Creativity
Creativity
Creativity
Current issue
Archive copies
Auroville Adventure
May 2005
collective housing
project
with
spaces
for
common facilities
to
accommodate
approximately
360 residents on
an area of about
2.17
hectares.
Group
was
the
de-facto
client,
the
project
was
actually
undertaken
later
Jocelyn,
fired
by
the
anything
else,
Ideals of Creativity
Unlike other collective housing projects, the project holders also
sought to map out the sociological, economic and environmental
objectives of Creativity. It was to become a social research
endeavour and a dynamic experiment in sustainable urban living for
a
culturally-diverse
group
of
approximately
50
Aurovilians,
which
was
widely
felt
to
be
undesirable.
Serious
were
increased
and
terraces
were
created
for
each
apartment. They did not touch the external lay-out of the Creativity
cluster and its housing blocks as they had agreed in the beginning
that this would remain solely the architect's responsibility. This
degree of involvement by the project holders, however, was not
always to the liking of the architect and gradually differences of
opinion led to estrangement. The architect complained that the
project holders had neither the architectural knowledge nor technical
expertise to tackle large-scale constructions. There was an increased
interference with our work, original concepts were questioned and
designs were changed after the project had taken off. Project holders
became architects and residents expressed their desires for their own
tailor-made apartments. That took an increasing amount of time and
design-energy and we got very discouraged. If they would have let
us built what we had designed, the project would have been much
cheaper. says Anupama. Also the lack of harmony between the
project holders and residents themselves made our work difficult.
The project holders in turn were dissatisfied that some of their
changes, which were discussed and agreed on before the final plans
were made, were not being implemented if they did not meet with
the approval of the architect, that they were never given copies of
the complete working drawings, and that the working drawings that
were given were often incomplete and not really understood by
them. The architects complained that as the project holders lacked
technical experience they were made to prepare many versions of
working drawings of every changing idea and that the project holders
stopped the construction at times as they couldn't arrive at a
decision unanimously. This all led to months of delay and bitter
exchanges, and added to the project's costs, observes Gillian.
Gradually, the pace of the project slowed down. We observed that
working drawings were also not being provided in time to the
contractor. He started to pull workers off the Creativity project to
work on other projects of the same architect to the extent that we
found that he was over-extending himself. Ultimately Anupama
withdrew from the direct interaction with project holders after a
gradual breakdown of the relationship with them. Her place was
taken by Sonali who, however, in the opinion of the project holders,
lacked sufficient experience. During her 4-months' maternity leave, a
Project Financing
The fundraising proved a major challenge, in particular as about a
third of the intended residents lacked personal means. A seeddonation from an anonymous donor of Rs 50 lakhs [US $ 108,000]
had launched the project. With the consent of all involved, this
money was used for the common infrastructure, and not to sponsor
housing for those without means. Says Gillian: We asked the
prospective residents to be committed to live in an intentional
community and offer whatever finances they could. The ideal was
you give what you can regardless of the spaces you are going to
occupy so that those without means can be sponsored. But this
proved to be unrealistic. Ultimately, the donation to be made for each
apartment was calculated on a square metre basis, and those without
sufficient means were asked to arrange for a loan with Auroville's
Financial Service, resulting in stress and personal hardships. A few
people were subsidized, not by the project, but by a special fund of
Auroville. The mood had changed from very off the ground' to very
on the ground'.
Added to this was that the estimates submitted were based on an
unrealistic time schedule of one year, whereas in reality it took three
and half years, creating added expenses. The estimates also did not
include the infrastructure costs, as the project holders and architect
planned to seek funding for the rain water harvesting and the solar
energy systems. This funding, however, never materialised. The
project holders later blamed themselves for being naive and
inexperienced, relying on the expertise of the architect and expecting
a professional approach which would have included the complete
infrastructure costs within the estimates. Nevertheless, the project
was always adequately supported financially and construction never
needed to be halted due to lack of funds.
The residents
Meanwhile,
the
residents
waited
and
endured
the
seemingly
the
quality
of
life
which
it
provides
an
interactive
Design flaws
In fact, unique to Auroville, the residents of Creativity have written to
the
design
was
We
made
the
proper
evaluation
sound
of
the
structures. But as we
feared,
the
semi-
indeed
creates
sound
escalate
the
the
large
roof
Lessons learned
Asked what lessons have been learned, Anupama retorts Not to
work anymore with a group client. We will henceforth only deal with
one person who represents the group. And if the group disagrees
amongst themselves, we'll
wait till they have reached
consensus.
Secondly,
the
will
need
to
be
does
future
about
aspects
of
construction
a
collective
her
apartment.
So
finishing.
experiences
of
The
Creativity
are now the basis for the design of Citadines. In Citadines there are
three or four project holders, each with a different task. But we only
deal with one person. The idea is to provide fully-furnished flats,
which will be allocated once they have been finished. And contrary to
the Creativity project, we want to make sure that here all designs are
ready before the first spade goes into the ground. We don't want to
start before every detail is ready and the funding is fully secured.
Looking back, the architects feel that Creativity has managed to
achieve many technical aims, though on the social level much was
left to be desired.
For the project holders too, the design and building experience of
Creativity should not be repeated. Says Gillian: Housing in Auroville
is collective property, and Auroville must make sure that collective
housing has the best standard possible. In future, a project like this
must be assessed by a group of independent specialists to prevent
mistakes and ensure that the project costs are realistic. The mistakes
of Creativity must be lessons for future collective housing projects.
After all, Auroville is about infusing consciousness into matter.
Gillian concludes We all failed in that we are supposed to be doing a
collective karma yoga here, which implies that we should not be
attached to the results of our work, that we should be doing it with
dedication and surrender. But it has been a hard path for all of us to
tread.
See also: "Planning Creativity"
Creativity fact sheet
Beginning of construction: August 2001
Expected date of completion: Autumn 2005
Work pending: doors and windows multi purpose room, courtyard
landscaping.
No. of apartments: 13 single units, 6 units for couples without
children, 2 family units, 5 single rooms with shared facilities,
2 guest rooms for singles, 3 guest rooms for couples.
Collective spaces: Kitchen, dining, multi-purpose room, atelier,
office, laundry, motorbike parking, storeroom.
No of permanent inhabitants: 38
Nationality of inhabitants: Indian, German, Dutch, Italian, French,
Australian, Colombian, Canadian, Spanish, English, American.
Average age of inhabitants: 50 years
Waste water treatment system: Root zone type, treated water is
used for irrigation.
Total built-up area: 1715 sq.m.
Total costs: Rs 1.79 crores
Cost
per
square
metre
including
collective
infrastructure: Rs 10,500
Architect: Kolam
Contractor: Auronirmatha
Home > Journals & Media > Journals > Auroville Today > May 2005
Current issue | Archive copies | Auroville Adventure
Auroville Universal Township
spaces
and