Guide To Elemental Cost Estimating 2013
Guide To Elemental Cost Estimating 2013
No responsibility for loss or damage caused to any person acting or refraining from action as a result
of the material contained in this guide can be accepted by the Africa Association of Quantity
Surveyors
CONTENTS
Table of Contents
Page
1.
FOREWORD .......................................................................................................................... 3
2.
INTRODUCTION ................................................................................................................... 4
3.
4.
5.
DEFINITIONS ....................................................................................................................... 20
6.
7.
8.
9.
1. FOREWORD
In 1998 the Association of South African Quantity Surveyors published the second edition of
the Guide to Elemental Cost Estimating & Analysis for Building Works. An amended
version was issued by the Africa Association of Quantity Surveyors during 2003. This guide
replaces both
A committee comprising Patrick Waterson and Andrew Koen under the chairmanship of
Martin Smith was established at the beginning of 2012 to examine whether there was a need
to revise and possibly expand the 1998 and 2003 editions to accommodate changes that
have taken place in the industry since those versions were published
The committee endeavoured to refine the principles established in the previous editions by
incorporating international advances in the industry to better guide quantity surveyors active
in Africa and further afield
Invaluable insight was gleaned, and is herewith acknowledged, from publications such as
RICS new rules of measurement: Order of cost estimating and elemental cost planning
(February 2009), Measurement of Buildings by Area and Volume (Canadian Institute of
Quantity Surveyors), UNIFORMAT II published by the National Institute of Standards and
Technology (NIST) and the American Society of Testing and Materials (ASTM) and
Uniformat published by The Construction Specifications Institute (CSI) in the United States
of America and Construction Specifications Canada (CSC)
The Services and Model Documentation Board of the Africa Association of Quantity
Surveyors comprising Corn de Leeuw (chairman) (South Africa), Michael Frimpong
(Ghana), Dan Kimoro (Kenya) and Segun Ajamlekoko (Nigeria) also provided input
2. INTRODUCTION
The elemental method is an approach towards calculating the total estimated cost of
construction projects. It considers the major elements of a building and, if properly
implemented, provides a cost estimate based on an elemental breakdown of the building
project
To achieve this goal the measurement and descriptions of building works for estimates
should be consistent. By ensuring that different building projects are measured and
described in the same manner, the data from one can be meaningfully applied to another. A
lack of consistency makes it extremely difficult for the employer and project team to
comprehend what is included in the cost estimate, cost limit or cost target, often casting
doubt about the cost advice provided
This guide presents a system which sets out principles and a model format for elemental cost
estimating which may be understood by all those involved in construction projects thereby aiding
communication between the design team and the employer. It provides a structured basis for
measuring building work and advances a consistent approach for dealing with other key cost
components associated with a building project. It should also assist the quantity surveyor in
providing effective and reliable cost advice
The primary objective of this guide is to present a system which sets out principles and a model
format for elemental estimating. It is not the intention to explain alternative estimating
methods, procurement methods or contract strategies
This guide is not intended to classify elements of major civil works. Buildings, however, are
usually accompanied by roads, utilities, parking areas, and other non-building features. The
building element External works and services is provided in order that users do not have to
resort to multiple elemental classifications for what is primarily a building project
time and costs for evaluating alternatives at the early design stage when economic analysis
is most important in establishing the most efficient choices between building alternatives
Elements
Elements are defined as major features, common to most buildings which usually perform a
given function regardless of the design, specification, construction method or materials used,
thus facilitating the use of information obtained from a building when estimating the cost of
other similar buildings
In selecting and defining the elements the following principles were used:
1. Each element should have a significant influence on the cost of a building and a high
frequency of occurrence
2. There should be consistency and simplicity in the definitions of elements. One of the
primary purposes of a standard list of elements and components is to enable cost
analyses to be made of completed projects
3. Wherever possible an element should be capable of measurement. Some of the
elements, such as Structural frame are related primarily to the horizontal surfaces of
the building, while others, such as External facade, are related primarily to the vertical
surfaces. These elements can usually be quantified, even in the very early stages of a
development, thus enabling a more accurate preliminary estimate to be made
4. Elements should apply to any building type
5. Elements separate building elements from building related external works and services
6. Elements should as far as is reasonable and practical relate to other international
elemental classifications such as the UNIFORMAT II (USA) and those of the Canadian
Institute of Quantity Surveyors (CIQS) and the Royal Institute of Chartered Surveyors
(RICS-UK)
ELEMENTS
COMPONENTS
Primary elements
Substructure
Ground floor
Solid floors
Insulation
Suspended floors
Steps
Ramps
Service ducts, trenches, etc
Pits and bases
Sub-surface drains
Catch pits, sumps, etc
Pumps
Structural frame
Slabs
Precast / composite decking systems
Ramps
Staircases and fire escapes
Columns
Beams
Portal frames
Space frames
Steel frames
Timber frames
External facade
Roofs
Construction
Coverings
Glazed roofs
Roof, lantern, skylights and openings
Dormers, hatches, etc
Waterproofing
Insulation
Trafficable surfaces
Eaves
Verges
Rain water drainage
Ventilators and cowls
Chimneys
Internal divisions
Partitions
Office partitions
Toilet partitions
Doors
Floor finishes
Finishes
Rails, corner protectors, etc
Ceiling finishes
Fittings
Built-in cupboards
