CRR 02428

Download as pdf or txt
Download as pdf or txt
You are on page 1of 74

HSE

Health & Safety


Executive

Principles for proof testing of


safety instrumented systems
in the chemical industry

Prepared by ABB Ltd


for the Health and Safety Executive

CONTRACT RESEARCH REPORT

428/2002

HSE

Health & Safety


Executive

Principles for proof testing of


safety instrumented systems
in the chemical industry

Stuart Nunns BSc, C Eng, FIEE, FInstMC


ABB Ltd
Pavillion 9
Byland Way
Belasis Hall Technology Park
Billingham
Cleveland TS23 4YS

Guiding principles for the proof testing of safety instrumented systems (SIS) in the chemical industry
have been developed through research into the practices of proof testing. The proof testing of SIS is an
integral component of the management of functional safety. Its purpose is to confirm the continued
operation of the required safety instrumented function and to contribute to the maintenance of the
required safety integrity level of the safety function.
The guiding principles were developed through direct contact with industrial end-users and suppliers of
SIS components, and through searches of incident data available within the public domain.
Consideration has been given to good practices as defined by international publications such as IEC
61508 and by sector guidance such as that provided by EEMUA. The guiding principles therefore
provide independent guidance on proof testing issues which are of interest and concern to chemical
industry end-users.
Examples of proof test practices and procedures have been provided together with a proposed
checklist of recommended practices which can be used by Field Inspectors. More detailed
recommendations are presented in the body of the report.
This report and the work it describes were funded by the Health and Safety Executive. Its contents,
including any opinions and/or conclusions expressed, are those of the author(s) alone and do not
necessarily reflect HSE policy.

HSE BOOKS

Crown copyright 2002


Applications for reproduction should be made in writing to:
Copyright Unit, Her Majestys Stationery Office,
St Clements House, 2-16 Colegate, Norwich NR3 1BQ
First published 2002
ISBN 0 7176 2346 7
All rights reserved. No part of this publication may be
reproduced, stored in a retrieval system, or transmitted
in any form or by any means (electronic, mechanical,
photocopying, recording or otherwise) without the prior
written permission of the copyright owner.

ii

CONTENTS
EXECUTIVE SUMMARY

IV

1. INTRODUCTION

2. RESEARCH METHOD

3. PRESENTATION OF RESULTS

4. GUIDING PRINCIPLES

4.1
4.2
4.3
4.4
4.5
4.6
4.7
4.8

Proof Test Practices


Content of Proof Test Procedures
Format of Proof Test Procedures
Planning and Scheduling
Records of Proof Testing
Competence
Awareness of Hazard and Risk
Management of Change

5
17
23
26
27
31
36
38

5. SEARCHES
5.1
5.2
5.3
5.4
5.5
5.6
5.7

41

Loss Prevention Journal


IChemE Loss Prevention Bulletin
Miscellaneous Literature Searches
Industry Incident Database
Major Accident Reporting System (MARS) Database Search
HSE Prosecutions Database (http://www.hse-databases.co.uk)
General Conclusions from Searches

41
41
41
43
44
44
44

APPENDIX 1 : GUIDING PRINCIPLES FOR PROOF TESTING

45

APPENDIX 2 : PROPOSED CHECKLIST FOR USE BY INSPECTORS

47

APPENDIX 3.1: EXAMPLE OF A FORMATTED PROOF TEST PROCEDURE

55

APPENDIX 3.2: EXAMPLE OF THE RECORDING OF PROOF TEST RESULTS

60

APPENDIX 3.3: EXAMPLE OF PROOF TEST DOCUMENT CONTROL

63

REFERENCES

65

GLOSSARY

66

iii

EXECUTIVE SUMMARY
A set of guiding principles upon which the proof testing safety instrumented systems (SIS)
should be based has been developed via research into chemical industry practices, experience
and views and via searches of data in the public domain. Interviews, questionnaires,
workshops and searches identified a set of issues relating to proof testing which were of
particular interest to a cross-section of the chemical industry. These issues have been used to
generate guiding principles, which address the following:

proof testing practices;

content of proof testing procedures;

format of proof testing procedures;

planning and scheduling;

proof test records;

competence;

awareness of hazard and risk;

management of change.

