1860 Hyp9318
1860 Hyp9318
1860 Hyp9318
1
Department of Civil Engineering, National Chung Hsing University, Taichung, Taiwan
Department of Statistics and Informatics Science, Providence University, Taichung, Taiwan
Abstract:
For many incised channels, one of the most common strategies is to install some hard structures, such as grade-control structures
(GCSs), in the riverbed to resist further incision. In this study, a series of experiments, including both steady and unsteady ow
conditions, were conducted to investigate the scouring process downstream of a GCS. Three distinct phases, including the initial,
developing and equilibrium phases, during the evolution of scour holes were identied. In addition, a semi-empirical method was
proposed to predict the equilibrium scour-hole prole for the scour countermeasure design. In general, the comparisons between
the experimental and simulated results are reasonably consistent. As the studies on temporal variation of the scour depth at GCSs
caused by oods are limited, the effect of ood hydrograph shapes on the scour downstream of GCSs without upstream sediment
supply was also investigated experimentally in this study. Based on the dimensional analysis and the concept of superposition, a
methodology is proposed to simulate the time evolution of the maximum scour depth downstream of a GCS for steady ows.
Moreover, the proposed scheme predicts reasonably well the temporal variations of the maximum scour depth for unsteady ows
with both single and multiple peak. Copyright 2012 John Wiley & Sons, Ltd.
KEY WORDS
INTRODUCTION
Channel incision receives public attention as a result of the
impacts on man-made structures and its high repairing or
replacement costs. Many civil engineering structures, such
as bridges and levees, have been extensively affected by
channel incision in Taiwan and also throughout the world.
One of the most widely used remedial measures is to install
grade-control structures (GCSs) in the river to limit further
degradation upstream of the GCSs. However, the GCSs
cannot completely solve the incision problem in case of
sediment starvation because edge failure may occur
downstream of the GCSs and nally damage the GCSs
through head cutting.
After a GCS is constructed, initially, the coarser sediment
particles are trapped upstream of the GCS, whereas the ner
particles may pass through it during oods. The GCSs are
usually 1.52 m higher than the original riverbed. When the
ow passes through a GCS, a critical ow condition may be
found immediately upstream of the GCS, whereas a
supercritical ow condition can be found on the ramp of
the GCS. Downstream of the GCS, an impinging/plunging
jet diffuses the energy into the pool. Far downstream of the
pool, a uniform ow may occur (Lenzi et al., 2003a).
Scour downstream of a GCS/drop has attracted many
researchers to study. Initially, they focused on the geometry
of the scour hole, especially for the equilibrium maximum
J.-Y. LU ET AL.
Sb
Srm
D50 (mm)
q (m2/s)
Fdd
xm,e (mm)
ym,e (mm)
lm,e (mm)
Fr
0.01
0.01
0.01
0.01
0.01
0.01
0.01
0.01
0.01
0.01
0.015
0.015
0.015
0.015
0.015
0.015
0.015
0.015
0.25
0.25
0.143
0.143
0.25
0.25
0.143
0.143
0.143
0.143
0.25
0.25
0.143
0.143
0.25
0.25
0.143
0.143
3.5
3.5
3.5
3.5
2.7
2.7
2.7
2.7
2.7
2.7
3.5
3.5
3.5
3.5
2.7
2.7
2.7
2.7
0.0167
0.0475
0.0167
0.0475
0.0167
0.0475
0.0167
0.0225
0.0283
0.0475
0.0167
0.0475
0.0167
0.0475
0.0167
0.0475
0.0167
0.0475
3.50
4.75
4.12
5.87
3.62
5.05
4.43
4.68
5.20
5.98
3.05
4.99
3.05
4.64
2.85
4.73
3.19
4.83
119
316
124
259
150
604
149
171
337
522
213
445
152
679
326
678
335
836
59
136
55
129
71
151
74
95
104
152
111
204
92
241
169
246
149
300
450
1450
470
1220
683
2500
700
894
1087
1750
888
1750
532
1950
857
2150
1056
2150
0.81
0.77
0.93
0.63
0.56
0.58
0.85
0.64
0.61
0.60
0.67
0.86
0.54
0.67
0.41
0.45
0.36
0.53
Sb
Srm
D50 (mm)
Type of
hydrograph
0.015
0.01
0.015
0.01
0.015
0.01
0.015
0.01
0.143
0.143
0.25
0.25
0.143
0.143
0.25
0.25
3.5
3.5
3.5
3.5
2.7
2.7
2.7
2.7
(a) ~ (d)
(a) ~ (d)
(a) ~ (d)
(a) ~ (d)
(a) ~ (d)
(a) ~ (d)
(a) ~ (d)
(a) ~ (d)
RESULTS
Scouring process
J.-Y. LU ET AL.
