Best Practice Guide For Environmental Protection On Construction Sites
Best Practice Guide For Environmental Protection On Construction Sites
Best Practice Guide For Environmental Protection On Construction Sites
2013
May 2013
ii
Disclaimer
The materials contained in this Best Practice Guide for Environmental Protection on Construction Sites
(hereunder Best Practice Guide) have been developed to provide guidance to interested parties, including
contractors and subcontractors, in managing environmental protection issues on sites. Every due care has
been exercised taking into account the circumstances of local working environment and requirements of the
laws of Hong Kong. Any advice or comment in this Best Practice Guide is given in this general context and
should not be relied upon as a substitute for legal or other professional advice.
This document is produced to provide practical guidance on managing environmental protection issues on
construction sites and to meet legal obligations. There is no intention whatsoever to offer exhaustive
guidance and interpretation of the environmental legislations and regulations of Hong Kong. Anyone wishing
to affirm the legal position of individual facts or situation should refer to the relevant regulations and other
related statutory documents or consult a lawyer.
Taking the advice and good management practice given in this document does not confer any immunity from
legal obligations, both criminal and civil.
Whilst every effort has been made to ensure the accuracy of the information provided in this Best Practice
Guide, the author, HKCA, their agents and the publishers accept no responsibility or liability for any loss or
damage caused, whether occasioned by negligence, misstatement or otherwise arising out of any errors,
omissions or inaccuracies in the materials.
Copyright
The copyright of this document rests with the Hong Kong Construction Association. Reproduction of any of
its contents for commercial purpose is not allowed.
Acknowledgements
The preparation of this document was placed under the stewardship of HKCA Environmental Committee that
gave the consultants direction and steer.
We would like to record our acknowledgments and thanks to the following Best Practice Guide Task Group
Members Ir Ringo Yu (convener)
Mr Eddie Tse
Mr Chris Telford
Mr Tony Yam
Mr Patrick Tang
Preface
HKCA is in support of green construction initiatives and is committed to take
lead in introducing those initiatives to our membership and the industry as a
whole. We are pleased to publish the Best Practice Guide for Environmental
Protection on Construction Sites 2013 (the Guide) to improving the environment.
The Guide was first published in 2002 and updated last in 2009. Given the current trend
of society and the significant new legislation, regulations and non-statutory guidelines/
codes of practice that have been issued lately, we commissioned AECOM Asia Co., Ltd.
to review and update the Guide and the key aspects of the update are as follows:
1.
2.
3.
4.
Update of statutory and regulatory requirements and new contractual requirements for government
projects and public housing projects.
Update section of the BEAM from HK-BEAM Society to be in line with the latest version, i.e. BEAM
Plus.
Add a new section for BEAM Plus and LEED credits related to contractors work and good practices,
and provide practical measures and minimum supporting submittal required for achieving each
concerned credits.
Provide hyperlinks to corresponding websites and relevant sections in the Guide
The purpose of the Guide is to provide a handy reference to frontline management teams in managing
certain critical and environmental-prone site issues. By drawing on past cases, good and bad trade practices,
the 2013 Guide aims to provide a framework for those who have direct influence over environmental
performance, with some useful pointers for continuous improvement.
Last, but not least, special thanks are due to the Task Group members of our Environmental Committee to
steer the project and have regular working sessions with AECOM to provide practical advice, insightful
directions and thorough review to various drafts of the book. I hope that this Guide may serve as useful
reference for industry practitioners and thus bring about significant beneficial change on the environmental
performance of the whole industry.
Ir Ringo S M Yu
Chairman of Environmental Committee, HKCA
May 2013
Table of Contents
10
11
12
13
14
15
16
Introduction
ENSR
Asia
(HK)
Limited
(ENSR)
was
commissioned by the Hong Kong Construction
Association (HKCA) to carry out the review and
revision works for the Best Practice Guide for
Environment Protection on Construction Sites (the
Guide) which was launched in 2002 and amended
in October 2004.
A desk top study was carried out to review and
update statutory and non-statutory information,
contained in the existing Guide which has changed
as a result of revised or new requirements. The
scope of this version of the Guide has been
expanded to cover wider aspects with respect to
environmental protection and management on
construction sites and to incorporate the latest best
practice.
To improve the readability of the Guide and keep it
up-to-date, hyperlinks to the existing statutory and
non-statutory requirements is provided in the
softcopy version of this revision.
The Guide focuses on the environmental issues
which are often encountered within the construction
industry and the practical mitigation measures to
reduce environmental impacts.
The purpose of the Guide is to provide the reader
with a general understanding of the environmental
pollution control ordinances and other requirements
relevant to construction activities. It gives practical
suggestions to the construction industry to
implement environmental protection measures on
sites to comply with current relevant environmental
requirements in Hong Kong and to promote best
available practice.
1-1
Table of Contents
List of Tables
Table 2.1
Table 2.1
Table 2.2
Table 2.2
Table 2.3
Table 2.4
Table 2.4
Table 2.5
Table 2.6
Practice Note for Registered Contractors Related to Construction Site ............................. 2-8
Table 2.7
Practice Note for Professional Persons Related to Construction Site ................................ 2-8
Table 2.9
Table 2.10
Compliance Path to meet both LEED and BEAM Plus requirement ....................................18
Table 2.11
List of Appendices
Appendix 2.1
2.1
Ordinance
Description
Summary
Air Pollution
Control
Ordinance, Cap
311 Section 48
Statutory defence:
Due diligence
Waste Disposal
Ordinance, Cap
354 Section 31
In any proceedings for an offence under section 11, 15, 15A, 15AA, 16, 16A,
17, 18A, 20E or 23 it shall not be necessary for the prosecution to prove that
the acts or omissions in question were accompanied by an intention,
knowledge or negligence on the part of the defendant as to any element of
the offence.
No need of mens
rea, actus reus
suffice
2-1
Table 2.1
Ordinance
Description
Water Pollution
Control
Ordinance, Cap
358 Section 10
In any proceedings for an offence under section 8(1), 8(1A), 8(2), 9(1) or 9(2)
in which it is alleged that the defendant caused matter to enter the waters of
Hong Kong or inland waters or a communal sewer or communal drain or
caused matter to be deposited as provided in section 2(3) it shall not be
necessary for the prosecution to prove that the acts or omissions in question
were accompanied by any intention, knowledge or negligence on the part of
the defendant as to any element of the offence.
2.2
Summary
No need of mens
rea, actus reus
suffice
construction work.
Regarding construction
activities,
the
ordinance mainly
concerns
construction dust or black smoke emissions as well
as specified processes such as operating a
concrete batching plant.
Abatement notices are usually issued to anyone
causing air pollution from a process or machinery
and they will be asked to reduce or stop their
emissions. Polluters failing to comply with the
notice will face prosecution.
The ordinance is the principle law for managing air
quality. Table 2.2 shows the relevant control
legislation related to construction site air pollution.
Table 2.2
Description of Control
2-2
Table 2.2
Description of Control
2-3
Table 2.3
Noise Control
General
Legislation
Description of Control
Noisy Products
2-4
Description of Control
2-5
Table 2.4
Description of Control
conditions
Description of Control
2.2.5
2-6
2.3
2.4
2.2.8
2-7
Non-Statutory Requirements
Table 2.6
Table 2.7
2-8
Table 2.8
2-9
Table 2.8
Sets out the trip ticket system for public works contracts.
2-10
Table 2.9
BEAM Plus Credits Related to Foundation and/or Superstructure Contractors during
Construction Stage
Foundation (F)
Superstructure (S)
Foundation (F)
Superstructure (S)
SA 10 Environmental
Management Plan
S
SA 12 Noise Pollution During
Construction
2-13
FSC
MA P3 Construction and
Demolition Waste Management
Plan
AFPA
MA 3 Prefabrication
Sustainable
Forest
2-14
The
unit
of
calculation
should
be
mass/volume/dollar value, which should be
consistent in overall.
Equation for sustainable forest product calculation
is illustrated in below:% of sustainable timber = (Total unit of permanently
timber originated from sustainable sources/ Total
unit of all permanently install timber) x 100%
For sample of BEAM Plus submission please refer
to Appendix 2.2.1
MA 7 Recycled Materials
MA 9 Regionally Manufactured
Materials
2-15
Contractor
should
submit
calculation
to
demonstrate the estimated aggregate annual water
use saving to achieve at least 20% (1 BEAM credit),
or 25% (2 BEAM credits), or 30% (3 BEAM credits).
For sample of Annual Water Use saving calculation
please refer to Appendix 2.4.4.
Energy Use (EU)
EU 3 Embodied Energy in
Building Structural Elements
Contractor
should
provide
commissioning
specification indicating that details testing and
commissioning requirements and cost provisions
for all building services system, equipment and
components.
Contractor should appoint a commissioning
authority and provide a commissioning plan that
embraces all specified commissioning work.
Contractor should provide a detailed T&C report for
all systems, equipment and components that
impact on energy use and indoor environmental
quality.
All the testing and commissioning documents shall
meet the requirements detailed in Section 8.5.18.5.4 in BEAM Plus Guidelines as a minimum
EU 11
Maintenance
Operation
and
2-16
Prerequisites
The applicant project MUST satisfy all the
prerequisites and qualify for a minimum number of
points to attain the established project ratings.
Failure of compliance would result in project
disqualification.
2-17
Table 2.10
LEED Credits a
There is no LEED related criteria. Please refer to section 2.4.4 for compliance.
SS P1 Construction Activity Pollution
Prevention
This is a prerequisite credit in LEED which MUST be complied for any rating.
There is no BEAM Plus related criteria.
Create and implement an erosion and sedimentation control plan for all
construction activities associated with the project.
There is no LEED related criteria. Please refer to section 2.4.4 for compliance.
There is no LEED related criteria. Please refer to section 2.4.4 for compliance.
There is no LEED related criteria. Please refer to section 2.4.4 for compliance.
There is no LEED related criteria. Please refer to section 2.4.4 for compliance.
MA P2 Use of Non-CFC
Based Refrigerants
EA P3 Fundamental Refrigerant
Management
MA P3 Construction and
Demolition Waste Management
Plan
MR 2 Construction Waste
Management
MA 11 Construction Waste
Reduction
MA 3 Prefabrication
There is no LEED related criteria. Please refer to section 2.4.4 for compliance.
MA 6 Sustainable Forest
Product
MR 7 Certified Wood
Use at least of 50% of wood-based materials and products that are certified in
accordance with the FSCs principles and criteria, for wood building components.
Stringent LEED criteria beyond BEAM Plus
- Calculation is based on cost only.
- Selection of materials origin is limited to FSC only.
2-18
LEED Credits a
MR 4 Recycled Content
MA 8 Ozone Depleting
Substances
EA 4 Enhanced Refrigerant
Management
MA 9 Regionally Manufactured
Materials
MR 5 Regional Materials
At least 10% (1 LEED point) or 20% (2 LEED points) of all building materials and
products that are extracted, harvested or recovered, as well as manufactured
within 500miles (800km) of the project site, based on cost only.
Stringent LEED criteria beyond BEAM Plus
- Regional materials are identified from point of extraction and harvest instead of
manufacture location.
- Calculation is based on cost only.
There is no LEED related criteria. Please refer to section 2.4.4 for compliance.
WE 3 Water Use Reduction
At least 30% (2 LEED credit), or 35% (3 LEED credits), or 40% (4 LEED credits)
of estimated annual saving from the baseline
Stringent LEED criteria beyond BEAM Plus
LEED requires an estimated annual saving of at least 20% as a prerequisite.
Flushing water use reduction from water closets and urinals cannot be included
in the calculation.
2-19
LEED Credits a
There is no LEED related criteria. Please refer to section 2.4.4 for compliance.
EU 10 Testing and
Commissioning
EA P1 Fundamental commissioning
of Building Energy Systems
EU 11 Operation and
Maintenance
EA 3 Enhanced Commissioning
There is no LEED related criteria. Please refer to section 2.4.4 for compliance.
2-20
LEED Credits a
MR 4 Recycled Content
Use materials with recycled content such that the sum of postconsumer recycled
content plus 1/2 of the pre-consumer content constitutes at least 10% (1 LEED
point) or 20% (2 LEED points). Calculation is based on cost only.
Stringent LEED criteria beyond BEAM Plus
- For LEED assessment, there is no separated calculation for outside surface
works and structure (MA 7a), building structure (MA7b) and interior components
(MA7c)
- Calculation is based on cost only, and the calculation equation should be
modified from BEAM Plus.