Cupboards fixed to walls
Pigeon hole fittings, mail boxes, etc
Room dividers
White, chalk, etc boards
Pinning, bulletin, etc boards
Building directories
Raised platforms
Counters
Kitchen floor and wall cupboards
10
Plumbing
Sanitary fittings
Pods
Sanitary fitting sundries
Plumbing
Duct covers
Cold water supplies
Hot water supplies
Steam and condensate distribution
Geysers
Boilers
Solar heating
Heat pumps
Water storage tanks
Booster pumps
Grey water systems
Builders work
Profit and attendance
Fire protection
Fire stops
Fire resistant paint, etc
Extinguishers
Hose reels
Water supply
Water storage tanks
Booster pumps
Builders work
Profit and attendance
Balustrade walls
Parapet walls
Steel handrails
Timber handrails
Steel balustrading
Timber balustrading
Glazed balustrading
11
Specialist
installations
Miscellaneous items
Special foundations
Sheet piling
Driven piles
Cast in-situ piles
Augured piles
Vibro-compacted columns
Establishment, etc
Pile testing, etc
Caissons
Raft foundations
Underpinning, etc
Shoring
Dewatering
Builders work
Profit and attendance
Sprinklers
Fire detection and alarm
Building evacuation
Foam generating
Fire suppression
Smoke ventilation / control
Builders work
Profit and attendance
Conveyance systems
Passenger lifts
Freight lifts
Car lifts
Wheel chair lifts
Hoists
Dumbwaiters
Pneumatic tubes
Chutes
Turntables
Transportation systems
Funiculars
Escalators
Travelators
Conveyors
Builders work
Profit and attendance
Air conditioning
Energy supply
Heat generating systems
Chillers
Cooling towers, etc
Piping and fittings, etc
12
Ventilation
Builders work
Profit and attendance
Electronic systems
Building management
Voice data
Television
Other electronic systems
Builders work
Profit and attendance
Other services
Gas installation
Other services
Builders work
Profit and attendance
13
Turnstiles
Builders work
Profit and attendance
Equipment
Signage
Building signage
Signage pylons, towers, etc
Directional, identification, safety, etc
Flagpoles
Builders work
Profit and attendance
Artwork
Cabinetry, etc
Window treatment
Floor mats, etc
Multiple seating
Interior landscaping
Interior seating benches, rubbish bins,
etc
Builders work
Profit and attendance
Miscellaneous items
Fireplaces, etc
Saunas
Jacuzzis
Other
Builders work
Profit and attendance
Commercial
Institutional
Ecclesiastical
Library
Theatre and stage
Instrumental
Audio-visual
Detention
Research
Medical
Mortuary
Builders work
Profit and attendance
14
Vehicular
Vehicular service
Parking control
Loading dock
Builders work
Profit and attendance
Other
Maintenance
Faade cleaning
Solid waste handling
Food storage service
Domestic appliances
Commercial kitchen
Cold rooms
Darkroom, etc
Athletic, recreational, playground and
therapeutic
Planetarium
Observatory
Agricultural
Builders work
Profit and attendance
Tenant installations
Tenant installations
Alterations
Alterations
Demolitions
Buildings
Relocation of buildings and utilities
Breaking up and removing
Taking down and removing
Toxic / hazardous building materials
and components
Site clearance
Earthworks
15
Lateral support
Dewatering
Sundries
Soil drainage
Soil drains
Laboratory and industrial liquid waste
drainage
Manholes, inspection chambers, etc
Pump stations
Waste water treatment plants
Septic tanks, etc
Sub-surface drains
Catch pits, inspection chambers,
sumps, etc
Pumps, etc
Water supply
Fire service
Incoming main
Site reticulation
Twin booster connections
Hydrants, pedestals, etc
Electrical installation
Electrification
Incoming main
Site reticulation
Site communications and security
Substations and transformers
Emergency power generating
Photovoltaic / wind generation
Fuel tanks
Street, bollard, etc lighting
Floodlighting
Builders work
Profit and attendance
16
Soil drainage
Storm water drainage
Water supply
Fire service
Electrical installation
Gas and fuel
Boundary walls
Screen walls
Retaining walls
Terrace and perimeter walls
Doors
Gates
Fences
Railings
Gates
Roads
Parking areas
Paving
Steps and ramps
Bridges
Kerbs and gutters
Bollards
Rails and barriers
Painted lines, markings and signage
Covered parking
Covered walkways
Pergolas
Canopies
Pools, etc
Sports facilities
Playing fields
Spectator seating, stands, etc
Change rooms, etc
Garden works
Landscaping
Irrigation systems
Miscellaneous items
17
Preliminaries
Preliminaries
Preliminaries
Contingency
allowances
Escalation
Pre-tender
Contract
Pre-tender
Contract
Tax
General allowances
Preliminaries
As it is a significant cost element in most construction projects it is recommended that the
allowance for principal contractors preliminaries be treated as a separate cost element and
added as a percentage to the total cost of the estimate. Alternatively, it can be assessed as
a lump sum. The allowance can be derived from analyses of past projects of a similar nature
and construction period
Subcontractors preliminaries are to be included in the unit rates applied to measured
quantities
Contingency and escalation allowances
Construction cost summaries should include mark-ups for:
1. Risk and contingency allowances
All building projects involve risk and uncertainty. The risk and uncertainty diminishes as
the building project progresses. The costs of major scope changes are not included in
this allowance. Major scope changes require additional funding or a change in
programme requirements
Contingency allowances should be treated as the following two separate and distinct
cost elements and included in each estimate of construction cost:
1.1. Price and detail development contingency
Considering the limited information about the building and site conditions available
at the initial concept stage the contingency allowance may be a significant
percentage of the total estimated costs. The more complex or unique the project is,
the higher the initial allowance may be. Price and detail development contingency
allowances reduce to zero by completion of the working drawings, when complete
project information is available. This allowance is for additional items or changes
that occur as the design and pricing progresses
18
19
5. DEFINITIONS
Symbols, abbreviations and definitions
Symbols contained in this guide are as listed below:
Symbols used for measurement
Symbol
mm
m
m
m
No
kg
kN
kW
t
Description
Millimetre
Metre
Square metre
Cubic metre
Number
Kilogram
Kilonewton
Kilowatt
Tonne
Unit of measurement
Per parking bay
Per m of construction area
Per m of construction area
Per m of construction area
Per m of construction area
Per m of construction area
Per bedroom
Per key
Per bedroom
Per seat
Per bed
Per cell
Per seat
Per seat
Per pupil
Abbr
Ea.
m
m
m
m
m
Ea.
Ea.
Ea.
Ea.
Ea.
Ea.
Ea.
Ea.
Ea.
Definitions
Component - means a measured item which forms part of an element or a sub element.
