Activit y Description Duration Predecessor
Activit y Description Duration Predecessor
You are the assistant project manager to Rassy Brown, who is in charge of the
Nightingale project. Nightingale was the code name given to the development of
a handheld electronic medical reference guide. Nightingale would be designed
for emergency medical technicians and paramedics who need a quick reference
guide to use in emergency situations.
Rassy and her project team were developing a project plan aimed at producing
30 working models in time for MedCON, the biggest medical equipment trade
show each year. Meeting the MedCON October 25 deadline was critical to
success. All the major medical equipment manufacturers demonstrated and took
orders for new products at MedCON. Rassy had also heard rumours that
competitors were considering developing a similar product, and she knew that
being first to market would have a significant sales advantage. Besides, top
management made funding contingent upon developing a workable plan for
meeting the MedCON deadline.
The project team spent the morning working on the schedule for Nightingale.
They started with the WBS and developed the information for a network, adding
activities when needed. Then the team added the time estimates they had
collected for each activity. Following is the preliminary information for activities
with duration time and predecessors:
Activit
y
Description
Duration
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
Architectural decisions
Internal specifications
External specifications
Feature specifications
Voice recognition
Case
Screen
Speaker output jacks
Tape mechanism
Database
Microphone/soundcard
Pager
Barcode reader
Alarm clock
Computer I/O
Review design
17
Price components
18
19
20
15
35
20
21
22
23
24
25
26
27
Integration
Document design
Procure prototype
components
Assemble prototypes
Lab test prototypes
Field test prototypes
Adjust design
Order stock parts
Order custom parts
Assemble first production unit
10
20
20
20
15
2
10
20
21
19,22
23
24
24
25, FS+8 time units
26, FS+13 time units
28
29
30
Test unit
Produce 30 units
Train sales representatives
10
15
10
27
28
29
10
20
18
15
15
4
2
2
2
40
5
4
3
4
5
10
5
Predecessor
None
1
1
1
2,3
2,3
2,3
2,3
2,3
4
4
4
4
4
4
5,6,7,8,9,10,11,12,13,1
4,15
5,6,7,8,9,10,11,12,13,1
4,15
16,17
16
18
Using Microsoft Project 2013 develop the schedule for activities (see Case
Appendix for further instructions)noting late and early times, the critical path,
and estimated completion for the project.
PART A
You need to answer the following:
1 Will the project as planned meet the October 25th deadline?
2 What activities lie on the critical path?
3 How sensitive is this network?
Rassy and the team were concerned with the results of your analysis. They spent
the afternoon brainstorming alternative ways for shortening the project duration.
They rejected outsourcing activities because most of the work was
developmental in nature and could only be done in-house. They considered
altering the scope of the project by eliminating some of the proposed product
features. After much debate, they felt they could not compromise any of the core
features and be successful in the marketplace. They then turned their attention
to accelerating the completion of activities through overtime and adding
additional technical manpower. Rassy had built into her proposal a discretionary
fund of $200,000. She was willing to invest up to half of this fund to accelerate
the project, but wanted to hold onto at least $100,000 to deal with unexpected
problems. After a lengthy discussion, her team concluded that the following
activities could be reduced at the specified cost:
PART B
As the meeting adjourns, Rassy turns to you and tells you to assess the options
presented and try to develop a schedule that will meet the October 25th
deadline. You need to answer the following questions:
1
If so, how would you recommend changing the original schedule (Part A)
and why? Assess the relative impact of crashing activities versus
introducing lags to shorten project duration.
The project will begin the first working day in January, 2010.
The following holidays are observed: January 1, Memorial Day (last
Monday in May), July 4, Labor Day (first Monday in September),
Thanksgiving Day (fourth Thursday in November), December 25 and 26.
If a holiday falls on a Saturday, then Friday will be given as an extra day
off; if it falls on a Sunday, then Monday will be given as a day off.
The project team works Monday through Friday.
If you choose to reduce the duration of any one of the activities
mentioned, then it must be for the specified time and cost (i.e., you
cannot choose to reduce database to 37 days at a reduced cost; you can
only reduce it to 35 days at a cost of $35,000).
You can only spend up to $100,000 to reduce project activities; lags do not
contain any additional costs.