ABSTRACT
Attached to a construction company that is building a building located at Semenyih,
Selangor and Hazard Identification, Risk Assessment and Risk Control (HIRARC) has
been carried out at the construction site. As known, construction industry is one of the
industries that have been classified as the highest number that contribute to the accident
and resulted fatal.
This report aims to identify the hazard and risk assessment for the most critical hazard
and recommend control measures and review measures for the construction and to
archive the above objectives, the methods used to identify the hazard is by observation
and risk assessment in the workplace. The results of above methods, the risk of the most
critical safety hazards in at the site is crushed by heavy object while the most critical
health hazard is exposed to extreme temperature(heat). Measure to control the risk of
both hazards is suggested is based on hierarchy of control which is elimination,
substitution, isolation, engineering controls, administrative controls and last but not least
personal protective equipments (PPE)
towards the hazards. Risk work activities interpreted by using risk tables (qualitative) and
schedule risk assessment matrix (quantitative).
INTRODUCTION
We are identified in the industry as a provider of quality products and services that
are cost effective, technologically advanced in compliance with our clients
requirement with standard accuracy.
We provide a safe and productive work environment where people work together
towards common objectives effectively, efficiently and with pleasure.
We design and build facilities that are safe and environmentally sound and our
work processes, actions and attitudes are geared towards prevention from
pollution and avoidance of all circumstances that could cause personal injury,
illness and negative impact on the natural environment. In order to achieve such
objective, the system will be structured in accordance with ISO 9001 and
implemented in accordance with the applicable local laws and regulations.
We will strive for continuous improvement of our performance in all quality, health,
safety and environmental aspects through proactive planning, awareness, creative
thinking, openness and dialogue with all stakeholders and involved parties to be
consistent with the alteration may be occurred.
We recognize that achievement of this policy depends on the personal commitment and
input of each individual in all levels. The management level personnel have a special
responsibility and shall lead by example to ensure that this policy is thoroughly
communicated and substantially implemented.
SITE CEARLANCE
SETTING OUT
EXCAVATION
STRUCTURE WORK
PILING WORK
INFRASTRUCTURE
HAND OVER
5
MACHINE MOBILIZATION
MACHINE
MOBILIZATION
INJECTING PILE
WELDING
JOINT
WORK PROCESS
MACHINE MOBILISATION
HAZARD
1.
1.
FLYING FRAGMENT
2.
EXCESSIVE NOISE
3.
DUST
4.
INJECTING OF PILE
1. RADIATION
WELDING JOINT
2. .HEAT
3. AKWARD POSTURE
3 OBJECTIVE
The objective or aim of this HIRARC assignment are;
To implement HIRARC
Identifying the safety and health hazard in the workplace.
To assess the risk arising from the nature of the workplace.
To propose and give the recommendation by using the
hierarchy of control.
To find out the 5 safety hazard and 3 health hazard through the
work activity.
To get the risk rating by using the formula (likelihood X
severity).
4 METHODOLOGY
Methodology is the method that helps to accumulate all the information for the findings.
Information about the work process, the potential risk and any existing hazard at the
workplace. In this assignment, there are 3 types of methodology were used which are
interview, observation, risk assessment steps, severity table, likelihood table and risk
rating table.
Hazard Identification Process
Hazard identification process is the first step in the risk management process. Hazard is
defined as anything that can cause harm to the workers, property of company, and
environment. The purpose of identifying hazards is to determine any situation in the
workplace that has the potential to harm the safety and health of people and damage the
plant. The method that used to be obtaining data of the hazard in this report was;
I.
Interview
Interview one of the staff has given any related information regarding the work process
and the whole information about existing risk and potential hazards. The interview
session was asking about;
II.
Observation
Observed the workstation area and the work process to identify existing risk and potential
hazards. The observation such as:
10
Likelihood Table
Severity Table
11
Risk Matrix
Risk Description
12
Effect
-Bone fracture
bag of cement
at shoulder.
Likelihood
5
Severity
4
Risk Level
20
Frequent
Major
Incident
Lost time
happened more
injuries or
than 1 time in
illness (5 or
a year.
more MC)
Very High
13
5 HIRARC TABLE
1.
