ITD Cementation India Limited
ITD Cementation India Limited
ITD Cementation India Limited
Phone
Fax
To,
The Project Manager,
Chartered Hotels Pvt Ltd.
Vibhuti Khand, Gomati Nagar
Lucknow, U.P.
DATE
Site
Our Contact
Horosit Saha
Direct Line
+91 9717296000
Sub: South Side Soil Retaining Works for Proposed Five Star Hotel Project at Lucknow .Submission of
Purchase order & Invoice of 6mm MS plate (Liner), 10mm Ms Plate (Insert Plate) & 32mm, 8mm
TMT Bar.
Kind Attention: Mr. Vivek Sinha (Project Manager)
Dear Sir,
We are here by submitting you the attached details of Purchase order & Invoice of 6mm
MS plate (Liner), 10mm Ms Plate (Insert Plate) & 32mm, 8mm TMT Bar for our piling work at
South Side Soil Retaining Works for Proposed Five Star Hotel Project at Lucknow, Uttar Pradesh.
This is for your kind information and record please.
Thanking you and assuring you of our best services at all the times.
Yours faithfully,
For ITD Cementation India Ltd,
____________________
Horosit Saha
(Authorised Signatory)
Encls. : As Above. Co
Phone
Fax
Site
To,
The Project Manager,
ITD Cementation India Ltd.
Division-2, Ghaziabad Flyover Project,
Pratap Vihar, Ghaziabad, U.P.
DATE
Our Contact
Direct Line
Horosit Saha
+91 9717296000
Sub: Construction of Six Lane Link Road between NH-24 by pass & NH-58 at Ghaziabad Including ROB
(Excluding Railway portion) on Delhi Howrah Rail Track in the State Of Uttar Pradesh .Submission of Initial
Lateral Load test Report.
Kind Attention: Mr. Sarfaraj Hussain (Project Manager)
Dear Sir,
We are here by submitting you the Initial Lateral Load Test report and field result of Pile No. TP-01
which was conducted on Dated-28.06.2013 for our piling work at Ghaziabad Flyover project under
Ghaziabad Development Authority (GDA), Ghaziabad, Uttar Pradesh.
This is for your kind information and record please.
Thanking you and assuring you of our best services at all the times.
Yours faithfully,
For ITD Cementation India Ltd,
____________________
Horosit Saha
(Authorized Signatory)
Encls. : As Above. Co
www.ltdcem.co.ln
To,
The Project Manager,
Phone
Fax
Site
DATE
Our Contact
Direct Line
Horosit Saha
+91 9717296000
Sub: Construction of Six Lane Link Road between NH-24 by pass & NH-58 at Ghaziabad Including ROB
(Excluding Railway portion) on Delhi Howrah Rail Track in the State Of Uttar Pradesh .Submission of RA Bill
for the work done on Month of June.
Kind Attention: Mr. Sarfaraj Hussain (Project Manager)
Dear Sir,
We are here by submitting you the RA Bill-3 against the work done on 1st June to 30th June of an
Amount of Rs. 8253940.55 (Rupees Eighty Two Lakh(s) Fifty Three Thousand Nine Hundred Forty and
paise Fifty Five only) for our piling work at Ghaziabad Flyover project.
We would therefore request you to release the Billed amount at the earliest.
Thanking you and assuring you of our best services at all the times.
Yours faithfully,
For ITD Cementation India Ltd,
____________________
Horosit Saha
(Authorized Signatory)
Encls. : As Above. Co
Centre (Through mail)
www.ltdcem.co.ln
To,
The Project Manager,
Phone
Fax
Site
DATE
Our Contact
Direct Line
Horosit Saha
+91 9717296000
Sub: Construction of Six Lane Link Road between NH-24 by pass & NH-58 at Ghaziabad Including ROB
(Excluding Railway portion) on Delhi Howrah Rail Track in the State Of Uttar Pradesh .Request Letter for JCB.
Kind Attention: Mr. Sarfaraj Hussain (Project Manager)
Dear Sir,
We are here by requesting you to kindly please arrange a JCB which will be used for Load Test work in
the Test pile near Eco Park at Ghaziabad Flyover project.
This is for your information and record.
Thanking you and assuring you of our best services at all the times.