Each element is subdivided into components (eg the element Roofs is subdivided into the
components of Construction, Coverings, Glazed roofs, etc). Where a specific component
forms a high cost portion of the estimate, such component should be further subdivided into
subcomponents
Construction area means the construction area of a building and is the total of all the
areas of a building measured on plan at each covered floor level over the external walls or
external lines of the outermost vertical enclosing planes or, where applicable, the centre line
of party walls between buildings
The following items are included in the calculation of construction area:
20
Escalation means an allowance included in the estimate for fluctuations in the prices of
labour, plant and equipment and materials. It can be positive or negative. Refer also to pretender escalation and contract escalation
Estimate base date means the date on which the cost of an estimate is determined as a
basis for calculating escalation, etc
Fluctuation Refer to pre-tender escalation and contract escalation
Functional unit means a unit of measurement used to represent the prime use of a
building or part of a building (eg per hospital bed, per hotel room / key and per m of retail
area). It also includes all associated circulation space
Overheads and profit Refer to principal contractors overheads and profit
Preliminaries Refer to principal contractors preliminaries
Pre-tender escalation means an allowance included for escalation during the period
from the base date of the estimate to the contract tender date. Refer also to contract
escalation
Principal contractor means the contractor appointed for the total construction and
completion of the building project
Principal contractors overheads and profit Refer to Principal contractors
preliminaries
Principal contractors preliminaries include costs associated with salaries and wages,
setting out, hoardings and gantries, signboards, offices, office furniture and equipment,
consumables, sheds, toilets, major plant, equipment, gear and loose tools, temporary
services, scaffolding, vehicles / transport, safety measures and equipment, cleaning,
insurances, head office administration proportioned to each project plus the return on capital
invested. It excludes costs associated with subcontractors overheads and profit and
subcontractors preliminaries
Quantity means the actual measured quantity of an element or component
Rentable area means the total revenue-producing area of the building as defined in the
SAPOA Method for Measuring Floor Areas in Buildings or other appropriate definition of
rentable (lettable) area
Sections means the subdivision of elements into the following sections: Primary Elements,
Specialist Installations, Equipment, Tenant installations, Alterations, External Works and
Services, Preliminaries, Contingency Allowances, Escalation and Tax
Subcontractor means a nominated or selected subcontractor who executes specialist
work within the building development
Subcontractors overheads and profit means overheads and profit that relate
specifically to building work which is to be carried out by a subcontractor, which overheads
and profits are to be included in the unit rates
Subcontractors preliminaries means preliminaries that relate specifically to building
work which is to be carried out by a subcontractor, which preliminaries are to be included
in the unit rates
22
Tenant installation allowances means allowances included in the total estimated costs
for all elements and components comprising the anticipated tenant installation costs within
the applicable rentable space
Unit quantity means the quantity (metre, area, number, etc) measured for each element
Unit rate means the monetary rate applied to an element or component per unit of
measurement (eg cost per m, cost per m and cost per m). The term is also relevant to
costs per m of construction area and cost per functional unit
23
CONTRACTORS FEE and TRAINING have been omitted as it fell largely in disuse
24
Component
A component is a subdivision of an element
Measurement required for element or component
The measurement required is the actual quantitative unit of the element or component. Each
of the elements or components is considered and evaluated in the plane in which it occurs
(eg the element Roofs would be evaluated per square metre in the various planes of the
roof, the component Downpipes per metre length and the component Dormers per unit
number). The quantity of an element or a component is measured and multiplied by a
monetary rate thus obtaining an estimated construction cost for that element or component
Unit
Unit denotes the unit of measurement of the individual element or component
Composition of element or component
Each element comprises various components. Each component comprises various parts or
subcomponents
25
26
CODE
100
SECTION AND
ELEMENT
CODE
COMPONENTS
MEASUREMENT
REQUIRED FOR ELEMENT
OR COMPONENT
UNIT
COMPOSITION OF ELEMENT
OR COMPONENT
PRIMARY
ELEMENTS
Substructure
100.10
Un-reinforced strip
footings
Length on plan
100.15
Reinforced strip
footings
Length on plan
27
100.20
Ground beams
Length on plan
100.25
Column bases
and pile caps
Number
no
100.30
Number
no
100.35
Columns
Length
100.40
Length on plan
28
walls
State height of wall
101
Ground floor
100.45
Concrete walls
Length on plan
100.50
Plinth finishes
Area on elevations
100.55
Rock, etc
excavation
Volume
100.60
Sundries
Measure dewatering to
basements under 602.45
Dewatering
Each component to be
measured in the applicable unit
of measurement
29
walls
101.10
Solid floors
101.15
Insulation
101.20
Suspended floors
Excavation, disposal of
excavated material, ant
proofing, concrete, brickwork
and ties to sleeper piers, wall
plates, sleepers, bearers, floor
joists, boarding, battens, slabs,
formwork and reinforcement,
etc
101.25
Steps
Excavations, disposal of
excavated material, filling,
compaction, ant proofing, hard
core, under floor waterproofing,
concrete, formwork,
reinforcement, etc
101.30
Ramps
Excavations, disposal of
30
101.35
Service ducts,
trenches, etc
Length on plan
Excavations, disposal of
excavated material,
compaction, ant proofing,
under floor waterproofing,
concrete, formwork,
reinforcement, brickwork,
gratings, covers, etc
101.40
Number
no
Excavations, disposal of
excavated material,
compaction, under floor
waterproofing, concrete,
reinforcement, gratings,
covers, etc
101.45
Sub-surface
drains
Length
Excavations, disposal of
excavated material, subsurface drains, stone chips,
geofabric filter blanket, floor
31
102
surface drains
Measure different types of
gratings, covers, etc to internal
manholes separately
101.50
Number
no
Excavations, disposal of
excavated material,
compaction, under floor
waterproofing, concrete,
reinforcement, gratings,
covers, etc
101.55
Pumps
Number
no
Structural frame
102.10
Slabs
32
reinforcement, structural
steelwork, stressing cables,
tamped finish, power floating,
broomed finish and sundry
items
102.15
Precast /
composite
decking systems
Area on plan of
precast/composite decking
systems
102.20
Ramps
102.25
Staircases and
fire escapes
33
level
otherwise), steel
reinforcement, metal pan,
structural steelwork, timber and
sundry items
102.30
Columns
Length
102.35
Beams
Length
102.40
Portal frames
102.45
Space frames
Area on plan
34
decorative paint
103
External facade
102.50
Steel frames
Area on plan
102.55
Timber frames
Area on plan
35
103.15
Concrete walls
103.20
Waterproofing,
drainage, etc
Area on elevation
103.25
Cladding
103.30
Finishes
Area on elevation
36
Curtain walls
Area on elevation
103.40
Doors to be measured
separately as "extra over".
