RESR001
RESR001
RESR001
January 2002
PIP RESR001
Packaged, Skid-Mounted
Industrial Process Refrigeration
This Practice is subject to revision at any time by the responsible Function Team and
will be reviewed every 5 years. This Practice will be revised, reaffirmed, or withdrawn.
Information on whether this Practice has been revised may be found at www.pip.org.
PIP will not consider requests for interpretations (inquiries) for this Practice.
PRINTING HISTORY
August 2000
Issued
January 2002
Editorial Revision/Technical Revision
Not printed with State funds
PIP RESR001
Packaged, Skid-Mounted
Industrial Process Refrigeration Systems
Table of Contents
1. Introduction .................................. 3
1.1 Purpose ............................................. 3
1.2 Scope................................................. 3
2. References ................................... 3
2.1 Process Industry Practices ................ 3
2.2 Industry Codes and Standards .......... 4
2.3 Government Regulations ................... 4
3. General ......................................... 4
4. System .......................................... 5
5. Compressors................................ 5
5.1
5.2
5.3
5.4
General .............................................. 5
Reciprocating Compressors .............. 6
Rotary Compressors.......................... 7
Centrifugal Compressors................... 7
6. Drivers .......................................... 8
6.1 Electric Motors
(Open Drive Systems) ....................... 8
6.2 Steam Turbine ................................... 8
General .............................................. 8
Shell and Tube................................... 8
Direct Expansion................................ 9
Subcooler........................................... 9
8. Vessels ......................................... 9
8.1 General .............................................. 9
8.2 Receiver............................................. 9
8.3 Oil Separator
(Rotary Compressor Systems) .......... 9
8.4 Oil Recovery Pots (Reciprocating or
Rotary Compressor) ........................ 10
8.5 Suction Knockout Drum ................... 10
8.6 Economizer (If Provided) ................. 11
General ............................................ 11
Pumps.............................................. 11
Reservoir ......................................... 12
Piping/Valves ................................... 12
Filters and Cooler ............................ 12
Lubrication System Tests ................ 13
Page 1 of 26
PIP RESR001
EDITORIAL REVISION/TECHNICAL REVISION
Packaged, Skid-Mounted Industrial Process Refrigeration Systems
January 2002
Page 2 of 26
PIP RESR001
Packaged, Skid-Mounted Process Industrial Refrigeration Systems
January 2002
1.
Introduction
1.1
Purpose
The purpose of this Practice is to specify requirements for packaged, skid-mounted
industrial process refrigeration systems.
1.2
2.
Scope
1.2.1
This Practice, along with the data sheet, appendix, and referenced
attachments, defines the minimum requirements for the performance, design,
fabrication, testing, inspection, and preparation for shipment of packaged,
skid-mounted process refrigeration systems. This Practice is not intended to
cover commercial or absorption chiller systems.
1.2.2
1.2.3
1.2.4
References
Applicable requirements in the latest edition (or the edition indicated) of the following PIP
Practices, codes and standards, and regulations shall be considered an integral part of this
Practice. Short titles will be used herein when appropriate.
2.1
Page 3 of 26
PIP RESR001
EDITORIAL REVISION/TECHNICAL REVISION
Packaged, Skid-Mounted Industrial Process Refrigeration Systems
January 2002
2.3
Government Regulations
U.S. Department of Labor, Occupational Safety and Health Administration
(OSHA)
OSHA 29 CFR 1910 - Occupational Safety and Health Standards
3.
General
3.1
Vendor submitting the bid shall assume full responsibility for the complete, as
shipped, unit.
3.2
3.3
A qualified project engineer shall be named and assigned by vendor. Such engineer
shall coordinate the project and serve as sole contact with purchaser from issuance of
purchase order through completion of startup and commissioning.
3.4
Page 4 of 26
PIP RESR001
Packaged, Skid-Mounted Process Industrial Refrigeration Systems
January 2002
3.5
4.
5.
System
4.1
4.2
Rating condition used to establish the capacity of the refrigeration package system
shall be included in the proposal. System-rated capacity shall be determined by the
purchasers specified performance data on PIP RESR001 Data Sheet.
