Suction Pile Spec
Suction Pile Spec
This cover page is a record of all revisions of the standard/specification identified above by number and title. All previous
cover pages are hereby superseded and are to be destroyed.
0
REV
9/12/00
DATE
BY
CHKD
ENG
APPV
GLH
EMDC
APPV
EXXONMOBIL DEVELOPMENT
COMPANY
GENERAL SPECIFICATIONS
EMDC-BRE-C-JS-0332.1001
Specifications
Page i of ii
Rev. 0
Table of Contents
1.
2.
3.
Scope...............................................................................................................................1
1.1.
Introduction............................................................................................................1
1.2.
Design Assumptions..............................................................................................1
References......................................................................................................................3
2.1.
Project Specifications............................................................................................3
2.2.
2.3.
Design Reports......................................................................................................4
Definitions.......................................................................................................................5
3.1.
General..................................................................................................................5
3.2.
Terms.....................................................................................................................5
3.3.
Acronyms...............................................................................................................7
4.
Pre-Design Deliverables................................................................................................8
5.
Pile Loads.......................................................................................................................9
6.
5.1.
Floating Systems...................................................................................................9
5.1.1.
Mooring.........................................................................................................................................9
5.2.
Subsea Systems..................................................................................................11
5.3.
5.4.
Transportation......................................................................................................11
5.5.
Lifting...................................................................................................................11
6.1.1.
6.1.2.
Floating Systems.........................................................................................................................12
Subsea Manifold..........................................................................................................................14
EXXONMOBIL DEVELOPMENT
COMPANY
GENERAL SPECIFICATIONS
7.
8.
EMDC-BRE-C-JS-0332.1001
Specifications
Page ii of ii
Rev. 0
6.2.
Design.................................................................................................................14
6.2.1.
6.2.2.
General........................................................................................................................................14
Suction-Installed Anchor Pile Sizing (Geotechnical Design)........................................................15
6.3.
6.3.1.
6.3.2.
6.3.3.
Embedment..................................................................................................................................19
Removal......................................................................................................................................19
Pile Retrieval and Reinstallation..................................................................................................20
6.4.
7.1.1.
7.1.2.
Floating Systems.........................................................................................................................22
Subsea Systems...........................................................................................................................22
7.2.
7.2.1.
7.2.2.
7.2.3.
7.2.4.
7.2.5.
7.2.6.
7.2.7.
7.2.8.
7.2.9.
7.2.10.
7.3.
Corrosion.............................................................................................................29
7.4.
Paint....................................................................................................................30
7.5.
Appurtenances....................................................................................................30
Company Intervention..................................................................................................31
EXXONMOBIL DEVELOPMENT
COMPANY
GENERAL SPECIFICATIONS
EMDC-BRE-C-JS-0332.1001
Specifications
Page 1 of 30
Rev. 0
1. Scope
1.1.
Introduction
This document describes the general geotechnical and structural design requirements for the
suction installed mooring piles (hereafter referred to as suction piles) for floating systems
(Surface Wellhead Platform (SHWP), Floating Production Storage Offloading vessel
(FPSO), oil offloading system, and riser supports), and subsea systems (subsea manifolds).
This specification assumes the suction piles will be designed and installed in normally to
slightly over-consolidated clayey soils.
The primary objective of this document is to provide a basis and methodology for the
design of the suction piles. This document summarizes the design requirements and
specifies the various analyses that shall be performed in the design and verification of the
suction piles. This document will also serve as a reference guide for third party verification
efforts and classification society review.
The CONTRACTOR shall use the most recent issue of the codes and standards listed in
Section 2.0 as part of this specification. If any conflicts exist between this specification
and the codes and standards referenced, the requirements of this specification shall govern.
Any conflict in Specifications shall be submitted to the COMPANY for resolution.
1.2.
Design Assumptions
Functional requirements are:
Suction-installed anchor piles shall be designed for the same in-place suite of
global load conditions as the component that it supports. The suction piles supporting
floating system moorings shall be designed to withstand maximum intact and one line
damaged mooring loads.
EXXONMOBIL DEVELOPMENT
COMPANY
GENERAL SPECIFICATIONS
EMDC-BRE-C-JS-0332.1001
Specifications
Page 2 of 30
Rev. 0
Full frictional resistance can be developed along the pile wall requiring
minimal soil displacement during installation
Reverse end-bearing can potentially be developed, requiring that the pile enter
the soil with low displacement of soils (e.g. minimal heave of soil plug at the mudline)
body.