Figure 2. Stepwise hydrographs for the tests under unsteady ow conditions: (a) symmetric; (b) delayed peak; (c) advanced peak; and (d) symmetric,
with a lower peak
Figure 3. Schematic diagrams of scouring process downstream of a grade-control structure under a typical steady ow condition
(1)
0:759
ys;me =P 351:3S1:667
Fdd
ht =D50 0:494
b
(2)
0:812
ls;me =P 11:3S0:595
Fdd
ht =D50 0:761
b
(3)
J.-Y. LU ET AL.
xs
xs U
C0 exp C1
1 exp C2
ls;me
n
(4)
where
C0, C1, and C2 are empirical coefcients; U
p
ght Seq ; g = gravitational acceleration; ht= tailwater
depth; n= kinematic viscousity. The coefcients C0, C1,
and C2 are determined using the scour-hole characteristics, which are as follows: (i) atxs = xs, me, ys/ys, me = 1;
(ii) atxs = xs, me, dys/dxs = 0; and (iii) atxs = ls, me, ys = a2,
where a2= equilibrium general scour depth in reach CD
(Figure 1), which can be estimated as follows based on
Gaudio and Marion (2003):
a2 ht hc
2 1=3
q
;
3=7
g
c D50
nq6=7
2 p
0:001
ht a2
2g 0:605
0:08
ht a2 3=2 ; (5b)
a2
3
ht a2
for a2 =ht 0:15
(6)
(7)
where bo = 0.0468 and b1 = 0.421 are coefcients determined by using SPSS. The coefcient of determination R2
for Equation (7) is 0.95. As shown in Figure 7, all the data
collapse in a narrow band. Although there are some
discrepancies between the measured and predicted results
at the initial stage of scour activity, the model, in general,
predicts the temporal variations of scour depths downstream of a bed sill under steady ow conditions
satisfactorily.
Evolution of maximum scour depthsingle-peak
hydrograph
Figure 5. Comparisons of the observed (circle) and predicted (curve) scour-hole proles under steady ow conditions for runs: (a) M1R4-5, (b) M1R4-8,
(c) M2R4-5, (d) M2R4-8, (e) S1R4-1, (f) S1R4-4, (g) S1R7-1 and (h) S1R7-4
J.-Y. LU ET AL.
Figure 6. Comparisons of the scour-hole proles predicted by the proposed method with the experimental data of Meftah and Mossa (2006)
scour depth curve for Q3. Because Q3 > Q2, the time
required for the scour depth to reach ys,2 for the ow
rate Q3 is less thant2. This time is designated as t2 in
Figure 8(b).
4. However, at time t3, as the ow rate decreases from Q3
to Q4 corresponding to t t2 t3 t2 , the scour
depth may remain unchanged, that is, ys,3 = ys,4. On the
other hand, if the slope of the recession limb is mild,
the scouring potential of Q4 may cause further scour,
which means ys,4 may be slightly greater than ys,3.
Furthermore, for the steep recession limb, the scour
depth remains unchanged because of the reduced
stream power. The ys curve may follow the pathC00 D
of the scour depth curve for Q4.
(8)
(9)
To determine the time lag ti, Equation (7) for the temporal
variation of the scour depth at a sill under steady ow
conditions is adopted.
