A procurement manager created 2 separate purchase orders with 5 items for wiring and cable
materials. During the goods receipt it was found that an additional item was delivered related to a
closed purchase order. What is the most efficient way for warehouse personnel to receive these
items into stock?
a)
Copy the 5 items from the purchase orders into a goods receipt
PO, and use the inventory goods receipt to receive the sixth
item.
b)
Copy the 5 items from the purchase orders into a goods receipt
PO and add an additional row in the goods receipt PO for the
sixth item.
c)
d)
3.
Create one goods receipt PO for the 5 items from the purchase
orders and a second goods receipt PO to receive the sixth item.
Company A is using SAP Business One. The company sells tablet computers. One of their prospects
has accepted a sales quotation for 10 tablets. After contacting the prospect for finalizing the delivery
details it was found that this prospective customer can provide Company A with an offer for new
office furniture. Company A is willing to accept this offer.
What option concerning the business partner is most logical for Company A to use when executing
both transactions in SAP Business One?
a)
Use the business partner type Lead to enter the sales order and
delivery, and create a business partner with type 'Vendor' to
create the purchase order.
b)
Enter the sales order as a customer sales order with the vendor
business partner number entered in the customer code field.
c)
d)
4.
Which report shows the earnings of the business for a selected period?
Cash Flow
b)
Trial Balance
c)
Balance Sheet
d)
5.
A user runs the payment wizard. Unexpectedly, not all of the open A/ P invoices to pay are presented
in the recommendation step,
What can be the reasons for that?
The A/P invoice is not in the date range that the user selected.
b)
The user did not choose the appropriate payment method in the
Payment Wizard selection criteria.
c)
d)
6.
A company has defined the posting periods as Quarters. How often should they run the period-end
closing utility?
b)
c)
d)
7.
a)
General authorizations
b)
Form settings
c)
d)
Report categories
8.
A company uses the services of an external organization for marketing and lead generation services
on a range of products. The company wants the external organization to use the features of SAP
Business One, so that lead information is accessible to the companys sales staff. What training is
most suitable for the staff at the external organization?
b)
c)
d)
9.
A company wants to use separate blocks of numbers for purchase orders. A block of numbers should
be allocated to each of the five buyers. How can the consultant implement this requirement in SAP
Business One?
Create employee master data for the buyers. Define the blocks of
numbers as user defaults and link them to the user accounts for
the buyers.
b)
c)
d)
10.
The sales manager wants to be informed whenever a sales document is about to be posted offering
more than 18% discount. The sales manager will then determine if the discount volume is
appropriate for this customers order. What is the best way to implement this?
b)
c)
The sales manager can re-open a sales order at any time and
change the discount amount if it is not appropriate.
d)
Solutions
1 a) Correct
2 a) Incorrect
3 a) Incorrect
4 a) Incorrect
5 a) Correct
1 b) Incorrect
2 b) Correct
3 b) Incorrect
4 b) Incorrect
5 b) Correct
1 c) Incorrect
2 c) Incorrect
3 c) Incorrect
4 c) Incorrect
5 c) Incorrect
1 d) Incorrect
2 d) Incorrect
3 d) Correct
4 d) Correct
5 d) Incorrect
6 a) Incorrect
7 a) Correct
8 a) Incorrect
9 a) Incorrect
10 a) Incorrect
6 b) Incorrect
7 b) Correct
8 b) Correct
9 b) Correct
10 b) Correct
6 c) Incorrect
7 c) Incorrect
8 c) Incorrect
9 c) Incorrect
10 c) Incorrect
6 d) Correct
7 d) Incorrect
8 d) Incorrect
9 d) Incorrect
10 d) Incorrect