Soil plug heave and internal pressures will be monitored to ensure that rate of
installation for self-weight and suction penetration occurs at a rate that will not cause
plug heave. Refer to installation specifications.
EXXONMOBIL DEVELOPMENT
COMPANY
GENERAL SPECIFICATIONS
EMDC-BRE-C-JS-0332.1001
Specifications
Page 3 of 30
Rev. 0
2. References
The DDCV (hull and mooring system) is considered to be a site-specific, fixed offshore installation that
will be unflagged. Det Norske Veritas (DNV) has been engaged by COMPANY to provide
classification services to ensure the various elements of the DDCV are designed, constructed, installed
and commissioned in compliance with a variety of classification society rules and guidelines,
recommended practices, codes, etc. DNVs classification scope of work is outlined in DNV letter
RNA440/CRCO/DWT2940-J-11, titled SWHP Class Requirements.
2.1.
Project Specifications
EMDC-EDE-G-NS-0230.2001, Design of Deck Structures for Floating Offshore
Platforms
EMDC-EDE-G-NS-0106.2001, Fabrication of Deck Structure for Offshore Platforms
EMDC-EDE-G-MS-0260.2002, Structural Materials
EMDC-EDE-G-KS-0213.2001, Structural Welding and Inspection of Offshore Platforms
EMDC-EDE-G-MS-0262.4007, Painting General Requirements
EMDC-BRE-C-NS-0217.1001, DDCV Hull Casting Specification
EMDC-BRE-G-ZS-0121.1002, General Glossary Specification
2.2.
API-RP-2SK
EXXONMOBIL DEVELOPMENT
COMPANY
EMDC-BRE-C-JS-0332.1001
Specifications
Page 4 of 30
GENERAL SPECIFICATIONS
Rev. 0
2.3.
DNV CN 30.1
DNV CN 30.2
DNV RP B401
Design Reports
None referenced.
EXXONMOBIL DEVELOPMENT
COMPANY
GENERAL SPECIFICATIONS
3.
EMDC-BRE-C-JS-0332.1001
Specifications
Page 5 of 30
Rev. 0
Definitions
3.1.
General
Unless noted below, terms and acronyms used in this specification shall be interpreted as
defined in General Glossary Specification, EMDC-BRE-G-SZ-0121-1002, or by a standard
English dictionary if not listed in the General Glossary Specification.
3.2.
Terms
The following terms shall be interpreted in this Specification as meaning:
Wave Frequency Range -
Cut-off Frequency
Sea-state
Wave Spectrum
Wind Spectrum
EXXONMOBIL DEVELOPMENT
COMPANY
GENERAL SPECIFICATIONS
EMDC-BRE-C-JS-0332.1001
Page 6 of 30
Rev. 0
Sept. 12, 2000
Data Sheet:
Anchor Points
Catenary
Dip Zone
Dynamic Mooring
Line Analysis
Mean Offset
Quasi-Static Analysis
Restoring Force
EXXONMOBIL DEVELOPMENT
COMPANY
GENERAL SPECIFICATIONS
EMDC-BRE-C-JS-0332.1001
Specifications
Page 7 of 30
Rev. 0
3.3.
Break Strength
Safety Factor
Seabed Slope
Alpha Factor
Acronyms
ROV
EXXONMOBIL DEVELOPMENT
COMPANY
EMDC-BRE-C-JS-0332.1001
Specifications
Page 8 of 30
GENERAL SPECIFICATIONS
Rev. 0
4. Pre-Design Deliverables
The following deliverables shall be issued by CONTRACTOR to COMPANY during early project
execution:
Suction Pile Design & Analysis Methodology A methodology document providing detailed
discussions and descriptions of the specific software and other analytical tools that will be used to
perform both preliminary pile sizing and final design. Modeling techniques, design constraints,
assumptions, and methodologies will be described. Method of performing preliminary sizing to
optimize the pile aspect ratio (L/D) versus steel weight prior to final suction pile design shall also
be described. The analysis tools and methods to be used shall be approved in advance by
COMPANY.
