Western Region.
And
In the matter of
Power Grid Corporation of India Limited,
B-9, Qutab Institutional Area,
Katwaria Sarai, New Delhi- 110016
.Petitioner
Vs
1. Northern Regional Power Committee
Central Electricity Authority,
18-A, Qutab Institutional Area, Shaheed Jeet Singh Marg,
Katwaria Sarai, New Delhi- 110016
2. Eastern Regional Power Committee
Central Electricity Authority,
14, Golf Club Road, Tollygunge,
Kolkata- 700033.
3. North Eastern Regional Power Committee
Central Electricity Authority,
Meghalaya State Housing Finance Co-operative Society Limited Building
Nongrim Hills, Shillong- 793003.
4. Southern Regional Power Committee
Central Electricity Authority,
Order in Petition No. 220/MP/2012
Page 1 of 30
Page 2 of 30
..Respondents
ORDER
The petitioner, Power Grid Corporation of India Limited, has filed this petition with
the following prayers:
"(a) Issue necessary direction to Regional Power Committee (RPC) for ensuring
the rectification of deficiencies observed during the protection audit and
implementation of all the protection and control system in line with the notification
dated 20th August, 2010 and monitoring of their healthiness for improvement of
stability and reliability of the grid by respective constituents;
(b) Issue necessary direction to RPC for review of various settings of protection
systems in view of changes / modification in the system / grid for stable and
reliable operation of integrated grid; and
(c) Pass such other relief as the Commission deems fit and appropriate in the
circumstances of the case and in the interest of justice.
2.
was convened by Minister of Power, Govt. of India with Chief Ministers/ Power
Ministers of different States of the Northern Region. In the said meeting, various
Page 3 of 30
resolutions were adopted to ensure smooth and reliable grid operation including
an independent third party audit of the protection systems. Ministry of power vide
its Memorandum No. 17.1.2012-OM dated 7.8.2012 directed that independent
third party audit of protection scheme shall be carried out within one month and
the Regional Power Committee shall monitor the same. PGCIL would fund and
carry out the audit in first instance.
(b)
The protection audit was carried out by Central Power Research Institute
(c)
The protection audit carried out at the stations of various utilities is as
under:
(a) Phase - I and II
Sl. No.
1
2
3
4
5
6
7
8
9
UPPTCL
POWERGRID
NTPC
HVPNL
BBMB
PDD
DTL
RGTPP
MPPTCL
Sub-station/
Switchyard
17
12
2
2
2
2
1
1
1
Page 4 of 30
(b)
Sl. No.
1
2
3
4
5
6
7
8
9
10
11
POWERGRID
NHPC
NTPC
RVPNL
UPRVUNL
NJPC
THDC
UPPCL
JPHYDRO
PSTCL
LANCO
Phase V and VI
(c )
(d)
Sub-station/
Switchyard
24
8
5
4
3
1
1
1
1
1
1
Sl. No.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
POWERGRID
BBMP
RRVPNL
HPGCL
RUVNL
PSTCL
UPRVUNL
UPCL
JAYPEE
PSPCL
UJVNL
HPSEB
NPCIL
NTPC
UPPTCL
PDD
Sub-station/
Switchyard
10
4
4
1
2
2
1
2
2
1
1
1
1
2
3
1
Electrical Plants and Electric Lines) Regulations, 2010 inter-alia provides that
Page 5 of 30
installation of protection and control systems in all the transmission systems are
necessary to minimize the damage to the equipment in the event of faults and
abnormal conditions. The relevant portion of the above regulations is extracted
hereunder:
(4) Protection and Control
(a) Protective Relaying System
Adequately sectionalized and graded protection relaying system shall be
provided for transmission lines, transformers and bus bars so as to automatically
isolate the faulty equipment and, thus, minimize the damage to the equipment in
the event of faults and abnormal conditions. All main protection relays shall be of
numerical type and communication protocol shall be as per IEC-61850/relevant
IS.
(b) Grouping of protection
(i) The protection functions shall be subdivided into two groups each being
independent and capable of providing uninterrupted protection even in the event
of one of the protection groups failing. Wherever two sets of DC sources are
available, the relays shall be electrically and physically segregated into two
groups (Gr. A and Gr. B) to obtain redundancy, and to take protection systems
out for maintenance while the equipment remains in service. Grouping shall be
done to the extent possible in such a way that each group can independently
carry out protective functions with near equal redundancy. Interconnection
between these two groups shall not generally be attempted. However, if found
absolutely necessary such interconnection shall be kept to the bare minimum.