MA 8 Ozone Depleting
Substances
EA 4 Enhanced
Management
MA 9 Regionally Manufactured
Materials
MR 5 Regional Materials
Refrigerant
There is no LEED related criteria. Please refer to section 2.4.4 for compliance.
Remark:
a
LEED addresses the different project development and delivery processes through the different rating systems, such as LEED for New
Construction (NC), LEED for Core & Shell (CS) and LEED for School etc. Credits described in Table 2.4.2 is according to LEED NC criteria in
general.
2-21
2.4.7
Specification
Table 2.11
Clause Reference
Remark
PRE.B8.2510
PRE.B8.2560
the
Environmental
PRE.B8.APPEND9
PRE.B8.510
PRE.B8.570
PRE.B8.APPEND9
PRE.B8.890
PRE.B8.899
SA 13 Water Pollution During
Construction
Conduct and
monitoring
report
on
construction
noise
PRE.B8.APPEND9
PRE.B8.2410
PRE.B8.2450
CON2.M080
2-22
Clause Reference
Remark
PRE.B8.2820
MA P3 Construction and
Demolition Waste Management Plan
PRE.B8.2520
PRE.B8.APPEND9
MA 3 Prefabrication
PRE.B8.2820
PRE.B8.2820
PRE.B8.2820
MA 9 Regionally Manufactured
Materials
PRE.B8.2820
MA 10 Demolition Waste
Reduction
PRE.B8.2820
MA 11 Construction Waste
Reduction
PRE.B8.2820
PRE.B8.2820
PLU2.T070
PRE.B8.2820
PLU2.M510
PRE.B8.2820
Commissioning
systems
PRE.B8.2820
PRE.B8.2820
electrical
and
mechanical
2-23
Clause Reference
Remark
PRE.B8.2820
PRE.B8.2820
2-24
Section
Activity / Source
Liability
Second or Subsequent
Offence
First Offence
Air Pollution Control
Ordinance (Cap. 311)
1983
10
A person who
commits the offence
30
Fine of $100,000
13
Fine of $200,000
6 months imprisonment
Fine of $20,000 for each day if offence continues
A2-1
Fine of $200,000
6 months imprisonment
Fine of $20,000 for each
day if offence continues
Maximum Penalties
Legislation
Section
Activity / Source
Liability
First Offence
29
Fine of $50,000
Second or Subsequent
Offence
Fine at Level 4
Fine at Level 5
Fine at Level 5
Fine at Level 6
3 months imprisonment
Fine of $10,000 each day if
offence continues during
the whole or any part of the
works
A2-2
Maximum Penalties
Legislation
Section
Activity / Source
Liability
Second or Subsequent
Offence
First Offence
Air Pollution Control
(Construction Dust)
Regulation (Cap.
311R) 1997 (cont)
5, 6
Fine at Level 4
Fine at Level 5
Fine of $5,000 each day if
offence continues during
the whole or any part of the
works
Fine at Level 5
Fine of $500 for every 15
minutes if offence continues
Fine at Level 5
3 months imprisonment
Fine at Level 5
Fine of $500 for every 15
minutes if offence continues
Fine at Level 5
3 months imprisonment
Fine of $500 for every 15
minutes if offence
continues
An owner of
premises who
operates any
chimney or relevant
plant
Fine of $20,000
Fine of $100 for every one
quarter of an hour during
the whole or any part of
which such offence is
knowingly and wilfully
continues
Fine of $20,000
3 months imprisonment
Fine of $100 for one
quarter of an hour during
the whole or any part of
which such offence
knowingly and wilfully
continues
3, 17
A person who
imports or
manufactures the
regulated paints
Fine of $200,000
6 months imprisonment
17
A person who
commits the offence
Fine at level 5
3 months imprisonment
A2-3
Maximum Penalties
Legislation
Section
Activity / Source
Liability
First Offence
Second or Subsequent
Offence
Fine at Level 5
Fine at Level 5
3 months imprisonment
A Competent
examiner who
commits the offence
Fine at Level 5
Fine at Level 5
3 months imprisonment
Building (Demolition
Works) Regulations
(Cap. 123C) 1962
3, 13
An authorized
person, and/or
registered specialist
contractor who is
guilty of the offence
Fine of $25,000
50
Fine of $10,000
74
Fine of $10,000
6 months imprisonment
An owner, agent or
master of a vessel
who commits the
offence
Fine of $50,000
2 years imprisonment
A2-4
Fine of $20,000
Section
Activity / Source
Liability*
First offence
Noise Control
Ordinance (Cap. 400)
1988
6 (1)
6 (2)
26
A2-5
Fine of $100,000
Fine of $50,000
Second or Subsequent
Offence
Fine of $200,000
Fine of $20,000 each day
if offence continues
Maximum Penalties
Legislation
Section
Activity / Source
Liability*
Second or Subsequent
Offence
First offence
Noise Control
Ordinance (Cap. 400)
1988 (cont)
Noise Control
Ordinance (Cap. 400)
2002
6 (3)
6 (4)
14 (1a)
14 (1b)
28A
Fine of $100,000
Fine of $200,000
Fine of $20,000 each day
if offence continues
Fine of $100,000
Fine of $200,000
Fine of $20,000 each day
if offence continues
A director or an
officer of the body
incorporate
--
--
*Remark: Liability for prosecution under the ordinance for an offence may include the management and supervisory staff of the Contractor, e.g. site agent, foreman.
A2-6
Section
Activity / Source
Liability
First offence
Waste Disposal
Ordinance (Cap.354)
1990
Second or Subsequent
Offence
13
Fine of $50,000
16
Fine of $200,000
6 months imprisonment
Fine of $500,000
6 months imprisonment
Fine of $10,000 each day
if offence continues
16A
Fine of $200,000
6 months imprisonment
Fine of $500,000
6 months imprisonment
Fine of $10,000 each day
if offence continues
17
Fine of $100,000
Fine of $200,000
6 months imprisonment
Fine of $10,000 each day
if offence continues
23
Fine of $200,000
6 months imprisonment
Fine of $500,000
6 months imprisonment
Additional fine of $10,000
each day if offence
continues
Fine of $100,000
Fine of $200,000
Additional fine of $5,000
per day if offence
continues
A2-7
Maximum Penalties
Legislation
Section
Activity / Source
Liability
First offence
Waste Disposal
Ordinance (Cap.354)
1990
23B
A person who
commits the offence
Fine of $100,000
23F
Fine of $100,000
Second or Subsequent
Offence
A2-8
Maximum Penalties
Legislation
Section
Activity / Source
Liability
First offence
Waste Disposal
(Chemical Waste)
(General) Regulation
(Cap. 354C) 1992
(For the details of the
requirements under s.9,
10, 12, 13, 15 and 18,
please refer to the
booklet Code of
Practice on the
Packaging, Labelling
and Storage of
Chemical Wastes )
Second or Subsequent
Offence
6, 38
Fine of $200,000
6 months imprisonment
7, 38
A registered waste
producer
Fine of $10,000
8(1), 38
A registered waste
producer
Fine of $200,000
6 months imprisonment
8(4), 38
Fine of $100,000
6 months imprisonment
9, 38
A waste producer
who commits the
offence
Fine of $100,000
6 months imprisonment
10, 38
A Waste producer
who commits the
offence
Fine of $100,000
6 months imprisonment
A waste producer
and the person
responsible for such
packing and storing
who commits the
offence
Fine of $100,000
6 months imprisonment
A2-9
Maximum Penalties
Legislation
Section
Activity / Source
Liability
First offence
Waste Disposal
(Chemical Waste)
(General) Regulation
(Cap. 354C) 1992
Second or Subsequent
Offence
12, 38
A waste producer
who commits the
offence
Fine of $50,000
6 months imprisonment
13, 38
A waste producer
who commits the
offence
Fine of $100,000
6 months imprisonment
5
6
7
8
9
A2-10
Maximum Penalties
Legislation
Section
Activity / Source
Liability
First offence
Waste Disposal
(Chemical Waste)
(General) Regulation
(Cap. 354C) 1992
14, 38
15, 38
Fine of $100,000
6 months imprisonment
Fine of $100,000
6 months imprisonment
18, 38
Fine of $50,000
6 months imprisonment
21, 38
Fine of $200,000
6 months imprisonment
A2-11
A waste producer
who commits the
offence
Second or Subsequent
Offence
Maximum Penalties
Legislation
Section
Activity / Source
Liability
First offence
Waste Disposal
(Chemical Waste)
(General) Regulation
(Cap. 354C) 1992
Second or Subsequent
Offence
22, 38
A person who
commits the offence
Fine of $100,000
6 months imprisonment
28, 38
Fine of $50,000
6 months imprisonment
29, 38
A person who
commits the offence
Fine of $100,000
6 months imprisonment
A2-12
Maximum Penalties
Legislation
Section
Activity / Source
Liability
First offence
Waste Disposal
(Chemical Waste)
(General) Regulation
(Cap. 354C) 1992
Second or Subsequent
Offence
30, 38
A waste producer
who commits the
offence
Fine of $200,000
6 months imprisonment
31, 38
Fine of $200,000
6 months imprisonment
32, 38
Fine of $200,000
6 months imprisonment
A2-13
Maximum Penalties
Legislation
Section
Activity / Source
Liability
First offence
Waste Disposal
(Chemical Waste)
(General) Regulation
(Cap. 354C) 1992
37, 38
Fine of $200,000
6 months imprisonment
Waste Disposal
(Charges for Disposal
of Construction Waste)
Regulation (Cap. 354N)
2004
Fine at Level 6
9 (1)
A main contractor
who commits the
offence
Fine at Level 5
9 (2)
A main contractor
who commits the
offence
Fine at level 5
A2-14
Second or Subsequent
Offence
Additional daily fine of
$10,000 if offence
continues
Maximum Penalties
Legislation
Section
Activity / Source
Liability
First offence
Waste Disposal
(Charges for Disposal
of Construction Waste)
Regulation (Cap. 354N)
2004
22
A person who:
1 Makes any statement or gives any
information that he knows to be incorrect in
a material particular;
2 Recklessly makes any statement or gives
any information that is incorrect in a
material particular; or
3 Knowingly or recklessly omits any material
particular from any statement or
information.
A2-15
A person who
commits the offence
Second or Subsequent
Offence
Fine at Level 6
Section
Activity / Source
Liability
First offence
Hazardous Chemical
Control Ordinance
(Cap. 595) 2008
A person who
commits the offence
Fine at Level 5
1 year imprisonment
A person who
commits the offence
Fine at Level 5
1 year imprisonment
A person who
commits the offence
Fine at Level 5
1 year imprisonment
16
Fine at Level 1
6 months imprisonment
18
Fine at Level 4
6 months imprisonment
21
Fine at Level 1
6 months imprisonment
26
A person who
commits the offence
Fine at Level 3
6 months imprisonment
29
A person who
commits the offence
Fine at Level 1
6 months imprisonment
A2-16
Second or Subsequent
Offence
Maximum Penalties
Legislation
Section
Activity / Source
Liability
First offence
Hazardous Chemical
Control Ordinance
(Cap. 595) 2008
32
A person who:
1 Without reasonable excuse, fails to comply
with a requirement made under subsection
(2)(a) or (b); or
2 Wilfully obstructs an authorized officer in the
exercise of any power conferred under
subsection (1) or (2).
A person who
commits the offence
Fine at Level 3
6 months imprisonment
33
A person who:
1 Without reasonable excuse, fails to comply
with a requirement made under subsection
(1)(b) or (c); or
2 Wilfully obstructs an authorized officer in the
exercise of any power conferred under
subsection (1).
A person who
commits the offence
Fine at Level 3
6 months imprisonment
40
A person who:
1 Produces any document or provides any
information that he knows to be misleading,
false or inaccurate in a material particular;
2 Recklessly produces any document or
provides any information that is misleading,
false or inaccurate in a material particular;
or
3 Produces any document or provides any
information that he has no reasonable
ground to believe to be true or accurate; or
4 When required to produce any document or
provide any information in respect of any
matter to an authorized officer in the
exercise of his powers under this
Ordinance, withholds the document or
information.