The research indicated that the proof testing of SIS is common practice but that some
organisations take a more structured and focused approach than others. The size of an
organisation, and therefore its ability to deploy engineering resources, was significant as was
a commonly held view that the reducing numbers of competent, experienced technical
personnel is beginning to have an impact on proof testing practices.
The research confirmed the existence of conflict between the need for realistic proof testing
and the need to minimise downtime, particularly within high throughput continuous processes
such as refining and bulk chemical manufacture. The increasing profile of IEC615081 was a
common theme throughout the research with manufacturing organisations expressing
trepidation over its potential impact on existing installations, notwithstanding its nonretrospective nature.
Examples of good and poor practice were encountered and have been highlighted in this
report, however, searches of published literature and incident databases provided no tangible
evidence that incidents have been directly attributed to issues relating to proof testing.

iv

1.

INTRODUCTION

This report relates to the proof testing of safety instrumented systems (SIS). It has been
produced as part of a research project funded by the Health and Safety Executive. The contract
was placed with Eutech Engineering Solutions Limited.
The objectives of the research were to define a set of guiding principles upon which proof tests
of SIS should be developed, to provide independent advice to HSE Field Inspectors and to
report on current practices, highlighting examples of good and poor practice where relevant.
The research gathered data from industry via interviews, workshops and questionnaires and
executed searches of data within the public domain. This report presents the findings of the
research.
The target audiences for the report are industrial end-users of SIS and HSE Field Inspectors.
Industrial end users should benefit from the communication and illustration of current practices.
The collation of experiences, views and examples gives an indication of what is practicable and
of the issues of concern to different sectors within the chemical industry.
The data generated by the industrial research is presented 'as found' in an attempt to provide a
genuine indication of the practices, experiences and concerns within industry. The data collected
during the research was analysed and the results used to generate and support a set of guiding
principles for the proof testing of SIS. Each principle is presented in this report and is supported
by the research data and a rationale based on recognised standards and guidance. The current
high profile of IEC615081 amongst end-users was evident throughout the research. Its principles
have been used to construct the rationales supporting the guiding principles.
Detailed recommendations have been generated to provide practical guidance on the application
of the guiding principles. The recommendations have been used to create a checklist for use by
HSE inspectors. The checklist is presented in Appendix 2.

2.

RESEARCH METHOD

The research consisted of five activities:

interviews with industrial end-user organisations;

follow-up questionnaires, discussions and interviews;

workshops attended by end-user organisations;

workshops attended by equipment suppliers;

searches of data and documentation, in the public domain.

The industrial research targeted a cross section of medium to large scale chemical
manufacturing organisations covering continuous and batch operators from the chemical,
petrochemical, refining, fine chemical and pharmaceutical sectors. Interviews with
representatives of end-user organisations were carried out via face-to-face discussions by
engineering consultants using a common interview script. An analysis of the interview coverage
is shown in Table 1. The reported distribution of SIS across the sectors examined is shown in
Figure 1. The interviews targeted personnel involved in the proof testing of SIS, specifically
those with responsibility for the management of proof testing and those responsible for its
execution.

15

10

Figure 1 : Distribution of reported SIS across industrial sectors


(total reported SIS: 19,465)

Chemical
42%

Refining /
Petrochem.
51%
Refining
6%

Fine Chemical
1%

Batch

Continuous

Pharmaceutical

Refining /
petrochemical

Refining

Fine Chemical

Total

Chemical

Table 1 : Analysis of interviewee characteristics

Following the initial collation and analysis of the data, further targetted information was
gathered through questionnaires, follow-up calls and further site visits.
Three workshops were held in order to facilitate the sharing of views and experience of
chemical manufacturing organisations, hereafter referred to as end users, and SIS equipment
suppliers. Workshops for end users were held at Teesside and Humberside whilst a workshop
for equipment suppliers was held at Teesside. The end user workshops were supported by
EPICC and HCF respectively. Analyses of the attendance of the end user and supplier
workshops are shown in Tables 2 and 3 respectively. The workshops were based on a common
agenda, however, the free exchange of views and experience was encouraged.