(ii) Even in cases when only one battery source is available, segregation of
protection and trip circuits in two groups may be considered by giving DC
supplies through separate fuses.
(c) The protection in respect of transmission lines, transformers, reactors and bus
bars are indicated in Schedule V.
(d) Disturbance recorders, Event loggers and time synchronizations equipments
Each 765 kV, 400 kV and 220 kV line shall be provided with facility for
disturbance recording, distance to fault location and time synchronizing
equipment (TSE). Event logger either stands alone or as part of substation or
switchyard automation system shall be provided for each 220 kV and higher
voltage class substation or switchyard. TSE complete with antenna, all cables,
processing equipment etc. shall be provided to receive synchronizing pulse
through global positioning system (GPS) compatible for synchronization of event
Order in Petition No. 220/MP/2012
Page 6 of 30
(e)
Regulations, 2010 (Grid Code) provides that every transmission licensee shall
comply with such technical standards of operation and maintenance of
transmission lines as may be specified by the Authority.
(f)
Regulation 2.4 of the Grid Code defines the role of RPC. Regulation
Page 7 of 30
(g)
protection audit carried out by CPRI for different utilities/sub-stations as per the
details given below:
(a)
(b)
and functional.
(c)
functional.
(d)
be made functional.
(e)
(f)
(g)
(h)
(i)
made functional.
(j)
Page 8 of 30
(k)
3.
The petitioner vide its affidavit dated 9.1.2013 has submitted that the third party
audit report containing deficiencies in different sub-stations has already been circulated
to all concerned utilities including Member Secretary of respective RPCs. The petitioner
has further submitted that entity wise/Organization wise details of the deficiencies, as
observed by CPRI, have already been submitted to
petition.
4.
During the hearing on 22.1.2013, all respondents were directed to file their
replies and action plan in the matter latest by 8.2.2013. Member Secretaries of all
RPCs were directed to submit the reports on action taken on protection audit along with
time frame of implementation for recommendations of protection audit.
5.
Replies to the petition have been filed by the Haryana Vidyut Prasaran Nigam
Limited, U.P Power Transmission Corporation Limited, Delhi Transco Limited, NTPC
Limited, Rajasthan Rajya Vidyut Prasaran Nigam Limited, North Eastern Regional
Power Committee, Eastern Regional Power Committee, Western Regional Power
Committee and Bhakra Beas Management Board.
6.
Haryana Vidyut Prasaran Nigam Limited (HVPNL) vide its affidavit dated
19.11.2012 has submitted that control area protection audit at 400 kV / 220kV Kirori and
400 kV Khedar was carried out by CPRI. HVPNL has complied with the Grid Code and
Order in Petition No. 220/MP/2012
Page 9 of 30
CEA`s Regulations. HVPNL has submitted that no sub-station has been commissioned
without protection system and control system. HVPVL in its further affidavit dated
28.2.2013
PLCC
protection channels along with protection coupler and Bus-Bar Protection of 400 kV
Kirori sub-station and its 220 kV feeders as mentioned in the audit report have been
rectified.
7.
12.2.2013 has submitted that replacement of old protection relay panels with new ones
is not always possible. UPPTCL is contemplating to replace only old/static relays with
numeric relays through retrofitting. The whole process may, however, take 9 to 12
month's time i.e. till February, 2014. UPPTCL has submitted the zone-wise actions
taken in the State to rectify the deficiencies along with action plan.
8.
Delhi Transco Limited (DTL) in its affidavit dated 11.2.2013 has submitted that
some deficiencies in respect of Bamnauli sub-station were pointed out in the report of
basic protection audit. The defects pointed out by the audit have been partially rectified.
However, full rectification work may take 6 to 14 months i.e. till April, 2014.
9.
report
NTPC Limited vide its affidavit dated 13.2.2013 has submitted that compliance
and
action plan for Protection Audit for NTPC stations have already been
submitted to respective RPCs. NTPC has annexed region wise reports/action plan with
its reply.
Page 10 of 30
about 9 to 12 months i.e. till February, 2014. However, minor defects shall be attended
within 3 to 4 months i.e. by June, 2013.