A person who
commits the offence
Fine at level 3
6 months imprisonment
A2-17
Second or Subsequent
Offence
Maximum Penalties
Legislation
Section
Activity / Source
Liability
First offence
A person who
commits the offence
Fine of $1,000,000
2 years imprisonment
A person who
commits the offence
Fine of $1,000,000
2 years imprisonment
A person who
commits the offence
Fine of $1,000,000
2 years imprisonment
13
A person who:
1 Wilfully resists, obstructs or delays any
authorized officer in the exercise of any
powers conferred on him by or under this
Ordinance;
2 Fails without reasonable excuse to comply
with any requirement made by an
authorized officer under section 10, 11 or
12;
A person who
commits the offence
Fine of $100,000
6 months imprisonment
Second or Subsequent
Offence
Fine of $100,000 for each
day on which the offence
continues
A2-18
Maximum Penalties
Legislation
Section
Activity / Source
Liability
First offence
A person who
commits the offence
Fine of $100,000
A person who
commits the offence
Fine of $100,000
A2-19
Second or Subsequent
Offence
Maximum Penalties
Legislation
Section
Activity / Source
Liability
First offence
A person who:
1 Import a controlled product from any
country or place which is not bound by the
terms of the Protocol unless the Director of
Environmental Protection is satisfied that
the country or place is in full compliance
with the relevant requirements of the
Protocol.
2 Import a portable fire extinguisher from any
country or place, whether or not bound by
the terms of the Protocol, unless the
Director of Environmental Protection after
consulting the Director of Fire Services
certifies that the portable fire extinguisher is
required for essential applications relating to
emergency situations or where lives are at
risk.
A person who
commits the offence
Second or Subsequent
Offence
Fine of $200,000
6 months imprisonment
A2-20
Section
Activity / Source
Liability
First offence
8(1), 8(2),
9(1), 9(2)
1.
The Occupier of
premises or
vessel; or
2.
The person
having
command or
charge of the
vessel; or
A Person
causing the
discharge
1.
8(1A), 8(2),
9(1), 9(2)
3.
2.
3.
A2-21
The Occupier of
premises or
vessel; or
The person
having
command or
charge of the
vessel; or
A person
causing the
discharge
$200,000
6 months imprisonment
Second or Subsequent
Offence
$400,000
6 months imprisonment
Fine of $10,000 each day
if offence continues
Maximum Penalties
Legislation
Section
Activity / Source
Liability
First offence
35
A person who:
1 Fails without reasonable excuse to comply
with the requirement of notice from
Authority (DEP); or
2 In compliance or purported compliance with
a notice from Authority makes any
statement which he knows to be false in a
material particular or recklessly makes any
statement which is false in a material
particular or knowingly omits any material
particular; or
3 In an application makes a statement or
gives an estimate which he knows to be
false in a material particular or who
recklessly makes a statement or gives an
estimate which is false in a material
particular or knowingly omits a material
particular from the application.
A person who
commits the offence
Fine of $10,000
40
A person who:
1 Wilfully obstructs an authorized officer in
exercise of any power conferred on such
officer; or
2 Fails without reasonable excuse to comply
with the requirement duly made by officer
under WPCO; or
3 In compliance or purported compliance with
any requirement produces any drawing,
document or record which he knows to be
incorrect or inaccurate in a material
particular or does not believe to be correct
and accurate.
A person who
commits the offence
Fine of $10,000
A2-22
Second or Subsequent
Offence
Maximum Penalties
Legislation
Section
Activity / Source
Liability
First offence
40A
A person who:
1 Tampers or interferes with a device that is
used for sampling any matter;
2 Tampers or interferes with a sample
obtained;
3
A person who
commits the offence
Fine of $10,000
Second or Subsequent
Offence
46
Depends on different
provision
Fine of $200,000
6 months imprisonment
17(2)
A person who
commits the offence
Fine of $10,000
17B
A person who
commits the offence
Fine of $200,000
6 months imprisonment
A2-23
Maximum Penalties
Legislation
Section
Activity / Source
Liability
Second or Subsequent
Offence
First offence
Dumping at Sea
Ordinance (Cap. 466)
1997 #
25 (1)
A person who:
1 Does anything without required permit; or
2 Causes or allows another person to do
anything for without required permit.
A person who
commits the offence
Fine of $200,000
6 months imprisonment
A person who:
1 Makes a statement which he knows to be
false in a material particular;
A person who
commits the offence
Fine of $200,000
2
3
6 months imprisonment
A person who
commits the offence
Fine of $200,000
6 months imprisonment
Further fine of $10,000 for each
day that the court is satisfied
that the failure to cease the
operation has continued.
25 (6)(b)
A person who
commits the offence
Fine of $200,000
6 months imprisonment
A2-24
Maximum Penalties
Legislation
Section
Activity / Source
Liability
First offence
Dumping at Sea
Ordinance (Cap. 466)
1997 #
25 (7)
A person who:
1 Intentionally obstructs the Authority or an
authorized officer in the performance of his
functions under this Ordinance;
2 Fails without reasonable excuse to comply
with a requirement made or direction given
by the Authority or an authorized officer in
the performance of his functions under this
Ordinance; or
3 In purporting to give information required by
the Authority or an authorized officer for the
performance of his functions under this
Ordinance(a)
Makes a statement which the person
knows to be false in a material
particular;
(b)
Recklessly makes a statement which is
false in a material particular; or
(c)
Intentionally fails to disclose a material
particular.
A person who
commits the offence
Second or Subsequent
Offence
Fine of $200,000
6 months imprisonment
#Remark: Liability for prosecution under the ordinance for an offence may include body corporate, management of the firm, the partner or the firm.
A2-25
Section
Activity / Source
Liability
Second or Subsequent
Offence
First offence
Environmental Impact
Assessment Ordinance
(Cap. 499) 1997
9, 26
A person who
commits the offence
Fine of $2,000,000
6 months imprisonment
Fine of $10,000 each day if
offence continues
(For summary conviction)
Fine at Level 6
6 months imprisonment
Fine of $10,000 each day if
offence continues
A2-26
Fine of $5,000,000
2 years imprisonment
Fine of $10,000 each day
if offence continues
(For summary conviction)
Fine of $1,000,000
1 year imprisonment
Fine of $10,000 each day
if offence continues
Maximum Penalties
Legislation
Section
Activity / Source
Liability
First offence
Environmental Impact
Assessment Ordinance
(Cap. 499) 1997
23, 27
A person who:
1
A person who
commits the offence
Second or Subsequent
Offence
Fine at Level 5
A2-27
Appendix 2.2.1
MA 6 Sustainable Timber Calculation Sample
No.
Component
Quantity
Total Timber
Cost
Sustainable
Timber?
Total Sustainable
Timber Cost
1
2
3
4
e.g. 8
e.g. 8
e.g. 2
e.g. 6,400
e.g. 8,000
e.g. 2,000
e.g. No
e.g. Yes (FSC)
e.g. Yes (FSC)
e.g. 0
e.g. 8,000
e.g. 2,000
Total:
16,400
Sustainable
Timber %
10,000
61.0%
* The exact full list of regional material items should be project specific, which should be suggested by the
project BEAM / LEED consultant.
A2-30
Hong Kong Construction Association
Appendix 2.2.2
MA 8 Ozone Depletion & Global Warming Potential calculation
HVAC&R
equipment
No. of
Units
Q
unit
(kW)
Refrigerant
GWPr
ODPr
Rc
(kg/kW)
Life
(yrs)
Lr
(%)
Mr
(%)
Total Q
unit
(kW)
Tr
(Lr x Life
x Mr)
LCGWP
LCODP
RAI
TRAI
11.2
R410a
1,890
0.76
10
2.0%
10%
11.2
30.0%
43.03
43.03
481.95
22.4
R410a
1,890
0.38
10
2.0%
10%
89.6
30.0%
21.52
21.52
1927.80
15.5
R410a
1,890
0.55
10
2.0%
10%
93
30.0%
31.09
31.09
2891.70
22.4
R410a
1,890
0.38
10
2.0%
10%
67.2
30.0%
21.52
21.52
1445.85
15.5
R410a
1,890
0.55
10
2.0%
10%
31
30.0%
31.09
31.09
963.90
Total Q
292
Total RAI
7711.20
Average RAI
26.41
* The exact full list of regional material items should be project specific, which should be suggested by the project BEAM / LEED consultant.
A2-30
Appendix 2.2.3
MA 9 Regional Materials Sample Checklist
No.
Items
Distance between
project site and
manufacture
Location of
Manufacturing
(km)
1
Product Cost
Within 800km
(HK$)
Concrete
e.g.PRC - Guangdong
e.g. 100
e.g. 4,000,000
Yes
Steel Bar
e.g.PRC - Guangdong
e.g. 100
e.g. 8,990,000
Yes
Structural steel
e.g.PRC - Guangdong
e.g. 100
e.g. 10,000,000
Yes
Gypsum
e.g.PRC - Guangdong
e.g. 100
e.g. 200,000
Yes
Masonry
e.g.PRC - Guangdong
e.g. 100
e.g. 300,000
Yes
Aluminum Profile
e.g. 950
e.g. 1,800,000
No
Timber Product
e.g. 950
e.g. 400,000
No
Glass
e.g. 950
e.g. 3,500,000
No
HK$ 29,190,000
HK$ 16,300,000
55.8%
* The exact full list of regional material items should be project specific, which should be suggested by the
project BEAM / LEED consultant.
* According to BEAM Plus Guidelines, building material taken into account in MA 9 credit is defined as the
final product at the point of manufacturing, not raw material at the point of extraction, harvest or recovery
A2-30
Hong Kong Construction Association
Appendix 2.2.4
WU 1 Annual Water Use saving calculation sample
Flow Devices
Model
Watering Duration
(sec)
Design
Baseline
Number of
Occupancy
Freq. of use
per occupant
per day
Annual
Operation
Day
Baseline
Pantry
Faucet
example
15
15
100
8.3
365
Sub-total =
45,625
75,738
45,625
75,738
Showers
Showerhead
example
300
300
100
0.1
9.5
365
Sub-total =
109,500
173,375
109,500
173,375
Restroom Faucet
Faucet
example
10
10
100
5.8
8.3
365
176,417
252,458
Sub-total =
176,417
252,458
331,542
501,571
33.9%
Remarks:
a
Flow devices include water taps for bath, basin, pantry, kitchen, and also shower heads and exclude water closet, urinal, water features, appliance and irrigation. There
should be separate entries for water use in male and female facilities.
b
Design flow rate is base on the equipment catalogues provided.
A2-30
Appendix 2.2.5
EU 3 Embodied Energy Sample Checklist
No.
Items
Product Model
Quantity
Unit
Concrete
m3
Reinforcement Steel
kg
Structural steel
kg
m2
Louvre
m2
Aluminum cladding
* The exact full list of regional material items should be project specific, which should be suggested by the
project BEAM / LEED consultant.
*Data input from the checklist will be used to calculate the total embodied energy of the building structural
elements
A2-30
Hong Kong Construction Association
Table of Contents
List of Table
Table 3.1
Items Requiring Budget Allocation for Equipment / Material with Respect to Different
Environmental Issues ...................................................................................................... 3-3
List of Appendices
Appendix 3.1
Appendix 3.2
Appendix 3.3
A2-30
Hong Kong Construction Association
Project Planning
3.1
Stage 1 Tendering
3-1
Table 3.1
Items Requiring Budget Allocation for Equipment / Material with Respect to Different
Environmental Issues
Environmental Issue
Noise Control
Drip trays
Labelling
Packaging
Hoardings
Hard paving
Noise barriers
Noise enclosures
Absorption materials
CNP applications
3-3
Table 3.1
Items Requiring Budget Allocation for Equipment / Material with Respect to Different
Environmental Issues (Continued)
Environmental Issue
Wastewater Control
Licence applications
oil interceptors
Sand bags
Sludge disposal
3-4
3.1.3 Programming
Good project planning involves developing a
programme that takes account of the sequencing of
construction activities to minimise environmental
impacts and allows the time necessary for
establishing environmental mitigation measures.
For example:
No construction activities can proceed during
restricted hours without a Construction Noise
Permit (note that a Construction Noise Permit
may not be issued if the predicted noise levels
exceed the standards set in the Technical
Memorandum, so avoid programming work in
restricted hours, whenever possible);
Avoid noisy activities during sensitive hours (e.g.
during school examination periods);
Select working practices and equipment that is
environmental friendly, e.g. using quieter plant
such as Quality Powered Mechanical
Equipment;
Sequence construction activities to minimise
land disturbance to reduce dust impact;
Schedule compaction and hydroseeding such
as soil stabilization to prevent environmental
impacts caused by heavy rain;
Schedule the procurement and installation of
pollution control equipment;
Schedule licence and permit applications; and
Schedule environmental monitoring, inspection,
training and meetings.