Yours faithfully,
For ITD Cementation India Ltd,
____________________
Horosit Saha
(Authorized Signatory)
www.ltdcem.co.ln
To,
The Project Manager,
Phone
Fax
Site
DATE
Our Contact
Horosit Saha
Direct Line
Ghaziabad Flyover
Project, Pratap vihar
+91
9717296000
Ghaziabad, Uttar
Pradesh
Sub: Construction of Six Lane Link Road between NH-24 by pass & NH-58 at Ghaziabad Including ROB
(Excluding Railway portion) on Delhi Howrah Rail Track in the State Of Uttar Pradesh .Request Letter for JCB.
Kind Attention: Mr. Sarfaraj Hussain (Project Manager)
Dear Sir,
We are here by requesting you to kindly please arrange a JCB which will be used for Area
Development work for your piling work near Eco Park at Ghaziabad Flyover project.
This is for your information and record.
Thanking you and assuring you of our best services at all the times.
Yours faithfully,
For ITD Cementation India Ltd,
____________________
Horosit Saha
(Authorized Signatory)
www.ltdcem.co.ln
Phone
Fax
Site
To,
The Project Manager,
ITD Cementation India Ltd.
Division-2, Ghaziabad Flyover Project,
Pratap Vihar, Ghaziabad, U.P.
DATE
Our Contact
Direct Line
Horosit Saha
+91 9717296000
Sub: Construction of Six Lane Link Road between NH-24 by pass & NH-58 at Ghaziabad Including ROB
(Excluding Railway portion) on Delhi Howrah Rail Track in the State Of Uttar Pradesh .Submission of Internal
Advise for the work done on Month of October & November -13.
Kind Attention: Mr. Sarfaraj Hussain (Project Manager)
Dear Sir,
We are here by submitting you the Internal Advise-07 & final against the work done on 1st October to
8th November of an Amount of Rs. 5808202.12 (Rupees fifty eight Lakh(s) Eight Thousand two
Hundred two and paisa twelve only) for our piling work at Ghaziabad Flyover project.
We would therefore request you to release the Billed amount, and also release the previous deducted
amount at the earliest.
Thanking you and assuring you of our best services at all the times.
Yours faithfully,
For ITD Cementation India Ltd,
____________________
Horosit Saha
(Authorized Signatory)
Encls. : As Above. Co
www.ltdcem.co.ln
Phone
Fax
Site
To,
The Project Manager,
ITD Cementation India Ltd.
Division-2, Ghaziabad Flyover Project,
Pratap Vihar, Ghaziabad, U.P.
DATE
Our Contact
Direct Line
Horosit Saha
+91 9717296000
Sub: Construction of Six Lane Link Road between NH-24 by pass & NH-58 at Ghaziabad Including ROB
(Excluding Railway portion) on Delhi Howrah Rail Track in the State Of Uttar Pradesh .Requirement of MS pipe
for concrete pipe line.
Kind Attention: Mr. Sarfaraj Hussain (Project Manager)
Dear Sir,
We are here by inform you that, in present site condition our work location is fully water logged. So we
required Mild steel pipe of N.B. 40(25 Nos.) for concrete pipe line to transfer concrete for our piling work
at Ghaziabad Flyover project.
We would therefore request you to kindly provide the said item for our piling work at earliest.
Thanking you and assuring you of our best services at all the times.
Yours faithfully,
For ITD Cementation India Ltd,
____________________
Horosit Saha
(Authorized Signatory)
Co
www.ltdcem.co.ln
Phone
Fax
Site
To,
The Project Manager,
ITD Cementation India Ltd,
Pratibha D-wall site, 29313CF
Delhi.
DATE
Our Contact
Direct Line
Horosit Saha
+91 9717296000
Dear Sir,
We are here by inform you that, as per instruction of Mr. Abhay Singh Yadav (By Mail) we are sending
Mr. Rajeev Ku. Singh (Tech. Asst.) ERP No.-2868 to your site. He is released from our site on 23 rd
August 2013 and he will be report to your site immediately.
Note: Out station allowance is cleared up to 31st July.
This is for your information and record please.
Yours faithfully,
For ITD Cementation India Ltd,
____________________
Horosit Saha
(Authorized Signatory)
Cc : Abhay singh Yadav
Sandeep Agnihotri
www.ltdcem.co.ln
Phone
Fax
Site
To,
The Project Manager,
ITD Cementation India Ltd.
Division-2, Ghaziabad Flyover Project,
Pratap Vihar, Ghaziabad, U.P.
