Optimizing Design & Control of Chilled Water Plants Part-5
Optimizing Design & Control of Chilled Water Plants Part-5
Optimizing Design & Control of Chilled Water Plants Part-5
Design and Control of Central Chilled Water Plants and the research variable flow chilled water plant. The
that was performed to support its development. The articles, and the
SDL course upon which it is based, are intended to provide techniques
for plant design and control that require little or no added engineering time compared to standard practice but at the same time result in
significantly reduced plant life-cycle costs.
A procedure was developed to provide
near-optimum plant design for most chiller plants including the following steps:
1. Select chilled water distribution
system.
2. Select chilled water temperatures,
flow rate, and primary pipe sizes.
3. Select condenser water distribution
system.
56
ASHRAE Journal
4. Select condenser water temperatures, flow rate, and primary pipe sizes.
5. Select cooling tower type, speed
control option, eff iciency, approach
temperature, and make cooling tower
selection.
6. Select chillers.
7. Finalize piping system design, calculate pump head, and select pumps.
plant has two of each major component (chillers, towers, condenser water
pumps, and chilled water pumps) each
sized for 50% of the load. This plant design is very common and was used as
the basis of the simulations and optimization for this series of articles and the
SDL course upon which it is based.
Note that the condenser water (CW)
pumps in Figure 1 do not have variable
speed drives (VSDs). Sequences for
variable speed CW pumps are also addressed in this article but, as discussed
in Part 21 of this series and in more detail below, VSDs on condenser water
About the Author
Steven T. Taylor, P.E., is a principal at Taylor
Engineering in Alameda, Calif.
a s h r a e . o r g
June 2012
VSD
VSD
Cooling
Tower 1
Cooling
Tower 2
VSD
Chiller 1
VSD
VSD
Chiller 2
VSD
(1a)
(2)
(3)
nus WB, F
CHWFR Chilled water flow ratio, actual flow divided
by total plant design flow
CHWST Chilled water supply temperature (leaving
evaporator temperature), F
CWFR Condenser water flow ratio, actual flow divided by total plant design flow
CWRT Condenser water return temperature (leaving
condenser water temperature), F
CDD65 Cooling degree-days base 65F
DP Differential pressure, feet H2O
KW/TON Chiller efficiency at AHRI conditions, kW/ton
DT Temperature difference, F
GPM/HP Tower efficiency per ASHRAE Standard 90.1
IPLV Integrated part load value per AHRI 550/590,
kW/ton
NPLV Non-standard part load value per AHRI
550/590, kW/ton
RANGE Design tower entering minus leaving water
temperature, F
PLR Plant part load ratio, current load divided by
total plant design capacity
TOPP Theoretical optimum plant performance
WB Design wet-bulb temperature, ASHRAE 1%,
F
WBDD55 Wet-bulb cooling degree-days base 55F
Variables
ASHRAE Journal
57
pumps are usually not life-cycle cost effective for plants serving office building type loads.
Also note in Figure 1 that the cooling towers do not include
any isolation valves to shut off flow to allow one tower to operate alone. As discussed in Part 42 of this series, towers generally can be selected with nozzles and dams that allow half
flow from one CW pump while still providing full coverage of
fill and it is always most efficient to run as many tower cells
as possible. So whether one or two CW pumps are operating, both tower cells are enabled and fans are controlled to the
same speed.
www.info.hotims.com/41640-35
58
A S H R A E J o u r n a l
June 2012
100
90
80
DP Setpoint = Head2
DP Setpoint = Head3
70
Pump kW (%)
DP Setpoint = 0 (Reset)
60
50
40
30
20
10
0
0 10 20 30 40 50 60 70 80 90
100
gpm (%)
* The curves in this figure assume pressure drop varies with flow to the 1.8 power since flow is typically in the transitional region between turbulent and laminar flow.
They do not account for the impact of opening and closing control valves, which change system geometry and hence the system flow characteristics. The curves
do include reductions to the efficiency of motors and VSDs at low load.