10.
Rajasthan Rajya Vidyut Prasaran Nigam Limited (RRVPNL) vide its affidavit
dated 26.2.2013 has submitted that the deficiencies observed in Phase- III, IV, V and
VI are not related to any mal operation or shortcoming of the protection systems.
Further, no indiscriminate tripling related to the grid failure was observed on 30 th and
31st July, 2012 in RVPNL System. The protection settings recommended by NRPC
particularly for power swing detection and all zone blocking has already been done by
RVPNL.
11.
Bhakra Beas Management Board (BBMB) vide its affidavit dated 8.8.2013 has
submitted as under:
(a)
(c)
balance static distance protection relays will be carried out during 2013-14
Page 11 of 30
12.
Northern Regional Power Committee (NRPC) vide affidavit dated 24.1.2013 has
submitted as under:
(a)
Page 12 of 30
(b)
heads of all the utilities which were covered in the protection audit to submit
fortnightly report in the prescribed format.
13.
Southern Regional Power Committee (SRPC) vide affidavit dated 15.2.2013 has
submitted as under:
(a)
approved third party audit in respect of 194 identified critical sub-stations in the
region.
(b)
The third party audit was concluded on 22.12.2012 with the active
(d)
Page 13 of 30
14.
North Eastern Regional Power Committee (NERPC) vide its affidavit dated
Power (Govt. of India) and headed by Chairperson, CEA, due to fund constraint,
independent third party protection audit was planned taking representations from
various
State
utilities,
NERPC/NERLDC
and
Central
Utilities
In NER, there are about 135 generating stations and sub-stations of 132
kV and above voltage class. The protection audit was planned in consultation
with NERLDC, STU, CTU and generating companies of NER. As on date,
protection audit in respect of about 100 sub-stations/generating stations has
been completed and rest of work is likely to be completed by February, 2013.
(c)
highlighted and discussed in OCC/PCC meetings. The course of action and time
frame of implementation of recommendations of protection audit will be planned
accordingly. The report on Protection Audit along with recommendations will be
submitted by 31.3.2013.
15.
North Eastern Regional Power Committee (NERPC) vide its affidavit dated
Page 14 of 30
rest of work was completed by February, 2013. The details of number of SubStations/generating stations of 132 kV and above voltage class in seven (7) State
Sector Utilities and four (4) Central Sector Utilities of the NE region are as under:
400 kV
Arunachal Pradesh
Assam
Manipur
Meghalaya
Mizoram
Nagaland
Tripura
POWERGRID
NEEPCO
NHPC
OPTC
TOTAL
(b)
220 kV
1
9
4
1
2
2
132 kV
4
39
9
19
7
6
13
9
4
1
1
7
14
111
Total No. of
subStations
5
48
9
20
7
6
13
15
7
1
1
132
Audit, DPR with cost estimate and action plan has to be prepared by STUs and
generating companies as per direction of Ministry of Power and Central
Electricity Authority
(d)
Page 15 of 30
(ii)
Control and Protection Units (BC and PUs) and Sub-station Automation
System (SAM) and providing TSE, DR and EL;
(iii)
(iv)
inter-trip facility;
(v)
(vi)
(vii)
Providing
required
fire
fighting
system/arrangement
for
transformers/reactors;
(e)
(viii)
(ix)
Page 16 of 30
16.
Eastern Regional Power Committee (ERPC) vide its affidavit dated 20.6.2013
The third party Protection Audit has been completed in all 400 kV sub-
(b)
(f)
Page 17 of 30
(g)
Among the IPPs, Maithon has submitted that PLCC has been rectified by
PGCIL. Maithon and PLCC protection of both channels is now in service. GMR
and Sterlite have not submitted any action/compliance plan for their 400 kV substations.
(j)
will be enabled shortly while estimates are being prepared for remaining
equipments to be replaced/ rectified.
17.
(a)
Page 18 of 30
(b)
18.
SRPC in its letter dated 31.12.2013 has submitted that CEA has sought DPR in
respect
of
Renovation
and
Up-gradation
of
Protection
Equipment
at
the
19.