Appendix 3.2 shows the items to be considered in
project programming.
Method
Statement
Preparation
3-5
3.2
3-6
3.2.7
3-7
3.3
Stage 3 Construction
3-8
3-9
Project Name :
Budget Schedule
Item
Description
Quantity
Unit
GENERAL
1.1
Preparation of an Environmental
Management Plan for the project
Item
1.2
Update Environmental
Management Plan
Month
1.3
Week
1.4
Month
1.5
Month
1.6
Month
1.7
Month
1.8
Item
1.9
Item
1.10
Item
1.11
Item
A3-1
Rate
Amount (HK$)
Item
Description
Quantity
Unit
DUST CONTROL
2.1
Item
2.2
2.3
Application of water/dust
suppression chemicals for dust
control
Job
2.4
Item
2.5
Month
2.6
Item
2.7
2.8
Item
3.1
Item
3.2
Job
3.3
Item
3.4
Litre
CHEMICAL WASTE
4.1
Rate
Amount (HK$)
Item
A3-2
Item
Description
Quantity
Unit
4.2
Job
4.3
Job
4.4
Item
4.5
Item
4.6
Item
WASTEWATER CONTROL
5.1
5.2
Unit
5.3
Operation/maintenance of
wastewater treatment system
Month
5.4
Month
5.5
Item
5.6
Item
NOISE CONTROL
6.1
Item
6.2
Month
A3-3
Rate
Amount (HK$)
Item
Description
Quantity
Unit
6.3
Item
6.4
Item
6.5
Item
WASTE MANAGEMENT
7.1
Item
7.2
Item
7.3
Ton
7.4
Job
7.5
Tonne
7.6
Tonne
TREE PROTECTION
8.1
Item
8.2
Tree transplanting
Item
8.3
Tree felling
Item
8.4
Item
8.5
Month
A3-4
Rate
Amount (HK$)
Item
Description
Quantity
Unit
COMMUNITY RELATIONS
9.1
Item
9.2
Item
9.3
Item
9.4
Rate
Sub-total
A3-5
Amount (HK$)
HK$
Considered in
programme
Yes
No
Remarks
GENERAL
AIR
NOISE
A3-6
Item
Considered in
programme
Yes
No
Remarks
WATER QUALITY
WASTE MANAGEMENT
TREE PROTECTION
A3-7
Remarks
Yes
No
Erection of hoarding
GENERAL
AIR
NOISE
A3-8
Planned
Remarks
Yes
No
Provide cut off drainage to prevent surface water leaving the site
WATER QUALITY
WASTE MANAGEMENT
TREE PROTECTION
Establish tree management plan
A3-9
Table of Contents
List of Appendices
Appendix 4.1
4.1
Terminology
Construction Dust
Dusty materials produced as a result of construction
work being carried out. This may include cement,
earth, pulverized fuel ash, aggregates, silt, stone
fines, sand, debris, sawdust and wooden chips.
Notifiable Work
Notifiable Work under the Construction Dust
Regulations includes:
Site formation
Reclamation
Building demolition
Work to be carried out inside a tunnel where it
is within 100m from the portal
Construction of building foundation
Construction of building superstructure
Road construction
Regulatory Work
Regulatory Work under the Construction Dust
Regulations includes, but is not limited to, road
opening or resurfacing, external renovation and
slope stabilization works.
Emergency Work
Emergency Work under the Construction Dust
Regulations is works required in an emergency
situation where human life or building safety is
being threatened. It also includes repair work that is
required as a result of a failure of utility services,
road collapse or road blockage.
Excluded Work
Excluded Work includes, but is not limited to,
internal renovation, a specified process, cleansing
and inspection of underground utilities, and works
to be carried out entirely under water.
4.2
Concrete
Batching
Building
Demolition
ACTIVITIES
GENERATING DUST
Soil
Excavation
Piling
Material
Handling/
Storage
4.3
Site
Clearance
4.3.1
4-1
4.4
I
Identification
of Dust
Impacts
IX
Mitigation Measures
for Dust Control
New
site?
New
construction site
or change of
notifiable
works?
Change?
VIII
Communication
CONSIDERATIONS
DURING THE
PLANNING STAGE
Complete Form
NA enclosed with
site location map
II
Programming of
Works
IV
Site Planning
Complete Form
NB
VII
Training
V
Water Supply
and Storage for
Dust
Suppression
III
Identification of
Dust Mitigation
Facilities
VI
Licence Application for
Specified Process and
Notification of
Commencement of Works
4-2
4-3
the
dust
Exemption
Some construction works are exempted
from certain dust control measures
because of the physical constraint in the
construction site in adopting the required
control measures:
Road construction work
Slope stabilization
4.4.2
Good Housekeeping
A good housekeeping checklist for construction
dust is attached in Appendix 4.1.
Site Boundary, Entrance and Hoarding
Except for road opening or resurfacing work or
construction work carried out in a construction site
that is completely paved or completely covered with
hardcore:
Vehicle washing facilities with high pressure
water jet are to be provided
4-4
Site Clearance
The work area for the uprooting of trees, shrubs,
or vegetation or for the removal of boulders,
poles, pillars or temporary or permanent
structures should be sprayed with water or dust
suppression chemical immediately before,
during and immediately after the operation so
as to maintain the entire surface wet
All demolished items which are likely to
dislodge dust particles when exposed should be
covered entirely by impervious sheeting or
placed in an area sheltered on the top and three
sides
Exposed Surface in Open Areas
Monitor the exposed surface condition and
spray with water or dust suppression chemicals
as necessary
Carry out compaction, turfing, hydroseeding
and vegetation planting as far as practicable to
protect the exposed surface
Do not place stockpiles of dusty materials
outside the construction site/hoarding
4-5
Concrete Production
For production of concrete or any other
substances using bagged cement or dry
pulverised fuel ash, the de-bagging, batching
and mixing processes should be carried out in
an area sheltered on the top and three sides
Storage of 20 or more bags of cement should
be either covered or enclosed in an area
sheltered on the top and the 3 sides
Providing a paved road prevents dust impacts and keeps the site
clean
4-6
4-7
4.4.3
Physical Barriers
Use of physical barriers to reduce dust dispersion:
Erect hoardings to contain the dust within the
site
The height of the hoarding should not be less
than 2.4m
Noise barriers can also serve as a barrier to
reduce dust emission
To increase the effectiveness of the barrier, it
should be placed as close to dust generating
activities as possible, and should shield against
the wind
Source (dust
generating
activity)
Dust enclosure
4-8
Frequency
Dosage
Heavy Traffic
Once every 2 4
weeks
Moderate
Traffic
Once every 2 6
weeks
Light Traffic
Once every 2 8
weeks
Grating
4-9
4-10
4.4.4
Site Examples
Good Practices
Bad Practices
Haul Road
Site Exit
4-11
Good Practices
Bad Practices
Dusty Operation
4-12
4.4.5
Building Works
Debris Chute
Any debris shall be covered entirely by
impervious sheeting or stored in a debris
collection area sheltered on the top and the 3
sides
Where a debris chute discharges into a skip or
container, it should be enclosed with impervious
sheeting or sprayed with water
Before debris is dumped into a debris chute, it
should be sprayed with water
Building Superstructure
Building Demolition
The area demolition work takes place shall be
sprayed with water or a dust suppression chemical
immediately prior to, during and immediately after
the demolition activities. Wet the working area prior
to, during and immediately after demolition.
Skip Hoist
Enclose the skip hoist by impervious sheeting
4-13
Contractual Requirements
Preparation of an Environmental Management Plan
(EMP) for construction projects has become a
common practice for the construction industry as
requested by some clients. The EMP may include
the requirements for construction dust mitigation
and the associated dust monitoring.
Some projects will require baseline
monitoring for consecutive days (normally 14
days) prior to starting the construction works.
1-hour
TSP
Statutory Requirements
Monitoring as specified under an EP for Designated
Projects is usually carried out in accordance with
the approve EM&A Manual. Those guidelines are
used in developing EM&A Programmes under the
EIAO.
24-hour
TSP
Aims to measure the
long term
construction impact
over a longer period
of time during
construction activities
4-14
4-15
No
Access roads
Construction areas
Debris chute
Materials that have the potential to create dust are totally enclosed
10
11
12
13
14
Remark
Material Handling
1
Hoarding of not less than 2.4 m high from ground level is provided along
the building site boundary
16
17
A4-1
No
Remark
Excavation
18
19
20
Any spoil, debris or material and silt are removed and the affected land
and areas are restored to the natural state
22
23
Surface of the areas within the site where there is regular movement of
vehicles are paved and any loose surface material is removed
24
Vehicles within the site are restricted to a maximum speed of 8 kph and
speed limit signage is put up at appropriate locations
25
26
27
28
29
A hard-surfaced road between any washing facility and the public road is
provided
30
31
Vehicles are inspected regularly and well maintained to ensure that they
are operating efficiently and that exhaust emissions are not causing
nuisance
32
Vehicle engines are turned off when they are not in use
33
34
A4-2
No
Remark
Demolition Works
35
Any area in which demolition work takes place is sprayed with water
immediately prior to, during and immediately after the demolition
activities to maintain the entire surface wet
36
37
38
39
41
Areas within 30m from the blasting area shall be wetted with water prior
to blasting
42
A4-3
Table of Contents
List of Figures
Figure 5.1
5.1
5-1
5.2
5.3.1
5.3
Cement Works
Works in which the total silo capacity exceeds 50
tonnes and in which cement is handled or in which
argillaceous and calcareous materials (fine dusty
materials) are used in the production of cement
clinker, and works in which cement clinker is
ground.
Specified Processes
5-2
Bitumen Plant
Mineral Works
Works in which the processing capacity exceeds
5000 tonnes per annum and in which: Metallurgical slag; or
pulverised fuel ash; or
Minerals, other than moulding sand in foundries
or coal at electricity works.
are subjected to any size reduction, grading or
heating by a process giving rise to dust, not being
any works described in any other specified process.
Complete of Form 1
5-3
Application payment
Air pollution control plan (2 copies)
A block plan, drawn to a scale of
1:500 and prepared & endorsed by
an authorized person (i.e. an
architect, engineer or surveyor
whose name for the time being on
the authorized persons' register kept
under section 3 of the Building
Ordinance) (2 copies)
Schematic diagrams of process flow
prepared & endorsed by a qualified
engineer (i.e. a registered
professional engineer in the building
services, gas, chemical, marine or
mechanical engineering disciplines
under the Engineers Registration
Ordinance) (2 copies)
2 copies of Business Registration
Certificate (BRC) and Certificate of
Incorporation (COI) of the applicant
5.4
5-4
5.5.4
Corporate
priority:
To
recognize
energy/emissions management as among the
highest corporate priorities; to establish policies,
programs and practices that make sustained
improvement to air quality on every site.
5-5
Table of Contents
List of Tables
Table 6.1
Permitted Hours of Operation for Percussive Piling (Not involving the use of diesel,
pneumatic and/or steam hammers) .................................................................................. 6-5
Table 6.2
Table 6.3
Sound Pressure Level of Some Commonly Used Quiet Plant 2 ....................................... 6-11
Table 6.4
Sound Power Level of Some Quality Powered Mechanical Equipment (QPME) .............. 6-11
Table 6.5
List of Appendices
Appendix 6.1
Flowchart to Determine the Need of a CNP for the use of PME ...................................... A6-1
Appendix 6.2
Sound Power Levels for Items of Powered Mechanical Equipment (PME) ...................... A6-2
Appendix 6.3
6.1
Terminology
Influencing Factor
Influencing Factor (IF) for classification of Area
Sensitivity Rating (ASR) of an area.
As defined by the Technical Memoranda (TM) of
Noise Control Ordinance (NCO), any industrial area,
major road or area within the boundary of Hong
Kong International Airport shall be considered to be
an IF.
The term major road means a road which has a
heavy and generally continuous flow of vehicular
traffic and, in normal circumstances, means a road
with an annual average daily traffic flow in excess
of 30,000. Where a major road has an unusually
low traffic flow rate (< 300 veh./hr.) at the time of
day under consideration, it shall not be considered
as an IF at that time.