DATE
Our Contact
Direct Line
Horosit Saha
+91 9717296000
Sub: Construction of Six Lane Link Road between NH-24 by pass & NH-58 at Ghaziabad Including ROB
(Excluding Railway portion) on Delhi Howrah Rail Track in the State Of Uttar Pradesh .Requirement of TMT
Bar Fe 500 for reinforcement cage making in piling work.
Kind Attention: Mr. Sarfaraj Hussain (Project Manager)
Dear Sir,
We are here by inform you that, we have required TMT Bar Fe 500 for making reinforcement cage in
our piling work at Ghaziabad Flyover project. The following quantity of steel dia. wise given below:
1) 16mm : 15 MT
2) 10mm : 5 MT
We would therefore request you to kindly provide the said item for our piling work at earliest.
Thanking you and assuring you of our best services at all the times.
Yours faithfully,
For ITD Cementation India Ltd,
____________________
Horosit Saha
(Authorized Signatory)
Co
www.ltdcem.co.ln
Phone
Fax
Site
To,
The Project Manager,
ITD Cementation India Ltd.
Division-2, Ghaziabad Flyover Project,
Pratap Vihar, Ghaziabad, U.P.
DATE
th
27 August 2013
Our Contact
Horosit Saha
Direct Line
+91 9717296000
Sub: Construction of Six Lane Link Road between NH-24 by pass & NH-58 at Ghaziabad Including ROB
(Excluding Railway portion) on Delhi Howrah Rail Track in the State Of Uttar Pradesh .Submission of Initial
Vertical Load test Report for TP-03.
Kind Attention: Mr. Sarafraj Hussain (Project Manager)
Dear Sir,
We are here by submitting you the Report for Initial Vertical Load Test on Pile No. TP-03 which was
conducted on Dated-21.08.2013 for our piling work at Ghaziabad Flyover project under Ghaziabad
Development Authority (GDA), Ghaziabad, Uttar Pradesh.
This is for your kind information and record please.
Thanking you and assuring you of our best services at all the times.
Yours faithfully,
For ITD Cementation India Ltd,
____________________
Horosit Saha
(Authorised Signatory)
Encls. : As Above. Co
www.ltdcem.co.ln
Phone
Fax
Site
To,
The Project Manager,
ITD Cementation India Ltd.
Division-2, Ghaziabad Flyover Project,
Pratap Vihar, Ghaziabad, U.P.
DATE
Our Contact
Direct Line
Horosit Saha
+91 9717296000
Sub: Construction of Six Lane Link Road between NH-24 by pass & NH-58 at Ghaziabad Including ROB
(Excluding Railway portion) on Delhi Howrah Rail Track in the State Of Uttar Pradesh .Submission of Internal
Advise for the work done on Month of August-13.
Kind Attention: Mr. Sarfaraj Hussain (Project Manager)
Dear Sir,
We are here by submitting you the Internal Advise-05 against the work done on 1st August to 31th
August of an Amount of Rs. 4134699.36 (Rupees Forty One Lakh(s) Thirty Four Thousand Six Hundred
Ninety Nine and Thirty Six paise only) for our piling work at Ghaziabad Flyover project.
We would therefore request you to release the Billed amount, and also release the previous deducted
amount at the earliest.
Thanking you and assuring you of our best services at all the times.
Yours faithfully,
For ITD Cementation India Ltd,
____________________
Horosit Saha
(Authorized Signatory)
Encls. : As Above. Co
www.ltdcem.co.ln
Phone
Fax
Site
To,
The Project Manager,
ITD Cementation India Ltd.
Division-2, Ghaziabad Flyover Project,
Pratap Vihar, Ghaziabad, U.P.
DATE
th
13 November 2013
Our Contact
Horosit Saha
Direct Line
+91 9717296000
Sub: Construction of Six Lane Link Road between NH-24 by pass & NH-58 at Ghaziabad Including ROB
(Excluding Railway portion) on Delhi Howrah Rail Track in the State Of Uttar Pradesh .Submission of Pour
cards for Test, Sump & Working Piling.
Kind Attention: Mr. Sarafraj Hussain (Project Manager)
Dear Sir,
We are submitting here with the Pour cards for Test, Sump & Working Piling for our piling work at
Ghaziabad Flyover project 29213 CF under Ghaziabad Development Authority (GDA), Ghaziabad, Uttar
Pradesh for the period of 16th April 13 to 8th November 13. Total Number of Pour Cards 424. Kindly
Return Signed copy of the same at the earliest.