4.3
4.4
4.5
Storage capacity for refrigerant receiver shall be sufficient to retain the entire system
refrigerant inventory when 90% full, including the volume of purchaser-furnished
heat exchangers and piping when applicable. Purchaser shall provide piping and
exchanger refrigerant volumes when they impact receiver sizing.
4.6
4.7
4.8
4.9
Unless otherwise specified on the data sheet, the system and all auxiliaries shall be
designed for unprotected outdoor installation.
4.10
The refrigeration system shall be designed for the area electrical classification as
specified on the data sheet.
4.11
Any special tools required for operation and/or maintenance shall be provided.
Compressors
5.1
General
5.1.1
The system shall have proper equipment to ensure that liquid does not enter
the compressor suction. Equipment supplied for this purpose shall be
detailed in the proposal.
Page 5 of 26
PIP RESR001
EDITORIAL REVISION/TECHNICAL REVISION
Packaged, Skid-Mounted Industrial Process Refrigeration Systems
January 2002
5.2
5.1.2
Vendor shall provide the type of compressor most suited for this specific
application unless purchaser has specified a desired compressor type on the
data sheet.
5.1.3
5.1.4
5.1.5
Cast iron and ductile iron pressure-containing parts shall not be used for
rotary and centrifugal compressors that handle flammable refrigerants.
5.1.6
5.1.7
5.1.8
Reciprocating Compressors
5.2.1
5.2.2
5.2.3
5.2.4
Page 6 of 26
PIP RESR001
Packaged, Skid-Mounted Process Industrial Refrigeration Systems
January 2002
5.2.5
5.2.6
5.2.7
5.2.8
5.2.9
5.3
5.4
Rotary Compressors
5.3.1
5.3.2
5.3.3
5.3.4
The seal system shall be designed to positively contain the refrigerant during
operation, startup, shutdown, and periods of idleness.
5.3.5
5.3.6
5.3.7
Centrifugal Compressors
5.4.1
5.4.2
Compressor capacity control may be variable speed drive, inlet guide vanes,
suction dampers, or a combination subject to purchaser approval. The
control system proposed shall be explained and detailed in the proposal.
5.4.3
5.4.4
5.4.5
Page 7 of 26
PIP RESR001
EDITORIAL REVISION/TECHNICAL REVISION
Packaged, Skid-Mounted Industrial Process Refrigeration Systems
January 2002
6.
Drivers
6.1
6.2
Steam Turbine
If a steam turbine is specified, it shall meet requirements of API 611 or API 612, as
specified by purchaser.
7.
Heat Exchangers
7.1
7.2
General
7.1.1
System heat exchangers shall be per PIP VECV1001 and PIP VESV1002 or
PIP VESSM001, as applicable.
7.1.2
Exchangers shall be arranged such that maintenance space for tube pulling or
cleaning shall be to the outside of the skid. Space required shall be shown on
proposal drawings.
7.1.3
7.1.4
The condenser and evaporator shall have a NPT 3/4 drain and vent
connection(s) on both the shell and tube sides, complete with valve and plug.
Drains shall be at the low point to allow for complete drainage.
7.2.2
7.2.3
7.2.4
Marine water boxes shall be provided when specified on the PIP VEDST003
Specification Sheet.
7.2.5
Any exceptions to this Practice or any referenced PIP Practices, TEMA, or,
PIP VEDST003 Specification Sheet shall be provided with the proposal.
7.2.6
For systems using water as the condensing media, a regulating valve shall be
provided by the vendor if required.
Note: The system shall be designed to allow for as low a condensing
pressure as possible to utilize the lower cooling water temperatures
without throttling. Minimum condensing pressure/water
temperature shall be provided in the proposal.
Page 8 of 26
PIP RESR001
Packaged, Skid-Mounted Process Industrial Refrigeration Systems
January 2002
7.2.7
7.3
7.4
Direct Expansion
7.3.1
7.3.2
Subcooler
Vendor shall provide design details with the proposal.
8.
Vessels
8.1
General
System vessels shall be per PIP VECV1001 and PIP VESV1002 or PIP VESSM001,
as applicable.
8.2
8.3
Receiver
8.2.1
The receiver shall be provided and sized to hold system charge when 90%
full (see Section 4.5).