Analysis Matrix Data Sheet A data sheet identifying the controlling load cases, seastates, and
environmental headings to be analyzed during the detailed suction pile design. This will include the
mooring line tensions for the intact and damaged conditions. It will also include the build-up and
decay data used to evaluate soil strength degradation due to cyclic loading.
Anchor Design Data Sheet - A data sheet listing the installation assumptions for verticality,
horizontal placement and padeye rotation (see Section 6.2.2.5).
EXXONMOBIL DEVELOPMENT
COMPANY
GENERAL SPECIFICATIONS
EMDC-BRE-C-JS-0332.1001
Specifications
Page 9 of 30
Rev. 0
5. Pile Loads
5.1.
Floating Systems
5.1.1.
Mooring
5.1.1.1.
Environmentally derived loads applied to the suction pile by the mooring line
will be obtained from dynamic mooring analyses approved by COMPANY.
The environmentally derived loads will generally consist of a mean offset load
with a cyclic component.
Seasonal Environmental Conditions
In offshore locations where extreme environmental conditions occur on a
seasonal basis, a two-tier criterion will be employed in evaluating the suction
pile response to the applied loading. This criterion includes: (1) seasonal
environmental loads, generally less severe than maximum storm conditions,
applied immediately after the hull is attached, and (2) extreme environmental
loads that may occur several months after installation is complete. The
CONTRACTOR shall evaluate the following loading conditions:
Load Condition 1: The appropriate storm loading (minimum 10 year
storm) or, if applicable, loop current loading will be applied, and mooring
line loads calculated corresponding to the environmental conditions that
prevail at the time the project schedule indicates the anchor lines are
attached to the hull. This calculation of mooring line loads will consider
both intact and one-line damaged conditions.
Load Condition 2: The maximum storm load for the 100-year return
period extreme environmental conditions will be applied, and mooring line
loads calculated. This calculation will also consider both intact and oneline damaged conditions.
EXXONMOBIL DEVELOPMENT
COMPANY
GENERAL SPECIFICATIONS
EMDC-BRE-C-JS-0332.1001
Specifications
Page 10 of 30
Rev. 0
In offshore locations where extreme environmental conditions occur on a nonseasonal basis, Load Conditions 1 and 2 shall be consolidated, and the design
shall consider the most severe environmental loading applied at the time the
anchor lines are attached to the hull.
If it is necessary to commence suction pile design work prior to the completion
of dynamic mooring analyses, then suitably factored quasi-static loads may be
used for preliminary suction pile design.
5.1.1.2.
The CONTRACTOR shall evaluate the pretension loads in the anchor piles
for the maximum pretension allowed in the operating manual.
5.1.1.3.
Mooring tensions will be provided to the suction pile designer that will allow
the impact of cyclic loading on the soil strength to be assessed. The mooring
tensions will be evaluated during the build-up and decay of the 100 year
design event. A rainflow or similar method shall be used to provide the
geotechnical designer with the cyclic components of the loading. These cyclic
components will be filtered into low frequency T>30 seconds and wave
frequency T<30 seconds prior to the rainflow analysis is performed.
5.1.1.4.
Fatigue Loads
Mooring tensions will be provided to the suction pile structural designer that
will allow the impact of fatigue loading to be assessed. The mooring tensions
will be evaluated for the full scatter diagram. These cyclic components will be
filtered into low frequency T>30 seconds and wave frequency T<30 seconds
prior to the fatigue summary. It is assumed that a spectral fatigue analysis
will be performed. The suction pile designer will be provided with both the
wave frequency RMS tension and zero crossing period and the low frequency
RMS tension and zero crossing period. The suction pile designer can
calculate the fatigue damage from these two types of loadings in two ways as
outlined in API RP 2SK.
The fatigue damage can be calculated for these terms separately and
then summed.
A combined RMS tension and zero crossing period can be calculated
and used to determine the total damage.
The CONTRACTOR must verify the validity of the method chosen as
described in API RP 2SK.
EXXONMOBIL DEVELOPMENT
COMPANY
GENERAL SPECIFICATIONS
5.2.
EMDC-BRE-C-JS-0332.1001
Specifications
Page 11 of 30
Rev. 0
Subsea Systems
The pipeline manifold will apply mainly steady-state loads to the anchor piles. These loads
include compression, lateral, moment, and torsion. Short-term loads that may be applied
include those due to thermal expansion and contraction. For the subsea manifold
foundation, the CONTRACTOR shall evaluate the suction pile response to the following
loading conditions:
5.3.
