Project Risk Management
Project Risk Management
Management Guide
Part I: Guidance for WSDOT Projects
Part II: Guidelines for CRA-CEVP Workshops
November 2014
To get the latest information on individual WSDOT publications, sign up for email updates at:
www.wsdot.wa.gov/publications/manuals
Foreword
Inaccurate cost estimating has vexed transportation projects for years. A noted study by B.
Flyvbjerg on the results of transportation project estimating found that, for the past 70 years,
the cost of transportation projects has been consistently underestimated in many parts of the
world, including the U.S.
The future is uncertain, but it is certain that these questions will be asked about our projects:
(1) How much will it cost? (2) How long will it take? And, of course, the obvious follow-up
question: Why? (Why that much and why that long?)
These questions are posed in the future tense, and we are being asked
to predict an uncertain future. Because the future is uncertain, the
fundamental answer to these questions is that an estimate is more
accurately expressed, not as a single number, but as a range. To
determine an accurate estimate range for both cost and schedule, risk
and uncertainty must be quantified.
What gets us in
trouble is not what
we dont know. Its
what we know for
sure that just aint
so.
~ Mark Twain
Estimates have two components: the base cost component and the risk (or uncertainty)
component. Base cost is defined as the likely cost of the planned project if no significant
problems occur. Once the base cost is established, a list of uncertainties is created of both
opportunities and threats, called a risk register. The risk assessment replaces general and
vaguely defined contingency with explicitly defined risk events and with the probability of
occurrence and the consequences of each potential risk event. Scope control is necessary for
project management and estimating. Cost estimates are reviewed and validated, and a base
cost for the project is determined.
Project risk management is a scalable activity and should be commensurate with the size and
complexity of the project under consideration. Simpler projects may utilize simple qualitative
analyses, as found in WSDOTs Project Management Online Guide in the Risk Management Plan
spreadsheet. Larger, more complex projects may wish to use more robust analysis techniques
via Monte Carlo simulation models.
The guidance in this manual has been developed by the Strategic Analysis and Estimating Office
(SAEO) in alignment with the goals of the Statewide Program Management Group. This
document would not have been possible without the contributions of dozens of key WSDOT
people who participated in the development and review of these guidelines. Credit is also due
to many of the consultant partners, academics, and others who continually advance the cause
of project risk management in the transportation industry.
Page i
Foreword
Page ii
Comment Form
NOTE: This document is a working draft. Your feedback and input are greatly appreciated.
From:
Date:
Phone:
To:
Subject:
WSDOT Headquarters
Development Division, Design Office
Attn: Strategic Analysis and Estimating Office
Mailstop 47330 PO Box 47330
Olympia, WA 98501-7330
Project Risk Management Comments
Page iii
Comment Form
Page iv
Contents
Foreword.. ................................................................................................................................................... i
Comment Form ............................................................................................................................................ iii
List of Exhibits .............................................................................................................................................viii
Page v
Contents
Section B
Section C
Description of Work......................................................................................................B-1
Project Team Status Prior to CRA/CEVP Workshop....................................................B-2
Project Team Responsibilities and Requirements ........................................................B-3
B-3.1 Items Required from the Project Team Prior to the Workshop ......................B-4
Risk Lead Duties ................................................................................................................... C-1
C-1
Section D
Page vi
Contents
Section E
Section F
Section G
G-1
Section H
H-5
H-6
H-7
H-8
H-9
H-10
H-11
Page vii
Contents
List of Exhibits
Part I: Guidance for WSDOT Projects
Exhibit 1-1
Exhibit 1-2
Exhibit 1-3
Exhibit 1-4
General Comparison of a Few Typical Characteristics of CRA and CEVP .......................... 1-7
Exhibit 1-5
Exhibit 1-6
Exhibit 1-7
Exhibit 1-8
Exhibit 1-9
Risk Management Schedule: With Workshop and Postworkshop Activities .................... 1-13
Exhibit 2-1
Exhibit 2-2
Exhibit 2-3
Exhibit 2-4
Exhibit 2-5
Example Risk ID Sheet from Project Management Online Guide, Qualitative ................... 2-8
Exhibit 3-1
Exhibit 3-2
Exhibit 3-3
Exhibit 4-1
Exhibit 4-2
Exhibit 4-3
Exhibit 4-4
Exhibit 5-1
Exhibit 6-1
Exhibit 6-2
Total Estimated Cost Impacts of Top 5 Risks for the Example Project ............................... 6-4
Exhibit 6-3
Exhibit 7-1
Exhibit 7-2
Exhibit 7-3
Exhibit 7-4
Page viii
Contents
Exhibit A-2
Preworkshop: Determine Need, Learn the Process & Assemble Project Information ...... A-6
Exhibit A-3
Exhibit A-4
Exhibit A-5
Exhibit A-6
Exhibit B-1
Exhibit C-1
Exhibit C-2
Exhibit G-1
Exhibit G-2
Exhibit G-3
Page ix
Contents
Page x
Part I:
Guidance for WSDOT Projects
Chapter 1: Project Risk Management Planning
Chapter 2: Risk Identification
Chapter 3: Qualitative Risk Analysis
Chapter 4: Quantitative Risk Analysis
Chapter 5: Risk Response
Chapter 6: Risk Monitoring and Control
Chapter 7: Project Risk Management Plan Template
Chapter 1
Current Status
Project Management Plan
Scope, Schedule, Estimate
Management
Planning
Risk Analysis
Risk
Identification
Qualitative
Quantitative
pre-response
analysis
Update
Project Management Plan
Results of
response actions
1-1
Risk
Monitoring
and Control
Implement Risk
Response Plan
TAKE ACTION!
Risk Response
post-response
analysis
Understanding project risks enables project teams to more effectively fulfill public
service expectations. Assessing project risk and uncertainty informs decision making
in our project development and delivery mission. These decisions contribute to public
safety and clarify project expectations. Informed project risk management adds value
on many levels to every project we deliver.
Estimating the cost of transportation projects is a fundamental responsibility of the
Washington State Department of Transportation (WSDOT). In recognition of the
fundamental and strategic importance of cost estimating, these guidelines provide
consistent practices across the agency to enhance methods for meeting this
responsibility. These guidelines were developed by the Strategic Analysis and
Estimating Office (SAEO), with contributions from a number of specialists in cost
estimating and project development.
No construction project is risk
free. Risk can be managed,
minimized, shared, transferred,
or accepted. It cannot be
ignored.
~ Sir Michael Latham, 1994
WSDOT Project Risk Management Guide
November 2014
Page 1-1
Chapter 1
Estimators must be shielded from pressures to prepare estimates that match any
preconceived notions of what a project should cost. Estimators need to prepare
estimates based on the scope of the project, the schedule of the project, and the
bidding conditions that are anticipated.
1-2
Page 1-2
Investment in
risk
management
Tolerance
for
risk
Chapter 1
1-3
2. Identify Risk
Events
3. Qualitative Risk
Analysis
4. Quantitative Risk
Analysis
5. Risk Response
More details on the steps above are found throughout this document.
Exhibit 1-2 provides a helpful comparison between risk and objectives for various types
of risk management. For this document we are interested in project risk management.
Page 1-3
Exhibit 1-2
Chapter 1
Type of Risk
Management
Generic
Project Risk
Management
Business Risk
Management
Description
Sample Objectives
Safety Risk
Management
Technical Risk
Management
Security Risk
Management
1-4
The project scope, schedule, and estimate package should include the most
current versions of the following items:
Project Summary
Detailed Scope of Work (commensurate with the level of development)
Project Cost Estimate (with Basis of Estimate completed)
o PE cost estimate
o ROW cost estimate
o Construction cost estimate
Previous Risk Analyses (if applicable)
Project Management Plan
Project Schedule
Page 1-4
Chapter 1
3. Midpoint for construction phases using the project award date and the
operationally complete date.
Page 1-5
1-5
Chapter 1
Statement of Policy
Required Process*
$10M to $25M
$25M to $100M
[1]
[1][3]
[1][2]
[2]
[1] In some cases, it is acceptable to combine a Value Engineering Study with a Risk-Based
Estimating Workshop.
[2] Projects $25 million and over should use the self-modeling spreadsheet in the scoping phase of
the risk-based estimating process, followed up by the more formal CRA or CEVP process during
the design phase.
[3] An informal workshop is composed of the project team (or key project team members); other
participants may be included as the Project Manager/project team deem necessary.
1-6
Page 1-6
Chapter 1
Exhibit 1-4
Details
Typical Length
Subject Matter Experts
Timing
CRA
CEVP
1 2 days
3 5 days
Internal and local.
Internal and external.
Any time; typically updated when It is best to start early in the process;
design changes or other changes
major projects are typically updated
to the project warrant an
as needed.
updated CRA.
General
An assessment of risks with an
An intense workshop that provides an
evaluation and update of costs
external validation of cost and
and schedule estimates.
schedule estimates and assesses risks.
Note: Risk assessments are orchestrated by the Cost Risk Estimating Management (CREM) Unit of the
Strategic Analysis and Estimating Office at Headquarters, in collaboration with the Project Manager.
The Project Manager submits a workshop request and works with the CREM Unit to ascertain the
type of workshop required and the candidate participants. (See Part II: Guidelines for CRA-CEVP
Workshops for more details.)
Exhibit 1-5 illustrates how project information develops and evolves over time. With
rising project knowledge comes an understanding that contending with some elements
of the project will require significant additional resources. These elements could involve:
scope; environmental mitigation and permitting; rising cost of right of way as corridors
develop in advance of the project; utilities; seismic issues; and other elements.
In the past, traditional estimating practices tended to produce the number for a
project; but the single number masks the critical uncertainty inherent in a particular
project. It implies a sense of precision beyond what can be achieved during planning,
scoping, or early design phases.
We recognize that an estimate is more accurately expressed as a range, not as a single
number. To determine an accurate estimate range for both cost and schedule, risk must
be measured. Formerly, WSDOT measured risk based on the estimators experience and
best judgment, without explicitly identifying the projects uncertainties and risks. That
has changed. Estimates are now composed of two components: the base cost
component and the risk (or uncertainty) component. The base cost represents the cost
that can reasonably be expected if the project materializes as planned. The base cost
does not include contingencies. Once the base cost is established, a list of risks is
created of opportunities and threats, called a risk register. The risk assessment
replaces general and vaguely defined contingency with explicitly defined risk events.
Risk events are characterized in terms of probability of occurrence and the
consequences of each potential risk event.
Page 1-7
Exhibit 1-5
Chapter 1
Executive Order (EO) E 1053 instructs employees to actively manage their projects.
EO E 1038 establishes, as policy, that WSDOT is to proactively assess and respond to
any risks that may affect the achievement of the departments strategic performancebased objectives and their intended outcomes. It further goes on to direct employees
to support the departments efforts to identify, share, and manage risk across all
organizations and functions.
Risk reviews are an integral part of budget development, with the intent that the
department makes informed decisions about risk tolerance. It can be inferred that
determined Enterprise Risk Management includes comprehensive project risk
management Project risk management is a major element in the Project Management
Plan, which is required for all WSDOT projects (EO E 1032). We, as stewards of the
public trust, must endeavor to inform decision makers of the uncertainty and risk
associated with the projects we develop. We must understand risk tolerance and
we must weigh the value of project decisions against project risks.