8.2.2
The receiver shall have a dip tube with vortex breaker and/or adequate
submergence to prevent vortexing in the liquid outlet line.
8.2.3
The receiver shall be supplied with a full-length, reflex type sight level
gauge.
8.2.4
The receiver shall have a minimum NPS 3/4 vent and drain.
8.2.5
8.3.2
Vendors design shall incorporate a method for removing oil from the dry
side of the separator.
8.3.3
8.3.4
8.3.5
The oil separator shall have a heater(s) that is capable of raising the oil
temperature from minimum ambient temperature to minimum allowable
starting temperature within 12 hours maximum. Any requirements for
Page 9 of 26
PIP RESR001
EDITORIAL REVISION/TECHNICAL REVISION
Packaged, Skid-Mounted Industrial Process Refrigeration Systems
January 2002
8.4
8.3.6
8.3.7
8.3.8
8.3.9
The oil separator shall have reflex type or bulls-eye type level gauges.
8.4.2
8.5
Page 10 of 26
8.5.2
On direct expansion units, the system shall be supplied with a suction trap to
prevent liquid from entering the compressor. The trap shall be arranged for
automatic draining.
8.5.3
8.5.4
Vendor shall provide design details of the suction knockout drum. Details
shall include mesh pad sizing (if applicable) and boil-out coil (if applicable).
8.5.5
8.5.6
8.5.7
8.5.8
Suction knockout drums shall be per PIP VECV1001 and PIP VESV1002 or
PIP VESSM001, as applicable.
PIP RESR001
Packaged, Skid-Mounted Process Industrial Refrigeration Systems
January 2002
8.6
9.
Vendors may include an economizer. The proposal shall describe the system
and state efficiencies and any additional costs associated with the
economizer.
8.6.2
8.6.3
8.6.4
8.6.5
8.6.6
Oil System
9.1
9.2
General
9.1.1
Vendor shall provide a pressurized lubrication system(s) that will supply oil
at pressure(s) and temperature(s) to bearings, seals, and controls as required.
9.1.2
9.1.3
9.1.4
9.1.5
The system refrigerant may be used as the cooling medium for the oil cooler
if specified and approved by purchaser.
Pumps
9.2.1
Main and auxiliary oil pumps shall be positive displacement and shall be
rated to sustain continuous operation of the compressor. Main (if required)
and auxiliary lube oil pumps shall be provided with maintenance block
valves and discharge check valves. (Vendor shall state whether main oil
pump is included in the proposal.)
9.2.2.
Auxiliary oil pump shall be electric motor driven. Requirements for the
motor shall be specified on the PIP RESR001 Data Sheet.
9.2.3
9.2.4
System low-oil-pressure switch shall start auxiliary oil pump and alarm on
the local control panel.
Page 11 of 26
PIP RESR001
EDITORIAL REVISION/TECHNICAL REVISION
Packaged, Skid-Mounted Industrial Process Refrigeration Systems
January 2002
9.3
Reservoir
9.3.1
9.3.2
9.3.3
9.3.4
9.3.5
9.4
9.5
Piping/Valves
9.4.1
Stainless steel tubing shall be used for lines NPS 1-1/2 or smaller.
9.4.2
9.4.3
Piping and tubing downstream of the oil filter shall be stainless steel. Carbon
steel piping upstream of the filter is acceptable.
9.4.4
Piping/tubing shall have a leak-free design that uses flanges and/or leak-free
tubing fittings. Use of threaded connections shall be minimized. Piping,
tubing, and flanges shall be proven leak-free per Section 22 of this Practice.
9.4.5
9.4.6
9.4.7
Each oil pump discharge line shall have a separate pressure relief valve.
9.4.8
Page 12 of 26
PIP RESR001
Packaged, Skid-Mounted Process Industrial Refrigeration Systems
January 2002
Materials of construction for filters and valve bodies shall be carbon steel
unless otherwise specified.
9.5.3
9.5.4
9.5.5
9.6
10.
Purge System
10.1
10.2
10.3
Vendor shall detail the purge system including a description of all associated
instrumentation, controls, and valves in the proposal.