Measure single, double and
rotating doors separately
State provisional sum net rate if
applicable
State if remote controlled
Measure bulkhead construction,
fixing and finishes thereof
separately
103.45
Windows
Area on elevation
103.50
Sun control
Area on elevation
103.55
Grilles, screens,
louvers, etc
Area on elevation
37
104
103.60
Doors
Number
no
103.65
Special doors
Number
no
Roofs
104.10
Construction
104.15
Coverings
38
Glazed roofs
Area
104.25
Roof, lantern,
skylights and
openings
Area
104.30
Dormers, hatches,
etc
Number
no
Construction, cladding,
covering, flashing, window,
glass and paint, etc
104.35
Waterproofing
39
Insulation
104.45
Trafficable
surfaces
104.50
Eaves
Length
104.55
Verges
Length
104.60
Rain water
drainage
Length
40
105
104.65
Ventilators and
cowls
Number
no
104.70
Chimneys
Number
no
Internal divisions
105.10
105.15
Concrete walls
105.20
Doors to be measured
separately as "extra over".
Measure single, double and
rotating doors separately
State provisional sum net rate if
applicable
State if remote controlled
Measure bulkhead construction,
fixing and finishes thereof
separately
105.25
Borrowed lights
Area on elevation
41
106
separately
105.30
Hatches and
access doors
Number
no
105.35
Screens, etc
Area on elevation
105.40
Doors
Number
no
105.45
Special doors
Number
no
Area on elevation of
partitions measured over
doors, sidelights, fanlights
and borrowed lights
Demountable, operable,
retractable/movable, fixed, fire
rated and glazed partitions,
frames, doors, fanlights,
borrowed lights, ironmongery,
finishes, attached skirtings and
cornices, glass, etc
Area on elevation
Partitions
106.10
Office partitions
42
107
106.15
Toilet partitions
Area on elevation
Toilet partitioning/cubicles,
finishes, attached skirtings, etc
106.20
Doors
Number
no
Floor finishes
107.10
Applied floor
finishes
43
107.15
Suspended floor
finishes
107.20
Raised access
floors
107.25
107.30
Skirtings, etc
Length
44
109
Internal wall
finishes
Ceiling finishes
108.10
Finishes
108.15
Rails, corner
protectors, etc
Length
45
openings)
110
Fittings
109.10
109.15
Nailed-up ceilings
109.20
Suspended
ceilings
109.25
Bulkheads
Length on plan
109.30
Cornices, etc
Length on plan
Construction area
46
finishes, etc
110.10
Built-in cupboards
Length
110.15
Cupboards fixed
to walls
Length
110.20
Pigeon hole
fittings, mail
boxes, etc
Length
110.25
Room dividers
Length
110.30
Area on elevation
110.35
Pinning, bulletin,
etc boards
Area on elevation
110.40
Building
directories
Number
no
47
110.45
Raised platforms
Area on plan
110.50
Counters
Length
Counters
110.55
Length on plan
110.60
Worktops,
benches, vanities,
etc
Length on plan
110.65
Shelving
Length
110.70
Seating benches
Length on plan
110.75
Lockers
Number
no
110.80
Telephone
Number
no
48
enclosures
111
separately
110.85
Tables
Number
no
110.90
Lecterns, etc
Number
no
Lecterns, etc
110.95
Miscellaneous
Number
no
Construction area
Electrical
installation
(refer also to 206,
207 and 608)
111.10
Main switchboard,
etc
Area
111.15
Circuit wiring
Area
111.20
Luminaires
Area
49
112
111.25
Emergency
lighting
Area
111.30
Special light
fittings
Number
no
111.35
Builder's work
Construction area
111.40
Profit and
attendance
Construction area
no
Plumbing
112.10
Sanitary fittings
Number
no
112.15
Pods
Number
no
50
112.20
Sanitary fitting
sundries
Number
no
112.25
Plumbing
Number
no
112.30
Duct covers
Number
no
112.35
Cold water
supplies
Number
no
51
112.40
Number
no
112.45
Steam and
condensate
distribution
Number
no
112.50
Geysers
Number
no
112.55
Boilers
Number
no
52
113
Fire protection
(refer also to 201)
112.60
Solar heating
Number
no
112.65
Heat pumps
Number
no
112.70
Water storage
tanks
Number
no
112.75
Booster pumps
Number
no
112.80
Grey water
systems
Number
no
112.85
Builders work
Number
no
112.90
Profit and
attendance
Number
no
no
53
Fire stops
Area
113.15
Fire resistant
paint, etc
Area
113.20
Extinguishers
Number
no
Extinguishers including
backing boards, etc
113.25
Hose reels
Number
no
113.30
Water supply
Number
no
113.35
Water storage
tanks
Number
no
113.40
Booster pumps
Number
no
113.45
Builders work
Number
no
54
113.50
114
Profit and
attendance
Balustrading,
handrails, etc
Number
no
Balustrading, handrails,
balustrade and parapet walls
114.10
Balustrade walls
Length
114.20
Parapet walls
Length
114.25
Steel handrails
Length
114.30
Timber handrails
Length
114.35
Steel balustrading
Length
114.40
Timber
balustrading
Length
114.45
Glazed
Length
55
balustrading
115
200
Miscellaneous
items
separately
State height
115.10
Catwalks, ladders,
etc
Length
Catwalk construction,
handrails, finishes, fire escape
ladders, chutes/slides, access,
loft ladders, including hatch
doors, etc
115.15
Bollards
Number
no
115.20
Other
Number
no
SPECIALIST
INSTALLATIONS
Special
foundations
200.10
Sheet piling
Area on elevation
200.15
Driven piles
Number
no
56
200.20
Number
no
200.25
Augured piles
Number
no
200.30
Vibro-compacted
columns
Number
no
Vibro-compacted columns
excluding builders work
200.35
Establishment, etc
Number
no
200.40
Number
no
200.45
Caissons
Number
no
200.50
Raft foundations
200.55
Underpinning, etc
Length on plan
Underpinning, special
precautions, etc excluding
builders work
200.60
Shoring
Area on elevation
57
builders work
201
200.65
Dewatering
200.70
Builders work
200.75
Profit and
attendance
Special fire
protection
systems
(refer also to 113)
201.10
Sprinklers
58
202
Conveyance
201.15
201.20
Building
evacuation
201.25
Foam generating
201.30
Fire suppression
201.35
Smoke ventilation
/ control
201.40
Builder's work
201.45
Profit and
attendance
Number of installations
no
59
systems
202.10
Passenger lifts
Number
no
202.15
Freight lifts
Number
no
202.20
Car lifts
Number
no
202.25
Number
no
60
202.30
Hoists
Number
no
202.35
Dumbwaiters
Number
no