June 2012
ASHRAE Journal
59
Wh/ft2yr
Wh/ft2yr
60
ASHRAE Journal
0
CHWST Reset,
Fixed DP
Fixed CHWST,
DP Reset
Reset CHWST
Then DP
June 2012
For plants with more consistent loads that do not vary with weather, such as
those serving data centers and those located in consistently humid climates
such as Miami, correlation of load with CWRT/CHWST temperature difference
is poor. For these plants, optimum CWST vs. wet-bulb temperature was found
to have better correlation. But for office buildings in general, the correlations in
Figure 7 were more consistent.
June 2012
DPmax
Tmax
DP
Setpoint
DPmin
DP
Setpoint
CHWST
Setpoint
CHWST
Setpoint
Tmin
0 50% 100%
CHW Plant Reset
Figure 5: CHWST Setpoint and CW DP Setpoint Reset sequenced off of CHW valves.
www.info.hotims.com/41640-25
ASHRAE Journal
63
Oakland
CWST
90
85
y=0.9133x+12.997
R2=0.927
80
75
70
65
60
55
50
45
40
35
30
30 35 40 45 50 55 60 65 70 75 80 85 90
90
85
y=0.1223x+58.823
R2=0.0119
80
75
70
65
60
55
50
45
40
35
30
30 35 40 45 50 55 60 65 70 75 80 85 90
CWST
Miami
OAWB
OAWB
Figure 6: TOPP optimum condenser water supply temperature vs. wet-bulb temperature.
Miami
y=47.729x+11.656
R2=0.7848
CWRTCHWST
CWRTCHWST
80
75
70
65
60
55
50
45
40
35
30
25
20
15
10
5
0
Atlanta
0 10 20 30 40 50 60 70 80 90
100
80
75
70
65
60
55
50
45
40
35
30
25
20
15
10
5
0
y=58.332x+4.0753
R2=0.9417
0 10 20 30 40 50 60 70 80 90
100
y=44.87x+4.2464
R2=0.9341
CWRTCHWST
CWRTCHWST
Oakland
80
75
70
65
60
55
50
45
40
35
30
25
20
15
10
5
0
0 10 20 30 40 50 60 70 80 90
100
80
75
70
65
60
55
50
45
40
35
30
25
20
15
10
5
0
y=57.434x+3.8301
R2=0.9475
0 10 20 30 40 50 60 70 80 90
100
Percent Total Design Chiller Capacity
ASHRAE Journal
a s h r a e . o r g
(1)
June 2012
A and B are coefficients that vary with climate and plant design
(see Modeling the Plant, Page 57). Equation 1 can be solved
for the optimum CWRT setpoint given the current CHWST:
(1a)
This setpoint must be bounded by the minimum CWRTCHWST difference at low load prescribed by the chiller
manufacturer. This minimum (9F [5C] for the chiller in
Figure 7) is a function primarily of the chillers oil management design and can range from only a few degrees for oilfree chillers (e.g., those with magnetic or ceramic bearings)
to as high as about 20F [11C]. The lower this minimum is,
the lower annual chiller plant energy will be, particularly in
mild climates.
So near-optimum tower performance can be achieved by
controlling tower fan speed based on condenser water return
temperature to the setpoint determined from Equation 1a.
Controlling tower fan speed based on return temperature rather than supply temperature is non-conventional but it makes
sense because it is the temperature leaving the condenser that
determines chiller lift, not the entering (supply) water temperature. Chiller efficiency is not sensitive to entering chilled
or condenser water temperature.
www.info.hotims.com/41640-65
66
CWFR = C PLR + D
(2)
(2a)
www.info.hotims.com/41640-30
A S H R A E J o u r n a l
June 2012
Miami
Atlanta
90
80
80
70
70
60
60
50
50
40
30
20
y=0.8431x+0.3286
R2=0.8284
CW gpm (%)
100
90
CW gpm (%)
100
40
30
y=0.9833x+0.2667
R2=0.8356
20
10
10
100
10 0 10 20 30 40 50 60 70 80 90
100
10 0 10 20 30 40 50 60 70 80 90
20
20
30
30
Percent Total Plant Design Capacity
Oakland
90
80
80
70
70
60
60
50
50
40
30
20
10
y=1.335x+0.1784
R2=0.8488
CW gpm (%)
100
90
CW gpm (%)
100
40
30
20
y=1.0327x+0.2503
R2=0.8333
10
100
10 0 10 20 30 40 50 60 70 80 90
0
100
10 0 10 20 30 40 50 60 70 80 90
20
20
30
30
Percent Total Plant Design Capacity
68
ASHRAE Journal
3
Optimum Number of Chillers
0
0 10 20 30 40 50 60 70 80 90
100
Percent Total Design Chiller Capacity
June 2012
Speed
100%
90%
Two Chillers
One Chiller
Surge Region
Refrigerant Lift
80%
Two Chillers
70%
One Chiller
60%
Chiller Staging
Figure 9 (Page 68) shows the optimum number of chillers
that should be run plotted against plant load for variable speed
centrifugal chillers. The graph shows that it is often optimum
to operate two chillers as low as 25% of overall plant load.