Page 13 of 26
PIP RESR001
EDITORIAL REVISION/TECHNICAL REVISION
Packaged, Skid-Mounted Industrial Process Refrigeration Systems
January 2002
11.
Controls
11.1.1 System shall be furnished with operating and safety controls for automatic
operation of the system. A complete list of all instrumentation to be supplied
by vendor shall be provided with the proposal.
11.1.2 Minimum required indications, alarms, and shutdowns shall be provided as
listed below and as identified on purchasers Monitoring System
Instrumentation table. Vendor shall provide any additional instrumentation
required for safe operation. A complete description of all instrumentation,
including manufacturer and model, shall be provided in the maintenance
manuals.
11.1.3 Vendor shall provide a description of the method of system capacity control
in the proposal.
11.1.4 System monitoring and control shall be provided by a single skid, locally
mounted microprocessor control panel.
11.1.5 Microprocessor control shall have the following features:
1. Graphic display with English units unless otherwise specified
2. First-out annunciation freeze screen display with manual reset
3. Battery back-up to maintain set-points during periods of no power
4. Common alarm contacts for connection to purchasers remote alarm
5. Alarm and shutdown contacts energized to close and fail open
6. Capability of two-way communication with purchasers distributed
control system (DCS) or other microprocessors when specified
7. Save program memory for restart after power failure
11.1.6 The operating capacity control signal shall be taken from the
chiller/evaporator process outlet temperature, the compressor suction
pressure, or as specified.
11.1.7 For centrifugal and screw compressor systems, control signal shall vary
refrigeration capacity in stepless, continuously variable mode to
automatically match process load demand.
11.1.8 Critical system variables for purchaser trend monitoring shall be
recommended by vendor.
11.2
Instruments
11.2.1 General Instrument System Design
Page 14 of 26
11.2.1.1
Pressure gauges shall have isolation valve with vent valve for
maintenance.
11.2.1.2
PIP RESR001
Packaged, Skid-Mounted Process Industrial Refrigeration Systems
January 2002
11.2.1.3
11.2.1.4
Level gauges shall have armored, external reflex gauge glass with
gauge cocks and ball checks.
11.2.1.5
11.2.1.6
11.2.1.7
11.2.1.8
11.2.1.9
11.2.2.1
11.2.2.2
Page 15 of 26
PIP RESR001
EDITORIAL REVISION/TECHNICAL REVISION
Packaged, Skid-Mounted Industrial Process Refrigeration Systems
January 2002
11.2.2.4
11.2.2.5
11.2.2.6
11.2.2.7
11.2.2.8
11.2.2.9
11.2.2.10 Rigid conduit and piping shall not be routed over the cases of
rotating machinery (or other equipment) and shall not be routed
over or in front of removable heads on vessels and exchangers or
where they impair the functionality of inspection openings or
panel doors. Drains shall be installed at low points, or a drip loop
with a low-point drain shall be used to prevent water from
draining down the conduit system into an instrument or enclosure.
11.2.2.11 Conduits shall be liquid-tight. Flexible conduits shall be used for
any rotating equipment and may be as long as 18 inches. Conduits
that are greater than 18 inches shall be rigid.
11.2.2.12 Power and instrument wiring shall be run in separate conduits and
shall be terminated in separate boxes.
11.2.2.13 Control, instrument, and electrical terminations shall be made
only on labeled terminal strips.
11.2.2.14 Conduit seals shall not be poured by skid supplier.
Page 16 of 26
PIP RESR001
Packaged, Skid-Mounted Process Industrial Refrigeration Systems
January 2002
11.3
11.2.3.1
11.2.3.2
11.2.3.3
11.2.3.4
11.4
Page 17 of 26
PIP RESR001
EDITORIAL REVISION/TECHNICAL REVISION
Packaged, Skid-Mounted Industrial Process Refrigeration Systems
January 2002
12.
13.
Control Panel
12.1
The control and monitoring panel shall be mounted on the driveline skid unless
otherwise specified.
12.2
The panel shall be stainless steel and shall meet the requirements of the area
classification. Panel shall be NEMA 4X as a minimum.
12.3
All pressure tubing and control wiring to sensing points shall be completed by
vendor.