NERPC has stated that the issue was discussed in 15th meeting of Protection
Sub-committee. SE(O) informed that the estimated cost projected in DPR for
rectification/renovations of sub-stations/generating stations of seven States of the
region is about ` 816 crore. Member-Secretary, I/C requested to all constituent States
of the region to take up the issue with their respective Power Ministry for approaching
the Ministry of Power, Government of India so that funding under NLCPR-Central is
approved at the earliest and the scheme is implemented early for smooth operation of
Order in Petition No. 220/MP/2012
Page 19 of 30
grid. However, the petitioner stated that certain works need to be carried out on urgent
basis by NER constituents even if funding is not available from external resources in
order to avoid unwarranted tripping/system isolation and smooth operation of the grid.
The Sub-committee requested to all constituent States to take up the matter with their
respective Power Ministry so that funding for execution of above work is made available
from NLCPR-Central to the constituent States of the region at the earliest.
20.
WRPC, SRPC, ERPC and NERPC and the Third Party Protection Audit Report
conducted by CPRI in association with the petitioner consequent to the grid
disturbances on 30/31.7.2012 to ensure smooth and reliable Grid operation at some
critical sub-stations identified by POSOCO. The summary of current status of
implementation of recommendations submitted by RPCs are tabulated below:
(1)
Western Region
Name of Sub-station
Bina (PG)
Status ( as on 20.12.2013)
(1) Audit completed in respect of Bina (PG) Substation, the only Sub-station of Western Region
figuring in the protection audit.
(2) POWERGRID has complied with the audit
observation.
Page 20 of 30
(2)
Southern Region
Status ( as on 30.12.2013)
(1) Audit completed in respect of 194 Sub-stations in
Southern Region by 22.12.2012.
(2) Minor defects may be attended within 1-6 months
and rectification/replacement may take 1 to 2 years.
(3) ` 665 crore (para 18) is required to take up the
work.
(4) Southern Region members have requested for 100 %
funding from PSDF.
(5) In 23rd SRPC meeting, utilities have agreed to carry
out implementation of recommendations relating to the
audit as per prioritization in phased manner.
Eastern Region
Name of SubStatus
station covered
Sub-stations under (1) Complied with observations at some of the stations.
POWERGRID
(2) Numerical relays at Subhashgarm 400 kV S/S will be
replaced by November, 2013.
(3) Voice communication with RLDC at Gaya 765 kV S/S
will be available by October, 2013.
(4) PLCC and Voice communication with RLDC at Patna
Order in Petition No. 220/MP/2012
Page 21 of 30
Sub-stations under
NTPC
Sub-stations under
DVC
Sub-stations under (1) Some of the equipments have been rectified and
procurement process is going on to rectify others.
WBSETCL
/WBPDCL
(2) Bus Bar protection (220 kV) at Kolaghat will be
available by July, 2014.
Sub-stations under
OPTCL/OHPC
Sub-stations under
NHPC (Teesta-V
400 kV substation)
Sub-stations under
JSEB
(Ramchandrapur
220 kV, Chandil
220 kV, TVNL 220
kV)
Page 22 of 30
given.
Sub-stations under (1) Bus Bar protection at Bodhgaya 220 kV S/S and
BSEB (Bodhgaya Biharshariff 220 kV S/S (132 kV level) is not available.
220
Biharshariff
kV)
kV,
220 (2) Local Breaker backup, Event logger, Synchronization
(5)
Northern Region
Name of Substation
Covered
46 Sub-stations
under
POWERGRID
21 Sub-stations
under UPPTCL
and 4 substations under
UPRVUNL
Status
Page 23 of 30
1 switchyard
under Lanco
1 sub-station
under DTL
(Bamnauli)
3 Sub-stations
under HPGCL
and 1 substation under
HVPNL
8 Sub-stations
under RRVPNL
and 2 substations under
RRVUNL
3 Sub-stations
under PSTCL
and 1 substation under
PSPCL
2 Sub-stations
under PTCUL
and 1 substation under
UJVNL
1 Sub-station
under HPSEB
(Kunuhar)
3 Sub-stations
under J&K
4 Sub-stations
and 3
switchyard
under BBMB
Page 24 of 30
10 Switchyards
under NTPC
01 Switchyard
under SJVNL
(Jhakri)
3 Switchyard
under JPVL
8 Switchyard
under NHPC
1 Switchyard
under THDC
(Tehri)
1 Switchyard
under NPCIL
(Narora)
21.
