A Study On Pre-Engineered Building - A Construction Technique

Download as pdf or txt
Download as pdf or txt
You are on page 1of 5

Farman Iqbal Shaikh et al. Int.

Journal of Engineering Research and Applications


ISSN : 2248-9622, Vol. 5, Issue 3, ( Part -2) March 2015, pp.05-09
RESEARCH ARTICLE

www.ijera.com

OPEN ACCESS

A Study On Pre-Engineered Building A Construction


Technique
Shrunkhal V Bhagatkar1, Farman Iqbal Shaikh2, Bhanu Prakash Gupta3 and
Deepak Kharta4
(1

Assistant Professor, 2,3,4 B.E (Civil) Student, 1,2,3,4 Department of Civil Engineering,
Sinhagad Academy Of Engineering, Sinhgad Technical Educations, Pune.)

ABSTRACT
Steel industry is growing rapidly in almost all the parts of the world. The use of steel structures is not only
economical but also eco friendly at the time when there is a threat of global warming. Time being the most
important aspect, steel structures (Pre fabricated) is built in very short period and one such example is Pre
Engineered Buildings (PEB).This review from the past experiences presents the results of experimental and
analytical studies done on Pre Engineered Building. Results show that these structures are economic, reduces
construction cost and time, energy efficient and flexibility of expansion.
Keywords : Pre-Engineered Building.

I.

INTRODUCTION

The scientific-sounding term pre-engineered


buildings came into being in the 1960s. Typically, a
pre-engineered building is a metal building that
consists of light gauge metal standing seam roof
panels on steel purlins spanning between rigid frames
with light gauge metal wall cladding. In other words,
it has a much greater vertical and horizontal
deflection. Pre engineered buildings are generally low
rise buildings which are ideal for offices, houses,
showrooms, shop fronts etc. One may think about its
possibility, but its a fact many people are not aware
about Pre Engineered Buildings. If we go for regular
steel structures, time frame will be more, and also
cost will be more, and both together i.e. time and cost,
makes it uneconomical. Thus in pre engineered
buildings, the total design is done in the factory, and
as per the design, members are pre fabricated and
then transported to the site where they are erected in a
time less than 6 to 8 weeks.
The first rigid-frame buildings introduced in the late
1940s could span only 40 ft. In a few years, 50-, 60-,
and 70-ft buildings became possible. By the late
1950s, rigid frames with 100-ft spans were made,
ribbed metal panels became available, allowing the
buildings to look different from the old tired
corrugated appearance. Third, collared panels were
introduced by Strand-Steel Corp. in the early 1960s,
permitting some design individuality.
At about the same time, continuous span cold-formed
Z purlins were invented (also by Strand- Steel), the
first factory-insulated panels were developed by
Butler, and the first UL-approved metal roof appeared
www.ijera.com

on the market.1st And last, but not least, the first


computer-designed metal buildings also made their
debut in the early 1960s. With the advent of
computerization, the design possibilities became
almost limitless. All these factors combined to
produce a new metal-building boom in the late 1950s
and early 1960s. As long as the purchaser could be
restricted to standard designs, the buildings could be
properly called pre- engineered.

II.

REVIEW OF LITERATURE

2.1 Syed Firoz, Sarath,Chandra Kumar et.al (2012)


observed that, The pre-engineered steel building
system construction has great advantages to the single
storey buildings, practical and efficient alternative to
conventional buildings, the System representing one
central model within multiple disciplines. Preengineered building creates and maintains in real time
multidimensional, data rich views through a project
support is currently being implemented by Staad pro
software packages for design and engineering.
Choosing steel to design a Pre-engineered steel
structures building is to choose a material which offers
low cost, strength, durability, design flexibility,
adaptability and recyclability. Steel is the basic
material that is used in the Materials that are used for
Pre- engineered steel building. It negates from
regional sources. It also means choosing reliable
industrial products which come in a huge range of
shapes and colours; it means rapid site installation and
less energy consumption. It means choosing to
commit to the principles of sustainability. Infinitely
recyclable, steel is the material that reflects the
imperatives of sustainable development.
5|P age