202.40
Pneumatic tubes
Number
no
202.45
Chutes
Number
no
202.50
Turntables
Number
no
202.55
Transportation
systems
Number
no
202.60
Funiculars
Number
no
61
203
Air conditioning
work
202.65
Escalators
Number
no
202.70
Travelators
Number
no
202.75
Conveyors
Number
no
202.80
Builder's work
Number
no
202.85
Profit and
attendance
Number
no
62
builders work
203.10
Energy supply
203.15
Heat generating
systems
203.20
Chillers
203.25
Cooling towers,
etc
203.30
203.35
63
attenuation, vibration
insulation, piping and insulation
excluding builders work
203.40
Ventilation and
exhaust systems
203.45
203.50
Heat recovery
equipment
203.55
Air conditioning
units
Window or through-the-wall
units excluding builders work
203.60
Reverse-cycle, etc
terminal heat
pumps
203.65
Self-contained air
conditioners, etc
64
builders work
204
203.70
Testing and
balancing
203.75
Other systems
and equipment
203.80
Builder's work
203.85
Profit and
attendance
Ventilation
204.10
Ventilation
65
205
204.15
Builder's work
204.20
Profit and
attendance
Heating and
cooling
205.10
Heat generating
systems
205.15
Cooling
generating
66
206
systems
generating systems
205.20
Builder's work
205.25
Profit and
attendance
Construction area
Special electrical
systems (refer
also to 111, 207
and 608)
206.10
Uninterrupted
power supply
Number
no
206.15
Clean power
supply
Number
no
206.20
Power factor
correction
Number
no
206.25
Lightning and
grounding
protection
Number
no
67
207
206.30
Power generating
Number
no
206.35
Other special
electrical systems
Number
no
206.40
Builder's work
Construction area
206.45
Profit and
attendance
Construction area
Construction area
Electronic
systems
(refer also to 111,
206 and 608)
207.10
Building
management
Number
no
207.15
Voice data
Number
no
207.20
Television
Number
no
207.25
Other electronic
systems
Number
no
68
208
209
207.30
Builders work
Construction area
207.35
Profit and
attendance
Construction area
Construction area
Other services
208.10
Gas installation
Construction area
208.15
Other services
Number
no
208.20
Builder's work
Construction area
208.25
Profit and
attendance
Construction area
Number
no
Communications
and security
209.10
Public address
and music
systems
69
209.15
Intercommunication
and paging
systems
Number
no
209.20
Telephone
systems
Number
no
209.25
Call systems
Number
no
209.30
Closed circuit
television systems
Number
no
209.35
Local area
network systems
Number
no
209.40
Clock and
programme
systems
Number
no
209.45
Fire alarm
systems
Number
no
209.50
Security and
detection systems
Number
no
209.55
Turnstiles
Number
no
70
210
209.60
Builder's work
Number
no
209.65
Profit and
attendance
Number
no
Construction area
Signage
210.10
Building signage
Number
no
210.15
Signage pylons,
towers, etc
Number
no
210.20
Directional,
identification,
safety, etc
Number
no
210.25
Flagpoles
Number
no
State height
210.30
Builder's work
Number
no
71
210.35
211
Profit and
attendance
Artwork,
furnishings, etc
Number
no
Construction area
Statues, ornamentation,
artworks, murals, fountains,
etc
211.10
Artwork
Number
no
211.15
Cabinetry, etc
Number
no
211.20
Window treatment
Number
no
211.25
Number
no
211.30
Multiple seating
Number
no
211.35
Interior
landscaping
Number
no
211.40
Interior seating
benches, rubbish
bins, etc
Number
no
72
212
211.45
Builders work
Number
no
211.50
Profit and
attendance
Number
no
Construction area
Miscellaneous
items
212.10
Fireplaces, etc
Number
no
212.15
Saunas
Number
no
212.20
Jacuzzis
Number
no
212.25
Other
Number
no
212.30
Builders work
Number
no
73
212.35
EQUIPMENT
300
Commercial
Profit and
attendance
Number
no
Construction area
300.10
Number
no
300.15
Number
no
300.20
Registration
Number
no
Registration equipment
installation excluding builders
work
300.25
Checkroom
Number
no
Checkroom equipment
installation excluding builders
work
300.30
Trading
Number
no
74
301
300.35
Commercial
laundry and dry
cleaning
Number
no
300.40
Vending
Number
no
300.45
Office
Number
no
300.50
Builders work
Construction area
300.55
Profit and
attendance
Construction area
Construction area
Institutional
301.10
Ecclesiastical
Number
no
301.15
Library
Number
no
75
301.20
Number
no
301.25
Instrumental
Number
no
Instrumental equipment
installation excluding builders
work
301.30
Audio-visual
Number
no
301.35
Detention
Number
no
301.40
Research
Number
no
301.45
Medical
Number
no
76
autoclaves, medical / LP
gases, etc) installation
excluding builders work
302
301.50
Mortuary
Number
no
301.55
Builders work
Construction area
301.60
Profit and
attendance
Construction area
Construction area
Vehicular
302.10
Vehicular service
Number
no
302.15
Parking control
Number
no
77
303
302.20
Loading dock
Number
no
302.25
Builders work
Construction area
302.30
Profit and
attendance
Construction area
Construction area
Other
303.10
Maintenance
Number
no
303.15
Facade cleaning
Number
no
303.20
Solid waste
handling
Number
no
Incinerators, compactors,
shredders, balers, etc
installation excluding builders
work
303.25
Food storage
service
Number
no
78
equipment installation
excluding builders work
303.30
Domestic
appliances
Number
no
303.35
Commercial
kitchen
Number
no
303.40
Cold rooms
Number
no
303.45
Darkroom, etc
Number
no
303.50
Athletic,
recreational,
playground and
Number
no
Athletic, recreational,
playground and therapeutic
equipment installation
79
therapeutic
400
303.55
Planetarium
Number
no
Planetarium equipment
installation excluding builders
work
303.60
Observatory
Number
no
Observatory equipment
installation excluding builders
work
303.65
Agricultural
Number
no
Agricultural equipment
installation excluding builders
work
303.70
Builders work
Construction area
303.75
Profit and
attendance
Construction area
Rentable area
Rentable area
TENANT
INSTALLATIONS
Tenant
installations
400.10
Tenant installation