Page 1-8
Chapter 1
Chapter 5 of the book Risk, Uncertainty and Government notes, lawyers and
economists are accustomed to think of contracts for future performance as devices for
allocating risks of future events. In order for us to understand this allocation of risk,
projects must be examined and the uncertainty and risks must be documented and
characterized.
Risk Management
Identify
Analyze
Respond
Monitor/Control
We can think of risk management as two pillars (depicted above). They are: IDENTIFY
and ANALYZE the risks, then, RESPOND, MONITOR, and CONTROL project risk.
Unless we incorporate the second pillar, we are not realizing the full value of risk
management. When preparing the Project Management Plan and work activities
for our project, we must include both pillars of risk management.
Page 1-9
1-7
Chapter 1
Determine the level of risk assessment for your project (Exhibit 1-6).
Incorporate risk management activities into the project schedule (Exhibit 1-7).
Make risk management an agenda item for regularly scheduled project meetings.
Communicate the importance of risk management to the entire project team.
Establish the expectation that risk will be managed, documented, and reported.
Page 1-10
Chapter 1
Exhibit 1-6
Project
Size ($M)
Exhibit 1-7
Notes
0 to 10
10 to 25
25 to 100
Over 100
Milestones include:
Milestones include:
Workshop
Preliminary Results Presented
Draft Report
Final Report
Page 1-11
Exhibit 1-8
Chapter 1
Request form
submitted by
Project Manager
Prep activities
Typical duration 45 days
(range: 30 to 60 days)
Final
workshop
report
Post activities
Typical duration 45 days
(range: 30 to 180+ days)
Page 1-12
Chapter 1
Exhibit 1-9
TASK NAME
Risk Assessment Process (90 days +/-) Typical timeline for CRA/CEVP
Shorter
Common
Longer
~30
~90
~120 +
Request Form submitted by the Project Manager to the Cost Risk Estimating Management
(CREM) Unit of the Strategic Analysis and Estimating Office (SAEO)
PREWORKSHOP ACTIVITIES
Start
24
30
44
5 or more
10
45
90 +
Page 1-13
Page 1-14
Chapter 1
Chapter 2
Current Status
Project Management Plan
Scope, Schedule, Estimate
Risk Identification
Risk
Management
Planning
Risk
Identification
Risk Analysis
Qualitative
Quantitative
pre-response
analysis
Update
Project Management Plan
Results of
response actions
2-1
Risk
Monitoring
and Control
Implement Risk
Response Plan
TAKE ACTION!
Risk Response
post-response
analysis
Planning
Scoping
Design/Plans, Specifications, and Estimate (Engineers Estimate)
Construction
As projects evolve through project development, the risk profile evolves and understanding
grows. Therefore, previously identified risks may change and new risks may be identified
throughout the life of the project.
2-2
Page 2-1
Risk Identification
Chapter 2
Lessons Learned Database Searching for lessons learned using key words
in the WSDOT Lessons Learned Database that are relevant to your project
can provide an abundance of information on projects that may have faced
similar risks.
Page 2-2
Chapter 2
Risk Identification
Identification # for each risk identified Assign a unique number to each risk for tracking
purposes. If available, do this by utilizing an established Risk Breakdown Structure (RBS);
the WSDOT RBS is provided in Exhibit 2-4.
Date and phase of project development when risk was identified Document the date
the risk was identified and in which project development phase (planning, scoping,
design/PS&E, construction).
Name of risk (does the risk pose a threat or present an opportunity?) Ensure each
identified risk has an appropriate name; for example, NEPA Delay or Reduction in
Condemnation. Also, document the nature of the risk with respect to project objectives
(threat or opportunity; you can do this by using the RBS for naming conventions.
Detailed description of risk event The detailed description of the identified risk must
provide information that is Specific, Measurable, Attributable (a cause is indicated),
Relevant, and Time-bound (SMART). Ensure the description is clear enough and thorough
enough so that others reading about the description of the risk will understand what it
means.
Risk trigger Each identified risk must include the risk trigger(s). Risks rarely just suddenly
occur; usually there is some warning of imminent threat or opportunity. Clearly describe
and document these warning signs and information about the risk. For example, NEPA
Approval Date may be considered a risk trigger on a project that has a risk of a legal
challenge.
Risk type Does the identified risk affect project schedule, cost, or both?
Potential responses to identified risk Document, if known, possible response actions
to the identified riskcan the identified threat be avoided, transferred, or mitigated, or
is it to be accepted? Can the identified opportunity be exploited, shared, or enhanced?
Comments about risk identification Risk management is an iterative process, so regularly
review project risks. As you identify new risks, document and assess them. Consider the
resulting risk register preliminary only until the completion of additional and appropriate
activities. These may include any or all of the techniques listed above and/or more
robust processes such as Cost Risk Assessment and Cost Estimate Validation Process
(CRA/CEVP) workshops. More detail about the WSDOT workshops for CRA/CEVP
is provided later in this document, and at:
www.wsdot.wa.gov/projects/projectmgmt/riskassessment
2-3
Page 2-3
Risk Identification
Chapter 2
4. Characterize risks in terms of impact and probability. Note: High-impact risks with
low probabilities should be of particular interest to the Project Risk Manager. 2
2-3.2 Tips for Risk Identification
Determine, for your project, what constitutes significant risk.
Thoroughly describe the risk; there are forms on the following pages to help
with this, or you may create your own.
Include specialty groups and/or other persons who may have meaningful
input regarding the challenges the project may face.
Determine who owns the risk and who will develop a response.
Exhibit 2-1
Risk Identification
Brainstorming: An effective method, brainstorming can range from a small informal project team
effort for simpler projects to a full-blown CEVP workshop. Effective brainstorming requires a skilled
facilitator, working together with the project team and specialists who can bring additional expertise.
Checklists and/or questionnaires to specialty groups: Checklists/questionnaires are quick and easy
to use, but limited in nature; they only deal with the items on the list. Each project is unique, so a
standard list will often not capture the project-specific risks of most concern.
Though it can be limited, a checklist/questionnaire can spark thinking prior to a more formal
brainstorming process.
Examination of past similar projects: Lessons learned from past projects help us to avoid repeating
mistakes. Using past examples requires prudent and objective judgment, since a previous project
may be similar but is nonetheless different because each new project has unique requirements and
features, including uncertainties and risks.
WSDOT Lessons Learned website:
http://wwwi.wsdot.wa.gov/projects/delivery/lessonslearned/
A combination of the above methods and/or others: It is quite likely that for most projects, a
combination of the above methods will be used to identify risks. The important thing is that, once
identified, the risks are properly documented (see the following exhibits):
Exhibit 2-2 Example SMART template for documenting identified risks (tailor to your needs).
Exhibit 2-3 Example of how template is used for an actual project risk.
Exhibit 2-4 Risk Breakdown Structure for categorizing and organizing risks.
Exhibit 2-5 Example of qualitative risk identification using spreadsheet from the Project
Management Online Guide: www.wsdot.wa.gov/projects/projectmgmt/pmog.htm
2
High-Impact, low-probability risks, referred to as black swan events by some, can devastate a project and,
unfortunately, are not always given the attention they deserve. This is due to the fact that the expected value of this
type of risk does not always rank it highly on risk register.
Page 2-4
Chapter 2
(7)
specific
Construction
Active
CNS 40
Threat
Discover
hazardous
materials
during
construction
(8)
discover
during
construction
RBS# CNS 40
MDL# PE.EV.10.10
(10)
[10a]
(11)
1.50$M
MIN
1.0Mo
MAX
6.0Mo
Most
Likely
2.0Mo
Risk Matrix
VH
Probability
(9)
Risk
Impact
($M, Mo)
MIN 0.50$M
Threat
Risk Trigger Details The project is over 4 miles in length. The area of
most concern, for exposure to unknown subsurface materials, is in the last
1.5 miles of construction; this risk exposure occurs in the final 12 months
of construction. Risk exposure Starts: March 2015 & Ends: March 2016.
Probability
Correlation
(6)
Risk
Trigger
Cost
Summary
Description
Threat and/or
Opportunity
Type
Construction Risks
Project Phase
Dependency
Status
Risk #
Premitigated
Schedule
Exhibit 2-2
Risk Identification
H
M
L
VL
VL
VH
Impact
Additional notes: What needs to be done? Who will do it? Due date?
Specific What is the specific issue of concern? Provide a detailed description.
Measurable Estimate the probability that this risk will occur; estimate the impact if it does occur.
Attributable What will trigger (cause) this risk to occur? How do we know? Who owns this risk?
Relevant Why is this risk important to our project? How critical is this risk?
Time-bound When are we at risk? Project risks have a shelf-life they do not last forever.
MDL = Master Deliverables List (Work Breakdown Structure)
Page 2-5
Risk Identification
Exhibit 2-3
Page 2-6
Chapter 2
Chapter 2
Exhibit 2-4
Risk Identification
Level
1
Project Risk
------------------------
Level
2
Level 3
-----------
Environmental
& Hydraulics
ENV
Structures &
Geotech
STG
Design / PS&E
Right-of-Way
Utilities
Railroad
Partnerships
Stakeholders
PSP
Management /
Funding
MGT
Contracting
Procurement
CTR
Construction
DES
ROW
UTL
RR
ENV 10
NEPA/SEPA
STG 10
Design Changes
DES 10
Design Changes
ROW 10
ROW Plan
UTL 10
Coordination
RR 10
Design
Coordination
PSP 10
Tribal Issues
MGT 10
Management
Change
CTR 10
Change in
Delivery Method
CNS 10
Traffic Control
and Staging
ENV 20
ESA Issues
STG 20
Design Changes
DES 20
Deviations' Approval
ROW 20
inflation
UTL 20
Conflicts
RR 20
Construction
coordination
PSP 20
Public
Involvement
MGT 20
Delayed
Decision Making
CTR 20
Contract
Language
CNS 20
Construction
Permitting
ENV 30
Environmental
Permitting
STG 30
Changes to
design Criteria
DES 30
architecture or
landscape changes
ROW 30
Limited Access
IJR
RR 30
Right of Entry
PSP 30
Additional Scope
for third parties
MGT 30
Cash Flow
Restrictions
CTR 30
Delays in
Ad/Bid/Award
CNS 30
Work Windows
ENV 40
Archaeological
Cultural
DES 40
Projects by other
agencies affected
ROW 40
Managed
Access Appeal
MGT 40
Political/Policy
Changes
CTR 40
Market
Conditions
CNS 40
Schedule
Uncertainty
ENV 50
Hazardous
Materials
DES 50
Changes to Design of
Traffic Items
ROW 50
Acquisition
Issues
MGT 50
State Workforce
Limitations
CTR 50
Delays in
Procurement
CNS 50
Marine
Construction
ENV 60
Wetlands /
Habitat
Mitigation
ENV 70
Stormwater,
Potential
Changes to Flow
ENV 80
Impacts during
Construction
DES 60
Design / PS&E
Reviews
ROW 60
Additional ROW
is required
CTR 60
Contractor NonPerformance
CNS 70
Earthwork
Issues (re-use,
CTR 70
Availability of
Specialty
Labor/Labor
CNS 80
Coordination
with Adjacent
Projects During
CNS 90
Contractor
Access / Staging
Coordination and
CNS 100
Construction
Accidents
CTR 900
Other CTR
Issues
CNS 900
Other CN
Issues
ENV 90
Permanent
Noise Mitigation
ENV 900
Other ENV
Issues
-----------
STR 900
Other STR
Issues
DES 900
Other Design
Issues
ROW 900
Other ROW
Issues
UTL 900
Other UTL
Issues
RR 900
Other RR
Issues
PSP 900
Other PSP
Issues
MGT 900
Other MGT
Issues
CNS
haul etc )
The RBS provides several functionsand benefitsto the project teamand to management, including:
1)Consistency with taxonomy (wording); 2) Organizesrisk events into commoncategories; 3)Helps identify trends with respect to common usage of riskeventcategories&event types,
categories&event typesalong with their probability and impact values; 4)Helps toidentify common risk events among projects that the Region and HQ offices should be aware of due to
theirpotentialcumulative effects; e.g. negotiating agreements with agencies or other municipalities;5) Provides a basisto work from for risk elicitors during CEVP workshops; 6) Provides a
basis for development of independent risk surveys for those that are unable to attend a CEVP workshop.