8
20
0
1=2 !b1 11
< 1
t
g
D
1
50
AA
t1
ln4@ys;me2 ys;me1 ys;me1 exp@b0
ht;1
g D50 1=2 :b0
ht;2
39b1
=1
ys;me2 5
;
(10)
8
20
0
1=2 !b1 11
< 1
t
t
t
D
g
h
2
1
50
t;3
1
AA
t2
ln4@ys;me3 ys;me2 ys;me2 exp@b0
ht;2
g D50 1=2 :b0
39 1
=b1
ys;me3 5
;
(11)
Figure 8. Illustrative scheme for computing time evolution of scour downstream of a GCS during a ood: (a) ow hydrograph, (b) time variations of
scour depth under steady ows, and (c) time variation of scour depth for an unsteady ow
Copyright 2012 John Wiley & Sons, Ltd.
J.-Y. LU ET AL.
Figure 9. Simulated and measured scour depth evolutions under stepwise hydrographs with single peaks: (a) symmetric, qp = 0.0475 m3/s, (b) delayed
peak, (c) advanced peak, (d) symmetric, qp = 0.0283 m3/s
CONCLUSIONS
Experiments on scour downstream of a GCS because of
ood events were investigated with two uniform sediments
without upstream sediment supply for various ramp slopes,
channel slopes and ow hydrographs. The proposed method
is proved to be a useful tool for the analysis of the problems
involving plunging jet scour induced by oods. Based on
the experimental results and the analysis of the scour
downstream of a GCS, the main ndings of the study are
summarized as follows:
1. According to the experimental observations, the hydraulic
jump formed downstream of a GCS-induced large
secondary ows and the vortices (xy plane), resulting
in the occurrence of the maximum scour depths near the
side walls.
2. Empirical formulae are derived to quantify the maximum
scour depth, the scour length, and the location of
the maximum scour depth downstream of a GCS
under steady ow conditions. The equilibrium scour
hole dimensions (xs,me, ys,me, ls,me) increase with an
increase in the channel slope, densimetric Froude
number, and tailwater depth and a decrease in the median
sediment size.
3. The equilibrium scour-hole prole downstream of a
GCS for steady ows can be estimated based on an
exponential function with three boundary conditions.
The comparison between the experimental data and the
predicted values gives good agreement.
4. The dimensionless maximum scour depth for steady
ows can be expressed as an exponential function of the
dimensionless time T. The empirical equation predicts the
temporal variation of the maximum scour depth
reasonably well.
5. Based on the dimensional analysis and the concept of
superposition, a scheme is proposed to estimate the
temporal variation of the maximum scour depth
downstream of a GCS under unsteady ow conditions.
ACKNOWLEDGEMENTS
REFERENCES
Bormann NE, Julien PY. 1991. Scour downstream of grade-control
structures. Journal of Hydraulic Engineering 117(5): 579594.
Breusers HNC, Raudkivi AJ. 1991. Scouring. Hydraulic structures design
manual, A. A. Balkema, Rotterdam, The Netherlands.
Cardoso AH, Bettess R. 1999. Effects of time and channel geometry on
scour at bridge abutments. Journal of Hydraulic Engineering, 125(4):
388399.
Chang WY, Lai JS, Yen CL. 2004. Evolution of scour depth at circular
bridge piers. Journal of Hydraulic Engineering 130(9): 905913.
Chatterjee SS, Ghosh SN, Chatterjee M. 1994. Local scour due to
submerged horizontal jet. Journal of Hydraulic Engineering, 120(8):
973992.
Chiew YM, Lim SY. 1996. Local scour by a deeply submerged horizontal
circular jet. Journal of Hydraulic Engineering 122(9): 529532.
Dargahi B. 2003. Scour development downstream of a spillway. Journal
of Hydraulic Research 41(4): 417426.
Dey S, Sarkar A. 2006. Scour downstream of an apron due to submerged
horizontal jets. Journal of Hydraulic Engineering 132(3): 246257.