Farman Iqbal Shaikh et al. Int. Journal of Engineering Research and Applications
ISSN : 2248-9622, Vol. 5, Issue 3, ( Part -2) March 2015, pp.05-09
A tall steel building is not more in the total number of
tall steel structures that are built around the world. A
large steel structures being built are only single storey
buildings for industrial purpose. Secondary structural
members span the distance between the primary
building frames of metal building systems. They play
a complex role that extends beyond supporting roof
and wall covering and carrying exterior loads to main
frames. Secondary structurals, as these members are
sometimes called, may serve as flange bracing for
primary framing and may function as a part of the
buildings lateral loadresisting system. Roof
secondary members, known as purlins, often form an
essential part of horizontal roof diaphragms; wall
secondary members, known as girts, are frequently
found in wall bracing assemblies. The majority of
steel structures being built are only low-rise
buildings, which are generally of one storey only.
Industrial buildings, a sub- set of low-rise buildings
are normally used for steel plants, automobile
industries, light, utility and process industries,
thermal power stations, warehouses, assembly plants,
storage, garages, small scale industries, etc. These
buildings require large column free areas. Hence
interior columns, walls and partitions are often
eliminated or kept to a minimum. Most of these
buildings may require adequate headroom for use of
an overhead traveling crane. A third type of
secondary framing, known by the names of eave strut,
eave purlin, or eave girt, acts as part purlin and part
girtits top flange supports roof panels, its web, wall
siding. Girts, purlins, and eave struts exhibit similar
structural behaviour. Since most secondary members
normally encountered in metal building systems are
made of cold- formed steel, our discussion starts with
some relevant issues in design of cold-formed steel
structures.
2.2 Aijaz Ahmad Zende 1, Prof. A. V. Kulkarni ,
et.al (Jan. - Feb. 2013) observes that even though
PEB
structures provides clear span, it weighs
lesser than that of Conventional Buildings. Infinitely
recyclable, steel is the material that reflects the
imperatives of sustainable development. For longer
span structures, Conventional buildings are not
suitable with clear spans. Pre-engineered building are
the best solution for longer span structures without
any interior column in between as seen in this present
work, an industrial structure has been designed for
88m. With the advent of computerization, the design
possibilities became almost limitless. Saving of
material on low stress area of the primary framing
members makes Pre- engineered buildings more
economical than Conventional steel buildings
especially for low rise buildings spanning up to 90.0
meters with eave heights up to 30.0 meters. PEB
structures are found to be costly as compared to
Conventional structures in case of smaller span
www.ijera.com

www.ijera.com

structures. To Conclude Pre-Engineered Building


Construction gives the end users a much more
economical and better solution for long span
structures where large column free areas are needed.
2.3 C. M. Meera (June 2013) observes that PreEngineered Building (PEB) concept is a new
conception of single storey industrial building
construction. This methodology is versatile not only
due to its quality pre-designing and prefabrication,
but also due to its light weight and economical
construction. The concept includes the technique of
providing the best possible section according to the
optimum requirement. This concept has many
advantages over the Conventional Steel Building
(CSB) concept of buildings with roof truss. This
paper is a comparative study of PEB concept and
CSB concept. Pre-Engineered Building concept have
wide applications including warehouses, factories,
offices, workshops, gas stations, showrooms, vehicle
parking sheds, aircraft hangars, metro stations,
schools, recreational buildings, indoor stadium roofs,
outdoor stadium canopies, railway platform shelters,
bridges, auditoriums, etc, explicitly as in. PEB
structures can also be designed as re-locatable
structures. Steel is a material which has high strength
per unit mass. Hence it is used in construction of
structures with large column-free space. Most of the
Industrial Structures require this criterion. An
Industrial Warehouse is a storage building and is
usually characterized as single storey steel structures
with or without mezzanine floors. The enclosures of
these structures may be brick masonry, concrete walls
or GI sheet coverings. The walls are generally nonbearing but sufficiently strong enough to withstand
lateral forces caused by wind or earthquake. The
designing of industrial warehouse includes designing
of the structural elements including principal rater or
roof truss, column and column base, purlins, sag rods,
tierods, gantry girder, bracings, etc. A combination of
standard hot-rolled sections, cold-formed sections,
profiled sheets, steel rods, etc. are used for the
construction of industrial steel structures. Industrial
buildings can be categorized as Pre-Engineered
Buildings (PEB) and Conventional Steel Buildings
(CSB), according to the design concepts. The paper
starts with the discussion of methods adopted in the
study. Introduction to PEB systems and CSB systems
are then described followed by the details of case
study. Loads and the load combinations adopted for
carrying out the analysis of the structure is well
defined in the further portions. A section depicting
the importance of the software used and the software
procedure followed is included. Final portion explains
the results obtained from the software analysis of the
case study and the inferences from the literature
studies. The paper aims at developing a perception of