12.4
12.5
Each terminal strip shall have 20% spare terminals for purchaser connections.
12.6
Process fluids and lube oil shall not be allowed into panel.
12.7
Panel-mounted gauges, indicators, and switches shall each be labeled for function
with engraved labels having black letters that are at least 3/8 inch tall on white
background. Labels shall be attached with stainless steel screws or rivets.
12.8
12.9
The control panel shall have low-watt-density space heaters, if required. Space
heaters shall maintain instrument manufacturers recommended minimum
temperature inside the cabinet at specified minimum site temperature.
12.10
Electrical
13.1
General
13.1.1 Motor starters and disconnects shall be provided by purchaser and installed
in remote motor control center (MCC).
13.1.2 Two diagonally opposite ground lugs on each skid shall be provided for
purchaser connection to facility grounding.
13.1.3 A hermetic compressor shall be wired at the factory with starting equipment
selected to match motor and system requirements of vendor.
13.2
Page 18 of 26
PIP RESR001
Packaged, Skid-Mounted Process Industrial Refrigeration Systems
January 2002
14.
15.
14.2
14.3
Threaded connections in refrigerant service shall not be larger than NPS 3/4.
14.4
14.5
Vent and drain connections or valves shall be socket-weld by threaded and have
plugs or blinds of the same material as the connection or valve.
14.6
Individual system components shall have isolation and vent valves to permit
maintenance with minimum depressuring of the system and/or piping.
14.7
All valves shall have a stainless steel identification tag. Purchaser shall provide tag
numbers.
14.8
All refrigerant isolation valves shall be back seat design with seal caps and socketweld or flanged connections.
14.9
The allowable forces and moments for purchaser connections shall be shown on the
outline drawing by vendor.
14.10
14.11
14.12
If required and approved by purchaser, vendor shall provide flexible expansion joints
to avoid excessive loads on the compressor.
14.13
The use of copper pipe and tubing shall not be acceptable without written approval
from purchaser.
14.14
Pressure-Relieving Devices
15.1
15.2
Vendors sizing basis as well as inlet pressure-drop calculations shall be provided for
purchasers approval.
15.3
The inlet pressure drop to the relief valve shall be calculated and shall meet
Paragraph M-7 of ASME Code, Section VIII, Division 1, Appendix M (i.e., shall be
less than 3%). In addition, for compressible fluid systems, the irreversible pressure
Page 19 of 26
PIP RESR001
EDITORIAL REVISION/TECHNICAL REVISION
Packaged, Skid-Mounted Industrial Process Refrigeration Systems
January 2002
losses in the relief valve inlet piping shall not exceed 3% of set pressure based on a
flow rate equal to the relief valve ASME-rated capacity (nameplate capacity).
15.4
16.
17.
Relief valve mounting locations and inlet and outlet piping requirements for
refrigerants that are toxic or hazardous may require special design considerations to
avoid liquid accumulation or undesirable discharges to the atmosphere. In such
applications, purchaser will advise relief valve mounting locations, piping layout,
pressure drop, and maximum back pressure (for relief valves piped to a closed
system).
Insulation
16.1
16.2
16.3
Vendor shall indicate on the system flow diagram which items shall be insulated and
shall recommended thicknesses of insulation.
Vendor shall provide the structural steel base upon which all system equipment shall
be mounted.
17.2
The common structural steel base shall be sufficiently rigid to provide for
satisfactory performance of the system when installed at purchasers site. Vendor
shall specify anchor points and foundation requirements.
17.3
Vertical jack bolts located next to anchor boltholes shall be provided for the
structural baseplate(s).
17.4
Vendor shall provide stainless steel shim packs for leveling of compressors and main
drives mounted on a structural steel skid. Shims shall be a minimum of 1/8 inch and
shall straddle boltholes.
17.5
17.6
17.7
17.8
17.9
Equipment, piping, and conduit shall not extend below the top of structural skid
beams. Piping and conduit shall not protrude beyond the outer perimeter of skid
beams.
17.10
17.11
17.12
Page 20 of 26
PIP RESR001
Packaged, Skid-Mounted Process Industrial Refrigeration Systems
January 2002
18.
17.13
System shall be provided with lifting lugs for a minimum four-point lift.