This RBS serves as a starting point inassessing project risks in CEVP and CRA workshops; and also for smaller projects that may not conduct a formal workshop.
RISK TRIGGER
(CAUSE or PRECIPITATING EVENT)
RBS CODE
RISK EVENT
CONSEQUENCE
(effect on project objectives)
PROBABILITY
IMPACT
($ or time)
$5M, 8 weeks
ENV 10.01
As a result of
70%
ENV 10.02
Because of
10%
ENV 10.03
Due to
10%
$0.1M, 6
months
$0.1M, 4
months
Page 2-7
Risk Identification
Project Name
Project Manager
Active Risk
Status
RBS Category
UTL
Risk Number
20
Project Phase
Design
Date
Risk Owner
M. Example
10
9
8
7
6
5
Very High
High
Medium
4
3
X
1
Very Lo to Lo
Impact
some
2
1
9
Low
Very Low
10
Hi to Very Hi
RISK 1
QUALITATIVE ANALYSIS
RBS Category
ENV
Risk Number
90
Project Phase
Design
10
9
8
7
6
5
3
2
1
Risk Owner
Green Jeans
High
Medium
Date
Very High
Very Lo to Lo
Impact
some
Low
Very Low
10
Hi to Very Hi
RBS Category
ENV
Risk Number
40
Project Phase
Design
May 33, 2929
Date
Risk Owner
Green Jeans
10
9
8
6
5
3
2
1
2
High
Medium
X
1
Very High
Very Lo to Lo
Impact
some
subsurface
utility
investigations
immediately;
assign team
member to
this full time.
RISK RESPONSE
STRATEGY
ACTION
TO BE TAKEN
press for
noise analysis
ASAP
Low
Very Low
RISK RESPONSE
STRATEGY
accept
probability
Item of Interest
ACTION
TO BE TAKEN
RISK 2
QUALITATIVE ANALYSIS
Status
RISK RESPONSE
STRATEGY
avoid
probability
Active Risk
Status
Date:
avoid
probability
Exhibit 2-5
Chapter 2
ACTION
TO BE TAKEN
monitor
supplemental field
investigation report due
November 31.
10
Hi to Very Hi
RISK 3
Page 2-8
Chapter 3
Current Status
Project Management Plan
Scope, Schedule, Estimate
Management
Planning
Risk
Identification
Risk Analysis
Qualitative
Quantitative
pre-response
analysis
Update
Project Management Plan
Results of
response actions
3-1
Risk
Monitoring
and Control
Implement Risk
Response Plan
TAKE ACTION!
Risk Response
post-response
analysis
General
Qualitative Risk Analysis assesses the impact and likelihood of the identified risks and
develops prioritized lists of these risks for further analysis or direct mitigation.
The project team assesses each identified risk for its probability of occurrence and its
impact on project objectives. Project teams may elicit assistance from subject matter
experts or functional units to assess the risks in their respective fields. (Source: WSDOT
Project Management Online Guide)
Qualitative risk analysis can be used by project teams:
As an initial screening or review of project risks.
When a quick assessment is desired.
As the preferred approach for some simpler and smaller projects where robust
and/or lengthy quantitative analysis is not necessary.
Qualitative: Observations that do not involve measurements and numbers; for
example, the risk of a heavy rainstorm affecting our erosion control is Very High.
Qualitative assessment: An assessment of risk relating to the qualities and subjective
elements of the riskthose that cannot be quantified accurately. Qualitative
techniques include the definition of risk, the recording of risk details and relationships,
and the categorization and prioritization of risks relative to each other.
Source: Project Risk Analysis and Management Guide, 2004, APM Publishing
Page 3-1
Chapter 3
Risk identification, as mentioned in 2-2.3, results in the generation of a risk register. The
risk register can be sizeable; it is necessary to evaluate and prioritize the risk events
identified in the risk register. Evaluation and prioritization is typically accomplished
by the project team and is an iterative process and can take place at various points in
project development. In some cases, the project team may enlist help from cost risk
experts and subject matter experts to evaluate and prioritize the risks.
A thoroughly developed register of risks that may affect project objectives is helpful.
We sometimes find ourselves in situations where moving forward is difficult because of
indecision. Identifying, describing, and assessing project risks allow us to prioritize them.
Prioritization can free us from indecision by providing specific, documented risk events
that we can act on to shift the odds in favor of project success. Prioritizing risks that
present the highest potential for significantly affecting project objectives gives Project
Managers the information necessary to focus project resources. Prioritization helps us
make decisions in an uncertain environment and address project risk in a direct and
deliberate manner.
Exhibit 3-2 offers an example of a qualitative risk matrix. Qualitative analysis can provide
a prioritized list of risks.
Qualitative analysis utilizes relative degrees of probability and consequence for each
identified project risk event in descriptive non-numeric terms (Exhibit 3-3).
3-2
Page 3-2
Chapter 3
Page 3-3
Exhibit 3-1
Chapter 3
Risk-Assessment Terms
Discernment
Judgment
Guess
Decision
Page 3-4
Chapter 3
Exhibit 3-2
Threat or
Opportunity
a
b
c
d
threat
threat
threat
threat
ROW 40.1
ENV 30.1
UTL 20.1
STG 20.4
Risk Title
Impact
Probability
high
very high
low
low
medium
high
very low
very high
RBS #
QUALITATIVE ANALYSIS
10
9
Very High
High
7
6
Medium
4
3
Low
c
1
some
Very Lo to Lo
Impact
Risk
Priority
Ranking
a
b
c
d
2
1
4
3
ROW 40.1
ENV 30.1
UTL 20.1
STG 20.4
RBS #
Hi to Very Hi
10
probability
Very Low
qualitative
risk analysis
Risk Title
Impact
Probability
high
very high
low
low
medium
high
very low
very high
Page 3-5
Exhibit 3-3
Chapter 3
Probability
(likelihood)
[1]
Synonyms
Approximate%
very high
almost certain
very sure
>90%
high
likely
pretty sure
80%
medium
possible
maybe
50%
low
unlikely
seldom
20%
very low
rare
improbable
<10%
Impact
(consequence)
[1]
Synonyms
Approximate%
very high
very critical
very strong
>10%
high
critical
strong
8%
medium
moderate
average
4%
low
mild
minor
2%
very low
very mild
very little
<1%
Page 3-6
Chapter 4
Current Status
Project Management Plan
Scope, Schedule, Estimate
Risk
Management
Planning
Risk Analysis
Risk
Qualitative
Quantitative
Identification
pre-response
analysis
Update
Project Management Plan
Risk
Results of
response actions
4-1
Monitoring
and Control
Implement Risk
Response Plan
TAKE ACTION!
Risk Response
post-response
analysis
General
Quantitative Risk Analysis numerically estimates the probability that a project will meet
its cost and time objectives. Quantitative analysis is based on a simultaneous evaluation
of the impacts of all identified and quantified risks. (Source: WSDOT Project
Management Online Guide.)
The Strategic Analysis and Estimating Office (SAEO) at WSDOT offers several tools for
quantitative analysis of risk. These tools are described in Executive Order E 1053 and
summarized in Exhibit 4-1.
Exhibit 4-1
Required Process*
Page 4-1
Chapter 4
Quantitative techniques, such as Monte Carlo simulation, can be a powerful tool for
analysis of project risk and uncertainty. This technique provides project forecasts with
an overall outcome variance for estimated project cost and schedule. Probability theory
allows us to look into the future and predict possible outcomes.
Note: Use of quantitative analysis, while very powerful, also can be misleading if not
used properly. WSDOT provides a comprehensive guide for risk workshops that, if
followed, helps ensure a consistent process and safeguards against biased and/or
misleading results. The comprehensive set of workshop guidelines is posted at:
www.wsdot.wa.gov/projects/projectmgmt/riskassessment/
The following caution comes from the paper Top Down Techniques for Project Risk
Management by Martin Hopkinson, presented at the 2006 PMI Conference in Madrid.
Poor modeling can produce an output that looks convincing to managers
but is so flawed that the results are dangerously misleading. On a project
with unrealistically tight targets, poor risk analysis may thus become a tool
that fosters management delusions about the prospects for success.
Project risk management is an integral component of ongoing project management.
Project Managers sometimes ask, when is the best time to conduct a CRA or CEVP
workshop? This is answered by reviewing the status of project development. When
a Project Management Plan is being developed and is kept current (i.e., appropriate to
the level of project development), with a well-written scope that can be communicated
and comprehended, along with the associated schedule and cost estimate, a project
team can begin in earnest preparing for risk assessment meetings.
For personalized service and guidance through preparation for the risk assessment,
contact the Cost Risk Estimating Management (CREM) Unit of the Strategic Analysis
and Estimating Office (SAEO). The CREM staff can offer assistance through the process,
including scheduling consultants and WSDOT resources to effect the completion of a
quantitative analysis, through either the workshop process or use of the self-modeling
spreadsheet.
When a project team prepares for a workshop, much of the work that is performed on
a daily or regular basis becomes the input for the analysis. This includes scope of work,
schedule estimate (with backup and assumptions), cost estimate (including the Basis of
Estimate), assumptions, and backup information. Estimates are used to make financial
decisions. Therefore, in order to facilitate this process, materials should be developed
that result in an informed decision-making process. Capital Program Management
System (CPMS) data requirements are listed in Exhibit 4-2.
Page 4-2
Chapter 4
Exhibit 4-2
4-2
Page 4-3
Chapter 4
the project team and cost-risk team; you can also participate in
interviews or contribute opinions in other ways such as surveys
(questionnaires).