6|P age

Farman Iqbal Shaikh et al. Int. Journal of Engineering Research and Applications
ISSN : 2248-9622, Vol. 5, Issue 3, ( Part -2) March 2015, pp.05-09
the design concepts of PEB structures and its
advantages over CSB structures.
2.4 Jatin D. Thaka r, 2 Prof. P.G. Patel observes
that Pre-engineered building are steel building
wherein the framing members and other components
are fully fabricated in the factory after designing and
brought to the site for assembly, mainly by nut-bolts,
thereby resulting into a steel structure of high quality
and precision. In conventional steel construction, we
have site welding involved, which is not the case in
P.E.B using nut-bolt mechanism. These structures use
hot rolled tapered sections for primary framing and
cold rolled sections (generally Zand Csections)
for secondary framing as per the internal stress
requirements, thus reducing wastage of steel and the
self- weight of the structure and hence lighter
foundations. International codes are referred in their
design as per the MBMA (Metal Building
Manufacturers Association) standards which are more
flexible allowing the use of built - up sections of
minimum 3.5 mm thickness against 6 mm as
minimum criteria in conventional steel sections
.There is use of steel of high strength (345MPa)
which prominently speaks about greater strength with
judicious use of steel as a result of tapered profile.
The tapered section concept was first adopted in
U.S.A keeping in mind the bending moment diagram.
At locations of high bending moment values, greater
depth is used while less moment encouraged the use
of lesser depths. Further unlike the conventional steel
sections, where Moment of inertia (I) remains
constant, it is not so in case of P.E.B due to varying
depths.
2.5 G. Sai Kiran , A. Kailasa Rao, R . Pradeep
Kumar (Aug 2014) observes that, In recent years, the
introduction of Pre Engineered Building (PEB)
concept in the design of structures has helped in
optimizing design. The adoptability of PEB in the
place of Conventional Steel Building (CSB) design
concept resulted in many advantages, including
economy and easier fabrication. In this study, an
industrial structure (Ware House) is analyzed and
designed according to the Indian standards, IS 8001984, IS 800-2007 and also by referring MBMA-96
and AISC-89. In this study, a structure with length
187m,width 40m,with clear height 8m and having RSlope 1:10,isconsidered to carry out analysis& design
for 2D frames (End frame, frame without crane and
frame with 3 module cranes). The economy of the
structure is discussed in terms of its weight
comparison, between Indian codes (IS800-1984,
IS800-2007) & American code (MBMA-96), &
between Indian codes (IS800-1984, IS800-2007).
2.6 S.D. Charkha and Latesh S (June 2014)
observes that, Using of PEB instead of CSB may be
www.ijera.com

www.ijera.com

reducing the steel quantity. Reduction in the steel


quantity definitely reducing the dead load. Reduction
in the dead load reducing the size of Foundation.
Using of PEB increase the Aesthetic view of
structure.
2.7 U. D. Dabhade1, N.A.Hedaoo2, Dr. L. M.
Gupta3 and Dr. G. N(2009) observes that, the time
savings of 55.3% is achieved due to use of steel
framed composite floor construction rather than
precast framed with precast concrete floor and 14.3%
time than that of steel framed with precast concrete
slab. The construction of steel framed composite floor
building saves time, which leads to an overall savings
in net cost. The direct cost required for steel framed
with composite floor is 23.10%, higher than precast
frame with precast concrete floor and only 0.52%
higher than steel framed with precast concrete floor.
Considering time related savings, the net cost required
for steel framed with composite floor is 12.99%, more
than precast frame with precast concrete floor and
2.32% less than steel frame with precast floor. The
steel framed with precast concrete floor saves 35.83%
construction time than precast frame with precast
concrete floor, which required extra 22.70% of direct
cost and 14.96% of net cost. However, study is
restricted to structural frame only. If other items are
also considered in the study like excavation work,
finishing items, services, cladding etc

III.

