Surface Mine Development (Hartman)
Surface Mine Development (Hartman)
5.1
5.2
The value of ore in $/ton ($/tonne) is the recoverable value, and production
cost in $/ton ($/tonne) is overall cost through refining or final processing,
exclusive or stripping. The stripping cost in $/yd 3 ($/m3) is the cost of breaking
and handling a unit volume of standard overburden. Since value minus cost
normally equals profit, and the profit is assigned zero at the pit limit, the
numerator becomes the stripping allowance.
Because ore grades actually vary throughout the pit and the ore price
fluctuate, the maximu allowable stripping ratio can change with time. Thus it
is helpful for a given property to prepare a table or graph showing the
variation of SRmax with the ore grade and price.
The maximum allowable stripping ratio also has physical significance
(soderberg and Rausch, 1968; Pfleider, 1973a). it enables us to locate the
ultimate pit boundary or limit for prevailing economic conditions and for
existing physical and geometric conditions in the pit (e. .g., for agiven pit
slope and formation dip). Using computer graphics and Mathiesons
interactive made, various alternatives can be explored readily, even for
complex geometries and in three dimensions (figure 5.4). At the value of
SRmax where the cost of surface mining first exceeds that of underground
mining, the portion of the ore body lying beyond the ultimate pit limit would
have to be mined by underground methods. A copper pit designed in this
manner with varying ore grades and critical SRmax = 3.0 yd3/ton (2.5 m3/tonne)
is shown in figure 5.5. Ore occurring in the ore body beyond this maximum
stripping ratio will have to be left or mined underground, as indicated.
The general principles of equipment selection and system design were set
forth in section 4.7. Now we apply them to the operating circumstances of
surface mining. It is not surprising that the selection of equipment is nearly
synonymous with specifying method, because material handling lies at the
heart of surface mining.
In selecting a particular stripping method and its corresponding equipment,
the ultimate aim is the removal of material (waste, overburden) at the least
possible cost (Pfleider, 1973a). Many factors are involved, of which the size of
the ore body, distribution of the values within the deposit, and consolidation
and compaction of the overburden are key and limit the range of method and
equipment choices. Other factors to be evaluated, however, are the presence
of geologic structures (faults, folds, shear zones, water-bearing zones, etc.)
and alteration products (which may render roads impassable or mineral
processing difficult); production rate and life; horizontal haul and vertical hoist
distances; and possible future uses for specialized stripping equipment
(subsequently during mining or reclamation or at other miners, etc.).
Pit geometry has a major effect on the type and size of equipment which can
operate effectively. Each major mechanical extraction method of surface
mining has its unique geometry; for example, open pit metallic and
nonmetallic miners are designed with many low benches, open cast and
auger coal miners generally consist of one or more highwall faces, and
dimensionstone quarries operate from a single high bench. Open pits tend to
be deep and laterally large, open casts are shallow and follow contours or
advance across the country in long narrow panels and quarries are usually
very steep and may be quite deep. These geometric distinctions definitely
favor or limit the kind of stripping equipment to be selected.
As a general rule, the largest equipment feasible and safe for the conditions is
also the best suited and lowest-cost equipment. Large materialshandling
machines especially possess productivity and cost advantages that seem to
have no upper limit, but practical limits (e.g., mobility) do prevail.
The choices of equipment and systems to mechanically strip ore, coal, or
stone deposits are many in theory but few in practice (Martin et al., 1982;
Atkinson, 1983) some of the machines employed in surface mining, arranged
by cycle of unit operations, are shown in figures 5.8a-e. There are three main
rock-breakage systems and six materials-handling systems in common usage
today, as follows, in order of popularity:
1. Rock breakage
a. No breakage necessary ( material: typical soil)
b. Drilling and blasting (usual choices: roller-bit rotary and ANFO or
slurry ; material: typical rock)
c. Ripping (material: stiff soil, weak rock-for scale of rippability, see
Pfleider, 1973, pp. 17-25)
2. Materials handling
a. Dragline (direct casting)
b. Power shovel or front-end loader and trucks
c. Dozer and front-end loader
d. Dozer and rubber-tired scrapper
e. Shovel or loader and hopper, crusher and conveyor
f.
Table 5.2
Prevailing relative costs for stripping systems are hard to obtain. For material
handling (haulage) equipment alone, the following are helpful as guides
(modified from Pfleider, 1973a, for an iron ore mine a 5.5-mi, or 8.9-km, haul)
Table
2.
In only instance does SRmax not establish the pit limit or exceed SR o in
magnitude, and that occurs when (1) the surface is flat, and (2) the deposit is
flat, tabular, and of constant thickness. In that singular case, SR max lacks
significance, and the pit limit are located at the property lines. Another
distinction is that SRo is an actual numerical ratio of yd3/ton (m3/tonne),
whereas SRmax is expressed in units of equivalent yards (see the next section).
Under long-range planning (section 5.2), we discovered that the maximum
stripping ratio, on the other hand, has mainly physical significance. It is
because of its economic basis that we can employ SR max to locate the pit
limits of a deposit in the general case, that is, an ore body of varying
thickness, dip, or grade occurring beneath an inclined or horizontal surface.
Equivalent Yardage2
In developing a relationship and procedure to locate the pit limits in an ore
body or coal deposit, we will employ a unit called the equivalent yard.
Equivalent yardage is the volume of overburden which costs a unit amount to
move (expressed in $/yd3, or $/m3) and is accepted as a standard for the mine
or district in which it occurs. It is a dimensionless unit. Examples of some
standards and typical cost are
Lake superior iron ranges (loaded and hauled)
Glacial till:
$0.25-0.5/yd3 ($0.33-0.65/m3)
$0.5-1.00/yd3 ($0.65-1.31/m3)
RATING
0.5
Lose sand
0.7
1.0
1.5
Shaley rock
1.5-2.5
Sandstone, limestone
2-3
Hard taconite
3-5
The surface is inclined, and the deposit is flat. In writing a relation for
maximum stripping ratio, we maodify eq.5.4 as follows:
Rumus SR : 5.10