This is for your kind information and record please.
Thanking you and assuring you of our best services at all the times.
Yours faithfully,
For ITD Cementation India Ltd,
____________________
Horosit Saha
(Authorised Signatory)
Encls. : As Above. Co
www.ltdcem.co.ln
Phone
Fax
Site
To,
The Project Manager,
ITD Cementation India Ltd.
Division-2, Ghaziabad Flyover Project,
Pratap Vihar, Ghaziabad, U.P.
DATE
Our Contact
Direct Line
Horosit Saha
+91 9717296000
Sub: Construction of Six Lane Link Road between NH-24 by pass & NH-58 at Ghaziabad Including ROB
(Excluding Railway portion) on Delhi Howrah Rail Track in the State Of Uttar Pradesh .Submission of Internal
Advise for the work done on Month of September-13.
Kind Attention: Mr. Sarfaraj Hussain (Project Manager)
Dear Sir,
We are here by submitting you the Internal Advise-06 against the work done on 1st September to 30th
September of an Amount of Rs. 5729253.04 (Rupees Fifty Seven Lakh(s) Twenty Nine Thousand Two
Hundred Fifty Three and Four paise only) for our piling work at Ghaziabad Flyover project.
We would therefore request you to release the Billed amount, and also release the previous deducted
amount at the earliest.
Thanking you and assuring you of our best services at all the times.
Yours faithfully,
For ITD Cementation India Ltd,
____________________
Horosit Saha
(Authorized Signatory)
Encls. : As Above. (6 No. pages)
Co
www.ltdcem.co.ln
Phone
Fax
Site
To,
The Project Manager,
ITD Cementation India Ltd.
Division-2, Ghaziabad Flyover Project,
Pratap Vihar, Ghaziabad, U.P.
DATE
Our Contact
Direct Line
Horosit Saha
+91 9717296000
Sub: Construction of Six Lane Link Road between NH-24 by pass & NH-58 at Ghaziabad Including ROB
(Excluding Railway portion) on Delhi Howrah Rail Track in the State Of Uttar Pradesh .Submission of Initial
Lateral Load test Report for TP-02 and Routine Vertical Load Test Report for Pile No.-24/261.
Kind Attention: Mr. Sarafraj Hussain (Project Manager)
Dear Sir,
We are here by submitting you the Report for Initial Lateral Load Test on Pile No. TP-02 and Routine
Vertical Load Test Report for Pile No. 24/261 which were conducted on Dated-26.09.2013 and
30.09.2013 respectively for our piling work at Ghaziabad Flyover project under Ghaziabad Development
Authority (GDA), Ghaziabad, Uttar Pradesh.
This is for your kind information and record please.
Thanking you and assuring you of our best services at all the times.
Yours faithfully,
For ITD Cementation India Ltd,
____________________
Horosit Saha
(Authorised Signatory)
Encls. : As Above. (2 Nos. Load Test Reports) Co
www.ltdcem.co.ln
Phone
Fax
Site
DATE
Our Contact
Direct Line
Horosit Saha
+91 9717296000
Sub: Construction of Six Lane Link Road between NH-24 by pass & NH-58 at Ghaziabad Including ROB
(Excluding Railway portion) on Delhi Howrah Rail Track in the State Of Uttar Pradesh .Submission of Initial
Lateral Load test Report for TP-03.
Kind Attention: Mr. Sarafraj Hussain (Project Manager)
Dear Sir,
We are here by submitting you the Report for Initial Lateral Load Test on Pile No. TP-03 which was
conducted on Dated-20.09.2013 for our piling work at Ghaziabad Flyover project under Ghaziabad
Development Authority (GDA), Ghaziabad, Uttar Pradesh.
This is for your kind information and record please.
Thanking you and assuring you of our best services at all the times.
Yours faithfully,
For ITD Cementation India Ltd,
____________________
Horosit Saha
(Authorised Signatory)
Encls. : As Above. (1 No. Load Test Report) Co
www.ltdcem.co.ln
Phone
Fax
Site
To,
The Project Manager,
GM Projects,
Arshiya Northern FTWZ Ltd.
Vill. Moujpur, Junction Road,
Khurja, Dist. Bulland Sahar, U. P. 203131
DATE
Our Contact
Direct Line
Hemendra Choudhury
+91 8191007701
Sub: Pile Foundation Works for Multipurpose Warehouses & Bulk Warehouses of Phase : II at FTWZ,
Khurja : Submission of Calibration certificates and Load increment Plan.