The risk register begins during risk identification and is further developed
during analysis (qualitative and/or quantitative). The risk register is a key
component of the Project Management Plan, and includes the following:
Prioritized list of quantified risks: Those risks that have the most
Page 4-4
Chapter 4
Exhibit 4-3
Preworkshop Activities
1. METHOD
a) Project team Determine need:
Confirm project title, PIN, WIN,
mileposts; set up Work Order;
and submit request form.
Assemble project information:
Current Basis of Estimate, cost
estimate, scope of work,
schedule. List issues of concern;
prepare to host the prep session
and risk assessment meeting.
b) CREM Negotiate with
consultants and prepare task
orders; prepare prep and risk
assessment meeting agendas;
provide orientation to the
process.
2. PREP meeting
a) SAEO Risk Lead & Coordinator
Develop flowchart; discuss
project scope of work, schedule,
and cost estimate. Document
assumptions and constraints.
Determine invitees and who will
invite them. Provide Risk
Identification sheets to the
project team; review how to use
them. Develop draft agenda and
plan for attendees.
b) Invitations Invites are sent by
the SAEO and Project Manager.
Invites are sent with a cover
memo and agenda.
3. REVIEW estimates
Project team works with CREM to
begin advance review of cost and
schedule estimates.
Meeting Activities
5. MEETING is convened
Project Manager hosts meeting.
Meeting Leader SAEO and/or
region coordinators direct the
meeting.
Risk Lead takes the lead during risk
elicitation.
Cost Lead takes the lead during cost
and schedule review and validation.
Project team provides:
Meeting venue
Internet connection(s)
Visual aids, such as:
story boards
plan sheets
aerial photos
r/w plans
project exhibits
other items
Project information, including:
Basis of Estimate
project cost estimate
project schedule
backup documentation
environmental documentation
r/w parcels information
r/w cost information
other pertinent information
Meeting Format for CRA/CEVP
Process overview
Review and finalize:
flowchart
base cost estimate
base schedule
base uncertainty
Finalize risk elicitation
Identify potential risk responses
Agree on mitigation meeting date
Postworkshop Activities
6. PERFORM analysis
a) Risk Leads Prepare preliminary
results presentation and draft
report; send to SAEO CREM Unit
for review and comment; then
send to Project Manager and Cost
Lead.
b) Project team Review draft
report; comments go to SAEO,
who works with the cost-risk team
to finalize report.
7. RESPOND to risks
a) Project team Develop and
implement risk response
strategies.
b) Postmitigation analysis CREM
works with project team to assess
impact of responses
c) MONITOR and control Monitor
responses and risks.
7-Step Process
1. Method
2. Prep meeting
3. Review estimates (cost and schedule)
4. Advance risk elicitation and identify uncertainty, initial
5. Meeting convened elicit risk and identify uncertainty, final
6. Analysis and documentation
7. Implement risk response actions, monitor and control
Page 4-5
Chapter 4
In order to fully understand our projects, we must determine what we know and
what we do not know about a project. In our industry, Civil Engineering
Transportation, we have devoted many resources to clearly explain what is known
of a project. We have many specialty offices that gather and provide data in
support of project delivery, including: aerial photography, surveying, site
investigations, bid histories, real estate services, right of way, utilities, access
management, environmental, hydraulics, structures, geotechnical, railroad, tribal,
planning and programming, ad/bid/award, construction, tolling, economic,
programming, external resource agencies and stakeholders, public interest groups,
and others.
Just as important is to devote some energy and resources to assess what is not
known and/or is uncertain about a project. One tool for accomplishing this is
intentional, thoughtful, and deliberate project risk management, as part of an
overall Project Management Plan. Risk assessment is not a measure of estimate
accuracy, as shown in the following:
The project team must examine each critical item and predict its possible extreme values
considering all risks, including compounding effects. It is important to understand that the
range, as considered in this method, is not the expected accuracy of each item. This is a key
issue. Risk analysis is not an analysis of estimate accuracy. Accuracy is dependent upon
estimate deliverables and estimate maturity.
AACE International Recommended Practice No . 41R-08
RISK ANALYSIS AND CONTINGENCY DETERMINATION USING RANGE ESTIMATING
TCM Framework: 7 .6 Risk Management
June 25, 2008
Page 4-6
Chapter 4
Exhibit 4-4
Initiate
and
Align
Project description
Boundaries
Team identification
Team mission
Milestones
Roles, responsibilities
Measures of success
Operating guidelines
Plan
the
Work
EPS/WBS
Schedule development
Estimate/Budget
Risk Management Plan
Change Management Plan
Communication Plan
Quality (QA/QC) Plan
Transition and Closure Plan
Endorse
the
Plan
Endorsement
Risk Planning
The project team, as part of their normal project
development and management activities, need to include
risk management in the work plan.
The team prepares a cost and schedule estimate based
on what is known about the project at that time. The
estimate reflects the project if things go as planned.
The team identifies and characterizes project
uncertainties and risk.
Manage scope,
schedule, budget
Manage risk
Manage change
Communicate
progress, issues, and
lessons learned
Transition
and
Closure
}
Identify and Analyze Risk
Work
the
Plan
Monitor risks
Identify new risks
Evaluate and update risks
Devise and implement response strategies
Determine effectiveness of responses
Report to management and stakeholders
Page 4-7
Page 4-8
Chapter 4
Chapter 5
Current Status
Project Management Plan
Scope, Schedule, Estimate
Risk Response
Risk
Management
Planning
Risk
Identification
pre-response
analysis
Update
Project Management Plan
Risk
Results of
response actions
5-1
Risk Analysis
Qualitative
Quantitative
Monitoring
and Control
Implement Risk
Response Plan
TAKE ACTION!
Risk Response
post-response
analysis
Taking Action
Following identification and analysis of project risks, Project Managers and project
teams must act. Accountability demands a response to identified project risks. Focus
should be directed toward risks of most significance. Effective project risk management
can shift the odds in favor of project success.
Early in project development, activities and information can seem chaotic, coming to us
from multiple directions and multiple sources. Risk management provides a structured
and disciplined way to document, evaluate, and analyze the information, so we emerge
with a well-organized and prioritized list of project risks. This prioritization rescues us
from indecision, with information we can use to direct our project risk management
resources.
In order to maximize the benefits of project risk management, we must incorporate
the project risk management activities into our Project Management Plan and work
activities. This means building risk management activities into our Work Breakdown
Structure (WBS). WSDOT has a readymade WBS in the form of its Master Deliverables
List (MDL) to help ensure our project work plans are comprehensive, consistent, and
complete. As shown above, the risk management steps include: Risk Management
Planning, Risk Identification, Qualitative Risk Analysis, Quantitative Risk Analysis, Risk
Response, and Risk Monitoring and Control.
Risk response requires effort to develop and implement response actions; we must plan
for expending this effort following the results of our risk analysis. To this end, we have a
number of tools readily available, including the Risk Management Planning spreadsheet
( www.wsdot.wa.gov/projects/projectmgmt/riskassessment/).
Page 5-1
Risk Response
Chapter 5
As indicated in Chapter 2, the Project Risk Manager should pay special attention to highimpact, low-probability risks. Team awareness and conscious monitoring of these risks
can be accomplished via team meetings, informing upper management, and seeking
counsel from appropriate experts.
5-1.1 Actions in Response to Risks
Threats
1. Avoid
2. Transfer
3. Mitigate
Opportunities
1. Exploit
2. Share
3. Enhance
4. Accept
EXPLOIT (opportunities)
Action taken to
ensure the
benefit of an
opportunity is
realized.
David Hillson)
TRANSFER (threats)
Action to
allocate
ownership for
more effective
management
of a threat.
Page 5-2
Transferring a threat does not eliminate itthe threat still exists; however, it is
owned and managed by another party. Transferring risk can be an effective way
to deal with financial risk exposure. Transferring project risk involves payment of
a risk premium to the party taking the risk; for example, insurance, performance
bonds, or warranties. Contracts may be used to transfer specified risks to another
party. (PMBOK)
Chapter 5
Risk Response
Transferring risk involves finding another party who is willing to take responsibility
for its management, and who will bear the liability of the risk should it occur. The
aim is to ensure that the risk is owned and managed by the party best able to deal
with it effectively. Risk transfer usually involves payment of a premium, and the
cost-effectiveness of this must be considered when deciding whether to adopt
a transfer strategy. (Effective Opportunity Management for Projects by David Hillson)
SHARE (opportunities)
Action to share
with a third party;
enhance/ exploit
opportunity.
Sharing a positive risk involves allocating ownership to a third party who is best
able to capture the opportunity for the benefit of the project. Examples of sharing
actions include forming risk-sharing partnerships, teams, or joint ventures, which
can be established with the express purpose of managing opportunities. (PMBOK)
Allocating risk ownership for an opportunity to another party who is best able to
handle it, in terms of maximizing probability of occurrence and increasing potential
benefits if it does occur. Transferring threats and sharing opportunities are similar
in that a third party is used; those to whom threats are transferred take on the
liability and those to whom opportunities are allocated should also be allowed
to share in the potential benefits. (Effective Opportunity Management for Projects
by David Hillson)
Hillson)
ENHANCE (opportunities)
Action to
enhance
opportunity.
Page 5-3
Risk Response
Chapter 5
This response aims to modify the size of the positive risk. We enhance the
opportunity by increasing the probability and/or impact of an opportunity thereby
maximizing benefits realized for the project. If the probability can be increased to
100%, this is effectively an exploit response. (Effective Opportunity Management for
The term accept refers to risks that remain after response actions and/or for
which response is not cost-effective are accepted; risks that are uncontrollable (no
response actions are practical) are also accepted. (Effective Opportunity Management
Action taken to
document
acceptance of
the risk.
5-2
Page 5-4
Chapter 5
Risk Response
high
transfer
(share)
avoid
(exploit)
low
Probability
Exhibit 5-1
accept
mitigate
(enhance)
low
high
Impact
5-2.3 Notes
5-2.3.1 General
1. Threat risks that have an estimated high impact and low probability can
create enormous havoc for a project. These types of risks are frequently
neglected when it comes to project risk managementbut they deserve
our attention. A high-impact risk with a low probability may have a
moderate expected value for ranking purposes, but it is much more
important than the ranking might reveal. It is these types of risks that
we read about in the news because they are not given the aggressive
risk response they merit. Pay attention to these risks!
2. Do not underestimate threats and the need to respond.
3. Most people pay attention to high-impact risks with high probabilities
as is appropriate.
4. Insignificant risks do not belong on the risk register and minor risks may
be aggregated or put on a list of things to look out for.
Page 5-5
Risk Response
Chapter 5
Page 5-6
Chapter 6
Current Status
Project Management Plan
Scope, Schedule, Estimate
Management
Planning
Risk
Identification
Update
Project Management Plan
Risk
Results of
response actions
6-1
Monitoring
and Control
Implement Risk
Response Plan
TAKE ACTION!
Risk Analysis
Qualitative
Quantitative
pre-response
analysis
Risk Response
post-response
analysis
General
Perhaps the phrase control is an illusion is familiar. Maybe weve had experiences
when this was true; however, this phrase does not tell the whole story. We may have
little or no control over the external environment, but we do have control over how we
interact with it. We have control over our state of readiness; we can look ahead and
improvise and adapt. We can actively monitor significant project risks, including highimpact, low-probability risks, and control the robustness of our response to identified
risk events and the quality of our documentation. Very importantly, we have control
over how earnestly we integrate risk management into our Project Management Plans.