The Protection Audit was carried out by CPRI for 42 sub-stations. Out of these,
only Bina (PG) sub-station comes under Western Region and the recommendations
contained in respect of Bina sub-station in the Protection Audit have been complied with
Page 25 of 30
by the petitioner. Constituent States and Utilities of Eastern Region and Northern
Region have submitted the time frame for implementation/ rectification of equipments in
their respective regions. Constituents of North-Eastern Region and Southern Region
have cited non-availability of funds as major constraints in implementation of
recommendations of Protection Audit report.
22.
Third Party Protection Audit is regularly being maintained by CEA. The information as
available on the website of CEA with respect to protection audit and also other aspects
of recommendation of Enquiry Committee, the status as on 19.9.2013 is as under:
"Third party protection audit in all the States of the country was completed by
April, 2013. Corrective action as per the observation of the audit has been
initiated and likely to be completed by September, 2013 where purchase is not
involved and by the end of the year 2014, where the procurement of equipment is
involved."
23.
affidavits/e-mails that minor defects were being attended to by some of the utilities and
work in some of the utilities is likely to be completed by 2015. Some of the utilities,
namely DVC, WBSETCL/WBPDCL, BSEB and JSEB have not given any time-frame for
completion of protection and control system.
24.
protection and control system is essential not only to protect the equipment/isolate the
faulty elements from the grid and avoid any major grid incident but also to facilitate
Order in Petition No. 220/MP/2012
Page 26 of 30
analysis of the problems/causes of trippings so that corrective action can be taken by all
concerned. It is not only essential to install the protection and control systems in all the
transmission elements and generating stations as per technical standards notified by
CEA, but also to keep them in healthy condition for safe and secure operation of the
grid. With the synchronous interconnection of NEW Grid and Southern Regional Grid,
provision for requisite protection and their healthiness assumes critical importance.
25.
Protection Audit in all the regions has been completed and RPCs are regularly
26.
The role of SLDCs has also been prescribed in Section 32 (e) of the Electricity
Page 27 of 30
27.
Since the protection system is a vital requirement for the safe and secure
operation of the grid, we have decided that in order to implement the recommendations
of the Protection Audit, a compliance mechanism with definite time line needs to be put
in place as under:
(a)
Each STU and CTU shall submit its action plan against each deficiency
within one month from issue of this order clearly stating the deficiencies which
can be corrected without any procurement (Category-A) and deficiencies
involving procurement of equipment (Category-B). However, action plan for
deficiencies dealt in Petition No. 146/MP/2013 shall be submitted therein;
(b)
concerned STU and CTU within 2 months of issue of the order and compliance
report in this regard shall be submitted to respective RPC.
(c)
Page 28 of 30
(d)
any deficiency in the STU system in regard to the Category-A deficiencies is not
corrected after 3 months of issue of this order, the concerned SLDC may
approach the respective State Commission for appropriate action against
defaulting State entity in accordance with State Grid Code. The Office-in-Charge
of the concerned SLDC shall be responsible for monitoring and ensuring
compliance of the action plan and filing of the petition as directed herein.
(e)
RPCs at the end of each quarter shall prepare a report on the protection
deficiencies and their rectification which shall be sent to this Commission with a
copy to CTU not later than 45 days of expiry of the quarter. The report shall
inter-alia identify deviations from time lines as well as the State sub-stations
which have interface with ISTS system. CTU shall take necessary action and
issue a show cause notice for disconnection to sub-station of STU for not
complying with the Standards for Protection and Control as per Central Electricity
Authority (Technical Standards for Construction of Electric Plants and Electric
Lines) Regulations, 2010 and Central Electricity Authority (Grid Standards)
Regulations, 2010.
28.
Accordingly, we direct CTU, STUs and Generating Companies /Stations of all the
regions to ensure rectification of defects in the protection system as pointed out in the
protection audit within the time frame specified in paragraph 27 herein and submit the
latest status of corrective actions to Member Secretary of the respective Regional
Power Committee within one month of issue of this order. All RPCs are directed to to
Order in Petition No. 220/MP/2012
Page 29 of 30
29.
monitoring the protection related issues and bring to the notice of the Commission any
instance of non-compliance of the Regulation 1.5 of the Grid Code in respect of the
protection related issues considered in the instant petition.
30.
sd/(V S Verma)
Member
Page 30 of 30