Noise Sensitive Receiver (NSR)
Noise Sensitive Receiver (NSR) means any
domestic premises, hotel, hostel, temporary
housing accommodation, hospital, medical clinic,
educational institution, place of public worship,
library, court of law, performing arts centre etc. Any
other premises or place, not being in the nature of
either industrial or commercial premises, which is
considered by the Authority to have a similar
sensitivity to noise as the premises and places
above shall also be considered to be a Noise
Sensitive Receiver. Any premises or place shall,
however, be considered to be a Noise Sensitive
Receiver only when it is in use for its intended
purpose.
6-1
Designated Areas
Designated Areas are areas that have further
controls imposed under the NCO. They are mostly
the urban areas of Hong Kong SAR and are set out
on plans held by EPD and available to view at
Regional Offices of EPD and at EPDs website. The
Designated Areas have been extended under laws
which will come into effect on 1 January 2009.
6.2
Statutory
and
Requirements
Non-Statutory
6.3
6-2
6.4
to
6.5
6.6
6.6.1
Percussive Piling
6-3
6-4
Permitted hours of
operation on any day
not being a holiday *
CNL-ANL 0 dB(A)
0700 1900
6.6.4
*The Authority may vary the timing (but not the total duration)
of the permitted hours of operation if it considers that such
variation would be justified by the nature or requirements of
any NSR which may be affected or of the percussive piling
under consideration.
No.
If you use a vibratory hammer for piling, it does
not involve the motion of driving a pile by
direct/indirect hammering. So you do not need to
have a Percussive Piling-CNP for the work.
Yes.
The use of excavator mounted breaker for driving
sheet piles will involve percussive hammering
actions and you do need to have a PP-CNP for
the work.
6-5
Special Case
Checklists
Guidelines
Examples
Level (ANL)
On line application of CNP
6.6.6 Special Cases
EPD may consider special cases for acceptance of
a CNP application. The provisions for special cases
are tabulated in Table 6.2.
Table 6.2 Provisions of Special Cases for CNP
Application
Special Case
Quiet working
method or
other special
factors for
PME
Quiet working
method or
other special
factors for
PCW
Descriptions
Use of Quality Powered Mechanical
Equipment (QPME) (see Section 6.8
for details);
Provide sufficient details of
particularly quiet PME or percussive
piling methods, e.g. a sound power
measurement report prepared by a
qualified person; or
Provide special noise mitigation
measures, e.g. enclosure or barrier
CNP may be granted for disposal of
rubble through plastic chutes as it is
considered as a quiet working
method; or
EPD is satisfied that location of the
work is effectively screened by
barriers, acoustic screens, buildings
6-6
Descriptions
Construction
work having
important
social
implications
Designated
geological
difficult areas
(PP-CNP only)
6.7.3
If I have a CNP, but I have not fully utilized
the plant list permitted in the CNP. Can I use
a PME, with a lower sound power level, to
substitute the permitted PME which I have
not used?
6.7
6-7
6.8
Validity Period
of QPME Label
(from the Date
of Issuance)
6 years
5 years
4 years
3 years
2 years
1 year
6-8
6.9
Noise Control
6-9
Excavator-mounted breakers
Excavator-mounted breakers are amongst the
noisiest items of general construction equipment.
To reduce noise from excavator-mounted breakers,
use of a hammer bracket (the bracket is made of
special alloy and the inside of it is lined with sound
insulation material). A noise reduction of up to 10
dB(A) can be provided.
Equipment with Internal Combustion Engines
Equipment with Internal Combustion Engines
include stationary and mobile plant, examples
include:
Stationary Plant: compressors, generators,
concrete pumps and welding sets
Mobile Plant: excavators, bulldozers, loaders
and dump trucks
The nature of the noise emissions relating to this
kind of equipment includes exhaust noise, cooling
system noise and engine noise. Control measures
for these include:
Exhaust Noise
- Install suitably designed exhaust silencers
Cooling System Noise (including noise from
water pumps, belts, pulleys and cooling fans)
- Replace poor fan blade design or damaged
fan blades with an aerodynamic model
- Install a contoured fan shroud or cowl with a
close fan tip-to-shroud clearance
- Remove all obstructions such as bars and
pipes from the inlet airflow
Engine Noise
- Installing a vibration isolator for individual
components to reduce transmission of
engine noise
- Installing specially designed partial or full
acoustic enclosures for individual noise
generating components. Partial or full
enclosures can result in a reduction in the
overall noise level of up to 5 and 10 dB(A)
respectively
- Apply damping material to vibrating panels
It is essential to regularly maintain and service all
mechanical plant and equipment:
6-10
Implement
a
preventive
maintenance
programme to ensure equipment is operating in
good order and not emitting abnormal noise
Make sure stocks of regularly required spare
parts are available
Piling
Typical noise sources for percussive piling include:
Ringing noise (radiated from the surface of the
pile);
Impact noise; and
Exhaust noise (created by the release of
pressurized gases from exhaust ports).
Control measures for piling include:
Use non-percussive piling techniques such as
pre-bore, vibratory hammers or hydraulic
hammer for driving steel piles.
Use resilient packing and dolly
- For percussive piling, the head of the pile
should be protected by a helmet fitted with
resilient packing over the top of the pile and
a dolly which cushions the blow of the
hammer.
Use of a shroud
- Enclose the complete pile and the pile
driver. The shroud should consist of a
robust framework fitted with an acoustically
designed cladding or acoustic panels.
- Alternatively, a flexible acoustic curtain of
appropriate thickness can be suspended to
enclose the whole length of the exposed
pile and pile driver.
Joint Cutter / Stone Saw
Noise mitigation measures that can be fitted to a
joint cutter and stone saw include:
A metal hood to screen the operator from the
machine;
Anti-vibration mounts between the engine/motor
and the support frame; and
A small pad supplied with water (for cooling the
blade) to serve as a viscous damping layer
between pad and blade.
Demolition and Concrete Breaking Works
Noise mitigation measures for demolition and
concrete breaking works include using nonpercussive equipment such as a hydraulic crusher
and quiet plant. The sound pressure level of some
commonly used quiet plant is shown in Table 6.3.
Hydraulic concrete cutter and crushers can
replace
excavator-mounted
percussive
breakers in demolition work resulting in noise
Sound Pressure
Level in dB(A) at 7
m from equipment
89 91
76 81
78 80
Bursting System
70 72
67 69
Pipe Jacking
60 65
60 65
Bulldozer, wheeled
110 114
Excavator, tracked/wheeled
93 114
Loader tracked
106 112
Loader, wheeled
104
Asphalt paver
101 112
95 113
108
Compactor, vibratory
102 109
Crane, mobile
94
Generator
87 102
Bulldozer, tracked
Roller, vibratory
QPME
95 109
Road roller
6-11
Noise Enclosures
An enclosure can be constructed from a variety of
materials and the maximum achievable noise
reductions for some materials are shown in Table
6.4. To achieve desirable results, material with
superficial density/surface mass of at least
2
10kg/m should be used.
In addition to effective materials used, the
enclosure should also be so constructed and
maintained that there is no noise leakage due to
defects (such as gaps, poorly sealed joints).
Max. achievable
noise reduction
dB(A)
Superficial
density (Kg/m2)
Material
Thickness (mm)
Brickwork
113
220
35 40
Compressed
strawboard
50
17
28
Chipboard
18
12
26
Plasterboard
13
12
26
Fibreboard
12
18
Plywood
21
Proprietary
product - Barrier
Composite
25
2.5
6-46*
Proprietary
product - Barrier
Composite
51
4.9
10-49*
Noise Barriers
Noise barriers reduce sound transmission by
breaking the direct path between the noise source
6-12
6-13
Arranging
delivery
of
noisy/bulky
equipment/material to avoid disturbance to
surrounding NSRs and within permitted hours
Providing adequate planning with contingency
to ensure that lengthy operations e.g. concrete
pours, can be completed within the permitted
hours
Avoiding carrying out noisy operation in early
morning. Schedule such operation after 9:00am
as far as practicable
Fabricating units off site to minimise impacts on
site, when practicable
Planning routes for construction vehicles
carefully, to reduce noise to nearby NSRs
Maintain equipment in good condition. Using
lubricant to reduce noise impacts
Monitoring noise on site regularly. If there is an
exceedance, further mitigation measures may
be necessary
Maintaining a good security system especially
at the site entrance to avoid unauthorised entry
of workers in restricted hours
Setting up a restricted hours patrol team to
ensure compliance with the NCO.
Requesting sub-contractors to obtain prior
permission (e.g. through a permit-to-work
system) before carrying out work during
restricted hours
Seek professional advice on noise control
measures
where
SPLT
n
i
=
=
=
Example 1
Addition of sound pressure levels of 2 PMEs;
SPL1 = 90dB and SPL2 = 95dB.
Total Sound Pressure Level
Method 1: by Equation
SPLT
= 10 log10(1090/10 + 1095/10)
= 96.0dB(A)
Instrumentation
Sound level meters need to comply with
International
Electrotechnical
Commission
Publications 651:1979 (Type 1) and 804:1985
(Type 1) (as referred to the GW-TM).
Other
noise
measuring
instrumentation shall be of
professional quality.
Example 2
Addition of sound pressure levels of N identical
PMEs each with SPLi dB(A)
Calibration Requirements
Immediately prior to and following each noise
measurement, the accuracy of the sound level
meter shall be checked using an acoustic calibrator
generating a known sound pressure level at a
known frequency. Measurements may be accepted
as valid only if the calibration levels from before and
after the noise measurement agree to within 1.0 dB.
= 10 log10(N x 10SPL/10)
= SPLi + 10 log10N
6.10
and
analysis
a comparable
Measurement Locations
When carrying out measurements at the
assessment point, the following requirements
should be observed:
For a building, the assessment point should
normally be at a position 1m from the exterior of
the building facade but may be at any other
point considered to be appropriate by EPD
For a place other than a building, the
assessment point shall be at a position 1.2m
above the ground, at a particular point
considered appropriate by Environmental
Protection Department
The construction noise levels shall be
measured in terms of A-weighting equivalent
continuous sound pressure level (Leq)
measured in decibels dB(A)
Measurement Parameters
The measurement parameters for different time
periods are set out below:
A-weighted equivalent sound pressure level over a
30-min, Leq(30min), should be used as the
monitoring parameter for the time period
between 0700-1900 hours on normal weekdays.
For all other time periods, when applicable, Aweighted equivalent sound pressure level over any 5min. period, Leq(5min), should be employed for
Noise Monitoring
6-14
Other Requirements
All noise measurements shall be rounded to the
nearest whole dB(A), with values of 0.5 or more
being rounded upwards.
Noise measurements should be made in
accordance with standard acoustical principles and
practices in relation to weather conditions.
Some projects require baseline monitoring
on consecutive days (normally 14 days)
prior to starting the construction works. It is
advisable to check your Contract, Particular
Specification or Environmental Monitoring &
Audit (EM&A) Manual (if any) to confirm
requirements.
For a Designed Project, baseline monitoring
is normally required. It can be either
arranged by the Employer or through the
Contractor under the contract.
To avoid delaying the commencement of
construction works, baseline monitoring
should be arranged as soon as possible
once the award of the construction contract
is confirmed.
6.11
Case Studies
6-15
Wire
saw
for
concrete
The photo is extracted from EPDs website
cutting
works
6-16
Appendix 6.1: Flowchart to Determine the Need of a CNP for Percussive Piling or the use of
PME/PCW
Construction work planned?
Yes
Do your
construction activities
involve percussive piling?
No
Yes
No
No
Will PME be used in restricted
hours*?