allowances
80
ALTERATIONS
Alterations
500.10
Temporary
barriers, screens,
etc
Area on elevation
Measure in detail
500.15
Removal of
existing work
Area
Measure in detail
Measure in number or length if
area is inappropriate
Measure removal of toxic /
hazardous building materials
and components under 600.30
Toxic / Hazardous building
materials and components
500.20
Cutting through
floors and ceilings
Number
no
Measure in detail
500.25
Building up
openings
Area
Measure in detail
Measure in number or length if
area is inappropriate
81
EXTERNAL
WORKS AND
SERVICES
600
Demolitions
500.30
Preparatory work
to existing
surfaces
Area
Measure in detail
500.35
Making good of
finishes, etc
Area
Measure in detail
Measure in number or length if
area is inappropriate
500.40
Openings through
existing walls, etc
Number
no
Measure in detail
500.45
Cleaning existing
surfaces
Area
Measure in detail
500.50
Protective
coatings to
existing surfaces
Area
Specialist painting/coating
systems, lime washing,
colourless water proofers, antigraffiti colourless coatings,
bird/vermin repellent coatings,
etc to protect existing internal
and external surfaces
Construction area
Complete demolition of
buildings, removal of rubble,
etc
600.10
Buildings
82
601
600.15
Relocation of
buildings and
utilities
Number
no
600.20
Breaking up and
removing
Area
Measure in detail
Measure in number or length if
area is inappropriate
600.25
Area
Measure in detail
Measure in number or length if
area is inappropriate
600.30
Toxic / hazardous
building materials
and components
Area
Measure in detail
Measure in number or length if
area is inappropriate
Allow for special hoarding
requirements under 7
Preliminaries
Area
Site clearance
601.10
83
602
601.15
Contaminated
land
Area
601.20
Trees
Number
no
601.25
Hedges, fences,
etc
Length
Earthworks
602.10
Grading and
excavation
Volume
602.15
Filling
Volume
602.20
Soil stabilisation
Area
84
electrochemical stabilisation,
sand stowing, compacting
surrounding soil and filling with
aggregates or hard fill, by
means of power vibrators, soil
nailing, ground anchors,
pressure grouting, compacting,
freezing of ground water and
subsoil, stabilising soil in situ
by incorporating
cement with a rotovator, etc
soil stabilisation measures
separately
602.25
Basement
excavation
Volume of excavations
measured over external
walls
602.30
Rock, etc
excavation
Volume
602.35
Lateral support
Length
602.40
Dewatering
Number
no
85
602.45
603
Sundries
Soil drainage
Volume of excavations
measured over external
walls
603.10
Soil drains
Length
603.15
Laboratory and
industrial liquid
waste drainage
Length
603.20
Manholes,
inspection
chambers, etc
Number
no
Manholes, inspection
chambers, etc complete with
channelling, covers, etc
86
604
605
603.25
Pump stations
Number
no
603.30
Waste water
treatment plants
Number
no
State capacity
State whether above or below
ground
603.35
Number
no
Sub-surface
water drainage
Storm water
604.10
Sub-surface
drains
Length
Excavations, sub-surface
drains, stone chips, geofabric
filter blanket, etc
604.15
Catch pits,
inspection
chambers, sumps,
etc
Number
no
604.20
Pumps, etc
Number
no
87
drainage
606
Water supply
605.10
Surface water
channelling
Length
605.15
Piping
Length
605.20
Ditches and
culverts
Length
605.25
Rain water
harvesting
Number
no
605.30
Retention ponds
Area
605.35
Manholes, catch
pits, inspection
chambers, sumps,
etc
Number
no
605.40
Pumps
Number
no
88
Potable incoming
main
Length
606.15
Potable site
reticulation
Length
606.20
Non-potable site
reticulation
Length
606.25
Chilled water
reticulation
Length of piping
606.30
Steam and
condensate
distribution
Length of piping
89
607
606.35
Storage tanks
Number
no
State capacity
State whether above or below
ground
606.40
Well systems,
boreholes, etc
Number
no
State depth
Fire service
607.10
Incoming main
Length
607.15
Site reticulation
Length
607.20
Twin booster
connections
Number
no
Booster connections,
standpipe, connection to
mains, etc
90
607.25
608
Hydrants,
pedestals, etc
Electrical
installation (refer
also to 111, 206
and 207)
Number
no
608.10
Electrification
Number
no
State capacity
608.15
Incoming main
Length
608.20
Site reticulation
Length
608.25
Site
communications
and security
Length
608.30
Substations and
transformers
Number
no
91
etc
608.35
Emergency power
generating
Number
no
608.40
Photovoltaic /
wind generation
Number
no
Photovoltaic or wind
generation systems, sundry
builders work, etc
608.45
Fuel tanks
Number
no
State capacity
State whether above or below
ground
608.50
Number
no
608.55
Floodlighting
Number
no
608.60
Builders work
Number
no
608.65
Profit and
attendance
Number
no
92
608.55 above
609
610
611
Storage and
distribution
Connection fees,
etc
Boundary,
Length of piping
no
610.10
Soil drainage
Number
no
610.15
Storm water
drainage
Number
no
610.20
Water supply
Number
no
610.25
Fire service
Number
no
610.30
Electrical
installation
Number
no
610.35
Number
no
93
etc
screen, retaining
walls, etc
612
611.10
Boundary walls
Area on elevation
611.15
Screen walls
Area on elevation
611.20
Retaining walls
Area on elevation
611.25
Terrace and
perimeter walls
Area on elevation
611.30
Doors
Number
no
611.35
Gates
Number
no
Length
Fences and
railings
612.10
Fences
94
613
screening, standards,
droppers, posts, footings, etc
612.15
Railings
Length
612.20
Gates
Number
no
Roads, paving,
etc
613.10
Roads
Area
613.15
Parking areas
Area
95
Paving
Area
613.25
Area
613.30
Bridges
Area
613.35
Length
613.40
Bollards
Number
no
Bollards, etc
613.45
Length
613.50
Painted lines,
Number
no
96
markings and
signage
614
615
616
Covered parking,
walkways, etc
separately
614.10
Covered parking
Area on plan
614.15
Covered
walkways
Area on plan
Foundations, construction,
covering, supports, etc
Pergolas,
canopies, etc
Minor