Table 2 : Analysis of end user workshop attendees


No. of
companies
represented

Refining

Chemical

Fine chemical

Other

22

Table 3 : Analysis of supplier workshop attendees


SIS components supplied
Total no. of attendees

Sensors

Logic solvers

Final elements

The search of publicly accessible data covered a variety of publications and databases. The
available information was searched for specific references to the proof testing of SIS,
particularly for reports of incidents arising from proof testing deficiencies. Where appropriate,
the method of review of each source of data is described in the relevant sections of the research
results.

3.

PRESENTATION OF RESULTS

The results of the research have been used to present an independent view of the sufficient and
practicable scope of proof testing. Analysis of good practice, as defined by recognised standards
such as IEC615081, and of the interviews, workshops and searches highlighted a number of key
issues associated with the proof testing of SIS. The key issues were refined to generate a set of
guiding principles and supporting recommendations, which could be used to implement or
assess good practice in the field of proof testing of SIS. The recommendations are summarised
in Appendix 2 in the form of a checklist for use by inspectors.
The results of the research are presented in detail with the intention of reporting the views and
experiences of the chemical manufacturing industry as fully and as accurately as possible. The
references to specific responses aim to provide an indication of the real issues of interest to
those involved, whilst the conclusions and recommendations aim to provide an independent
view of the results.
The presentation of the results of interviews and workshops follows a consistent format. The
statement of each guiding principle is supported by a rationale, which describes the context in
which the statement is made. The rationale is followed by a collation of the relevant views and
evidence obtained via the interviews, workshops and questionnaires. Examples of good and
poor practices are highlighted and referenced to the relevant guiding principles. Good and poor
practices are not attributed to specific sources. Conclusions and recommendations arising from
the research are then presented. To aid reference, the guiding principles are collated in
Appendix 1.
The appendices also contain proof test procedures, or sections thereof, which are presented to
illustrate some of the issues and recommendations arising from the research.

4.

GUIDING PRINCIPLES

4.1

PROOF TEST PRACTICES

4.1.1

Statements of Guiding Principles

(a) The proof test of a SIS should reflect real operating conditions as accurately as possible. If
reasonably practicable, the SIS should be initiated by manipulation of the process variable
without driving the process into the demand condition. Any approach which involves
driving the process into the demand state should be accompanied by risk assessment and
additional controls.
(b) Where process variables cannot be safely or reasonably practicably be manipulated,
sufficient confidence in the correct operation of sensors should be gained by other means,
such as comparison with other measurements.
(c) The inherent difficulties associated with testing valves and in-line flowmeters should be
addressed during the design phase of SIS and additional provisions such as corroborative
measurements should be made where necessary.
(d) Proof tests should address the necessary functional safety requirements of SIS, including
functions such as response time and valve leakage class.
4.1.2

Rationale

Effective SIS proof testing should confirm the correct operation of the sensing element(s) and
actuating devices, also known as final elements. There is known to be a wide range of
techniques adopted by the end-user community in their approach to SIS testing and the
following sections provide a summary of the techniques encountered during the research. A
variety of techniques were encountered, including examples of both good and poor practice, as
were examples where a deficiency was discovered and how it was addressed or improved.
The most satisfactory test of a system will manipulate the process variable in order to achieve a
full end to end test. However, practicability is very much dependant on the nature of the
process, the process materials and associated risk, and on the tolerable upsets to the process and
to production.
4.1.3

Research Data

Testing Pressure Loops


There was unanimous agreement that process pressures should not be manipulated in order to
initiate SIS due to the potential of releasing significant stored energy [consistent with principle
4.1.1(a)].
The most popular alternative was considered to be the injection of a pressure signal in to the
measuring instrument via an isolation and vent valve arrangement positioned as close to the
primary element as possible, using a suitable fluid medium. Conversely, one end-user was of the
opinion that testing of pressure measuring instruments can only safely be carried out on special
test rigs in a workshop environment, again, because it is not considered safe to raise the pressure
of a process [inconsistent with principle 4.2.1 (d)]. Pressure loops are usually designed so that
the process input can be isolated from the measuring instrument and a calibration pump
connected at a suitable point. The pressure can then be raised to check the operation and
calibration of the instrument and so test the majority of the safety system.

