Resource Progress Curves in Primavera P6 (Print Friendly View)

This document discusses features in Primavera P6 for displaying resource progress curves. It describes how the activity usage profile and tracking feature can be used to link actual and remaining resource curves. The document provides steps for customizing the activity usage profile and tips for accurately capturing resource actuals and avoiding issues with budgeted values.

Uploaded by

anmol6237
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
594 views8 pages

Resource Progress Curves in Primavera P6 (Print Friendly View)

This document discusses features in Primavera P6 for displaying resource progress curves. It describes how the activity usage profile and tracking feature can be used to link actual and remaining resource curves. The document provides steps for customizing the activity usage profile and tips for accurately capturing resource actuals and avoiding issues with budgeted values.

Uploaded by

anmol6237
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 8

22/08/2015

ResourceProgressCurvesinPrimaveraP6(PrintFriendlyView)

ResourceProgressCurvesinPrimaveraP6

Writtenby:2/5/201312:22:00AM

ThisdocumentdiscussesthefeaturesofP6thatcurrentlylinktheactualandforecastresource
curve,whiletouchingonsomeofthecurrentshortfallsinmanagingresourcesinP6.Indepth
coverageofeachfeaturedescribedhereinisbeyondthescopeofthisdocument.

Displayingacontiguousresourcecurvelinkingtheactualcurvewiththeremainingcurvehas
oftenseemednotpossibleinP6,duetomostP6teachingoccurringonlyontheResource
UsageProfile(wherethisisnotpossible).ThisabilityisavailableinP6usingtheActivity
UsageProfileortheTrackingfeature.
NotethatBaselineoptionsarenotavailableintheResourceUsageProfile,onlybudgeted
values.Budgetedvaluesessentiallydonotworkonceyouhaveprogressinyourschedule.
Question:WhatisthedifferencebetweenBudgetedvs.Baseline?TheyareNOTthesame.

SampleResourceUsageProfile
TheRemainingUnitscurvestartsatzero(0).Plannerswouldliketheactualcurveto
linkwiththeremainingcurve(likeitdidinP3).
TheBudgetedUnitsarespreadovertheactivitybythePlannedStartandPlanned
Finishdatesoftheactivity,whichwillchangewhenthedatadatemoves(for
activitiesnotstarted).
Note:TherearenoBaselineUnitsorBaselineCurvesavailableintheResource
UsageProfile.

ActivityUsageProfile

UsetheActivityUsageProfileinP6toviewcostorunitvaluesovertimeaccordingtothe
selectedtimescale.TheActivityUsageProfiledisplaysresourceallocationsforallactivities
orforselectactivities.
http://www.projectcontrolsonline.com/Blogs/tabid/103/EntryId/105/ResourceProgressCurvesinPrimaveraP6.aspx

1/8

22/08/2015

ResourceProgressCurvesinPrimaveraP6(PrintFriendlyView)

Thisprofilecandisplayresourcelabor,unitsandcostswithperiodicverticalbarsaswellasa
varietyofcumulativecurves(early,late,baseline,earnedvalue(EV))forperiodsbasedon
theselectedtimescale.

Thereareavarietyofcustomizationoptionsavailable.PleasereadtheP6Helpforadditional
informationorrefertoyourcompanyP6TrainingManuals.

SampleActivityUsageProfile

Steps
1.SelectView>ShowonBottom>ActivityUsageProfile(onthetoolbar)

2.Periodicamountsaredisplayedontheleftaxis,cumulativeamountsontherightaxis(They
arenotcustomizable)
3.Displaythetimescaleinweeksforbestresults,unlessyourdatadateisthecalendarmonth
end
http://www.projectcontrolsonline.com/Blogs/tabid/103/EntryId/105/ResourceProgressCurvesinPrimaveraP6.aspx

2/8

22/08/2015

ResourceProgressCurvesinPrimaveraP6(PrintFriendlyView)

4.CustomizeyourheadersandfootersinPrintPreview

Tocustomizetheactivityusageprofileoptions:

SelectDisplay(orrightclickinthegraph)>

ActivityUsageProfileOptions:

Stepstocreateanactualcurvelinkedtoaremainingunitscurve:
Resourceloadtheschedule.
Createandassignaprojectbaseline(allowsuseofthevariousEarnedValue(EV)unit
options)
Inordertogettheresultdesired,youwillneedtoensureyouselecttherightcumulative
curves.

TheResourceUnitsgraphabovewascreatedusingthefollowingoptions(ForLaborUnits):
BaselineBar
http://www.projectcontrolsonline.com/Blogs/tabid/103/EntryId/105/ResourceProgressCurvesinPrimaveraP6.aspx

3/8

22/08/2015

ResourceProgressCurvesinPrimaveraP6(PrintFriendlyView)

ActualBar
ActualCumulativeCurve
RemainingEarlyBar
PlannedValueLaborUnits
EstimateatCompletionLaborUnits

TheRemainingEarlyCurvebeginsatthedatadatestartingat0h(whichwasnotthecaseinP3).To
getalinkedcurve,eitherusetheEstimateatCompletionLaborUnitscurveorcombinethiscurve
withtheActualcurvetoclearlydifferentiatebetweenhistoricalvs.forecastvalues.