construction
work
615.10
Pergolas
Area on plan
Foundations, construction,
covering, supports, etc
615.15
Canopies
Area on plan
Construction, covering,
supports, etc
Miscellaneous structures on
site such as gate houses,
guard huts, boiler houses, substation buildings, bicycle
stores, prefabricated/timber
workshops, sheds, stores,
97
617
618
Minor construction
work
Pools, etc
Area on plan
All elements
Number of pools
no
617.10
Swimming pools,
etc
Number
no
617.15
Decorative
fountains and
water courses
Number
no
617.20
Change rooms,
etc
Area on plan
no
Number
no
Sports facilities
618.10
Playing fields
98
619
separately
618.15
Spectator seating,
stands, etc
Number
no
618.20
Change rooms,
etc
Area on plan
Garden works
619.10
Landscaping
619.15
Irrigation systems
99
620
7
700
Miscellaneous
items
800
620.10
Site / street
furniture and
equipment
Number
no
620.15
Other
Number
no
Construction area
Construction area
Construction area
PRELIMINARIES
Preliminaries
700.10
Construction area
Preliminaries
CONTINGENCY
ALLOWANCES
Contingency
allowances
100
10
1000
1001
800.10
Construction area
800.15
Construction
contingency
Construction area
900.10
Pre-tender
Construction area
901.15
Contract
Construction area
Construction area
ESCALATION
TAX
Value added tax
1000.10
Construction area
1001.10
Sales tax
Construction area
Sales tax
101
8. EXAMPLES
Elemental estimate cost summaries
The proposed summary sheet for presenting building and site work elemental costs with cost
analysis parameters provides an efficient tool for communicating economic information to
decision makers in a quickly understood, concise format that helps them make project
choices
The summary format helps them:
1. Understand the cost profile of the entire project
2. Analyse cost using analytical parameters. This can be done for most elements without
having to refer to back-up information contained in the detail sheets
3. Identify potential cost overruns early to initiate corrective action
Site
Drawing numbers
Scale
Status of cost plan
Basis of cost plan (ie assumptions)
Estimate base date
Inclusions and exclusions
Description
The list of sections and elements
Cost
Cost is the cost of an element and is the aggregate of the component costs comprising the
particular element
Quantity
Quantity is the actual measured quantity of an element or component
Unit
Unit denotes the unit of measurement of the individual element or component
Cost per square metre is the cost of the element divided by the construction area. Where
appropriate and/or required by an employer, costs may also be expressed as a cost per
functional unit as an alternative to, or in addition to, the cost/m. The functional unit may be
an employer defined unit. It is therefore essential to define the functional unit clearly when
costs are expressed in this way
Cost (percentage) %
Cost % is the cost of the element expressed as a proportion of the total cost
103
EXAMPLE A
TYPICAL EXAMPLE OF THE LAYOUT OF AN ELEMENTAL ESTIMATE
ELEMENT 103: EXTERNAL FACADE
Elements
Component
Description
103 External
facade
103.10 Brick
and block walls
103.30 Finishes
103.35 Curtain
walls
103.45 Windows
103.60 Doors
5 860
622.03
3 645 125
956
375.00
358 500
1 809
125.00
226 125
142
1 650.00
234 300
1 946
1 450.00
2 821 700
no
4 500.00
4 500
Element
Rate
Cost
R*
193.61
104
3.53
EXAMPLE B
TYPICAL EXAMPLE OF AN ELEMENTAL ESTIMATE SUMMARY
ESTIMATE OF ESCALATED CONSTRUCTION COST AT CONTRACT COMPLETION
DATE INCLUDING VALUE ADDED TAX (VAT)** (28/02/2014)
SUMMARY OF CONSTRUCTION COST
Construction
Cost
Primary elements
Specialist installations
Equipment
Tenant installations
Alterations
External works and services
Price and detail development
contingencies
Preliminaries
ESTIMATE OF CONSTRUCTION COST
EXCLUDING CONSTRUCTION
CONTINGENCIES (04/07/2012)
Construction contingencies
ESTIMATE OF CURRENT
CONSTRUCTION COST EXCLUDING
VAT** (04/07/2012)
Pre-tender escalation
Contract escalation
ESTIMATE OF ESCALATED
CONSTRUCTION COST AT CONTRACT
COMPLETION DATE EXCLUDING
VALUE ADDED TAX (VAT)** (28/02/2014)
R*
49 962 950
19 483 050
14 215 300
R*
2 653.79
1 034.85
755.05
% of
construction
cost
%
48.36
18.86
13.76
4 183 700
222.22
4.05
10 542 000
559.94
10.20
98 387 000
5 225.85
95.23
4 923 000
261.49
4.77
5 487.33
100.00
9 480 100
7 312 500
503.54
388.40
9.18
7.08
6 379.27
116.26
16 814 360
893.10
16.28
7 272.37
132.54
18 827m
:
:
:
:
:
4 July 2012
1 February 2013
1 March 2013
28 February 2014
1 March 2014
105
Rate
per m
ESCALATION:
Pre-tender escalation
Contract escalation
:
: 159.5
: 174.0
: 456.2
: 503.2
USER NOTE:
Other items comprising the total capital investment for the project should be reflected elsewhere eg:
Property costs
Local authority costs
Promotional costs
Sundry costs
Financing costs
Professional fees
Funding costs
Tenanting costs
106
EXAMPLE B - continued
100
101
102
103
104
105
106
107
108
109
110
111
112
113
114
115
2
200
201
202
203
204
205
206
207
208
209
210
211
212
3
300
301
302
303
4
400
5
500
Description
PRIMARY ELEMENTS
R*
49 962 950
18 827
Cost per
unit
R*
2 653.79
Substructure
Ground floor
Structural frame
External facade
Roofs
Internal divisions
Partitions
Floor finishes
Internal wall finishes
Ceiling finishes
Fittings
Electrical installation
Plumbing
Fire protection
Balustrading, handrails, etc
Miscellaneous items
2 097 660
1 313 000
14 139 400
8 402 130
2 144 660
2 305 540
4 000 500
2 418 010
1 603 890
3 503 400
271 000
5 289 500
944 650
480 850
1 048 760
-
5 252
5 252
18 889
5 860
5 806
3 393
5 931
18 168
8 712
19 632
18 827
18 827
93
226
883
-
m
m
m
m
m
m
m
m
m
m
m
m
no
no
m
m
399.40
250.00
748.55
1 433.81
369.39
679.50
674.51
133.09
184.10
178.45
14.39
280.95
10 157.53
2 127.65
1 187.72
-
111.42
69.74
751.02
446.28
113.91
122.46
212.49
128.43
85.19
186.08
14.39
280.95
50.18