Pressure injection was deemed satisfactory for non-hazardous process materials but was not
recommended for those of a hazardous nature. To illustrate this point, an end-user cautioned
against considering "direct injection" at impulse lines as necessarily a first choice of test
method. "First line breaks" with hazardous materials that are flammable, toxic or irritant have
the potential to cause injury, damage plant or cause environmental incidents. There is always the
possibility of leaving valves shut or not refitting blanks. Therefore, this particular end-user
always considers the need for risk assessment when designing SIS hardware and writing proof
test methods in order to avoid testing the plant in such a way that there is the possibility of
adverse effects on persons, the environment or plant. Where the risk is deemed acceptable,
precautions such as the use of protective equipment are taken. Where risk is deemed to be
unacceptable, simulation techniques would be used [potentially inconsistent with principle 4.2.1
(a)].
A weakness of pressure injection was considered to be the inability to test the full extent of
impulse lines, however, some end-users depressurise transmitters under test via the impulse line
into the process, thus proving that the impulse line is clear [consistent with principle 4.2.1 (a)].
Two other options for dealing with hazardous process media were cited. If the measuring
element is SMART, then the functionality of the device can be used to drive the signal to the
trip value. If it is not, then a current signal must be injected into the loop at a suitable point to
simulate the output of the measuring instrument. Neither of these techniques proves that the
measuring instrument is working correctly [principle 4.2.1(b)], however, with a SMART
instrument some confidence in the on-line measurement may be provided by self-diagnostic
features. Where non-SMART instruments are used the measurements should be corroborated
[principle 4.1.1(b)], firstly by comparison with duplicate instrumentation or other
instrumentation in the surrounding vicinity or by calibration and test under safe conditions.
Other examples of pressure SIS proof testing were cited as follows.

On a liquid process one end-user generally uses a direct mounting instrument. This is
difficult to test on-line, due to the way that the instrument would need to be tested so they
wait until the plant is shutdown and then inject a pressure, in-situ at the instrument
[inconsistent with principle 4.4.1 (b)].

Testing of a pressure loop is usually done, by injecting a signal into the measuring
element, after isolating it from the process. However, this means that the impulse line and
tapping are not being proved. Where possible the signal is injected as close to the tapping
as possible to minimise this, but when the instrument is remote from the tapping, this
increases the difficulty of testing [lack of consideration of testing requirements at the
design phase leads to potential inconsistency with principle 4.2.1 (a)].

Another end-user's method is to isolate the pressure transmitter and zero it. They then
inject zero, full scale and trip equivalent signals into signal lines and check any
receivers and trip devices. Where the process materials are non-hazardous they open the
vent and process tappings to check process flow through impulse lines before closing the
vent and re-commissioning [consistent with principle 4.2.1 (a)].

An end-user uses a "Beemax" pump to simulate a high pressure, however, on one of their
most critical trips the pressure needs raising to 21.5 bar. This particular installation is on
the roof of the plant and the method allows for a real test of the system. To facilitate
this, they use a nitrogen cylinder with calibrated gauges, which is situated near to the
installation [consistent with principle 4.1.1 (a)]. Other pressure installations use either
close coupled cells, generally where toxic materials are in use, or remote transmitters with
impulse lines which are kept as short as possible. Where toxic materials are evident, the
input to the logic solver is tested either by injecting a current signal at a suitable point, or
by using the facilities of SMART transmitters to drive their outputs to trip points
[inconsistent with principle 4.2.1 (a)]. Transmitters with impulse lines on non-toxic
applications are tested by pressure signal injection.

A bursting disk interspace trip, part of a triple redundant system, connected by an impulse
line to a transmitter is tested during plant shutdown due to inadequate process isolation
[potentially inconsistent with principle 4.4.1 (b)]. To test the element, the transmitter is
removed to the workshop [inconsistent with principle 4.2.1 (d)] for test and calibration.
The end-user would like to improve the installation in the near future by fitting double
block and bleed valves to each of the three instruments, instead of the common isolation
presently in place, to allow on line testing.

Another end-user uses a direct connection to the process line for all duties via a manifold
or line-specification isolation with vent and drain valves to allow live process testing.
Alternative measurements are generally monitored during the testing routine. The
transmitter is isolated from the process and vented or injected with pressure from a test
rig to simulate the required trip condition. This is seen as a fundamental test of the whole
system and includes calibration. Care is needed to separately check impulse lines by way
of a separate maintenance routine as they are prone to blockage [consistent with principle
4.2.1 (c)], and a trip test does not include the impulse lines when injecting a pressure
signal at the primary element.