Kind Attention : Shri Akhil Jain (GM Projects)
Dated : 26.09.2012
Dated : 03.10.2012
Dear Sir,
Enclosed please find herewith the following documents towards the conducting of pile load test for test.
1) Calibration Certificate of LVDT.
www.ltdcem.co.ln
Phone
Fax
Site
Thanking you and assuring you of our best services at all the times.
Yours faithfully,
For ITD Cementation India Ltd,
____________________
Hemendra Choudhury
(Authorised Signatory)
Encls. : As Above.
To,
The Project Manager,
GM Projects,
Arshiya Northern FTWZ Ltd.
Vill. Moujpur, Junction Road,
Khurja, Dist. Bulland Sahar, U. P. 203131
DATE
Our Contact
Direct Line
Hemendra Choudhury
+91 8191007701
Sub: Pile Foundation Works for Multipurpose Warehouses & Bulk Warehouses of Phase: II at FTWZ,
Khurja: Submission of Calibration certificates of Compressive testing machine & Batching plant.
Kind Attention : Shri Akhil Jain (GM Projects)
Dated : 26.09.2012
Dated : 03.10.2012
Dear Sir,
We are here by submitting you the Calibration certificates of compressive testing machine, Batching
plant Macon M25 and Batching plant Macon M25-2 for our piling work at your Arshiya Northern FTWZ
Ltd. Khurja location.
www.ltdcem.co.ln
Phone
Thanking you and assuring you of our best services at all the times.Fax
Site
Yours faithfully,
____________________
Hemendra Choudhury
(Authorised Signatory)
Encls. : 1) Compressive Testing Machine calibration Report.
2) Batching Plant Macon M25 calibration Report.
3) Batching Plant Macon M25-2 calibration Report.
To,
The Project Manager,
GM Projects,
Arshiya Northern FTWZ Ltd.
Vill. Moujpur, Junction Road,
Khurja, Dist. Bulland Sahar, U. P. 203131
DATE
Our Contact
Direct Line
Hemendra Choudhury
+91 8191007701
Sub: Pile Foundation Works for Multipurpose Warehouses & Bulk Warehouses of Phase: II at FTWZ,
Khurja: Submission of 2Nos of pressure Gauge .
Kind Attention : Shri Akhil Jain (GM Projects)
Dated : 26.09.2012
Dated : 03.10.2012
Dear Sir,
We are here by submitting you the Two Nos of pressure gauge of capacity 700kg/cm as you
instructed for, at your Arshiya Northern FTWZ Ltd. Khurja location.
www.ltdcem.co.ln
Phone
Fax
Site
Thanking you and assuring you of our best services at all the times.
Yours faithfully,
____________________
Hemendra Choudhury
(Authorised Signatory)
Encls. : As above
To,
The Project Manager,
GM Projects,
Arshiya Northern FTWZ Ltd.
Vill. Moujpur, Junction Road,
Khurja, Dist. Bulland Sahar, U. P. 203131
DATE
Our Contact
Direct Line
Hemendra Choudhury
+91 8191007701
Sub: Pile Foundation Works for Multipurpose Warehouses & Bulk Warehouses of Phase: II at FTWZ,
Khurja: Submission of Initial cyclic load increment plan for Test pile-02.
Kind Attention : Shri Akhil Jain (GM Projects)
Dated : 26.09.2012
Dated : 03.10.2012
Dear Sir,
We are here by submitting you the Initial Cyclic Load Increment plan for Test pile No.-TP/02, MPWH02 towards conducting the pile load test for our piling work at your Arshiya Northern FTWZ Ltd. Khurja
location.
www.ltdcem.co.ln
Phone
Fax
Site
____________________
Hemendra Choudhury
(Authorised Signatory)
Encls. : As above
To,
The Project Manager,
GM Projects,
Arshiya Northern FTWZ Ltd.
Vill. Moujpur, Junction Road,
Khurja, Dist. Bulland Sahar, U. P. 203131
DATE
Our Contact
Direct Line
Hemendra Choudhury
+91 8191007701
Sub: Pile Foundation Works for Multipurpose Warehouses & Bulk Warehouses of Phase: II at FTWZ,
Khurja: Minutes of Meeting.