PRE ENGINEERED BUILDING


(PEB)

It is a combination of precast & prefabricated


structures. Pre engineered buildings are generally low
rise buildings which are ideal for offices, houses,
showrooms, shop fronts etc. The application of pre
engineered buildings concept to low rise buildings is
very economical and speedy. Buildings can be
constructed in less than half the normal time.
Although PEB systems are extensively used in
industrial and many other non residential
constructions worldwide, it is relatively a new concept
in India.

IV.

ADVANTAGES OF PEB

PEB is a suitable Construction technique for


developing countries for the following reasons:
4.1 Reduced construction time
Buildings are typically delivered in just a few weeks
after approval of drawings. Foundation and anchor
bolts are cast parallel with finished, ready for the site
bolting. PEB will reduces total construction time of
the project by at least 50%. This also allows faster
occupancy and earlier realization of revenue.
4.2 Lower cost
Due to the systems approach, there is a significant
saving in design, manufacturing and on site erection
7|P age

Farman Iqbal Shaikh et al. Int. Journal of Engineering Research and Applications
ISSN : 2248-9622, Vol. 5, Issue 3, ( Part -2) March 2015, pp.05-09
cost. The secondary members and cladding nest
together reducing transportation cost. Steel buildings
that are properly insulated save natural resources,
energy and money.
4.3 Flexibility of expansion
Buildings can be easily expanded in length by adding
additional bays. Also expansion in width and height is
possible by pre designing for future expansion.
4.4 Large clear spans
Buildings can be supplied to around 80M clear spans.
4.5 Quality control
As buildings are manufactured completely in the
factory under controlled conditions the quality is
assured.
4.6 Low maintenance
Buildings are supplied with high quality paint
systems for cladding and steel to suit ambient
conditions at the site, which results in long durability
and low maintenance coats.
4.7 Energy efficient roofing and wall system
Buildings can be supplied with polyurethane
insulated panels or fiberglass blankets insulation to
achieve required U values.
4.8 Architectural versatility
Building can be supplied with various types of
fascias, canopies, and curved eaves and are designed
to receive pre cast concrete wall panels, curtain walls,
block walls and other wall systems. All the
components are available in different colours also.
4.9 Single source responsibility
As the complete building package is supplied by a
single vendor, compatibility of all the building
components and accessories is assured. This is one of
the major benefits of the pre engineered building
systems.
4.10 Sustainability
Steel is 100% recyclable and is the most recycled
material in the world. Thus, each ton of recycled steel
saves 2,500 pounds of iron ore and approximately
1,000 pounds of coal.

V.

APPLICATIONS OF PEB

In the USA, where the PEB concept was originally


conceived during the early years of this century,
nearly 70% of all single storey non-residential
construction now utilizes pre-engineered buildings.
Applications range from small car parking sheds to 90
m (+), wide clear span aircraft hangars to low- rise
multi-storey buildings.

www.ijera.com

www.ijera.com

The most common applications of pre-engineered


buildings are:
5.1 Industrial
Factories, Workshops, Warehouses, Cold stores, Car
parking sheds, Slaughter houses, Bulk product
storage.
5.2 Commercial
Showrooms, Distribution centers, Supermarkets, Fast
food restaurants, Offices, Labor camps, Service
station, Shopping centers. Schools, Exhibition halls,
Hospitals, Theatres/auditoriums, Sports halls.
5.3 Institutional
Schools, Exhibition halls, Hospitals, Theatres, Sport
halls.
5.4 Recreational
Gymnasiums, swimming pool enclosures, Indoor
tennis courts.
5.5 Aviation & Military
Aircraft
hangars,
Administration
Residential barracks.

buildings,

5.6 Agricultural
Poultry buildings, Dairy farms, Greenhouses, Grain
storage, Animal confinement.

VI.

MAIN COMPONENTS

6.1 Main Frame


Rigid steel frames of the building are mainly
considered as the Main Frames of PEB. PEB rigid
frame comprises of tapered columns and tapered
rafters (the fabricated tapered sections are referred to
as built-up members). The tapered sections are
fabricated using the state of art technology wherein
the flanges are welded to the web. Splice plates are
welded to the ends of the tapered sections. The frame
is erected by bolting the splice plates of connecting
sections together.
6.2 Purlins, Grits and Eave Struts
Purlins, Grits and Eave Struts are secondary structural
members used to support the wall and roof panels.
Purlins are used on the roof; Grits are used on the
walls and Eave Struts are used at the intersection of
the sidewall and the roof. Secondary members have
two functions: they act as struts that help in resisting
part of the longitudinal loads that are applied on the
building such as wind and earthquake loads, and they
provide lateral bracing to the compression flanges of
the main frame members thereby increasing frame
capacity.