Page 6-1
Chapter 6
The Project Manager and project team apply their Project Management Plan
through project development and completion of their deliverables. Monitor
the project status, looking for trends that can indicate variations (good and bad)
in the project execution. Results of the analysis need to be communicated and
adjustments made through a change management and/or issue resolution process.
The ability to describe the history of the project and how it evolved is essential to
developing lessons learned for the future.
Helpful Hints
Be thorough and tenacious in gathering status update information for
risks.
Monitor status and trends continually (scope, schedule, cost estimates,
quality of product, etc.).
Address problems and issues immediately; in fact, anticipate and discuss
in advance if possible.
Communicate.
6-1.2.3
Page 6-2
Chapter 6
The spreadsheet is conveniently arranged into four sections: (1) risk identification,
(2) risk analysis, (3) risk response, and (4) monitor and control. In this chapter, we
focus on monitor and control.
Exhibit 6-1 focuses on the second pillar of risk management, as recorded in the RMP
spreadsheet, and indicates how to use the entries to document the risk response
actions and their effectiveness in the monitoring and control portion of the spreadsheet.
Exhibit 6-1
The following pages describe how to use the RMP spreadsheet to monitor and control
project risk.
Page 6-3
Chapter 6
Notice that the first group of columns in the RMP spreadsheet is devoted to IDENTIFY
and ANALYZE: the first pillar of risk management (see Chapter 2). The remaining
columns are devoted to the second pillar of risk management: RESPONSE, MONITOR,
and CONTROL.
In Chapter 5, we reviewed in some detail risk response actions; in this chapter, we
follow up and follow through with monitoring and control. The way we monitor and
control risk is to regularly review the effectiveness of the response. Are the response
actions working? Are things getting better? Are we more confident about our ability
to meet project objectives after the response actions have been implemented?
In effect, response, monitor, and control are natural components of our day-to-day
project management activities (e.g., communicate with the project team and ascertain
how things are going; make note in the Risk Management Plan and document the
results).
It is always prudent to quantify and analyze the project risks. Although a project may
have very few risks, which may appear easily manageable, some of these risks could
have a high likelihood of occurring or a high impact. Only by initiating a quantitative
analysis will the likelihood, value, and impact of these risks be identified.
In Exhibit 6-2, the example project had identified over 50 risks, of which 23 were
deemed significant enough to warrant inclusion in the quantitative risk analysis model.
There were only 5 that emerged as the top-ranked risks. These few had the expected
value of $7.1M and provided the Project Manager with the appropriate prioritized list
of risks to manage. The other 40+ risks were not simply ignored; they provided issues
awareness for the various specialty groups and were dealt with as each specialty group
deemed appropriate for the relevant risks. These additional risks also acted as a watch
list for the project.
Exhibit 6-2
Page 6-4
Total Estimated Cost Impacts of Top 5 Risks for the Example Project
Chapter 6
Exhibit 6-3 depicts a performance measure for the effectiveness of risk management
on this project.
Exhibit 6-3
When reporting on the risk management efforts for this project, we can summarize as
follows:
The total dollar amount planned for response actions was $0.6M, to achieve
reduced project risk exposure by an estimated $3.8M (expected value of risk
reduction). After implementing the response actions, we found the total cost
of the response actions was $0.7M, which avoided an estimated $3.7M in
project costs.
This example illustrates an excellent return on the dollar for risk management efforts.
Other benefits, less quantifiable, included:
Improved communication among team members and externally with
Identified areas of concern for each specialty group as it helped develop the
Greater confidence by the Project Manager and project team during project
development.
Page 6-5
Page 6-6
Chapter 6
Chapter 7
7-1
Project Risk
Management Plan Template
General
A project Risk Management Plan (RMP) describes how a project team will incorporate
the risk management process into its Project Management Plan. Particular emphasis
should be given to how a project team will respond to risks and monitor and control
risk throughout the life of the project. By identifying and analyzing risks, and then
responding to risks aggressively and monitoring the effectiveness of the response,
project teams can improve the odds of meeting project objectives.
The template in Exhibit 7-1 is a convenient tool for project teams wishing to develop
a detailed Risk Management Plan document; typically, this is more common for highly
complex projects and/or projects with significant risk.
The template presents an organized approach and is meant as a starting point only;
project teams must tailor the document to meet the needs of the Risk Management
Plan for their project.
7-2
6.
7.
8.
9.
Risk identification
Risk assessment and analysis
Risk Response actions/allocations
Risk monitoring and control
Page 7-1
Exhibit 7-1
Chapter 7
###,
MP
limits:
__________________________________Project Manager:_______________________________
__________________________________Risk Manager:__________________________________
__________________________________WIN:_________________________________________
PIN:__________________________________
L#:___________________________________
Introduction
This document is the Risk Management Plan for this project. It is a plan of action that describes
how this project team will deal with uncertainty and risk. Project risk management is an ongoing
and integral part of project management and is performed throughout the life of the project.
The Project Manager is responsible for reviewing and maintaining the Risk Management Plan
to ensure that risk is appropriately dealt with by the project team.
Project Manager Review
Initial and date after each review and update of this Risk Management Plan:
Year
Quarter 1
Quarter 2
Quarter 3
Quarter 4
2015
2016
2017
Page 7-2
Chapter 7
7-3
www.wsdot.wa.gov/projects/projectmgmt/
Page 7-3
Exhibit 7-2
Chapter 7
Project
Manager
Project Team
Member
Page 7-4
Chapter 7
MDL Name
Cost Risk
Estimate &
Management
Description
Cost Risk Assessment (CRA) is an integral element of project risk
management at WSDOT, and quantifies, within a reasonable range,
the cost and schedule to complete a project. We will identify, assess,
and evaluate risk that could impact cost and/or schedule during
project delivery.
PE.PD.04.20 CRA
CRA is a workshop process similar to, but less intense than, Cost
Workshop
Estimate Validation Process (CEVP). The CRA workshop for this
project is planned for January 2015 and is included in the project
schedule; pre- and postworkshop activities are also included in the
project schedule.
Note: Project teams need to add tasks and subtasks as appropriate to their project work activities
using the appropriate MDL items.
Page 7-5
Chapter 7
Page 7-6
Chapter 7
7-4
As a project develops, its risk profile will change. Risks are identified, and response
actions are implemented, which changes the nature of the project risk profile and new
risks are identified. During risk identification, we identify risk events. The first time this
is accomplished, it constitutes a list of primary risks; as actions are taken, secondary
risks can emerge as a result of implementing the treatment response to the primary risk.
2
3
This is also referred to as risk treatment, risk mitigation, risk management, or risk prevention in some publications.
Practical Risk Management by David Hillson and Peter Simon (with edits).
Page 7-7
Chapter 7
Where possible, we will deal with secondary risks as part of the primary risk response
action. When developing our response actions, we will be vigilant in considering the
ramifications of the response actions. We will take measures to include strategies
that deal with the primary risk as well as secondary risks and endeavor to minimize
or eliminate residual risk as part of risk response efforts.
7-4.2 Risk Monitoring and Control
Monitoring and control are not complete unless communication has occurred.
COMMUNICATION is the lynch-pin of effective project management and risk
management.
Communication within and among the project team will be crisp, concise, complete,
correct, and timely, as will the communication to upper management and executives.
Effectiveness of the risk response actions will be monitored and reported regularly,
as indicated previously, at our project meetings; adjustments will be made as needed.
7-4.2.1 Risk Monitoring and Control (Communication)
Project Team
o
o
Accountability
o
Page 7-8
The Project Manager must specify criteria for risk management success,
including targets and measures used to assess performance.
Follow up with risk owners regarding the status of completing the risk
response actions and the resulting effect; track resource allocation(s)
associated with risk response actions.
Chapter 7
Exhibit 7-4
CRA
Workshop #3
CRA
Workshop #4
Workshop Date(s)
CRA
Workshop #1
CRA
Workshop #2
CRA
Workshop #3
CRA
Workshop #4
CRA
Workshop #1
CRA
Workshop #2
CRA
Workshop #3
CRA
Workshop #4
ENV
STG
DES
ROW
UTL
RR
PSP
MGT
CTR
CNS
Number of Risks
Value of Threats $
Value of
Opportunities $
Page 7-9
Page 7-10
Chapter 7
Part II:
Guidelines for
CRA-CEVP Workshops
(Includes Common Assumptions)
CRA-CEVP
Project Risk Assessment
Section A
A-1
Purpose
This document establishes consistency in project risk assessment and risk-based
estimating at the Washington State Department of Transportation (WSDOT). Guidance
is provided for: Project Managers, project teams, Risk Leads, Cost Leads, region Cost
Risk Assessment (CRA) Coordinators, and subject matter experts (SMEs). The Cost Risk
Estimating Management (CREM) Unit, part of WSDOTs Strategic Analysis and Estimating
Office (SAEO), delivers the project risk assessment and risk-based estimating program
for WSDOT. Projects vary in terms of size, location, and complexity. The process
can be tailored to the needs of the project. Risk assessments are accomplished through
the committed and diligent work and contributions of our partners in the consulting
community and WSDOT staff who contributed to the development of these guidelines.
Three questions are fundamental to the search for a more accurate estimate on
projects:
(1) How much will it cost?
(3) Why?
Page A-1
Section A
A-1.1
1
2
3
4
5
6
7
*Use as a quick reference; more detailed information is found throughout this document.
Page A-2
Section A
A-1.2
Statement of Purpose
The purpose of cost risk assessment is to: (1) provide the Project Manager and project
team with actionable information that can be used to shift the odds in favor of project
success, and (2) provide a useful, sound, and objective analysis and report that the
project team will own and act upon to improve, as well as to validate and confirm, their
project cost and schedule.
The following steps should be followed by those embarking on a project risk
assessment; the process provides a number of tangible benefits:
1. Review or validate base estimates of cost and schedule using WSDOT specialists/
estimating experts to serve as Cost Leads and to schedule reviewers, subject
matter experts, and others as appropriate.
2. Document assumptions and constraints to develop the estimated project cost and
schedule ranges.
3. Replace (or greatly reduce) the traditional project contingency with defined
risks that can be more clearly understood and managed.
4. Identify and quantify major risk events in a project that can cause significant
deviations from the base cost or schedule.
5. Use a Monte Carlo simulation analysis that models the collective impact of base,
uncertainties, and risks for the project to produce an estimated cost and schedule
range.
6. Develop possible responses to risks. Promote proactive risk management by
project teams. Provide the project team with actionable information on risk events
that allows them to manage the risks (threats/opportunities) on an ongoing basis,
to better control project costs and schedules.
7. Perform a post-response analysis to ascertain the effectiveness of planned
and/or implemented risk response actions.
The project risk management performance can be measured by the Project Manager or
risk analyst by comparing premitigated to postmitigated results, then identifying risk
responses to ascertain the amount of risk relief to be accomplished through risk
management efforts.