17.14
17.15
Vendor shall provide a drawing that indicates system lifting points, rigging
requirements, center of gravity of each skid, and the weight at each point.
Noise
Vendor shall provide a best estimate for the noise level at a distance of 3 feet from each skid.
Where the sound pressure level exceeds PIP RESR001 Data Sheet requirements, vendor shall
include information indicating additional sound treatment required to obtain the conditions
specified.
19.
20.
Vendor shall assume full responsibility for the performance of necessary torsional
studies and the elimination of any lateral or torsional vibrations that may affect the
operation of the system. Vendor shall be responsible for the total system including
the drive motor.
19.2
Torsional and lateral critical speeds or system resonances shall be 20% above or
below any operating speed.
19.3
Painting
20.1
Unless otherwise specified, the painting shall be the vendors standard. The proposed
paint system shall be detailed in vendors proposal.
20.2
Components that are inaccessible after fabrication shall be primed and coated with
paint acceptable for service conditions for the component before installation.
20.3
20.4
Surfaces that cannot be accessed for painting after assembly shall be prepared and
primed before final assembly.
20.5
Top or final coat shall not be applied until all fabrication and assembly is complete
and all surfaces are primed in areas to be coated.
20.6
Primer(s) shall be applied the same day as surface preparation and before oxidation.
20.7
Paints and coatings shall be stored, mixed, catalyzed, thinned, and applied according
to manufacturers instructions.
Page 21 of 26
PIP RESR001
EDITORIAL REVISION/TECHNICAL REVISION
Packaged, Skid-Mounted Industrial Process Refrigeration Systems
January 2002
20.8
21.
Exposed alloy equipment shall not be painted. However, alloy equipment shall be
painted before being insulated.
Inspection
21.1
21.2
Special Considerations
21.2.1 Vendor shall provide a safe work area and testing equipment for purchasers
representative.
21.2.2 The intent of purchasers surveillance activity is to monitor and audit
vendors quality control (QC) effort to assure compliance with purchase
order specification and drawings so that quality requirements are attained
and verifiable. The purchasers representative will participate and witness
surveillance activities as deemed necessary.
21.2.3 All fasteners in a pressure/process containment application that are supplied
by vendor shall conform to ASTM/ANSI standards for chemical and
physical properties. In accordance with ASTM/ANSI, the fasteners shall
bear the manufacturers symbol (stamp) and the applicable specification
grade. Any fastener found without the above-mentioned features shall be
cause for rejection.
21.3
Documentation
The following documents/records shall be made available by the vendor/subvendor
for review by the purchasers representative:
Page 22 of 26
PIP RESR001
Packaged, Skid-Mounted Process Industrial Refrigeration Systems
January 2002
Prefabrication Meeting
A prefabrication meeting shall be held when specified on data sheet PIP RESR001D
to review all order requirements with vendors responsible personnel. Site and design
personnel are encouraged to attend.
21.5
Surveillance Schedule
The following surveillance activities shall be conducted by purchaser as a minimum:
1. Preliminary - Inspection of shop before start of fabrication
2. Intermediate - Witness hydrostatic/pneumatic tests of all pressure vessels
3. Intermediate - Inspect motor at motor vendors facility
4. Intermediate - After blast cleaning but before painting, accomplish electrical
check-out and witness functional test of all controls
5. Final - Witness mechanical run (if specified) and leak test
22.
Purchaser shall be notified at least 5 days before any testing, including testing of
parts or assemblies in subvendors facilities.
22.2
Purchaser reserves the right to conduct a field performance test with the participation
of the vendors representative. If this test is to be conducted, purchaser and vendor
shall agree beforehand on the acceptance criteria.
22.3
Before assembly on system skid, pressure vessels and/or heat exchangers shall be
pneumatic-tested or hydro-tested at fabrication facilities. Hydro-tested components
shall be thoroughly drained in accordance with the applicable purchase order
specifications.
22.4
22.5
Compressors shall be given manufacturers standard pressure and running tests. Test
procedure shall be provided to purchaser at least 2 weeks before test.
22.6
22.7
After final assembly, oil system shall be tested by operation for 1 hour at design flow
rate. Compressor and bearings shall be bypassed during oil system run test.