This result may seem somewhat counterintuitive; conventional wisdom is to run as few chillers as possible. That is true for
fixed speed chillers, but not for variable speed chillers, which
are more efficient at low loads when condenser water temperatures are low.
Figure 9 shows that staging chillers based on load alone
will not optimize performance since there is a fairly wide
range where either one or two chillers should be operated.
70
Load
www.info.hotims.com/41640-3
A S H R A E J o u r n a l
D63898asjl_1206885.indd 1
June 2012
5/10/12 8:28:54
(3)
Oakland
80
70
60
CWRTCHWST
surge, the chiller controllers will speed up the compressors and throttle inlet guide vanes to control capacity. This
reduces chiller efficiency so that it would then be more efficient to operate one chiller rather than two. But if the lift
is low (green line in Figure 10), the chillers would not be
in surge so operating two chillers would be more efficient
than operating one. So in addition to load, chiller staging
must take chiller lift into account. (This consideration applies only to centrifugal chillers; surge does not occur with
positive displacement chillers such as those with screw
compressors.)
Figure 11 shows the optimum number of operating chillers (blue dots indicate one chiller while red dots indicate two
chillers) for example TOPP simulations. For all plant design
options and for all climate zones, good correlations were
found for the optimum staging point described by a straight
line:
50
40
30
20
10
0
0 10 20 30 40 50 60 70 80 90
100
Percent Total Design Chiller Capacity
Albuquerque
80
70
60
CWRTCHWST
June 2012
40
30
20
10
0
0 10 20 30 40 50 60 70 80 90
100
Percent Total Design Chiller Capacity
Chicago
Example
80
70
60
CWRTCHWST
50
50
40
30
20
10
0 0 10 20 30 40 50 60 70 80 90
100
Percent Total Design Chiller Capacity
One Chiller
Two Chillers
71
+20%
180,000
Summary
+3%
160,000
+1%
+4%
Real vs
Real CS
+8%
140,000
120,000
100,000
80,000
60,000
40,000
20,000
References
1. Taylor, S. 2011. Optimizing design and control of chilled water plants
part 2: condenser water system design. ASHRAE Journal 53(9):2636.
2. Taylor, S. 2012. Optimizing design and control of chilled water
plants part 4: chiller and cooling tower selection. ASHRAE Journal
54(3):6070.
3. Hartman, T. 2005. Designing efficient systems with the equal
marginal performance principle. ASHRAE Journal 47(7):6470.
4. Hydeman, M., G. Zhou. 2007. Optimizing chilled water plant
control. ASHRAE Journal 49(6):4554.
www.info.hotims.com/41640-28
72
200,000
0
TOPP vs TOPP CS
CWP kWh
CHWP kWh
Tower kWh
AHRI
Constant
Reset CS CWST CS
Chiller kWh
Figure 12: TOPP vs. real sequences for both constant speed
and variable speed CW pumps.
www.info.hotims.com/41640-4
A S H R A E J o u r n a l
June 2012
5. ANSI/ASHRAE Standard 90.1-2010, Energy Standard for Buildings Except Low-Rise Residential Buildings.
6. Rishel, J.B. 2001. Wire-to-water efficiency of pumping systems.
ASHRAE Journal 43(4):4046.
7. Taylor, S. 2002. Degrading chilled water plant T: causes and
mitigation. ASHRAE Transactions 108(1):641653.
8. Taylor, S. 2007. Increasing efficiency with VAV system static
www.info.hotims.com/41640-68
74
A S H R A E J o u r n a l
June 2012