The workshop process provides a tool for the project team to evaluate the quality and
completeness of the current project estimate. It is intended to increase confidence in
the project cost and schedule forecasts and to identify areas of uncertainty.
The workshop process is not intended to recreate the wheel or second-guess the
project team. It is not a substitute for other necessary project management functions
such as project control and value engineering.
Page A-3
Section A
A-1.3
1.
2.
3.
4.
5.
6.
7.
A-1.4
A-1.4.1
Critical Participants
The main criterion for project workshop participation has to be, Who is absolutely
critical to identify the problems we are dealing with? The criterion of criticalness
should include not only technical expertise and responsibility, but also problemsolving and team skills. Workshop participants should:
1. Be involved
2. Be heard (in relation to their responsibility and/or expertise)
Page A-4
Section A
Recommended Participants
Preparation for the workshop may take one or several meetings depending on the
project size and complexity, and the knowledge of the participants. The Project
Manager/project team should work with the workshop coordinator and cost-risk team
(described below) to identify the best combination of participants at each meeting
(Exhibit A-1). All participants do not need to attend all meetings. The goal is to
effectively use time for all parties in a manner that ensures a sound and objective
analysis (Exhibit A-2).
Exhibit A-1
Estimator*
Scheduler*
Lead Designer*
Key Technical Experts
Subject Matter Experts
Project Team Experts
Agency Experts (HQ, et al.)
Other Stakeholders
External Consultants
Cost-Risk Team Members
Risk Lead*
Risk Lead Assistant
Cost Lead*
CREM Workshop
Coordinator
Page A-5
A-1.4.2
Section A
Preworkshops
The Project Manager, working with the SAEO, accomplishes the prep activities in
Exhibit A-2.
Exhibit A-2
Preworkshop: Determine Need, Learn the Process & Assemble Project Information
Strategy Session
Orientation Session
Note: The best workshops, in terms of being effective and efficient, are those that have had
ample advance work conductedparticularly in the areas listed above.
Page A-6
Section A
A-1.5
A-1.6
The process, when properly followed, provides a sound base estimate and identifies
risk events that can cause the project to turn out differently than planned. Attempting
to revise estimates for the analysis outside this framework can make it difficult to
disentangle effects and can make the management of risks less effective.
Identification and quantification of risk events will provide the project team with
knowledge regarding identified risk events. The Project Manager must decide what
action to take in response to the identified risks: avoid, transfer, mitigate, or accept
the risk. Decisions regarding risk management may affect project budget and schedule.
The human element introduces an additional layer of complexity into the risk process, with a multitude of influences both
explicit and covert. These act as sources of biaswhich affect every aspect of risk management. (Source: Understanding and
Managing Risk Attitude by Hillson and Murray-Webster.) In our processes, we attempt to condition (prepare) participants to
be aware of bias and make efforts to avoid and reduce bias in workshop inputs.
Page A-7
A-1.7
Section A
3. The Cost Lead reviews the basis for the estimate of project cost and schedule
durations, and discusses it with the project team member(s) who prepared
and/or compiled the estimate.
4. At the prep meeting, remind the project team to work up initial lists of risks to
the projectboth threats and opportunitiesthat have the potential to cause
the project cost/schedule to be significantly and measurably different than
planned.
5. Inform participants that it is okay to have outcomes significantly different from
what was plannedas long as they are plausible. At a very early stage of design,
the divergence from planned values is expected to be greater.
A-1.8
"Judgment Under Uncertainty: Heuristics and Biases" Tversky & Kahneman, 1974
Page A-8
Section A
A-1.8.1
The anchoring and adjustment bias is the phenomenon of experts thinking they know
more than they actually do. If you ask an expert for their best guess first, they will tend
to provide inadequate ranges. Following are better ways to reduce biased answers:
1. Ask experts for the limits of the potential ranges first.
2. When providing extremes, experts should be able to describe the type of outcome
that will generate the extreme case.
3. Ask the expert for a plausible low and plausible high. These can be treated in
a variety of ways by the analyst who quantifies the risk. A standard needs to be
established.
a. One method is to ask the expert for a plausible minimum and plausible
maximum.
b. Another method is to ask the expert for a low and high percentile (i.e., 10%
and 90%), and then use this information to generate the distribution.
c. A third method is to request another low and high percentile that the expert
wishes to provide.
4. After obtaining the highs and lows, ask for the experts most likely value.
A Note on Risk Identification and Assessment
Consider: Those relatively new to risk analysis sometimes claim that it is nothing more
than guessing. However, this view does not represent the actuality that assigning
values for probability and impact relies on the expertise and professional judgment
of experienced participants. The determination of a value for the probability of
occurrence and its consequence to project objectives, if it occurs, is a new activity
for many people, and can seem strange at first.
In any field, with experience, professionals develop intuition and an ability to
understand projects to a greater degree than those not involved with project
development and delivery in their industry. This experience and intuition is extremely
valuablein a risk workshop forum we surround ourselves with wise counsel to
seriously and thoroughly discuss the project. It might be helpful to examine the word
guess and compare it to other words, such as discernment and judgment, that
more appropriately describe risk assessment (see Exhibit 3-1 in Part 1 for the
definitions and synonyms).
Page A-9
A-1.8.2
Section A
Availability Bias
Experts are always receiving new information to add to their knowledge base.
Frequently, when approached for their judgment, experts will have recent information
that they have not had time to blend in to their knowledge base.
One practical way to address this information availability bias is to ask the expert
a simple follow-up question regarding the issue being elicited: Is there recent
information you are using to provide your judgment? If the answer is yes, then ask,
How does that new information weigh in relative to all the other information you have
accumulated over the years? If the availability bias exists here, the expert will often say
something like, Thats a good question; let me think about it and get back to you or
Ive thought about it and I have given the new information the proper weighting.
A-1.8.3
This is the case where experts have base information, but dont use it. Instead, they
match an event with a stereotypical case. Biases, in expert response, can potentially
lead to understating the range, so it is important that the risk elicitor properly prepare
participants, and monitor and question participants if a bias is detected.
A-1.9
Conflict Resolution
Although uncommon, there may be situations where a significant difference of opinion
has arisen between workshop participants, either during or following the workshop.
There are many resources and references on the topic of conflict management and
conflict resolution. This workshop guide is not a substitute for those resources, many
of which can be found at libraries and bookstores. However, a progressive process for
resolving such disagreements at workshops is offered below:
1. Capture the difference as a range
One benefit of the CRA/CEVP workshop process is that it allows input in the form
of ranges and percent probabilities. Usually, the ability to capture input in ranges
meets the needs of participants offering input. For example, if one participant
states, This risk event could cause $1 million in additional cost, and another
says, This risk event could cause up to $3 million in additional cost, we can
simply offer to capture the risk with a $1 million to $3 million impact range.
Typically, this will satisfy the parties with differing opinions about the impact.
(Note: Participants offering opinions should be able to state why they have the
opinion and document the information used to develop the opinion.)
2. Evaluate different scenarios
If we are not able to resolve the difference by capturing it as a range, in some
cases it may be appropriate to evaluate additional scenarios that address the
different opinions being offered. This is practical in some casesto a point. Having
too many scenarios can add cost and complexity to the workshop and may not be
necessary or helpful to the overall evaluation of the project.
Page A-10
Section A
A-2
A-3
A-3.1
Page A-11
Section A
event occurs)
Relationship with other events (independent versus correlated with other events)
Focus on significant risks (particularly include those risks that are high-impact, lowprobability)
Nature of Event Occurrence
Frequency of occurrence
Number of occurrences during the project
Number of potential outcomes (consequences)
Event is independent or correlated with other events or among project activities
Consequences of Event Occurrence to Project Objectives
Defined in terms of cost impacts, schedule impacts, or both
Uncertainty in event outcome
Elicitation 3 can be accomplished in a number of ways and may utilize any one or
a combination of the following approaches:
In the workshop
Through a questionnaire
Through interviews of individuals or small groups in advance of the workshop
By teleconferencing
Other methods
Elicit To draw forth; to bring out from the data in which they are implied. To extract, draw out (information) from a
person
Page A-12
Section A
Weed out smaller, less significant risks that do not warrant inclusion in a
formal quantitative analysis; these can be summarized into a watch list
for the project team
Guidance on:
o
o
A-3.1.1
Anchoring
Worst- and best-case scenarios for consequences
Elicitation of Subgroups
Rather than having everyone attend every elicitation session, subgroups can in some
cases provide a more efficient and effective approach to help ensure a properly focused
elicitation with the correct SMEs present. This approach can help keep the number of
individuals in the meeting to a manageable size. Group dynamics may begin to
deteriorate after a group reaches a certain large size (i.e., many contributions but not
necessarily from knowledgeable participants), and subdividing the elicitation provides
a practical offset to the size problem. The subdivision of elicitation can happen on the
same day, which could allow each of the Risk Leads to take a group into a separate room
for elicitation.
The following elicitation subgroups have been used:
1. Right of Way, Utilities, and Railroad
2. Environmental, Cultural Resources, Stormwater
3. Structures, Geotech
4. All Others: Design, Traffic, Work Zone Traffic Control, Constructability (staging/
sequencing), scope issues/uncertainties, public pressures/opposition, local
jurisdiction concerns, local market conditions/uncertainties, uncertainty in the
base, management, and other costs.
A-3.2
Page A-13
Section A
Report Preparation
The workshop report, which documents the results and process followed, is built in
service of and to support the project teams risk management and project delivery
efforts. Report preparation is a collaborative effort primarily between the project team
and the cost-risk team, with final control of editing and publishing the report resting in
the hands of the Project Manager. Exhibit A-3 provides a guide/checklist for report
writing and Exhibit A-4 provides a flow chart.
A-3.3.1
Draft Report
The draft report is due two weeks after the workshop (or after the final inputs
document has been provided to the risk modeler). Every attempt should be made
to provide inputs by the final day of the workshop. Allow one week for comments.
A-3.3.2
The final report (Exhibit A-5) is due two weeks after the draft report is delivered (one
week after comments are due). This report should be ready and complete with the onepager summary of the analysis and Risk Management Plan spreadsheet. If no comments
are received for the draft report, the draft report becomes the workshop report of
record.
Page A-14
Section A
Exhibit A-3
Page A-15
Exhibit A-4
Section A
START
Project Manager
determines need for risk
assessment report.
Cost Lead
Review cost/schedule
Validate cost/schedule
Prepare report write-up
Risk Lead
Make notes
Identify major risks
Provide mitigation options
All parties involved in the report writing and review process are accountable for ensuring the
quality, accuracy, and completeness of the material they produce that is to be included in the
report. The Cost Estimate Validation Process utilizes teams of experts working on behalf of
the project team.
Page A-16
Section A
Exhibit A-5
Workshop Report
Responsible Party
Project Manager
and Project Team
Members
Subject Matter
Experts
Risk Lead
Cost Lead
CREM Unit
Workshop
Coordinator
A-3.4
Responsibilities
The Project Manager, along with the project team, just as they did before the
workshop, owns the Project Management Plan, and all project development and
delivery responsibilities. This includes all project cost and schedule estimates and
the Risk Management Plan. The Project Manager uses the information in the
report in aiding and assisting their risk management and project management
activities.