(App. 6.2)
No
Yes
Yes
CNP is required
CNP is required
CNP is required
Complete Form
EPD 75(s)
according to TM1
Complete Form
EPD 74A(s)
according to TM2
Complete Form
EPD 74A(s) and
according to TM3
A6-1
Appendix 6.2: Sound Power Levels for Items of Powered Mechanical Equipment (PME)
Identification Code
CNP 001
CNP 002
Description
100
3
Air compressor, air flow > 10m /min and <= 30m /min
3
102
CNP 003
104
CNP 004
Asphalt paver
109
CNP 021
90
CNP 022
Batching plant
108
CNP 023
108
CNP 024
108
CNP 025
111
CNP 026
114
CNP 027
122
CNP 028
122
CNP 029
105
CNP 030
Bulldozer *
115
CNP 041
Conveyor belt
90
CNP 042
Concrete corer
117
CNP 043
112
CNP 044
109
CNP 045
96
CNP 046
96
CNP 047
109
CNP 048
112
CNP 049
95
CNP 050
Compactor, vibratory
105
CNP 061
Derrick barge
104
CNP 062
118
CNP 063
Dredger, grab
112
CNP 064
103
CNP 065
98
CNP 066
Dumper
106
CNP 067
Dump truck *
117
CNP 081
Excavator/loader, wheeled/tracked
112
CNP 101
Generator, standard
108
CNP 102
100
CNP 103
95
CNP 104
Grader
113
CNP 121
108
CNP 122
95
CNP 123
104
A6-2
Identification Code
Description
CNP 141
Lorry
112
CNP 161
90
CNP 162
105
CNP 163
90
CNP 164
115
CNP 165
115
CNP 166
100
CNP 167
114
CNP 168
100
CNP 169
108
CNP 170
113
CNP 171
117
CNP 181
128
CNP 182
123
CNP 183
116
CNP 184
111
CNP 185
Road roller
108
CNP 186
Roller, vibratory
108
CNP 201
108
CNP 202
114
CNP 203
115
CNP 204
Scraper
119
CNP 221
Tug boat
110
CNP 222
Tractor
118
CNP 241
Ventilation fan
108
CNP 261
Winch (pneumatic)
110
CNP 262
Winch (electric)
95
CNP 263
Winch (petrol)
102
CNP 281
88
CNP 282
103
CNP 283
85
Classified as Specified Powered Mechanical Equipment (SPME). A more stringent Basic Noise Level is applied to the
different Area Sensitivity Rating for the use of SPME at the construction site in Designated Areas.
A6-3
Description
CNP 005
Agitator (electric)
90
CNP 006
95
CNP 031
115
CNP 051
Concrete burster
90
CNP 052
94
CNP 053
97
CNP 054
109
CNP 055
103
CNP 056
112
CNP 070
Dredger, suction
103
CNP 071
89
CNP072
110
CNP 082
94
CNP 105
Grout mixer
90
CNP 106
Grout pump
105
CNP 107
Generator, portable
100
CNP 131
99
CNP 172
115
CNP 173
102
CNP 174
100
CNP 175
Power swivel
100
CNP 176
87
CNP 177
104
CNP 187
108
CNP 188
Road sweeper
107
CNP 189
97
CNP 190
105
CNP 205
Saw, wire
101
CNP 206
Soil pump
103
CNP 284
94
CNP 285
107
CNP 141
112
CNP 142
105
CNP 143
101
CNP 144
112
CNP 145
Lorry, with crane/grab, 5.5 tonne < gross vehicle weight <
38 tonne
105
CNP 067
117
CNP 068
Dump truck, 5.5 tonne < gross vehicle weight < 38 tonne
105
CNP 069
Dump truck, with grab, 5.5 tonne < gross vehicle weight <
38 tonne
105
A6-4
0 0.5
1.0 1.5
2.0 3.0
3.5 4.5
5.0 7.0
7.5 12.0
> 12.0
3.0
2.5
2.0
1.5
1.0
0.5
0
Table A6.3.2 Correction Factors to Obtain the PNL from Sound Power Level at Given Distances
Distance
(m)
Correction
(dB(A))
Distance
(m)
Correction
(dB(A))
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15 16
17 18
19 21
22 23
24 26
27 29
8
8
14
18
20
22
24
25
26
27
28
29
30
30
31
32
33
34
35
36
37
30 33
34 37
38 41
42 47
48 52
53 59
60 66
67 74
75 83
84 93
94 105
106 118
119 132
133 148
149 166
167 187
188 210
211 235
236 264
265 300
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
This table is valid for distances of up to 300m. For distances greater than 300m, the EPD shall calculate appropriate
correction factors having regard to standard acoustical principles and practices.
A6-5
Table of Contents
List of Tables
Table 7.1
Pollutant Load of Wastewater from Different Types of Construction Works ....................... 7-8
Table 7.2
Table 7.3
List of Figures
Figure 7.1
Figure 7.2
Figure 7.3
Figure 7.4
Figure 7.5
Figure 7.6
List of Appendix
Appendix 7.1
7.1
Terminology
7.2
Sewage/Foul Water
It is the subset of wastewater that is contaminated
with feces or urine, but is often used to mean any
waste water. "Sewage" includes domestic,
municipal, or industrial liquid waste products
disposed of, usually via a pipe or sewer or similar
structure.
Suspended Solids
Suspended solids (SS) is an indicator on how many
unsettled particulates are the in water, which also
affects the transparency of water. The major
source of SS on a construction site is silt. The
7-1
Construction Site
Wastewater
Surface
Runoff
Main source
is from
Rainwater
which falls
onto the
site area
which runs
off the site
or needs to
be pumped
General
Nature:
silty water
pH (neutral
to alkaline)
Sewage
Effluent
Mainly
generated
from
Toilet
waste
Canteen
Effluent
General
Nature:
cloudy
water
Moderate
level of
organic
matter
(e.g.
BOD5
and
COD)
High level
of E.Coli
May
contain
O&G
7.3.2
7.3
Wastewater Management
Minimisation
of
Generation
of
Wastewater
Water consumption on site should be monitored to
minimise wastewater generation. This can be
achieved by installing water meters to monitor and
control usage.
To identify opportunities to minimize water
consumption, the following flowchart can be used.
7-2
Pipework receiving
rainwater from
cascade channel
Pumping
System
Rainwater Discharge
The temporary site drainage system including
perimeter channels, catchpits and pumping system
should be provided on site to divert contaminated
rainwater to wastewater treatment facilities for
treatment prior to discharge.
If heavy rainfall results in large quantities of
wastewater being produced at a
construction site, would the contaminated
water need to be treated before discharge?
Yes, all contaminated runoff is required to be treated
before discharge to meet the statutory requirements.
The Contractor should take all necessary preventive
measures, to avoid the contamination of surface runoff
e.g. covering stockpiles of materials with sheeting.
7.4
Construction
site
wastewater
is
mainly
contaminated by interaction with soil and resulting
in high level of suspended solids and alkalinity.
Wastewater treatment systems deployed on site
are often required to remove suspended solids and
to neutralize alkaline water.
7.4.1
7-3
Influent
Neutralization Tank
Effluent
7-4
Chamber
1
Sludge
Zone
Chamber
2
Sludge
Zone
Chamber
3
Sludge Zone
7-5
Clarified
Liquid
Influent
Settled solids
discharged
from tube
7.4.6 Neutralization
The permitted range of effluent pH value (usually
from 6 to 9) is stipulated in the Discharge Licence.
On a construction site, wastewater is usually
alkaline due to contamination with cement from
concrete and grout. Therefore neutralization with an
acid is required using a pH neutralization tank.
7.4.7
pH Neutralization Tank
7-6
7.5
Determine temporary
Drainage Layout
Site logistics
The temporary site drainage should be arranged
through the entire site area such that all the
wastewater can be collected and delivered to
treatment facilities.
Determine Pollutant
Load
7-7
Foundation
Building
SS content
Silty
Muddy
Silty
pH
Neutral to
Alkaline
Alkaline
Alkaline
7-8
7.6
Trade Effluent
(including
contaminated
surface runoff)
Discharge to
Foul Sewer or
Storm Drain or
Watercourses
after
appropriate
treatment
Sewage Effluent
Discharge to
Storm Drain or
Watercourses
after
appropriate
treatment
Discharge to
Foul Sewer
No Need to
Apply for a
Effluent
Discharge
Licence
7-9
not
no
not
be
7-10
Important Reminders
7.7
7-11
7.8
Site Examples
Good Practices
Bad Practices
Temporary Drainage
Site Exit
7-12
Good Practices
Bad Practices
Construction Site Runoff
7-13
7.9
There are many types of packaged wastewater treatment systems available from the market to treat
construction site wastewater. The use of commercial wastewater treatment plants is recommended for their
higher treatment efficiency and relatively compact size.
Their treatment principles and relevant
characteristics are shown in Figure 7.6 and summarized in Table 7.2 respectively.
Figure 7.6 Commercial Wastewater Treatment Plant
Influent
Coagulation
+
Flocculation
(by either a reaction tank
with mechanical mixer or a
static mixer)
Coagulant:
Polyaluminium
Chloride
Flocculant:
Polyacrylamide
Sedimentation
(with either tube or plate
settler module)
Sludge
Acid:
H2SO4 (Sulphuric
Acid) or Citric Acid
Neutralization
(Optional)
Effluent
Table 7.2
Treatment
[m3/hr]
10
20
40
80
120
Maximum
Suspended
[mg/L]
< 20,000
7-14
Influent
Solids
<1
Table 7.3
Construction Activities
Suspended Solids
Concentration
Conclusion*
Building
(Site B1)
Influent: 1284mg/L,
Effluent: 10 mg/L
Building
(Site B3)
Civil Engineering
(Site C1)
Influent:
12590
mg/L,
Effluent: 4 mg/L
* The discharge standard for the suspended solids of the sites was 30 mg/L.
7-15
Table 7.3
Construction Activities
Suspended Solids
Concentration
Conclusion*
Civil Engineering
(Site C2)
After
2nd
219mg/L,
tank:
After
3rd
207mg/L,
After
4th
149mg/L
tank:
Coagulant
dosing
7.5L/min
(proprietary chemical so the dosage
and concentration did not know)
Civil Engineering
(Site C3)
Civil Engineering
(Site C4)
7.5L/min with
tank:
* The discharge standard for the suspended solids of the sites was 30 mg/L.
7-16
Yes
No
10
11
12
(No
13
14
15
16
17
18
19
Sand and silt in the wheel washing bay are removed regularly
20
Remark
A7-1
Implemented?
Construction Site Runoff
Yes
No
21
22
23
24
25
26
27
Chemical toilets are provided in the case that connection to the existing
foul sewer main is not possible
28
29
30
Treated wash water is reused for non potable use, where possible, like
dust emission control and vehicle washing.
31
32
Sewage from toilets and similar facilities is discharged into a foul sewer
if connection to foul sewer can be made
33
34
35
Vehicle and plant servicing areas and lubrication areas are located
within roofed area as far as possible
36
37
38
39
40
41
42
43
A7-2
Remark
Table of Contents
List of Tables
Table 8.1
Table 8.2
List of Appendices
Appendix 8.1
Appendix 8.2
Waste Management
8.1
Terminology
Vegetation;
Packaging Waste; and
Other Organic Materials.
C&D Waste
C&D waste which means any substance, matter or
thing that is generated from construction work and
abandoned, whether or not it has been processed
or stockpiled before being abandoned, but does not
include any sludge, screenings or matter removed
in or generated from any desludging, desilting or
dredging works. And it is those materials not
suitable for reclamation. Subject to recovery of
reusable or recyclable items, C&D waste is
disposed of at landfills. The following substances
are example of C&D waste:
Bamboo;
Timber;
Generally inert C&D material from demolition works
8-1
Landfills
Landfills refer to the strategic landfill sites managed
by EPD. At present, three strategic landfills are in
operation:
West New Territories (WENT) Landfill;
South East New Territories (SENT) Landfill; and
North East New Territories (NENT) Landfill.
C&D waste disposed of at landfills should contain
not more than 50% by weight of inert C&D
materials.
In
accordance
to
Waste
Disposal
(Designated
Waste
Disposal
Facility)
Regulation (Chapter 354L), the following
Criteria should be adopted.
For a load of construction waste not consisting
entirely of bamboo, plywood or timber delivered
by a vehicle:Inert Waste Content 50%.
For goods vehicles with demountable skips:
Weight Ratio 0.25
The depth of the waste loaded >1 meter
For other types of vehicles:
8-2
Weight
Ratio
>1.0 metre
1.0 metre
Any Ratio
0.25
Vehicle Type
Vehicles with
demountable
skips
> 0.25
Any Ratio
0.20
> 0.20
Waste
Disposal
Facilities
Landfills
Landfills
Sorting
Facilities
Landfills
Landfills
Sorting
Facilities
Sorted Construction
Waste
100% Inert
Construction Waste
Public Fill
Reception Facilities
Mixed Construction
Wastes
Sorting Facilities
8.3
Construction
Waste
Charging Scheme
Disposal
Landfills
Inert Waste
Content <=50%
Weight Ratio =
Weight of in-weighbridge Tare weight of vehicle
8.2
Statutory
and
Requirements
Photocopy of
HKID or BR
Certificate
Photocopy of
Proof of
company
address
Photocopy of
construction
work contract
Case 1
Case 2
Non-Statutory
8-3
8.3.3 Payment
EPD will issue a monthly demand note and
waste transaction information to the accountholder
The account-holder pays charges within 45
days from the date of demand note. The
charges may be paid by post, in person,
through phone payment service (PPS) or
internet
If the charges are not paid by due date, the
account-holder shall pay a surcharge of 5%
of the unpaid amount.