5.4.
Transportation
The structure shall be analyzed for the forces imposed during transportation. The forces
shall include the self weight of the suction anchor and inertial loads developed from a
motion analysis.
5.5.
Lifting
The suction pile and lift attachments (padeyes, trunnions, etc.) shall be analyzed for lift for
the loads during installation and removal onto the transport barges, and during mooring
installation
EXXONMOBIL DEVELOPMENT
COMPANY
GENERAL SPECIFICATIONS
EMDC-BRE-C-JS-0332.1001
Specifications
Page 12 of 30
Rev. 0
Floating Systems
6.1.1.1.
Final suction pile design shall be based on the pile loads obtained from
dynamic mooring analysis, and the following load factors and soil resistance
factors:
For Intact Mooring System:
Load Factor =
1.30
Load Factor =
1.20
EXXONMOBIL DEVELOPMENT
COMPANY
GENERAL SPECIFICATIONS
EMDC-BRE-C-JS-0332.1001
Specifications
Page 13 of 30
Rev. 0
6.1.1.2.
The pretension load analysis shall evaluate the suction pile design to minimize
the potential for long term pile displacements due to creep. The analysis shall
evaluate the suction pile design for the condition of the vertical component of
the pretension anchor load resisted by pile axial skin friction.
For maximum allowable pretension in the anchor the following load and
resistance factors shall be used:
1.30
0.30
6.1.1.3.
Suction piles may also support other component structures (e.g. risers) that
apply vertical uplift and lateral loading to the foundation. For these
structures, the CONTRACTOR shall evaluate the anchor pile design to
minimize the potential for progressive pile failure and long term pile
displacements due to creep. The analysis shall evaluate the anchor pile design
for the tension load resisted by the pile axial skin friction and, if applicable,
lateral loads and associated moments.
For load cases that include lateral loading and/or moments, the soil skin
friction resistance from the mudline to the first point of zero lateral deflection
shall be ignored. The CONTRACTOR shall account for soil degradation due
to cyclic loading, as appropriate.
For maximum allowable pretension in the anchor the following load and
resistance factors shall be used:
1.30
0.30
EXXONMOBIL DEVELOPMENT
COMPANY
GENERAL SPECIFICATIONS
6.1.2.
EMDC-BRE-C-JS-0332.1001
Specifications
Page 14 of 30
Rev. 0
Subsea Manifold
The compressive load analysis shall evaluate the anchor pile design for
adequate bearing capacity. The analysis shall consider dead loads - D, live
loads - L (e.g. fluid flow and thermal expansion/contraction) and moments
associated with both loading conditions.
The following load and resistance factors shall be used:
6.2.
Load Factors =
1.3D+1.5L
0.7
Design
6.2.1.
General
Suction piles are typically used in conjunction with taut-leg type mooring
lines, due to this pile design's capability of withstanding horizontal and
vertical loads. The suction piles shall be designed to withstand maximum
intact and one line damaged mooring loads.
The design process shall comprise the following engineering activities:
1. Global sizing of the suction pile based on soil strength properties;
2. Global sizing of the suction pile to ensure that the pump-in suction
pressure is acceptable for the available soil strength (i.e., soil plug
stability check);
3. Global sizing of the suction pile to ensure that the pump-out pressure is
acceptable for the available soil strength, in case that anchor removal is
necessary.
6.2.2.
General
EXXONMOBIL DEVELOPMENT
COMPANY
GENERAL SPECIFICATIONS
EMDC-BRE-C-JS-0332.1001
Specifications
Page 15 of 30
Rev. 0
provide adequate capacity for the mooring line loads (combined lateral and
axial loading), and soil properties, in conjunction with the load and soil
resistance factors defined in section 6.1.1 and 6.1.2, above. The
CONTRACTOR shall calculate the potential configurations of the chain
between the seabed and the chain attachment point at the anchor, and use the
most severe conditions in design. COMPANY will provide the
CONTRACTOR soil properties for design purposes.
6.2.2.2.
Floating Systems
6.2.2.3.