25.54
55.71
-
2.03%
1.27%
13.69%
8.13%
2.08%
2.23%
3.87%
2.34%
1.55%
3.39%
0.26%
5.12%
0.91%
0.47%
1.02%
SPECIALIST
INSTALLATIONS
19 483 050
18 827
1 034.85
1 034.85
18.86%
3 360 590
5 252
639.87
178.50
3.25%
2 125 680
10 504
202.37
112.91
2.06%
1 840 000
8 603 700
1 553 080
1 325 000
-
3
7 667
5 252
18 827
-
no
m
m
m
m
m
m
613 333.33
1 122.17
295.71
70.38
-
97.73
456.99
82.49
70.38
-
1.78%
8.33%
1.50%
1.28%
-
515 000
18 827
27.35
27.35
0.50%
135 000
25 000
18 827
18 827
m
m
m
7.17
1.33
7.17
1.33
0.13%
0.02%
EQUIPMENT
Commercial
Institutional
Vehicular
Other
m
m
m
m
Tenant installations
ALTERATIONS
Alterations
Special foundations
Special fire protection
systems
Conveyance systems
Air conditioning
Ventilation
Heating and cooling
Special electrical systems
Electronic systems
Other services
Communications and
security
Signage
Artwork, furnishings, etc
Miscellaneous items
Cost
Quantity
Unit
Cost per
m
R*
2 653.79
Cost %
48.36%
TENANT INSTALLATIONS
107
EXAMPLE B continued
Description
Cost
Quantity
Unit
R*
EXTERNAL WORKS AND
SERVICES
600
601
602
603
604
605
606
607
608
609
610
611
612
613
614
615
616
617
618
619
620
Demolitions
Site clearance
Earthworks
Soil drainage
Sub-surface water drainage
Storm water drainage
Water supply
Fire service
Electrical installation
Gas and fuel distribution
Connection fees, etc
Boundary, screen, retaining
walls, etc
Fences and railings
Roads, paving, etc
Covered parking,
walkways, etc
Pergolas, canopies, etc
Minor construction work
Pools, etc
Sports facilities
Garden works
Miscellaneous items
Cost per
unit
R*
Cost per
m
R*
Cost %
14 215 300
18 827
755.05
755.05
13.76%
1 204 520
10 146 330
31 000
198 050
44 500
32 800
115 000
895 000
5 619
26 258
100
667
182
120
62
5
m
m
m
m
m
m
m
m
m
m
no
214.37
386.41
310.00
296.93
244.51
273.33
1 854.84
179 000.00
63.98
538.92
1.65
10.52
2.36
1.74
6.11
47.54
1.17%
9.82%
0.03%
0.19%
0.04%
0.03%
0.11%
0.87%
265 800
932 300
184
2 688
m
m
1 444.57
346.84
14.12
49.52
0.26%
0.90%
350 000
-
3 354
-
m
m
no
no
m
no
104.35
-
18.59
-
0.34%
-
4 183 700
18 827
222.22
222.22
4.05%
10 542 000
18 827
559.94
559.94
10.20%
98 387 000
18 827
5 225.85
5 225.85
95.23%
4 923 000
18 827
261.49
261.49
4.77%
18 827
5 487.33
5 487.33
100.00%
16 792 600
9 480 100
7 312 500
18 827
18 827
18 827
563.55
257.14
306.41
563.55
257.14
306.41
16.26%
9.18%
7.08%
16 814 360
-
18 827
-
m
m
m
m
m
m
847.12
-
847.12
-
16.28%
-
18 827
7 272.37
7 272.37
132.54%
108
8. INDEX
Africa Association of Quantity Surveyors . 3
Agricultural ....................................... 15, 80
Air conditioning ................................ 12, 62
Air conditioning units ........................ 13, 64
Altar........................................................ 75
Alterations .................................... 7, 15, 81
Animal shelters ...................................... 97
Applied floor finishes ........................ 10, 43
Artwork, furnishings, etc ................... 14, 72
Association of South African Quantity
Surveyors ................................................. 3
Athletic, recreational, playground and
therapeutic ....................................... 15, 79
Audio-visual ..................................... 14, 76
Augured piles ................................... 12, 57
Autoclaves ............................................. 76
Autopsy table ......................................... 77
Baggage handling .................................. 61
Balers ..................................................... 78
Balustrade walls ..................................... 55
Balustrading, handrails, etc .............. 11, 55
Band risers ............................................. 76
Banners.................................................. 72
Basement excavation ....................... 15, 85
Beams ................................................ 9, 34
Bedhead trunking ................................... 76
Benefits of elemental cost estimating ...... 6
Bicycle stores ......................................... 97
Boiler houses ......................................... 97
Boilers .............................................. 11, 52
Bollards ................................ 12, 17, 56, 96
Booster pumps ........................... 11, 53, 54
Borrowed lights ................................ 10, 41
Boundary walls................................. 17, 94
Boundary, screen, retaining walls, etc17, 93
Bowling greens ...................................... 98
Breaking up and removing ............... 15, 83
Brick and block walls........ 9, 10, 28, 36, 41
Bridges ............................................. 17, 96
Builders work11, 12, 13, 14, 15, 16, 50, 53,
54, 58, 59, 62, 65, 66, 67, 69, 71, 73, 75,
77, 78, 80, 92
Building directories........................... 10, 47
Building evacuation .......................... 12, 59
Building management ...................... 13, 68
Building signage............................... 14, 71
Building up openings........................ 15, 81
Buildings .......................................... 15, 82
Built-in cupboards ............................ 10, 47
Bulkheads ........................................ 10, 46
Bullet resistant teller window .................. 74
Cabinetry, etc ................................... 14, 72
Caissons .......................................... 12, 57
Call systems ..................................... 13, 70
Canopies .......................................... 17, 97
Car lifts ............................................. 12, 60
Card access ........................................... 70
Windows ............................................ 9, 37
Wine cellar, equipment .......................... 78
Worktops, benches, vanities, etc..... 11, 48
Zebra crossings ..................................... 96
114