Dated: 26.09.2012
Dated: 03.10.2012
Dear Sir,
We have discussed about the trial mix conducted at site and their cube strength results. Some of the
routine pile cube results also witnessed by us and our client. We are enclosing all trial mix results and
details of concrete mix design which are used at our site for reference.
www.ltdcem.co.ln
Phone
Fax
Site
Yours faithfully,
For ITD Cementation India Ltd,
____________________
Hemendra Choudhury
(Authorised Signatory)
Encls. :
To,
The Project Manager,
AVP Projects,
Arshiya Northern FTWZ Ltd.
Vill. Moujpur, Junction Road,
Khurja, Dist. Bulland Sahar, U. P. 203131
DATE
Our Contact
Direct Line
Hemendra Choudhury
+91 8191007701
Sub: Pile Foundation Works for Multipurpose Warehouses & Bulk Warehouses of Phase: II at FTWZ,
Khurja: Submission of Initial vertical load increment plan for Test pile-03.
Kind Attention : Shri Vijay Singh Raghav (AVP Projects)
Dated : 26.09.2012
Dated : 03.10.2012
Dear Sir,
We are here by submitting you the Initial Vertical Load Increment plan for Test pile No.-TP/03,
MPWH-01 towards conducting the pile load test for our piling work at your Arshiya Northern FTWZ Ltd.
Khurja location.
www.ltdcem.co.ln
Phone
Fax
Site
Yours faithfully,
For ITD Cementation India Ltd,
____________________
Hemendra Choudhury
(Authorised Signatory)
Encls. : As above
To,
The Project Manager,
AVP Projects,
Arshiya Northern FTWZ Ltd.
Vill. Moujpur, Junction Road,
Khurja, Dist. Bulland Sahar, U. P. 203131
DATE
Our Contact
Direct Line
Hemendra Choudhury
+91 8191007701
Sub: Pile Foundation Works for Multipurpose Warehouses & Bulk Warehouses of Phase: II at FTWZ,
Khurja: Submission of standard deviation report of compressive strength of cubes.
Kind Attention: Shri Vijay Singh Raghav (AVP Projects)
Dated: 26.09.2012
Dated: 03.10.2012
Dear Sir,
We are here by submitting you the standard deviation report of 28 days compressive strength of
concrete cubes for the month of November and December for our piling work at your Arshiya Northern
FTWZ Ltd. Khurja location.
www.ltdcem.co.ln
Phone
Fax
Site
Thanking you and assuring you of our best services at all the times.
____________________
Hemendra Choudhury
(Authorised Signatory)
Encls. : As above
To
The Site Incharge
ILFS, Cuttack
Odisha
Kind Attn:- Mr. Onkar Kulkarni (07389905369)
Copy to: Mr.Manish Kumjar/Mr.V.R.Gopakumar/Mr.R.G.Shetty
Mr.P.K.Haldar/Mr.P.B.Naik
Subject: Transfer of Mr. Manas Kumar Bidhar-Superintendent (Safety) (S3) (Emp. Code:-2460)
As per transfer order dated 1st January 2013, Mr. Manas Kumar Bidhar , Superintendent (Safety)(Emp.
Code:-2460) is releasing from 26912CF (Division-3), Piling and foundation works for Multipurpose
Warehouse and Warehouse Phase-II at Arshiya Northern FTWZ Limited, Khurja, Distt:Bulandshahar, Uttar Pradesh w.e.f. 04.01.2013 after duty hours and informed him to report at ILFS
Project, Cuttack for his further assignment.
The following particulars are furnished for your perusal and necessary action.
www.ltdcem.co.ln
1.
2.
3.
4.
5.
6.
7.
8.
Date of release
Salary paid upto
Outstation paid upto
Advance paid towards Traveling
Amount of Recovery
Nature of work carried out
Furniture issued by Company
Ticket arranged by
Regards,
www.ltdcem.co.ln
:
:
:
:
:
:
:
:
Phone
Fax
Site
Dear Sir,
This is to inform you that Our work will be going as normal working day on 16th march (Sunday)
instead of Tuesday on 18th march. Tuesday on 18th march is a Local Holiday. Our ready mix concrete
suppliers ultratech & RMC India both will not be supplying the RMC at 17 & 18 th march.
In this view of above , we decided 16 march is a working day instead of 18th march. Matter already
discussed with client.
Regards;
Horosit Saha
ITD Cemantation India Limited
31913 CF,Chartered Hotel
Lucknow,U.P
Mobile:- +91 9717296000
www.ltdcem.co.ln