Oneoptionistoshowjustthecurves,withouttheperiodicbars(i.e.justshowthecurves).

Note:Ifyouremovethebars,someperiodicvaluesontheleftofthegraphwillstillshow,butignore
them(2,4,5,6,8hetc.).Usethecumulativevaluesontherightsideofthegraph.

GeneralP6Settings(ActivityandProject,useDefaultWBSEarnedValueSettings)
DurationType=FixedDuration&Units
PercentCompleteType=Units%Complete
Resources=Driving
CalculationsTabSettingsintheProjectsWindowbelow:

TabularEarnedValueinformationintheActivitiesTable:

http://www.projectcontrolsonline.com/Blogs/tabid/103/EntryId/105/ResourceProgressCurvesinPrimaveraP6.aspx

4/8

22/08/2015

ResourceProgressCurvesinPrimaveraP6(PrintFriendlyView)

Note:Theabovecolumnshavebeenrenamedinthislayout.

TrackingFeature:
Summaryinformationallononepage
ProvidesresourceanalysisattheProjectorWBSlevel

Tips:
AvoidusingBudgetedValuesorCurvesonceyouhaveprogressintheschedule.
Ifyoudonthaveabaseline,youwillbedependentonplanneddates(whichslide).
http://www.projectcontrolsonline.com/Blogs/tabid/103/EntryId/105/ResourceProgressCurvesinPrimaveraP6.aspx

5/8

22/08/2015

ResourceProgressCurvesinPrimaveraP6(PrintFriendlyView)

ResourceActuals

TomoreaccuratelycaptureresourceactualsbyperiodrequiresusingtheFinancialPeriodsfeaturein
P6,otherwisetheoverallactualcurvewillbeincorrectasitsspreadovertheactivitylifetime.

InthecompanyP6Production&Stagingdatabases,thefinancialperiodsaresetuptomatchthe
companymonthlyfiscalperiodcutoffs.DuetoP6Limitations,thereisnoabilitytohavemultiple
variationsoffinancialperiodsinthecurrentversion(P68.2).Thenumberofperiodsislimitedand
cannotoverlap.

Thecumulativeindividualactualresourcecurveforeachresourceisadjustedeverytimethedatadate
ismoveduntiltheresourceiscomplete.Theactualresourcecurveisspreadbasedontheresource
curveassigned,justliketheforecastcurveisspread.Thecumulativecurveisasumoftheparts.

Theactualunitsarenotstored,bydefault,byanyperiod,butdistributedbasedontheresourcecurve
assigned(fromtheresourcestartdatethroughthedatadatetotheresourcefinishdate.

Thismeanstheactualperiodicamountswillbeadjustedoverthelifetimeoftheactivityduration,as
newactuals(earned)arerecordedforaresourceassignment.Thiswillaffectthehistoricalresource
curves,astheyarearollupofalltheactivitiesresourceassignments,distributedbythepercentages
allocatedtotheassignedresourcecurve.

InSummary,donotrelyontheaccuracyofthehistoricalprogressdatashowninP6.Inorderto
achievemoreaccuratehistoricaldata,storetheperiodicunitsinthefinancialperiodsfeatureinP6.
Theforecastbarsandcurvesareaccurate,butonlythehistoricalbaselineorPVcurveisaccurate,not
theactualcurve.

Resourceassignment(historical)withnocurve(linearbydefault)

ActivityUsageProfilewithalinearcurve

http://www.projectcontrolsonline.com/Blogs/tabid/103/EntryId/105/ResourceProgressCurvesinPrimaveraP6.aspx

6/8

22/08/2015

ResourceProgressCurvesinPrimaveraP6(PrintFriendlyView)

RelatedSearch
byWanderBurst

PopupBlocked

AllowOnce

AllowAlways

Options

RelatedSearches

Construction
Engineering
CivilEngineering

SameResourceassignmentwithcurveadded
Notethesignificantadjustmentoftheactualunitshistogramandcurve

ProjectControls
ProjectCost
Management
ConstructionAnd
ProjectManagement

SameActivityUsageProfilewithabellshapedcurve(samedataasabove)

ConstructionProjects
CostEngineering

WhilethegraphicsinP6arelimited,particularlywithcustomizationcapabilities,theydosavetime
versuscustomizinggraphsinexcel.

Itisimportant,priortoproceedingdownaP6resourcemanagementpath,toensurethateach
ProjectsunderstandingoftheabilitiesofP6arecorrect,priortoovercommittingandunderdelivering.
Itisoftenseenthatplannersandprojectsembarkonacomplexpath,withouttestingifthe
softwarewillsupporttherequirements.

http://www.projectcontrolsonline.com/Blogs/tabid/103/EntryId/105/ResourceProgressCurvesinPrimaveraP6.aspx

7/8

22/08/2015

ResourceProgressCurvesinPrimaveraP6(PrintFriendlyView)