8|P age

Farman Iqbal Shaikh et al. Int. Journal of Engineering Research and Applications
ISSN : 2248-9622, Vol. 5, Issue 3, ( Part -2) March 2015, pp.05-09
6.3 Sheetings and Insulation
Panels used for sheeting purpose are generally of
ribbed steel sheets used as roof and wall sheeting,
roof and wall liners, partition and soffit sheeting. The
steel sheets are generally produced from steel coils
having thickness 0.5 mm to 0.7 mm high tensile
stress.
6.4 Paints and Finishes
Normally the primary and secondary steel are coated
with one coat (35 microns) of red oxide paint without
any special treatment to steel. However, if some
special paint has to be applied to steel in order to give
better anti corrosion properties, then the steel
members have to be shot blasted and then coated
with the special paints. For houses; inside and outside
painting on walls and falseceiling is to be provided.
6.5 Doors and Windows
Steel or aluminium framed doors and windows are
fixed to the purlins or the supporting profiled steel
either by welding or bolted to the flanges already
fixed to the purlins. Proper flashings are applied
wherever necessary.
6.6 False Ceiling
False ceiling is usually required for residential
buildings or offices. A metal frame work is hung from
the ceiling and false ceiling of rigid boards are either
bolted or placed over the frame work.
6.7 Partition Walls
Partition walls are usually required for residential
building or offices. Partition wall comprises of two
rigid boards having insulation sandwiched in between
and fixed to the steel columns or supporting profiled
steel and purlins. Alternatively prefab sandwich
panels can also be fixed to the columns and purlins.
6.8 Flooring
Flooring is usually of conventional nature consisting
of cement concrete. For intermediate floors; metal
decking sheet is fixed to purlins and concrete poured
over it.

VII. CONCLUSION
From the past advancement, the use of PEB is
implemented and continuously increasing, but its
usage is not throughout the construction industry. It is
reviewed that PEB structures can be easily designed
by simple design procedures in accordance with
country standards, it is energy efficient, speedy in
construction, saves cost, sustainable and most
important its reliable as compared to conventional
buildings. Thus PEB methodology must be
implemented and researched for more outputs.

www.ijera.com

www.ijera.com

REFERENCES
Journal Papers:
[1] C. M. Meera (June 2013). Pre engineered
building design of an industrial warehouse.
International journal of engineering sciences &
emerging technologies. Volume 5 Issue 2 ,
pp:75-82
[2] Aijaz Ahmad Zende, Prof. A. V. Kulkarni,
Aslam Hutagi (Feb 2013) . Comparative Study
of Analysis and Design of Pre-EngineeredBuildings and Conventional Frames. IOSR
Journal of Mechanical and Civil Engineering,
Volume 5, Issue .
[3] Jatin D. Thakar, 2 Prof. P.G. Patel. Comparative
study of pre engineered steel structure by
varying width of structure . International
journal of advanced engineering technology,
volume 4, issue 3
[4] Syed Firoz1, Sarath Chandra Kumar B1,Design
concept
of
pre
engineered
building.
International journal of engineering research &
applications, volume 2 , issue 2 , pp:267-272
[5] G. Sai Kiran , A. Kailasa Rao, R . Pradeep
Kumar (Aug 2014) . Comparison of Design
Procedures for Pre Engineering Buildings
(PEB): A Case Study. International Journal of
Civil, Architectural, Structural & Contruction
Engineering, Volume 8, No. 4
[6] S.D. Charkha1 and Latesh S (June 2014).
Economizing Steel Building using Preengineered Steel Sections. International
journal of research in civil engineering ,
architecture & design, volume 2 , issue 2
[7] U. D. Dabhade1, N.A.Hedaoo2, Dr. L. M.
Gupta3 and Dr. G. N(2009). Time and Cost
Evaluation of Construction of Steel Framed
Composite Floor with Precast Concrete Floor.
International Symposium on Automation and
Robotics in Construction.

Websites:
[1] www.wikipedia.org
[2] www.infinityfab.com
[3]www.zamilsteel.com
[4] www.kirbyinternational.com
[5]www.tatabluescopesteel.com

9|P age

You might also like