Testing Level Loops


As was the case for pressure systems, some end-users expressed concerns over testing level
systems by manipulating the process measurement. Provided that it is concluded that it is not
reasonably practicable to perform the test by manipulating the process variable as principle
4.1.1(a), the use of risk assessment and secondary instrumentation to monitor the surrounding
conditions should allow this method of testing to be used.
One end-user also felt that raising or lowering levels until trips operate could lead to hazardous
situations. If the trip does not operate, or operates at the wrong value, the condition being
prevented could occur, therefore the only time that level SIS can be tested in a safe manner is
during a shutdown of the plant when the correct level can be set up in order to test the correct
operation of the level measurement [inconsistent with principles 4.4.1 (b) and 4.1.1 (a)]. The
end-user therefore carries out online testing by injecting a signal to simulate the level
measurement and so test the safety system under a defeat, but realises that this does not test the
level-measuring element. It is possible to use a radioisotope system to give indication of the
actual level in a vessel and compare this against the level measurement reading in order to gain
confidence in the measuring device [consistent with principle 4.1.1 (b)].
Wherever possible, one end-user with pneumatic instrument systems increased the measured
variable's actual value until the trip or alarm operated, assuming that the operating point
indicated by the panel instrument would be correct. This assumption was based on the belief
that they needed to have two faults giving identical errors for it to be covert. However, an
incident caused them to change this practice to one of actually pressure-injecting transmitters
wherever possible. The incident was caused by a large air leak affecting both the indicator and
pressure switch to the same degree, which prevented a level alarm operating and resulted in an
overfilled storage tank [inconsistent with principles 4.1.1 (a) and 4.2.1 (a)].
Another end-user's measurement philosophy involves one of three approaches; either a direct
coupled pad cell, a vibrating fork level switch or, in some instances, a radar device. Due to the
toxic and corrosive nature of the process, signals are injected to test the logic solver and the
instrument is generally removed for calibration and testing at a shutdown to give confidence in
the measuring instrument [inconsistent with principles 4.2.1 (d) and 4.1.1 (a)].
With radioactive level and density initiators, one end-user usually isolates the radioactive
sources for high trips and uses a test source for low trips. Level switches mounted directly on
vessels are tested during a shutdown, during water trials or re-commissioning, following
removal and examination of the switch [potentially inconsistent with principles 4.4.1 (b), 4.2.1
(d) and 4.1.1 (a)].

During discussion, an end-user contended that testing of a level system depends on the
installation. If it is a differential pressure (DP) installation then the item is treated as a pressure
signal, and a pressure is injected at the cell to simulate level. Where it is a fixed level switch,
then the level is generally raised and the system tripped in anger [inconsistent with principle
4.1.1 (a)]. They avoid doing this type of test under a trip defeat as they feel that the potential
exists for creating a hazardous situation. They have considered installing chambers on the sides
of columns or tanks to allow draining and filling to test sensors under realistic conditions but
this is known to be costly and where hazardous materials are present, this could endanger the
people carrying out the testing.
Another example an end-user discussed, applied to a reactor where the initiator is a direct
mounted level switch. They would wait until a shutdown [potentially inconsistent with principle
4.4.1 (b)] when they would remove the switch [inconsistent with principle 4.2.1 (d)] and test it
with water [inconsistent with principle 4.1.1 (a)]. Realising the shortcomings of this, they are
looking at improving this by moving towards a self-checking probe [consistent with principle
4.1.1(b)] or a method to test the switch in-situ with the actual process medium [consistent with
principle 4.1.1 (a)].
One end-user provided an example involving a toluene tank analogue level and high level trip.
Here, the end-user employs a flange-mounted capacitance probe with dual redundant high level
switches, allowing testing on line. They would proceed as follows:
1)

Remove, inspect & operate high level switch to verify operation [inconsistent with
principles 4.2.1 (d) and 4.1.1 (a)];

2)

Use software override facility to over-ride the trip off the analogue signal;

3)

Fill tank until level switch trips the feed flow [inconsistent with principle 4.1.1 (a)];

4)

Check the calibration of the analogue instrument at this datum point.