NO
HAZARD INDETIFICATION
WORK
ACTIVITI
HAZARD
WHICH CAN
CAUSE /
EFFECT
2.
EXISTING RISK
CONTROL ( IF
ANY)
MACHINE
STRUCK BY
FATAL /
HANDLE BY COMPETENT
MOBILISATION
MOVING
PERMANENT
PERSON
MACHINE
DISABILITY
RISK ANALYSIS
3.
RISK CONTROL
4.
RISK RATING
CONTROL
MEASURE/
LAW &
REGULATION
RECOMMENDATION
2
10
administrative Control
-ensure the machine was handle
by a competent person
-Place signalman to give direction
and communicate with operator
directly
14
FLYING
SCRATCH
FRAGMENT
EXCESSIVE
NOISE
2
HEARRING
DAMAGE
administrative Control
-job rotation
-increase length of frequent break
Personal Protective Equipment
(PPE)
-provide suitable PPE like ear
muff, ear plug
Engineering Control
-install water spray
PERSONAL PROTECTIVE
EQUIPMNET
INJECTING OF
PILE
DUST
LUNG DAMAGE
CRUSHED BY
FATAL
PERSONAL PROTECTIVE
Administrative Control
-job rotation
-increase length of frequent break
Personal Protective Equipment
(PPE)
-provide suitable PPE like face
mask
EQUIPMNET
3
FALLING /
HEAVY OBJECT
12
Isolation
-Provide barricade to avoid other
worker to enter piling work site
-Place warning sign to inform
other worker that piling work are
being caried out
Engineering Control
-Service the lump frequently
Administrative Control
-Provide training to all worker
-Ensure person that handle piling
machine is a competence person
Personal Protective Equipment
(PPE)
-Provide proper PPE like safety
helmet, safety boot and etc
15
RADIATION
HEAT
PERSONAL PROTECTIVE
DAMAGE EYE
EQUIPMNET
DEHYDRATION
-JOB ROTATION
Engineering Control
-Reduce the temperature and
humidity through air cooling
-Provide cool, shaded work areas
-Provide air-conditioned rest area
- Increase air movement if
temperature is below 35C (e.g., use
fans)
Administrative Control
-Employer should assess the demands
of all jobs and have monitoring and
control strategies in place for hot
days and hot workplaces
-Increase the frequency and length of
rest breaks
-Schedule strenuous jobs to cooler
times of the day
-Provide cool drinking water near
workers and remind them to drink a
cup about every 20 minutes, or more
frequently, to stay hydrated
Personal Protective Equipment
(PPE)
-Provide proper PPE like protective
clothing
-Influence worker to wear light
summer clothing should be worn to
allow free air movement and sweat
evaporation.
Administrative Control
-provide training to worker
PERSONAL PROTECTIVE
EQUIPMNET
WELDING JOINT
AKWARD
POSTURE
BACK PAIN
Administrative Control
-provide training to worker
-frequent break
16
6.1
Critical hazard is defined as the hazard which poses the highest risk rating in the Hazard
identification, Risk analysis and Risk control of HIRARC FORM. This is to identify by
calculating the risk which is likelihood multiply severity. In order to identify the value of
the risk, use the risk matrix table to know the value lies at what stage and use risk rating
table to determine the range of the hazard. They are two types of critical hazards such as
safety critical hazard and health critical hazard.
Most critical safety hazard
Work activity: Injecting pile (crushed by heavy object)
Engineering Control
-Provide barricade to avoid other worker to enter piling work site
-Place warning sign to inform other worker that piling work are being caried out
Administrative Control
-Provide training to all worker
-Ensure person that handle piling machine is a competence person
Personal Protective Equipment (PPE)
-Provide proper PPE like safety helmet, safety boot and etc
17
18
19
Training
Inspections
Work procedures
- Create awareness among the employee and use it as training tool as well.
- Set risk management standards (OSHAS 18001 & ISO 1900), based on on acceptable
safe practices and legal requirement. (OSHA 1994 & FMA 1967)
- Reduce incidents in the workplace by creating safety culture among the workers.
- Save costs by being proactive instead of reactive.
Reduce medical bills, compensation cost, retrain new workers and repair damage
property.
Workers will trust to the employer who that concern about the safety and health
and welfare.
20