Page 23 of 26
PIP RESR001
EDITORIAL REVISION/TECHNICAL REVISION
Packaged, Skid-Mounted Industrial Process Refrigeration Systems
January 2002
22.8
Oil system filter and screens shall be visually inspected after test for identification of
foreign particles. Test shall not be considered accepted until no particles are visible
on the screens or are detectable by touch.
22.9
A continuity test shall be performed on all electrical circuits before final inspection.
22.10
All shutdown and safety devices, except relief valves and rupture disks, shall be
functionally tested by simulating the conditions required for actuation.
22.11
22.12
If system consists of more than one skid, each skid shall hold vacuum on the
refrigerant side as listed in Section 22.11 of this Practice.
22.13
Vacuum shall be broken with dry nitrogen, and system shall be pressurized to 15 psi
for shipment.
22.14
Page 24 of 26
23.
PIP RESR001
Packaged, Skid-Mounted Process Industrial Refrigeration Systems
Documentation
Item
1. Drawing List
2. Noise Data Sheets
3. Completed Equipment Data Sheets
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
Certified
!
!
!
!
!
!
!
Page 25 of 26
PIP RESR001
EDITORIAL REVISION/TECHNICAL REVISION
Packaged, Skid-Mounted Industrial Process Refrigeration Systems
January 2002
System Instrumentation
Alarm
Shutdown
Local
Panel
High/Low
Level Indication
Condenser
High
High
Low
Low
Compressor
Suction Pressure
Low
Discharge Pressure
Low
Suction Temperature
Low
Low
Discharge Temperature
High
High
Bearing Temperature
High
High
Reservoir Level
Low
Low
!
!
Vibration
Oil System
Reservoir Temperature
Pump Discharge Temperature
Low
Low
High
High
High
High
Low-Pressure Switch
Low
Oil Separator
Level Indication
Receiver
Level Indication
Bearing Temperature
High
Vibration Probes
High
Winding Temperature
!
!
Low
!
!
!
!
!
Page 26 of 26
PIP RESR001
Packaged, Skid-Mounted Process Industrial Refrigeration Systems
January 2002
In-Process
A.1.1
A.1.2
Review all mill test reports, certificates of compliance, ASME Code data
reports, microprocessor shop logs, pressure test results on vessels,
compressor assembly records, and certification of compressor run test.
A.1.3
A.2
A.1.5
A.1.6
A.1.7
Witness compressor mechanical run test and leak testing of the complete
system before painting.
Electrical Check-out
A.2.1
A.2.2
A.2.3
A.2.4
A.2.5
Page A-1
PIP RESR001
EDITORIAL REVISION/TECHNICAL REVISION
Packaged, Skid-Mounted Industrial Process Refrigeration Systems
January 2002
that danger tag states that more than one voltage source is within the
panel, if applicable.
A.2.6
Verify guards or covers for line voltage terminations of under 250 volts
to ground; verify fully enclosed housings for terminations of 250 volts
and more to ground.
A.2.7
A.2.8
A.2.9
A.2.10 Verify correct tubing and piping runs, valve locations, air supply, spot
check of fittings, and tubing supports.
A.3
Motor Inspection
A.3.1
Page A-2
A.3.2
A.3.3
A.3.4
A.3.5
A.3.6
A.3.7
PIP RESR001
Packaged, Skid-Mounted Process Industrial Refrigeration Systems
January 2002
A.3.8
Ensure that motor leads are undamaged and that compression lugs are
installed.
A.3.9
Ensure that temperature sensor and space heater leads are terminated on
terminal blocks in accordance with drawings.
A.3.10 Check the number of temperature sensors and ensure that the
temperature sensors have the correct operating temperature.
A.3.11 Identify spare temperature sensors and check all temperature sensors for
operation.
A.3.12 Ensure that airflow openings have stainless steel screens.
A.3.13 Verify proper sizing and installation of cooling fans.
A.3.14 Check shaft end float, as specified.
A.3.15 Ensure that copies of vendors standard commercial test results are
provided.
A.3.16 Ensure that shaft was stress relieved before final machining.