Subsea Systems
In carrying out the suction pile design for subsea manifold, the
CONTRACTOR shall consider pile set-up (Section 6.2.2.4) and, if
applicable, soil creep and cyclic degradation of soil strength in calculating pile
capacity. The CONTRACTOR shall perform the design using analysis
methods appropriate for the principal modes of loading being considered and
resistance mechanisms of the suction pile.
EXXONMOBIL DEVELOPMENT
COMPANY
EMDC-BRE-C-JS-0332.1001
Specifications
Page 16 of 30
GENERAL SPECIFICATIONS
6.2.2.4.
Rev. 0
Pile-Soil Set-up
Floating Systems
Seasonal Environmental Conditions
Load Condition 1: The CONTRACTOR shall use a pile-soil set-up factor(s)
for both internal and external skin friction corresponding to the project
schedule's time interval between the pile last installed, and the attachment of
the hull. If the sequence of pile installation is known, then different set-up
factors may be applied to individual piles.
Load Condition 2: The CONTRACTOR shall use a pile-soil set-up factor(s)
for both internal and external skin friction corresponding to the project
schedule's time interval between the pile last installed and the first potential
occurrence of the extreme environmental load. If less than full pile set-up has
occurred, then different set-up factors may be applied to individual piles.
Non-Seasonal Environmental Conditions
The design procedures described under Load Condition 2, above, shall apply.
Pretension Load Case
The design procedures described under Load Condition 1, above, shall apply.
6.2.2.4.2.
Subsea Systems
Compressive Load Case
EXXONMOBIL DEVELOPMENT
COMPANY
GENERAL SPECIFICATIONS
EMDC-BRE-C-JS-0332.1001
Specifications
Page 17 of 30
Rev. 0
The CONTRACTOR shall use a pile-soil set-up factor for both external and
internal skin friction corresponding to the project schedule's time interval
between pile installation and application of the structure. If the pile is
designed to mobilize the end bearing capacity, then full end bearing resistance
shall be used to calculate pile capacity at the time of installation.
6.2.2.5.
The following applies only to suction piles for surface wellhead platform,
floating production storage offloading and oil offloading systems. The suction
pile design calculations shall include sensitivity studies to demonstrate that the
solution has been optimized and is robust. These studies shall include the
following:
1. Calculation of the change in pile capacity for the following three
scenarios:
a) Pile penetration of 1.5 and 3 m less than design penetration.
b) Full penetration but assuming the top 1.5 and 3m are disturbed during
installation (or later eroded) and, therefore, provide negligible axial
and lateral resistance.
c) Padeye is 1.5m higher and lower than the selected optimum depth
2. Develop a suite of pile capacity curves, for cases shown in the figure
below in which the pile is not in vertical alignment and for misorientation
of the padeye. The analysis will consider:
a) the pile out of vertical alignment + 2.5; +5.0; -2.5; -5.0 in
directions both parallel and perpendicular to the mooring line direction
(no torsional misorientation)
b) a "misorientation" analysis considering the padeye torsionally rotated
5 and 10 out of alignment.
c) Integration of these analyses (a and b) will be necessary to account for
combined effects.
EXXONMOBIL DEVELOPMENT
COMPANY
GENERAL SPECIFICATIONS
EMDC-BRE-C-JS-0332.1001
Specifications
Page 18 of 30
Rev. 0
Installation tolerance
governing for lateral
resistance
In s ta lla tio n to le r a n c e
g o v e r n in g fo r v e r tic a l
r e s is ta n c e
Seabed
Seabed
Mooring line
Minimum
penetration
M o o r in g lin e
M in im u m
p e n e tr a t io n
Target
penetration
T a rg e t
p e n e tr a tio n
M o o r in g lin e
O r ie n t a tio n to le r a n c e
EXXONMOBIL DEVELOPMENT
COMPANY
EMDC-BRE-C-JS-0332.1001
Specifications
Page 19 of 30
GENERAL SPECIFICATIONS
6.3.
Rev. 0
Embedment
The CONTRACTOR shall calculate the allowable differential pressure inside
the pile during self-weight penetration, in order to prevent the channeling of
water through the soil plug and along the outside wall of the pile. The
allowable differential pressure shall not exceed 50% (F.S. = 2.0) of the value
to cause incipient flow (maximum differential pressure). The
CONTRACTOR shall report the results as a graph of "allowable differential
pressure and maximum differential pressure" versus "penetration below the
mudline".