Prepare
C&D
materials
disposal
schedule for the whole construction
period.
Update the disposal schedule at least
half-yearly.
Keep CHIT stock for sufficient use for
the coming 2 months.
Replenish CHIT as and when required.
8.3.4
8-4
Change/Closure/Reinstatement of an
Account
Prescribed Form 5 should be used for
notification of changes in Account information.
Prescribed Form 6 should be used for
application for closure or reinstatement of an
Account.
8.4
8-5
8.5
Government
Waste
Facilities for C&D Material
Disposal
Type of construction
waste accepted
Charge
per
#
tonne
Consisting entirely of
inert construction
$27
waste++
Sorting facilities
Containing more
than 50% by weight
of inert construction
waste++
$100
$125
Containing any
percentage of
inert construction
++
waste
$125
Landfills
Outlying Islands
Transfer Facilities@
8.6
8.6.1 Planning
The options for waste management are listed in
preferred order:
1 Avoidance;
2 Minimization;
3 Recycling;
4 Treatment; and
5 Disposal.
Proper planning for waste reduction should be
carried out before site operations commence. It can
be achieved by:
Preparing a waste management plan as part of
the overall Environmental Management Plan
Setting out waste reduction targets and
programmes
Arranging on-site sorting and proper waste
disposal
Setting up a good housekeeping practice
Setting up a waste management monitoring and
audit programme
Non-inert C&D
Material
Inert C&D
Material
8.5.2
Waste Management
8-6
8-7
Concrete
Recycling
for
use
as
aggregate in new concrete.
Recycling
for
use
as
unbounded aggregate in roads
or fill.
The specification facilitating
the
use
of
recycled
aggregates can be found in
WBTC 12/2002 and ETWB
TCW 24/2004.
Excavation Spoil
Topsoil
Timber
Metals
Reuse.
Recycle.
Reuse.
Packaging and
Plastics
Reuse
and
encouraged.
8-8
Recycling
should
be
Video Shows
Some videos showing low waste construction
design and technologies can be viewed at EPDs
website.
8-9
8.7.4
8-10
8.8
Case Studies
Metal Mold
Reinforcing steel
8-11
8.9.1
Timber
8.9
Terminology
8-12
8.9.2
8-1
8.9.3
8.9.4
Application Procedures
Document:
Covering letter
Completed application form with authorized
signature and company chop
Copy of a valid Business Registration
Certificate (BRC) of the permit applicant
Dredging plan(s) & layout plan(s) with
coordinate
explicitly
showing
the
dredging/excavation areas and the depth of
dredging/excavation
Sectional drawings showing the interface
between sediment layers requiring different
Type of disposal
Documents certifying the award of Contract
(from the Waste Producer/ Client to the Main
Contractor, and from the Main Contractor to
the Dumping Operator if applicable)
Method statement for the dumping operation
Documents certifying that you are the waste
producer
Sediment quality report on the proposed
dredging excavation areas
Allocation of mud disposal capacity endorsed
by Marine Fill Committee (MFC) of the Civil
Engineering and Development Department or
EPD
Letter from Resident Engineer stating that will
provide Independent Supervision to ensure
the dumping is carried out in an
environmentally acceptable manner
Name and License number of vessels to be
employed for dumping operation
Name and BRC copy of Main Contractor/
Dumping Operation
Crossed cheque made payable to The
Government of the Hong Kong Special
Administrative
Region
containing
the
application fee
Copy of the up-to-date dumping returns of the
project.
8-1
Preferred storage
Under
cover
Secure
area
Special Requirements
On
pallets
Banded
Concrete pavers
Wood
Metals
Cladding
Paints
Bituminous felts
Insulating material
Ceramic tiles
Glass fibre
Ironmongery
Oils
Kerbstones
Clay & slate tiles
Topsoil, subsoil
Reinforcement
Steelwork
Note:
The manufacturers instructions/recommendations for handling and storage of materials should be followed in conjunction with
the above recommendations.
A8-1
Implemented?
General (Non Construction)
Yes
No
All vehicles carrying waste are properly fitted with side and tail
boards, and with tarpaulin covered
Remarks
General (Construction)
9
10
11
Chemical waste
Packaging waste
General waste
12
13
14
15
16
17
18
19
A8-2
Implemented?
General (Construction)
Yes
No
20
21
A8-3
Remarks
Table of Contents
List of Figures
Figure 9.1
Figure 9.2
Figure 9.3
Figure 9.4
Figure 9.5
Figure 9.6
Figure 9.7
Figure 9.8
List of Appendices
Appendix 9.1
9.1
Terminology
Fire hazard.
Chemical Waste
Any substance or thing being scrap material,
effluent or an unwanted substance or by-product
which:
Contains any substance or chemical specified
in Schedule 1 of the Waste Disposal (Chemical
Waste) (General) Regulation and
Causes pollution or constitute a danger to
health or risk of pollution to the environment
9.2
Storage
Storage
Collection
T ransportation
Disposal
Packaging and Labelling
Monitor &
Control
Collection
Monitor &
Control
Transportation
Monitor &
Control
Disposal/Treatment
9-1
9.3
9.4
9.5
Application of Licence /
Registration
9-2
Waste
producer
to
identify nature of waste.
Review processes and
carry out laboratory test if
necessary.
NO
Does the waste
contain any
chemical listed in
Schedule 1
(Appendix A)
YES
Is the waste o
Chemical Waste
For complete listing of
Streams
No
Appendix
A&
(Appendix
B) B, please
refer to the EPD Guide.
NO
Although Appendix B
does not include a list
for construction
activities, registration is
usually required.
YES
9-3
Not subject
to
Registration
No
SUBJECT TO
REGISTRATION
REQUIREMENT
Seek advice
from EPD
If waste includes
any substance(s)
(i.e. Asbestos)
listed in Part A of
the Schedule,
Notification to EPD
is also required
9.6
If chemical waste
is reprocessed /
treated / recycled
on site, including
any on-site
treatment before
discharge, a Waste
Disposal Licence is
required
If chemical waste
containers sized
more than 450 L are
used for on-site
storage, approval is
required from EPD
Complete
EPD 132
for Notification
to EPD at least
10 working
days before
any intended
waste disposal
operation
Complete EPD
126 for Waste
Collection
Licence
Complete EPD
127 or On-line
Application for
Waste Disposal
Licence
Complete
Application for
Approval to use
Chemical Waste
Container(s)
Exceeding 450
Litres
9-4
9-5
Waste Collector
keeps trip-ticket
during transportation
Waste Producer
retains 1 copy
Waste
Producer to
produce copies
on request
Waste
Collector
retains 1
copy
Records of
trip-tickets in
computer or
other format
accepted by
EPD
(EPD may
check records)
Disposal
Point
Manager
retains
original
9.6.6 Packaging
Chemical waste should be packed and held in
containers of suitable design and construction so as
to:
Prevent leakage
Prevent spillage or escape of contents under
normal conditions of handling, storage and
transport
The recommended types of containers are listed as
below:
The use of any container with a capacity
exceeding 450 litres is subject to the approval
of the EPD.
9-6
9-7
Securely Closed
XXX
yyyyyy
Chemical
Waste
Container
No Mixing of Incompatible
Waste
9.6.7 Labelling
Every container of chemical waste should be
labelled clearly, in both Chinese and English
The waste producer should ensure that the
information contained on the label is accurate
and sufficient so as to enable proper and safe
handling, storage and transport of the chemical
waste
The label should be securely attached to a
suitable part of the container (to the sides of
9-8
CHEMICAL WASTE
Chemical name/Common name
Symbol
Particular Risks
Safety Precautions
Title of Label
Not be less than 1/20th of the area of the label. For
small-size labels, the minimal size of the characters
should be around 5mm high.
Symbol
Not be less than 1/10th of the label 2area
No case shall be less than 500mm
Minimum dimension should be 25mm 25mm
Chemical Name
Waste types and codes for different chemical
wastes can be found in EPDs A Guide to the
Registration of Chemical Waste Producers. Waste
9-9
< 50 litres
90mm 100mm
50 450 litres
120mm 150mm
180mm 200mm
9.6.8 Storage
The chemical waste producer should provide a
suitable area for temporary storage of chemical
waste. The illustrations are shown in Figure 9.8.
The storage area should be used for chemical
waste storage only. It is strictly forbidden to
store chemical waste with either chemicals or
dangerous good substances in the same
storage facility.
The storage area should be located close to the
source of waste generation.
The storage area should be enclosed on at
least three sides by a wall, partition or fence
with a height of not less than two metres or at
least the total height of containers in the stack.
Suitable materials for enclosures:
- Concrete
- Brick
- Steel with protective coating or treatment
Enclosures should be rigidly erected and fixed
to the area.
Adequate space should be allowed within the
storage area for container handling by workers
Storage of
incompatible wastes
in different areas
Impermeable floor
made of suitable
materials to withstand
normal abrasion and
chemical action of the
stored chemical waste
9-10
9.7
Drip tray to
contain leakage
Vent
Holes
Storage of
incompatible waste
in separate areas
Storage shelves should be fitted with a leakproof tray or spill catcher trays in its base to
retain the capacity of the largest container or
20% of the total storage capacity in that shelf,
whichever is greater, so that chemical waste
can be retained within the trays if spillage
occurs, without overflowing to other shelves or
outside the shelves.
Storage shelves should be strong enough to
carry the full weight of the filled containers
being stored.
Ventilation holes of at least 30mm diameter
located at the top and bottom of the side panels
of the cupboard.
9-11
9-12
Implemented
Yes
No
Chinese Characters
Appropriate symbol
The storage area is kept dry and clean and is used for storage of
chemical waste only
For liquid waste, about 100mm air space is allowed between top
of container and level of liquid contents
10
11
12
A9-1
Remarks
Implemented
Yes
No
13
The location for waste storage is labelled clearly and away from
any potential hazard e.g. heat generating activities
14
15
16
17
18
19
20
Disposal records i.e. trip tickets for chemical waste are retained
21
22
23
24
ii
Remarks
Table of Contents
10
General.......................................................................................................................... 10-1
Terminology ................................................................................................................... 10-1
Land Contamination Caused by Construction Activities .................................................. 10-1
Land Uses with Potential to Have Land Contamination ................................................... 10-1
Contamination Assessment Process .............................................................................. 10-2
Soil Contamination Treatment Technology ..................................................................... 10-3
List of Figures
Figure 10.1
10 Land Contamination
10.1
General
This
section
explains
the
contamination
assessment process adopted in Hong Kong and
describes commonly available contamination
treatment technology.
10.2
Terminology
10.3
by
may
10-1
and
and
10.4
Contaminated Land
Contaminated land refers to land which has been
polluted by hazardous substances as a result of
industrial or commercial operations carried out on
and around the site over a number of years. Very
often, these contaminants pose hazardous risks or
may cause detrimental effects to the land users or
the nearby environment.
fuel,
10.5
Plan and
design site
investigation
Prepare CAR
Site concentration
above RBRGs?
Submit
CAR to
EPD for
approval
Yes
Contaminated Land.
Conduct site
investigation
No
Obtain
endorsement of
CAP from EPD
Assessment process
Implement RAP
After remediation, submit
Remediation Report to
EPD for endorsement
10-2
10.5.2 Contamination
Assessment
Report
(CAR)
The CAR should be submitted to EPD after land
contamination investigation is completed.
The content of the CAR should include:
Procedure of land contamination investigation
Field results
Laboratory results
Interpretation of results
Plans showing contaminant distribution
10.5.3 Remediation Action Plan (RAP)
If the CAR shows that contamination is above an
acceptable level as defined in RBRGs, a RAP
should be devised. The RAP should be submitted
to EPD after site investigation is completed, but
prior to commencement of site remediation. It is to
be submitted together with the CAR if remediation
is required.