Farhoudi J, Smith KVH. 1985. Local scour proles downstream of
hydraulic jump. Journal of Hydraulic Research 23(4): 343358.
Gaudio R, Marion A. 2003. Time evolution of scouring downstream of
bed sills. Journal of Hydraulic Research 41(3): 271284.
Gaudio R, Marion A, Bovolin V. 2000. Morphological effects of bed sills
in degrading rivers. Journal of Hydraulic Research 38(2): 8995.
Hoffmans GJCM, Verheij HJ. 1997. Scour Manual. Hydraulic structures
design manual, A. A. Balkema, Rotterdam, The Netherlands.
Kothyari UC, Garde RCJ, Ranga Raju KG. 1992. Temporal variation of
scour around circular bridge piers. Journal of Hydraulic Engineering
118(8): 10911106.
Lenzi MA, Marion A, Comiti F. 2003a. Interference processes on scouring
at bed sills. Earth Surface Processes and Landforms 28(1): 99110.
Lenzi MA, Marion A, Comiti F. 2003b. Local scouring at grade-control
structures in alluvial mountain rivers. Water Resources Research 39(7):
11761188.
Lenzi MA, Marion A, Comiti F, Gaudio R. 2002. Local scouring in low
and high gradient streams at bed sills, Journal of Hydraulic Research
40(6): 731739.
Lu JY, Hong JH, Su CC, Wang CY, Lai JS. 2008. Field Measurements
and Simulation of Bridge Scour Depth Variations during Floods.
Journal of Hydraulic Engineering 134(6): 810821.
Lu JY, Shi ZZ, Hong JH, Lee JJ, Raikar RV. 2011. Temporal Variation of
Scour Depth at Nonuniform Cylindrical Piers. Journal of Hydraulic
Engineering 137(1): 4556.
Marion A, Lenzi MA, Comiti F. 2004. Effect of sill spacing and sediment
size grading on scouring at grade-control structures. Earth Surface
Processes and Landforms 29(8): 983993.
Mason PJ, Arumugam K. 1985. Free jet scour below dams and ip
buckets. Journal of Hydraulic Engineering 111(2): 220235.
Meftah MB, Mossa M. 2006. Scour holes downstream of bed sills in lowgradient channels Journal of Hydraulic Research 44(4): 497509.
Melville BW, Chiew YM. 1999. Time scale for local scour at bridge piers.
Journal of Hydraulic Engineering 125(1): 5965.
Mia MF, Nago H. 2003. Design method of time-dependent local scour
at circular bridge pier. Journal of Hydraulic Engineering 129(6):
420427.
Oliveto G, Hager WH. 2005. Further results to time-dependent local
scour at bridge elements. Journal of Hydraulic Engineering 131(2):
97105.
Pagliara S. 2007. Inuence of sediment gradation on scour downstream of
block ramps. Journal of Hydraulic Engineering 33(11): 12411248.
Schoklitsch A. 1932. Kolkbidung unter uberfallstrahlen. Die Wasserwirtschaft.
Tregnaghi M, Marion A, Bottacin-Busolin A, Tait S. 2011. Modelling
time varying scouring at bed sills. Earth Surface Processes and
Landforms 36(13): 17611769.
Tregnaghi M, Marion A, Coleman S. 2009. Scouring at bed sills as a
response to ash oods. Journal of Hydraulic Engineering 135(6):
466475.
Tregnaghi M, Marion A, Coleman S, Tait SJ. 2010. Effect of ood
recession on scouring at bed sills. Journal of Hydraulic Engineering
136(4): 204213.
Tregnaghi M, Marion A, Gaudio R. 2007. Afnity and similarity of local
scour holes at bed sills. Water Resources Research 43: W11417. DOI:
10.1029/2006WR005559
Water Resources Planning Institute. 2009. Investigation of failure
mechanism and new scour countermeasures at grade-control structures
(2/2). Water Resources Agency: Taiwan, R.O.C. (in Chinese).
Hydrol. Process. (2012)