The pile geometry will also be selected to ensure that the maximum vacuum
required for pump-in embedment will not exceed 50% of the critical vacuum
at which soil plug heave inside the pile can occur. This will provide a safety
factor against soil plug uplift of 2.0 during all phases of the pump-in
embedment. The pump-in suction required at increasing pile penetration will
be plotted against the suction causing soil plug uplift in order to check that the
required safety factor will be met anywhere between self penetration and
maximum penetration.
For the purpose of sizing the suction pumps, an upper bound, static undrained
soil shear strength profile will also be developed for the stratigraphy. For pile
installation, alpha values less than the reciprocal of the soil sensitivity shall
not be used. The design and the upper bound undrained soil shear strength
profiles will be provided to the installation CONTRACTOR for pump design.
6.3.2.
Removal
The suction pile design shall account for removal of the pile within a seven (7)
day period after embedment proceeds. Pump-out pressure shall be based on
pile resistance corresponding to seven (7) days of set-up. This pressure shall
not exceed 75% of the pressure at which plug failure occurs. It shall be
assumed that the recovery vessel will be capable of applying an uplift load at
the top of the pile, which will be well in excess of the submerged pile weight.
Since the pump-out pressure is typically higher than the maximum embedment
vacuum, the pump-out pressure may govern the structural design of the pile
top. This shall be taken into account when defining the suction pile geometry.
6.3.3.
EXXONMOBIL DEVELOPMENT
COMPANY
EMDC-BRE-C-JS-0332.1001
Specifications
Page 20 of 30
GENERAL SPECIFICATIONS
Rev. 0
the type of winches used on large anchor handling vessels, and on the strength
of the wire rope and spreader bar used for installation of the suction anchor.
With regard to reinstallation of the pile, analyses will be performed to
determine the minimum x-y distances that the pile can be reinstalled relative to
the original pile location. In the calculations, the following plug conditions
will be assumed: (1) the soil plug is extruded and remains intact when the pile
is retrieved; and (2) the soil plug is removed with the pile.
6.4.
Design loads.
4. Design and Analysis Contains design analyses, results and recommendations for:
Chain configuration.
EXXONMOBIL DEVELOPMENT
COMPANY
GENERAL SPECIFICATIONS
EMDC-BRE-C-JS-0332.1001
Specifications
Page 21 of 30
Rev. 0
6. Appendices - Contains details of each of the sections in the main body of the report.
The CONTRACTOR shall submit a draft written final report for review by COMPANY
prior to submitting the final report. The CONTRACTOR shall incorporate in the final
written report all reasonable modifications to the draft final report requested by
COMPANY.
EXXONMOBIL DEVELOPMENT
COMPANY
GENERAL SPECIFICATIONS
EMDC-BRE-C-JS-0332.1001
Specifications
Page 22 of 30
Rev. 0
Floating Systems
The suction pile structure shall be designed to withstand the maximum loads
(and corresponding soil reactions) applied by the mooring line, the maximum
vacuum required for pile embedment, and the maximum internal pressure
required for pile pump-out (Sections 5.1, 5.3, 5.4 and 5.5).
7.1.2.
Subsea Systems
The suction pile structure shall be designed to withstand loads applied by the
following: maximum operational loads, transportation, lifting, lowering, the
maximum vacuum required for pile embedment, and the internal pressure
required for pile pump-out (Section 5.1, 5.3, 5.4 and 5.5) and recovery.
7.2.
EXXONMOBIL DEVELOPMENT
COMPANY
EMDC-BRE-C-JS-0332.1001
Specifications
Page 23 of 30
GENERAL SPECIFICATIONS
7.2.2.
Rev. 0
p = 0 Fy
Where:
0 = basic usage factor
Fy = material yield strength
The basic usage factor shall be 0.8 for the maximum in-place loading
condition and 0.6 for normal operating, transportation, lifting, lowering and
recovery
It should be noted that the permissible stresses are based on the fiber stresses
for simple beam analyses, and the membrane, or mid-thickness, stresses for
finite element analyses using plate elements.
For laterally loaded plates also exposed to inplane (e.g. membrane) stresses,
the surface Von Mises stress computed at the middle of the plate field (e.g.
midway between stiffeners and/or girders) shall not exceed the following:
p = (0 + 0.1) Fy
However, the nominal elastic stress calculated in the middle of the plate field
due to lateral pressure acting alone shall not exceed 0Fy.