During the workshop process, the subject matter experts are responsible for their
opinions and the objective advice offered during the workshop and report
preparation.
The Risk Lead is responsible for: preparing workshop participants; conducting the
risk elicitation; the modeling, analysis, and conclusions to be drawn from the
analysis; and writing the Risk Lead portion of the report. The Risk Lead uses a
quality control (QC) checklist as a guide to ensure an effective workshop
experience that results in a sound and objective analysis of project costs,
schedules, and risks. The Risk Lead clearly identifies candidates for mitigation
and possible strategies for mitigating these key risks.
The Cost Lead is responsible for reviewing and validating the project cost estimate
and schedule, and preparing the Cost Lead portion of the report.
The workshop coordinator is responsible for ensuring the appropriate participants
are in attendance at the appropriate times. In addition, the workshop coordinator
or others in the CREM Unit will perform the review of the report against the QC
checklist.
Required
Data
In order to load agency management systems and provide budget information, specific
data needs to be provided to the region program management offices. This data is then
loaded into the Capital Program Management System (CPMS) and transferred to the
Transportation Executive Information System (TEIS) for use in gaining budget approval.
A-3.5
Management Endorsement
Along with the data provided by the project team, agency management endorses which
costs are to be used and the schedule to be assumed. Guidance on use and reporting of
CEVP/CRA results and CPMS data requirements are provided in Instructional Letter
4071 posted at: http://wwwi.wsdot.wa.gov/publications/policies/fulltext/4071.pdf
Page A-17
A-4
Section A
A-4.1
Preparation
The project team, Project Manager, appropriate specialty groups, and appropriate
stakeholders must perform a reasonability check on materials developed prior to the
workshop. The Cost and Risk QC checklist provided in Exhibit A-6 should be used by
the Project Manager to ensure the project team is ready for the workshop. When the
workshop is convened, most attendees should already be familiar with, and have had
an opportunity to comment on, the scope, schedule, and cost estimate that the project
team has developed. The scope, schedule, and cost estimate will be the subject of
review and analysis at the CRA or CEVP workshop. At the discretion of the CREM Unit,
region Risk Manager, or Project Manager, the workshop may be postponed if the cost
and risk quality control checklist items are not all satisfactorily completed.
Exhibit A-6
Page A-18
Section A
A-4.2
A-5
Page A-19
Section A
Over time and as the project matures, the project risk profile will change. Typically, as
risks are successfully dealt with and project knowledge increases, the risk exposure will
diminish.
When it comes to Cost Risk Assessment, remember
It is iterative in nature and represents a snapshot in time of that project for
It normally deals with identifiable and quantifiable project-type risks (i.e., those
events that can occur in planning, design, bidding, construction, and changed
conditions).
at this point, these risks are generally not included. This is an area for review
and developmentin particular, how to characterize such events in a useful
manner for better management of the projects. All exclusions and assumptions
need to be clearly documented in the workshop report.
An event or effect that cannot be reasonably anticipated or controlled compare ACT OF GOD
Page A-20
Section B
B-1
Description of Work
Project teams typically look to the Cost Risk Assessment/Cost Estimate Validation
Process (CRA/CEVP) workshop process as a tool to help improve the accuracy,
consistency, and confidence in their project cost and schedule estimates. This process
also helps Project Managers and project teams with their project risk management
efforts, a required component of all Project Management Plans.
During this collaborative process, uncertainty within a project is identified and
quantified. Development of risk-based estimates through the CRA/CEVP workshop
process is a collaborative effort between the project team, experts in cost and risk
analysis, and external subject matter experts. The two main elements of an estimate
are: base cost, which represents the cost if the project materializes as planned, and risk
events, a combination of the probability of an uncertain event and its consequences. A
positive consequence presents an opportunity; a negative consequence poses a threat.
Note that risk events are separate from variability that is inherent in the base.
Project schedules and cost estimates are owned by the project teams, and they must be
updated regularly. This may involve conducting workshops periodically (typically, every
one to two years). The workshop effort begins with a request from the project team. The
process focuses on the project team for input of primary information; the project team
utilizes the workshop results as they deem appropriate, to more effectively manage their
projects.
Workshops are usually held early in project development (Exhibit B-1), from late planning
to the early stages of developing the contracts plans, specifications, and estimate (PS&E).
Risk management is an ongoing project management activity; the Project Manager and
project team should continue to proactively manage risk up until advertising the
contract. Continuing risk management and risk assessment should look at the knowledge
gained through the workshop process, and pay particular attention to evaluating the
sequence of construction activities and scheduling through completion of the PS&E.
Page B-1
Exhibit B-1
Section B
Timing of Workshops
B-2
Page B-2
Section B
To ensure workshop quality and effectively use the participating subject matter experts,
the Project Manager and project team do the following:
Submit CRA/CEVP workshop request forms at least 8 weeks prior to the
workshop; for some projects, such as SR 520 and AWV, Project Managers have
asked that the forms be submitted at least 12 weeks in advance.
The items above need to be completed and turned in early so that workshop
participants can learn the basic elements of the project and begin review of cost
estimate key items. Project estimate review and risk assessment are the main
workshop topics.
B-3
The Project Manager is to ensure the availability of project team members who can
speak to the issues raised in the workshop and are familiar with the documentation.
The project team must be prepared to identify applicable risk elements (global and
project-specific), the interrelationships of the risks, and the characterization of the risks
in terms of likelihood and impacts. If the project team is interested in pricing the project
for different delivery methods (e.g., design-bid-build vs design-build), they need to be
prepared to discuss this.
Page B-3
Section B
The project team, working collaboratively with the workshop team, should be prepared
to discuss and determine:
Exclusions.
Funding
Programmatic issues
Others
Adequate subject matter expert participation.
Authority to ensure input is objective.
The optimal process balance between effort and accuracy; level of analytical detail; and
how to handle dependence, correlations, and distributions.
The probabilistic risk-based integrated cost and schedule modeling needs.
Global versus project-specific risks and other uncertainties.
Treatment of base uncertainties.
B-3.1
Page B-4
Section B
Page B-5
Page B-6
Section B
Section C
C-1
Description of Work
Risk Leads participate in a peer-level review or due diligence analysis on the scope,
schedule, and cost estimate for various projects to evaluate quality and completeness,
including anticipated risk and uncertainty in the projected cost and schedule.
selected projects.
These functions are critical to WSDOT's success in delivering projects on time and on
budget. It is anticipated that Cost Risk Assessment (CRA) and Cost Estimate Validation
Process (CEVP) reviews for each project can be accomplished in a reasonable time
frame, including a 1- to 5-day concentrated workshop. WSDOT personnel, with the
aid of multiple specialty groups, will coordinate CRA/CEVP. Work may include the
documentation of the viability of assumptions made regarding a project's configuration,
scope, schedule, character, and, through risk analysis, the potential impact of risk events
that may occur. The project may include creating reports that document information
determined or discovered.
Risk workshops vary based on project needs, but include risk identification, probabilistic
risk assessment, development of management strategies, a probabilistic look at the
effectiveness of management strategies, and other variants. The Risk Lead must use
consistent methodology for probabilistic risk assessments.
Flowcharts should as simple as possible but still represent the project activities in a realistic manner, with proper sequence
and durations (Exhibit C-1).
Page C-1
Section C
The Risk Lead plays a vital role in ensuring the analysis is sound and objective. It is also
imperative that the analysis process and results are clear and usable by the project
team. The process, as documented, must include the underlying assumptions and
constraints of the analysis in a manner that is easily comprehended by the project team,
who will have to communicate the results of the workshop to others. The report should
tell the story of the project scope, schedule, and cost estimate.
Exhibit C-1
Flowchart Example
Flowchart Activities
DESIGN (18 mo)
Env. Doc.
(EA/Tech
Reports, BO,
NEPA/SEPA)
(6 mo)
(Plans, Acquisition)
(17 mo)
Mitigation area
acquired
(county)
(16 mo)
End CN
ROW
FS
-2
M
Const.
A/B/A
(3mo
wsdot)
Const.
(wsdot)
(36 mo)
Permitting
Start Date:
12/1/2008
(12 mo)
This flowchart is simple and easy to follow. It meets the needs for risk modeling.
Page C-2
Section C
Exhibit C-2
PRECONSTRUCTION
Assumed Ad
Date
Summer
(June)
2016
WSDOT
PERMITTING
AGREEMENTS
FUNDING
FONSI DEC 2013
September
2011
Assume
3 mos (ABA)
CONSTRUCTION
January
2013
END
Construction
August 2021
Notice that this very simple flowchart is often all that it is needed. It focuses on the two
dates of most interest: the Advertisement Date and Completion of Construction.
Page C-3
Page C-4
Section C
Section D
D-1
Description of Work
The Cost Lead serves as the major subject matter expert for cost estimating and leads
and directs those portions of the Cost Risk Assessment/Cost Estimate Validation
Process (CRA/CEVP) devoted to review or validation of the project base cost estimate.
The Cost Lead commits to supporting the cost risk assessment effort and the quality of
input and analysis.
D-1.1
D-1.1.1
Page D-1
Section D
3. Provide a written report on the base cost estimate review and validation, and
schedule the review for inclusion in the risk analysis workshop report to the
project office and CREM Unit. The report is due within one week following the
end of the workshop or earlier if required and agreed to at the workshop.
D-1.1.2
Typical cost questions to be asked by the Cost Lead and subject matter experts:
Have you completed the Project Estimate Basis form? What is the basis of the
Page D-2
estimate?
o How current is it? When was it updated?
o Do unit prices correlate to similar scope projects in the area? Are they
truly comparable?
o Does the current scope of the work match the scope that the estimate
is based on?
o Does the estimate include engineering, engineering services during
construction, construction management services?
What is the stage of the design?
What is the accuracy of the survey data?
What field investigations have been done? Describe the existing conditions.
What geotechnical work has been done to date? Is there data from past
projects in the area?
Cuts and fills: What has been assumed for reuse, import, export and disposal,
temporary stockpiling, haul distances, location of imported materials?
Are there assumptions on compaction? Seasonal variability?
Are there assumptions on stability of cuts, sheeting, retaining walls, slope
protection during construction?
If dewatering is required, are there perched water tables and other
maintenance of excavations during construction, treatment of dewatering to
meet permits?
ROW: How current are surveys and estimates of costs? Partial or full parcels?
Are there temporary utilities, staging areas, parking storage, lay down?
Is there knowledge of utilities in project area, relocation requirements, ability
to isolate and shutdown? Are replacements needed prior to isolation? Can
replacements be installed at proper elevation?
Is there erosion protection?
Are there special conditions: extraordinary staffing requirements, night work,
stop times due to fish or wildlife issues, noise limits, dust control?
What has been assumed for overhead, insurance, bonding, project
management, safety, QC community liaison, trailers, utilities, parking, home
office overhead, profit?
Are there assumptions for material availability: backfill, sheeting, piles,
concrete, rebar access for delivery, double handling requirements?
Section D
Are production rates assumed? Is this work similar to other work done in the
D-1.1.3
area?