A.3.17 Review shipping preparations with vendor. Ensure that the motor is
mounted on a rigid skid.
A.4
Final
A.4.1
Inspect paint for proper coverage and application per specified paint
system.
A.4.2
A.4.3
Page A-3
PIP RESR001
EDITORIAL REVISION/TECHNICAL REVISION
Packaged, Skid-Mounted Industrial Process Refrigeration Systems
January 2002
Page A-4
RESR001D
Item No.:
/
" Purchaser
# Manufacturer
Information to be Completed by:
Applicable to:
" Proposal
" Purchase
" As Built
" For:
" Site:
" No. Req.:
" Manufacturer:
Date:
By:
Unit:
Service:
Type:
Model:
# Serial No.:
" MATERIALS OF CONSTRUCTION
Page 1 of 2
January 2002
Max
Norm
Min
Condenser
Evaporator
Channels
Tubes
Tubesheets
Shell
Other Requirements:
TEMA Class
Fouling Factor (Hr-Ft2-F/Btu)
Reservoir Mtrl. of Construction:
Mfg. Standard
SS
Comments:
Hazardous:
Yes
No
Flammable:
Corrosive:
Comments:
Yes
Yes
No
No
Indoor
Altitude, (Ft)
Group
Other
Max
CS
Max (F)
Summer
Min (F)
Winter
Case 1
Case 2
Preferred Refrigerant
Operating Hr/Year
Comments:
Comments:
" NOISE CONTROL
Allowable Noise Limit
Comments:
" UTILITIES
dBA @ 3 Ft
# DESIGN DATA
Refrigerant
Capacity (tons)
Turndown to
Turndown by:
Sliding Valve
Compressor Type:
Centrifugal
Open
Discharge Muffler:
%
Valve Loaders
Screw
Hermetic
Yes
Other
Reciprocating
Other
Semi-hermetic
No
Power Reqts
Cooling Water Reqts
Comp. Air Reqts
Flow (GPM)
Press (Psig)
Press (Psig)
Temp (oF)
Flow (CFM)
Flow (CFM)
(Lbs.)
(GPM)
Class
Power
Water
Voltage
Temp (oF)
Group
Flow (CFM)
Division
$/BHP
$/GPM
Flow
Pressure:
Item No.:
/
RESR001D
Page 2 of 2
January 2002
Date:
By:
Required
Witnessed
Pre-fabrication Meeting
Shop Inspection
Mfg. Standard Shop Tests
Vacuum Leak Test
Mechanical Run Test
Lube System Test
Vessel(s) Hydro Test
Instruments Systems Test
Condensing Media
Air
Temperature (oF)
Min
Inlet Pressure (Psia)
Max. Allowable Pressure Drop (Psi)
Max Outlet Temperature (oF)
Min/Max Velocity (FPS)
Comments:
Water
Max
Comments:
" INSTRUMENTATION AND CONTROLS
Voltage:
Other
Alarm
Phase:
Hertz:
Preferred Vendors List, Attached
Number of Points
Annunciator
Fist-Out
Yes
Yes
Shutdown
No
No
Mfg. Standard
API 614
Other
" MONITORING
Centrifugal Compressor:
Comments:
Radial
Temperature
No
No
Rotary Compressor:
Vibration Detection
Direct
/
/
Temperature Detection
Belt Driven
Encl.
AGMA Ratio:
Temperature Axial
Comments:
" PRESSURE/TEMPERATURE INDICATIONS
Pressure and Temperature Indications per Section 23
and Attached:
Yes
# COUPLINGS
Mfg.
No
Comments:
Model
Type
Low Speed
High Speed
Main/Aux Oil Pump
By Purchaser
By Mfg.
Comments:
Other
by Purchaser
Charged
Dry
W
Sizing per
Preferred Mfg.
" ACCESSORIES
# MISCELANEOUS
Paint:
Mfg. Standard
Insulation:
by Mfg.
Total System Weight:
Maximum Component Weight:
Approximate Floor Space:
L
Maintenance Space Required:
Comments:
3
Axial
Vibration
Purge Unit
Filter Dryer with Indication
Other (Describe Below)
Comments:
Economizer
2
1
REV
DATE
BY
CHECK
APPROVED