7.2.3.
Buckling Checks
The buckling strength of the piles shall be checked in accordance with the
DNV Rules for Classification of Mobile Offshore Units, Part 3, Chapter 1,
Section 5 and DNV Classification Note 30.1 Buckling Strength Analysis.
The maximum permissible value of the usage factor, p, shall be calculated as
follows:
p = 0
Where:
=
coefficient depending on the type of structure and reduced
slenderness, , as per Table 7.1
0 = basic usage factor, as per Section 7.2.2
EXXONMOBIL DEVELOPMENT
COMPANY
GENERAL SPECIFICATIONS
EMDC-BRE-C-JS-0332.1001
Specifications
Page 24 of 30
Rev. 0
0.2
1.10
1.00
1.0
1.10
1.00
1.00
1.00
0.80
1.025 0.125
1.050 0.250
0.840 0.200
0.90
0.80
0.64
Buckling checks for piles used to moor floating systems shall be based on the
results of the finite element analysis.
7.2.4.
Fatigue Analysis
Fatigue damage is to be considered for the in-place condition. The total
fatigue damage times a safety factor of 10 shall be less than unity for the
design life of the platform.
Fatigue analysis of suction piles used to support subsea systems is required
only for piles subjected to significant dynamic loading. Analysis methodology
should follow DNV CN 30.2.
The fatigue analysis of suction piles used for mooring floating systems shall
be based on a spectral analysis using appropriate S-N data and stresses from
highly refined FE models. The detailed fatigue analysis for stiffened plate
structural details shall be consistent with the fatigue analysis principles set
forth in "FPSO Fatigue Methodology Specification", COMPANY Report No.
99-3053 (herein referred to as FMS).
The general methodology for the fatigue analysis of suction piles used for
mooring shall be consistent with Section 8.4 of the DDCV Hull Structural
Design Specification, EMDC-BRE-C-NS-0201.1001. The following
guidance can be found in this document:
General Methodology
Misalignment
EXXONMOBIL DEVELOPMENT
COMPANY
GENERAL SPECIFICATIONS
EMDC-BRE-C-JS-0332.1001
Specifications
Page 25 of 30
Rev. 0
7.2.5.
7.2.6.
7.2.7.
EXXONMOBIL DEVELOPMENT
COMPANY
GENERAL SPECIFICATIONS
7.2.8.
EMDC-BRE-C-JS-0332.1001
Specifications
Page 26 of 30
Rev. 0
EXXONMOBIL DEVELOPMENT
COMPANY
EMDC-BRE-C-JS-0332.1001
Specifications
Page 27 of 30
GENERAL SPECIFICATIONS
Rev. 0
Structura
l
Category
A
Item Description
Yield
Type
Min. Yield
Strength
Toughness Requirements
(Mpa)
T < 0.75"
(19mm)
0.75"(19mm) T
2.0"(50 mm)
T > 2.0"
(50mm)
248
NA
NA
NA
II
344
CV2
CV2Z4
CV2ZX
III
412
CV2
CV2ZX
CV2ZX
PRIMARY MEMBERS
248
NT
CV1
CV2
II
344
CV1
CV2
CV2X
III
412
CV2
CV2Z5
CV2X
SECONDARY MEMBERS
248
NT
NT
CV1
II
344
CV1
CV1
CV1
III
412
CV2
CV2
CV2Z5
248
NA
NA
NA
II
344
CV2Z4
CV2ZX
CV2ZX
III
412
CV2Z4
CV2ZX
CV2ZX
PRIMARY MEMBERS w/
Through thickness loading
MOORING CONNECTION
PADEYE AND LIFTING
POINTS
Padeye main plates and
attachment points
SPECIAL
II
III
Notes:
NT No impact testing required
CV1 Charp V-Notch category 1 as defined below
CV2 Charp V-Notch category 2 as defined below
Z4 Through thickness testing required - API S4
Z5 Sulfur limit to improve through thickness properties - API S5
X API RP2Z Prequalified steel - API S11
ZX API S4+S11
Table 7.3 Structural Steels Minimum Performance Requirements
Toughness Classes
EXXONMOBIL DEVELOPMENT
COMPANY
GENERAL SPECIFICATIONS
Specified Minimum
Yield Strength
Mpa
(ksi)
240/248
Yield Type
I
II
III
EMDC-BRE-C-JS-0332.1001
Specifications
Page 28 of 30
Rev. 0
NT(1)
CV1(1)
CV2 (1)
(No testing)
Test @ LAST
20 J
20 J
20 J
(35/36)
(15 ft lbs)
(15 ft lbs)
(15 ft lbs)
344
35 J
35 J
35 J
(50)
(25 ft lbs)
(25 ft lbs)
(25 ft lbs)
412
45 J
45 J
45 J
(60)
(35 ft lbs)
(35 ft lbs)
(35 ft lbs)
Notes:
For some grades of steels the steel standard requirements for impact testing may be more or less
stringent than required in the specification. Where there is a conflict between the specification and
any steel standard requirements, the more stringent requirements have been specified in the steel
specifications.