Are there assumptions for maintenance of traffic, staging of construction,
needed temporary barriers, ramps, bridges, supports, technology?
Is there estimated mitigation, noise walls, stormwater detention ponds,
wetlands?
What contingencies are built into the estimate?
Has a change order allowance been built into the estimate?
Typical Schedule Questions
D-1.1.4
schedule?
In what season is it expected that the Notice To Proceed (NTP) will be issued?
Will certain months be lost due to the start date?
If the NTP is issued as planned, can the landscaping be completed in the
required season for the specified plantings?
Has mobilization and demobilization time been included in the schedule? How
many workers are assumed to be working on the project at the peak of
construction?
Does the construction phasing and traffic management plan match the schedule
assumptions?
How many concurrent work areas are assumed? Are there crews available to
staff all of those areas?
What are the assumed production rates for each of the major elements:
earthwork, foundations, piers, beams, deck, subbase, base, paving, etc.?
Tips for Cost Leads
1. The project team owns the estimatelet them establish what they want out
of the process.
2. Dont get bogged down in details; keep the discussion relevant to the overall
size of the project and commensurate with the level of design at the time of
the analysis. For example, dont waste a lot of time discussing a $100,000 item
on a $50,000,000 project.
D-2
Page D-3
Section D
Cost Leads need to take the time to listen to the project team explain the history of
the estimating process for their project. While the project team talks through how
the estimate was generated, they are mentally checking that the process is correct.
Following is a step-by-step guide through the assessment process for Cost Leads.
D-2.1
D-2.2
D-2.3
D-2.4
D-2.5
Page D-4
Section E
E-1
Description of Work
Cost Risk Estimating Management (CREM) is a program created and developed to
better estimate transportation projects. The CREM Unit is part of the Washington
State Department of Transportation (WSDOT) Strategic Analysis Estimating Office.
The program provides the framework for two comparable processes: Cost Estimating
Validation Process (CEVP) and Cost Risk Assessment (CRA). These processes involve
intensive collaborative workshops where transportation projects are examined by teams
of top engineers, Risk Managers, and external and internal subject matter experts
(SMEs) from local and national private firms and public agencies, and from WSDOT
specialty groups within the project team.
Page E-1
Section E
Stay aligned to the workshop process and focus on fulfilling the ultimate
Be familiar with the WSDOT process for CRA and CEVP workshops, including
Page E-2
Section F
F-1
Description of Work
Cost Risk Assessment Coordinators1 help accomplish the Cost Risk Assessment/Cost
Estimate Validation Process (CRA/CEVP) program in accordance with department
policy and guidelines. It is expected that the Headquarters (HQ) CRA Coordinator will
provide direct support and coordination to project teams around the state. For those
regions that have a CRA Coordinator, the HQ CRA Coordinator will work with the region
CRA Coordinator to ensure the effective use of CRA/CEVP workshops in the regions.
Project Managers and project teams use the workshop results to actively manage risk.
Project teams know the details of their projects; cost-risk teams know the workshop
process, modeling, and the goals of the risk analysis effort, and the limitations of risk
analysis. The region CRA Coordinator should be familiar with Washington State
Department of Transportation (WSDOT) resources available in the field of cost-risk
management.
F-1.1
4. Work with the project office to make sure appropriate location(s) are reserved
for the workshop (adequate size and space), and that other helpful meeting
items are available (including Internet access).
5. Be familiar with the CRA/CEVP workshop process.
6. Be familiar with the CREM website. It is frequently updated and additional
material is occasionally posted:
www.wsdot.wa.gov/projects/projectmgmt/riskassessment/default.htm
7. Help identify training needs, and take advantage of training opportunities as they
arise (cost estimating class, risk-based estimating class).
Page F-1
Section F
F-2
F-2.1
workshop. Work with the team early to help them identify, well in
advance (8 weeks lead time or more), appropriate timing for a
workshop. These target dates can be entered into the project work
schedule.
Once a time frame for a workshop is established, take the following steps:
1. Go to the Cost Risk Estimating Management (CREM) website and
download a workshop request form:
www.wsdot.wa.gov/projects/projectmgmt/riskassessment/
2. Work with the project team to make sure the form is completed in its
entirety. During this time, check Outlook Calendar WSDOT re VERA to
determine dates that may be available for workshops, and include this
information in the workshop request form.
3. Meet with the area engineer or project development engineer and design
team to give an overview of the workshop process.
Page F-2
Section F
4. Work with the CREM Unit to determine appropriate Cost Leads, Risk Leads,
and subject matter experts, and help complete the participation matrix.
5. Determine who will send invitations to workshop participants. Often the
region will invite the region participants and project team, and the CREM
workshop coordinator will invite others (Cost Lead, Risk Leads, SMEs, HQ
representatives, etc.).
6. Continue to communicate/coordinate to make sure workshop materials are
being made ready and available by the project team to the cost-risk team
and subject matter experts. Follow up with certain workshop participants
to ensure their participation in the process is well timed and appropriate.
7. Attend prep sessions and workshops.
8. Postworkshop: Follow up with the CREM workshop coordinator and others
as appropriate to make sure action items are being communicated, and
follow up on them to make sure they are progressing. Help tie up any
remaining loose ends from the workshop. Make sure the risk register
properly documents the risks discussed at the workshop (particularly
the larger risks).
F-2.2
2. Assist with coordinating advance elicitation between the project team and
Risk Leads.
3. Work with the CREM workshop coordinator to help develop an effective
agenda; i.e., participants in the workshop will know what to expect and when
to attend.
4. Advocate for early completion of appropriate specialty work for the subject
project.
Page F-3
Page F-4
Section F
Section G
G-1
Guidance
The following guidance is for Cost Leads, Risk Leads, and anyone preparing risk models,
and for all those interested in the technical aspects of risk-based estimating and
modeling. Be sure to emphasize that project risk management focus and prioritization
goes beyond simply ranking risks by expected value. A careful review of the results is
required and risks with high impacts, low probabilities must also be included among the
significant risks identified for focused attention and response actions.
G-1.1
BASE UNCERTAINTY
Base cost
Base Variability + x%
Lower cost:
For many projects, the greatest uncertainty is market conditions; given that fact, we
need to make sure we adequately capture and represent market uncertainty in the
model. There are times when we enjoy a highly favorable bidding environment (highly
competitive), and other times when the bidding climate is not as competitive. Given the
volatility in the market and the many varied factors influencing bids, we must capture
both possibilities (bids could come in worse than planned, i.e., over the Engineers
Estimate, or better than planned, i.e., under the Engineers Estimate). To that end,
Exhibit G-2 provides a simple example of how to capture this uncertainty.
Page G-1
Exhibit G-2
Section G
Bid Result
BETTER than planned[1]
WORSE than planned[2]
Impact
15%
10%
[1] BETTER than planned indicates that, as a result of favorable market conditions in the
form of a highly competitive bidding environment, it is estimated there is a 40% chance
that bids will come in up to 15% below the Engineers Estimate.
[2] WORSE than planned indicates that, as a result of market condition influences in the
form of a noncompetitive bidding environment, it is estimated there is a 10% chance that
bids will come in up to 10% above the Engineers Estimate.
G-1.2
G-1.3
Page G-2
Section G
Exhibit G-3
Triangular Distribution
Uniform Distribution
0.5
0.14
0.4
0.3
0.2
0.1
0
x1
x2
x3
x4
Relative Likelihood
0.12
0.1
0.08
0.06
0.04
0.02
0
0
X1 = 20%
X2 = 45%
X3 = 30%
X4 = 5%
Multipoint discrete distribution: In some cases, a
risk element can only take particular values (i.e., is
not continuous) or be used to approximate a
continuous distribution.
10
Value
15
20
Page G-3
G-1.4
Section G
G-1.5
G-1.6
risks indicating the risks, in a prioritized order, that most significantly affect
project objectives. This information provides a roadmap to the risks that have
the most promise for benefiting the project through proactive efforts to
respond to the risks.
The more significant risks, sometimes termed candidates for mitigation, are
oftentimes known by the Project Manager and project team in advance of the
formal analysis. The Monte Carlo simulation more formally quantifies and ranks
these significant risks. It identifies those risks that are most responsible for
variation in the bottom line (cost or schedule) as determined from the
modeling.
An effective way to present risks that have the largest potential impact to the
G-1.7
Page G-4
Section H
H-1
Common Assumptions
General Overview
The common assumptions in this section allow completion of Cost Risk Assessment
(CRA) and Cost Estimate Validation Process (CEVP) workshops within the time allowed
and resources available. They have been chosen to produce the best results possible
under these constraints. Consequently, workshop results are, in general, limited by
these assumptions. It is also noted that project-specific assumptions are often also
required to allow a defined project to be put forward for evaluation.
Evaluated risks reflect a snapshot of the project at the time of the risk assessment.
The snapshot is based on the project scope presented by the project team from current
plans and available information. This means that the risk model is based on current best
estimates for costs, schedules, risks, and construction phasing and activity sequencing.
Risk identification depends on the expertise of the project and cost-risk teams.
H-2
Scope
Scope The sum of the products, services, and results to be provided as a
Scope Change Any change to the project scope. A scope change almost always
(Source: Project Management Institute, PMI PMBOK GUIDE, 2004, 3rd Edition)
WSDOT may elect, on its own initiative, to revise the scope of the project by adding,
removing, or revising particular elements of the project. Such items are not risk events.
Instead, these can be treated as alternative project scenarios or deltas to the base
assumed project.
Scope variations (commonly referred to as scope creep) are uncertain items or events,
not entirely within WSDOTs control, that may cause variations to the scope and hence
changes to the schedule or budget. They are considered risks and will be captured as
risk events and included in the risk-based estimate analysis.
Page H-1
Common Assumptions
H-3
Section H
H-4
H-4.1
Bridge Seismic
Soil Liquefaction Design Criteria: Existing criteria are provided in the WSDOT
Geotechnical Design Manual. Bridge projects built in the lowland areas of western
Washington and in Seismic Design Category D may be affected by soil liquefaction
during seismic events. Designs for new bridges and the widening of existing bridges
must identify the liquefaction risk and estimate the costs of mitigating or resisting
soil liquefaction to maintain a stable structure during a seismic event.
Check with the Bridge and Geotechnical offices to ensure the current policy is being
used. The cost of bridge projects with liquefiable soils may include soil modification,
foundation retrofit, or complete bridge replacement. The assessment of these projectspecific risks and the importance of the structure must be addressed by geotechnical
and structural engineers.
Confirm that the AASHTO Guide Specifications for LRFD Seismic Bridge Design manual
being used is current and applicable.
H-4.2
Wall Seismic
Confirm that the AASHTO Guide Specifications for LRFD Seismic Bridge Design manual
being used is current and applicable.
H-5
Page H-2
Section H
H-6
H-6.1
Common Assumptions
H-6.2
Phase
PE
R/W
n/a
n/a
H-7
Caution needs to be exercised regarding market condition risks. While Risk Leads must be thorough in making
sure to capture and recognize risk uncertainties, they must also guard against the potential of double counting.
The analysis must clearly document what is being used and why.
Page H-3
Common Assumptions
H-8
Section H
H-9
Page H-4