The content of the RAP should include:
Background information from CAR
10.6
Soil
Contamination
Technology
Treatment
10-3
10.6.4 Solidification/Stabilization
Solidification/Stabilization is an in-situ or ex-situ
immobilization technique that treats contaminated
soil by mixing soil with binding agents, e.g. cement
so that the contaminants become to chemically and
physically bound within a stable mass.
Solidification/stabilization has been used on certain
contaminated sites in Hong Kong and is
demonstrated as a successful treatment method for
inorganic contaminated soil, e.g. decontamination
works at the Cheoy Lee Shipyard at Pennys Bay,
reclamation works at North Tsing Yi Shipyard site
and a few isolated sites identified in the Deep Bay
Link project.
In-situ Method
Application and Environmental Benefits
Applicable to clean-up inorganic contaminants
(including radionuclides).
Timeframe is short to medium-term.
Limitations and Environmental Downsides
Depth of contaminants may limit some types of
application processes.
Future usage of may weather the materials
and affect ability to maintain immobilization of
contaminants.
No/Limited effectiveness against VOCs, SVOCs
and pesticides depends on type of methods
employed.
Increase in volume of material following
treatment.
Certain wastes are incompatible with variations
of the processes.
Treatability studies are generally required.
Reagent delivery, effective mixing and
confirmatory sampling are more difficult than
ex-situ application.
Solidified material may hinder future site use.
10-4
Ex-situ Method
Application and Environmental Benefits
Applicable to clean-up inorganic contaminants
such as heavy metals.
Limitations and Environmental Downsides
The effectiveness reduces with the presence of
organic contaminants.
Large boulders may hinder the mixing process.
Soil sorting is necessary before the treatment
taken place.
Increase in volume of material following
treatment.
10.6.5 Soil Washing
Soil Washing is an ex-situ soil separation
processes mostly based on mineral processing
techniques. It is a water-based process for
scrubbing soils ex-situ to remove contaminants.
Application and Environmental Benefits
Applicable to clean inorganic contaminants
such as heavy metals from coarse-grained soils.
Limitations and Environmental Dis-benefits
The effectiveness of the treatment depends on
soil particle size. Fine soil particles may require
the addition of a polymer to remove them from
the washing fluid.
Complex waste mixtures make formulating
washing fluid difficult.
Requires further treatment and disposal for
residuals.
10.6.6 Excavation and Landfill Disposal
Excavation and landfill disposal is an ex-situ
method whereby contaminants are removed by
excavation of the contaminated soil and direct
disposal to landfill.
Application and Environmental Benefits
Most simple and quickest way to dispose of
contaminated soil.
Wide experience in Hong Kong.
Applicable to all waste or mixture that meet
landfill disposal criteria.
10-5
Table of Contents
11
11.2
Terminology
Tree Management
11.2.2 Hierarchy
for
Tree
Management
Consideration
No tree should be unnecessarily felled or pruned.
The following order of priority should be adopted for
tree management considerations:
(a) Retain the trees at their existing locations with
protection;
(b) If (a) is not possible, transplant the affected
trees to other permanent locations within the
site, so as to increase the trees survival rate
after transplantation and minimize the loss of
greenery on the local environs. This should be
considered as far as possible unless the trees
affected are of low conservation and amenity
value, or have a low chance of surviving or
recovering to its normal form after transplanting;
(c) If both (a) and (b) are not possible, transplant
the trees to a permanent location off site.
Location of receptor site should preferably be
within the same area for retention of amenity
11-1
11-2
Private Projects
The control procedures for tree felling or
transplanting for private projects are detailed in
Lands Department Practice Note 7/2007 and
extracted as below:
The lot owners or their Authorized Person (AP)
shall submit an application to DLO under the
tree preservation clause of the lease.
The application should contain a conceptual
proposal comprising the tree survey submission,
the tree removal proposal together with
justifications for tree felling, transplanting, tree
preservation/protection measures and a
conceptual compensatory planting proposal and
a detailed compensatory planting proposal.
To ensure compliance with the tree
preservation clause, the pre-sale consent will
not be given unless and until approval to all
aspects of the tree removal including any
required compensatory planting proposal of the
application has been obtained.
11.2.5 Penalty for Illegal Tree Felling
Illegal tree felling is liable for prosecution and fine.
For trees on unleased Government land, they are
protected under the Forests and Countryside
Ordinance. Under the Ordinance, any person who
fells any trees on unleased Government land is
punishable by a fine up to $25,000 and
imprisonment up to one year.
For trees on leased Government land, felling of
trees not in accordance with the tree preservation
clause of the lease is punishable by a fine. The
amount of fine may be as high as few ten
thousands dollars per tree.
11.3
Slipper orchids ()
Birdwing Butterfly ()
Orchids ()
11-3
Azaleas ()
Pitcher-plants ()
11.4
11-4
Table of Contents
12
12 Resources Management
12.1
Rationales
Management
for
Resources
12.2
Measures
Management
for
Resources
12-1
lighting
and
12.2.3 Water
Use rainwater harvesting systems to capture
freshwater for site use. More detail can be found in
Section 7.4.4 of this Guide.
Install flow restrictors and automatic shut-off
systems and other water flow devices to faucets.
This will ensure that water use is reduced at all
times.
Encourage staff to always completely turn off all
faucets and report any possible leaks. Post
reminder signs to tell people to turn off faucets and
indicate the number to call to report leaky faucets.
Establish a monitoring and repair programme to
ensure that pipes are in good working order and
that leaks and other problems are repaired as soon
as they are detected.
Reuse treated wastewater whenever practicable
(e.g. for dust suppression).
12.2.4 Paper
Use double-sided photocopying and printing.
Encourage the use of E-mail for both internal and
external communication, or if this is not possible
circulate material rather than making copies for
individuals.
Avoid photocopying
required.
faxed
documents
unless
12-2
Table of Contents
13
List of Figures
Figure 13.1
13-1
N
O
P
Q
Community Facilities
Tourist and Recreational Developments
Residential and Other Developments
Miscellaneous
2.
13-2
13.1.5 Responsibility
of
Contractors
in
Environmental Complaint Investigation
When an environmental complaint is received, it
should be referred to ET for coordination. The
validity of the complaint should be investigated by
ET in consultation with IEC. If the complaint is
justified to be due to the execution of the
construction work, the Contractor is responsible to
propose and implement mitigation measures to
alleviate the situation. The performance of the
mitigation measures will be reviewed by ET and
additional mitigation measures may be required by
ET if necessary.
13.2
Implication to Contractor
13-3
13-4
Table of Contents
14
List of Tables
Table 14.1
Table 14.2
Table 14.3
List of Figures
Figure 14.1
Figure 14.2
Relationship amongst Environmental Aspect, Impact and Objective and Target ............. 14-2
Management
Review
Environmental
Policy
Checking /
Corrective Action
Continual
Improvement
Planning
- Environmental Aspects
- Legal & Other Requirement
- Objectives & Targets
- Environmental Management
Program
Implementation
- Structure and Responsibility
- Training, Awareness Competence
- Communication
- EMS Documentation
- Document Control
- Operational Control
- Emergency Preparedness / Response
14.2
Environmental Policy
14-1
Figure 14.2
Relationship between Environmental Aspect,
Impact and Objective and Target
Identify Aspect
Evaluate Significance
Periodic
Review
No
Significant?
Yes
Manageable?
Keep Record
No
Yes
Mitigation and/or
Operating Control
environmental
education
Work
towards
the
achievement
sustainable development.
14.3
Measure / Monitor
Follow-up
Complies?
and
Yes
No
of
Take corrective
action
Raise nonconformance
Planning Stage
14-2
14-3
Environmental Impacts
Pollution of air
Respiratory impacts on
local residents
Odour nuisance
Consumption
water
of
fresh
Use
of
powered
mechanical equipment
Construction
impacts
on
residents
Generation
construction wastes
of
noise
local
Targets
Improve employee
awareness of
environmental issues
14.4
Implementation Stage
14.3.5 Development
of
Environmental
Management Programme
Environmental management programme is an
action plan that it translates the organizations goals
and policy commitments into concrete actions so
that environmental objectives and targets are
achieved. An individual programme should be
developed for each target.
The programme should include the following
elements:
Why That is the specific target to be achieved
in the programme
What A list of detailed actions to be done in
order to achieve the target
Who the responsible person for each specific
action
When the time frame and schedule for
completing each specific action
14-4
Sample Environmental
Responsibilities
Typical Person(s)
Responsible
Chairman, Managing
Director, Board of
Directors
Develop environmental
policy
Chairman, Managing
Director, Environmental
Director/Manager
Develop environmental
objectives, targets and
programmes
Managers of a project or
department
Environmental
Director/Manager
Assure regulatory
compliance
Ensure continual
improvement
All Managers
Quantity Surveyor,
Finance/Accounting
Managers
All Staff
14.4.2 Training
An analysis of training needs should be undertaken
to determine the appropriate training for each grade
of staff. The training provided to staff should be
relevant to the achievement of environmental
policies; objectives and targets; and management
programme. Employees should be trained to have
knowledge on proper procedures to perform their
tasks
and
understand
the
environmental
consequence if such procedures are deviated.
14.4.3 Communication
Communication channels should be established to:
Demonstrate management commitment to
implement environmental protection on site.
Deal with concerns and questions about the
environmental aspects of the organisation
activities, products or services.
Raise the environmental awareness of the staff
on the organisations environmental policies,
objectives, targets and programmes.
Inform internal or external interested parties
about
the
organisations
environmental
management system and performance as
appropriate.
This could be done by:
Displaying the companys environmental policy,
objectives, targets and programme to the public;
Displaying contact details of nominated
correspondents (include name of person,
address, telephone number and fax number);
Regular internal environmental meeting to
review environmental performance;
Meeting
with
interested
parties
and
stakeholders to seek their environmental
concerns; and
Distribution of companys environmental report
addressing the work done with respect to
environmental protection.
14.4.4 EMS Documentation and Control
Operational processes and procedures should be
defined and appropriately documented and updated
as necessary. The organisation should clearly
define the various types of documents to establish
and specify effective operational procedures and
control.
site
specific
Environmental
14.4.6 Emergency
Preparedness
and
Response
The Contractor should carry out the following tasks:
Identify the possibilities for accidents and
emergency situations.
Develop
emergency
preparedness
and
response procedures.
Evaluate, revise and test the procedures.
14-5
14.5
Checking Stage
14-6
14.6
Management Review
14.7
14-7
Table of Contents
15
15.1
15-1
15.2
15.3.4 Water
Pollution
Control
Training
Materials
Train-the trainer Package for Water and Waste
15.3
Handbook
EPD Guidelines
Pollution Control
Green
Construction
Management
and
References
Video
on
on
Air
Dust
15-2
Table of Contents
16
16
16.1
16-1
Principles
Air from electric blower
Air is forced into the
water filled container
Reused plastic
bottles
Reused plastic from
the safety helmet
Mobile Sprinkler
Schematic Design of Dust Suppressor
Dust Suppressor
16.2
16-2
Door Closer
Installing a door closer to keep the door closed at
all times reduces the unnecessary loading on the
air conditioner compressor and reduces the power
consumption.
Timer Control
Installing a timer to control the site office containers
main electrical power supply. As a result, the main
power will be switched on/off automatically on a
daily basis or as required.
Window Blind
Installing window blind so that direct sunlight cannot
enter the office container.
It can reduce
consumption of energy for air conditioning.
16.3
Green Cladding
Container Colour
Painting the container with a coat of white paint give
power consumption reduction in air-conditioning
demands.
Roof
Constructing a roof to shade the container from
direct sunlight and to create an insulation layer of
air in the roof void above the office container ceiling.
16-3
Felling
Cutting
and
Composting
Sorting
Watered Daily
Stirred Daily
During site clearance, hay and grass clippings byproducts can be used to composting into valuable
fertilizer to minimizing waste to disposal to landfill.
16-4
Batteries
Fluid
(32% of
Sulphuric Acid)
Batteries
Fluid
pH
Regulator
(44% of
(66% of
Sulphuric Acid) Sulphuric Acid)
Conc.
Sulphuric
Acid
1L
2L
3L
0.301
0.603
0.904
0.444
0.887
1.331
0.753
1.505
2.258
1.354
2.707
4.061
4L
5L
1.205
1.507
1.774
2.218
3.010
3.763
5.415
6.769
16-5