7.2.9.
Tolerances
Requirements for construction tolerances of the suction piles are given in
project specifications noted in Section 2.1.
7.2.10.
Metocean Criteria
Design conditions for the transportation analysis will be determined by
COMPANY as required by the project on a case by case basis.
7.3.
Corrosion
The suction piles shall have a cathodic protection system design to provide the required
design life for the piles. All internal and external surfaces (submerged or buried) shall be
protected by galvanic anodes. The design basis and calculations shall be conducted in
accordance with DnV RP B401 Recommended Practice Cathodic Protection System Design
(1993). Due to the stagnant conditions, the design current density for internal surfaces of
the pile shall be 1.0 mA/ft2. The anodes shall be placed above the mudline. The
CONTRACTOR shall provide COMPANY, for review and approval, a Cathodic Protection
System Design Report for the suction piles.
7.4.
Paint
The CONTRACTOR shall have the piles painted as follows:
EXXONMOBIL DEVELOPMENT
COMPANY
EMDC-BRE-C-JS-0332.1001
Specifications
Page 29 of 30
GENERAL SPECIFICATIONS
7.5.
Rev. 0
1.
The section of the pile that will be designed to be above the mudline including the
pile top will be painted a high visibility yellow.
2.
The pile will be marked in 0.25 meter increments on the side of the pile in order to
gauge penetration during self embedment and embedment. The distance from the
pile bottom will be marked numerically every meter in 1/3-meter high numbers.
3.
The pile top will be marked with a pile number and lift weight.
Appurtenances
The structural design CONTRACTOR will be required to interface with the installation
CONTRACTOR to determine the requirements for installation interfaces. These should
include but are not limited to the following:
1. Suction Port Typically a 20 API flange. This flange must be set high enough to
allow the suction skid to land and maneuver with out interfering with anodes or other
appurtenances on the pile top.
2. Lowering padeyes or trunions The configuration of these appurtenances shall
properly interface with the lowering equipment used by the installation
CONTRACTOR
3. Vent ports the top of the pile shall be fitted with closable vents used to vent water
during self-penetration and closed for suction embedment. These ports shall be large
enough to allow the pile to be self penetrated at a sufficient speed without risking pile
instability or damage to the soil around the pile due to blow-by.
4. Bullseye Used to view the pile verticality using the ROV.
5. Transponder frames used to house the transponder used to locate the piles during
installation. These frames shall be placed such that the transponders do not interfere
with the installation operations and such that they can easily be recovered.
6. Handling Padeyes The CONTRACTOR shall install such padeyes as required by the
installation contractor for the handling of the suction piles.
8. Company Intervention
The following table highlights all of the areas in this specification that require COMPANY intervention
or approval in the design process suction piles.
SECTION
1.1 Scope
4.0 Deliverables
INTERVENTION
Any conflict in Specifications shall be submitted to
COMPANY for resolution.
Pre-design deliverables that CONTRACTOR
EXXONMOBIL DEVELOPMENT
COMPANY
EMDC-BRE-C-JS-0332.1001
Specifications
Page 30 of 30
GENERAL SPECIFICATIONS
Rev. 0
SECTION
INTERVENTION
must clear with COMPANY are : (1) Analysis
methodology (software and analysis tools); (2)
Data sheet identifying load cases; (3) Pile
design data sheet listing assumptions for
verticality, placement tolerance, rotation.
Mean and offset storm loads derived from
mooring analyses shall be approved by
COMPANY