In future, they hope to use a low-level, physical dip of the tank to confirm the zero calibration
[consistent with principle 4.1.1 (b)].
Discussions with another end-user identified the following approach. The method of testing
varies depending on measurement technique. If the system uses a DP arrangement, this is
treated as if it was a pressure installation and differential pressure injected at the cell to simulate
the level. In other cases, they adjust the process level to the trip point if this can be done safely
[consistent with principle 4.1.1 (a)], or remove and test the initiator in a container [inconsistent
with principles 4.1.1 (a) and 4.2.1 (d)], for certain high level devices, where possible. For
SMART devices they rely on the nature of the device to simulate the trip condition, via a hand
held communicator, together with a functionality check. With devices such as radar, it is
becoming increasingly difficult to carry out a total fundamental test. End-users are becoming
increasingly reliant on the SMART nature of devices to test the output stages of electronics.
They then assume that if the input stage is working at the current level, it will still work at the
trip point [inconsistent with principles 4.1.1 (a), 4.1.1 (b) and 4.2.1 (a)].
One end-user devised a method to test a stock tank trip system as follows. The old system
would involve draining and decontamination of the tank and disposal of the effluent, breaking
of pipe-work under mask and suit conditions and draining and refilling of the system several
times during testing which was very time consuming. The method was improved based on past
operating data [consistent with principle 4.5.1 (b)] to coincide with offloading of a railcar into
the stock tank from a routinely calibrated weighbridge, tripping the transfer system in anger
using the weighbridge for comparison. Although the SIS may be in a demand mode, the weight
measurement is used as a control measure [consistent with principle 4.1.1 (a)], however, it relies
on the weight measurement providing an accurate representation of level. For other installations,
pad cells are used and, similar to pressure measurements on systems containing toxic material,
the trip values are simulated by injecting a current signal or using the SMART functionality of
the transmitter to drive the output to the trip value [inconsistent with principle 4.2.1 (a)]. On

some stock tanks, a dip-pipe, coupled with a fluidic logic system is used. Here, a mini dip-pipe
and valve system has been installed locally to the fluidics which allows the system to be tested
with a portable container of water, as the fluidic system only needs a few inches water gauge to
operate [consistent with principle 4.1.1 (a)]. Where a dip-pipe measurement is used on a nontoxic system with a DP cell, the cell is pressure-injected using suitably calibrated test
equipment. Although it is realised that this is not testing the dip-pipe, confidence is gained by
having duplicate measurement systems on the vessel [consistent with principle 4.1.1 (b)].
An incident with a trip on a pumped liquor supply to a filter was reported by an end-user. When
the level in the filter reached a certain point, the logic solver would close a valve in the supply
line. On this occasion, the valve did not close and the level overflowed out of the filter. On
further investigation, it was found that the seats of the trip valve had been contaminated with the
product, which had solidified and jammed the valve open [failure to detect this situation implies
failure to adopt principle 4.2.1 (a)]. As this could well occur again on similar installations at the
same site, it was decided to modify the system by tripping the pump as well when a high level
was detected. Eight filters were modified in this way to prevent any reoccurrence [without
careful consideration of the functional safety requirements, the potential exists to violate
principle 4.1.1 (d)].
The following example of proof testing using the process fluid was encountered [consistent with
principle 4.1.1 (a)]. As shown in Figure 2, it involves the addition of a pocket around the level
probe and is suitable for some types of capacitance and conductivity probe when used for high
level trips. The pocket has a hole beneath the probe, which allows the process fluid to enter the
pocket when the level in the vessel rises. There is a breather hole in the side of the pocket to
allow vapour in the pocket to escape.
LT1

Figure 2 : An example of a level SIS


proof testing arrangement
The line connected to valve A comes from a pump that is used to transfer process fluid into the
reactor vessel. For trip testing, the normal process valve into the vessel (not shown) remains
closed and valve A is opened. This allows process fluid to enter the pocket around the level
sensor.

The sizing of the holes in the pocket and the sizing of the pipe through valve A is such that the
flow rate through valve A is greater that the flow rate through the hole in the bottom of the
pocket. This means that the pocket fills with process fluid and activates the level trip. On
closing valve A, the process fluid in the pocket drains into the reactor and the trip can be reset.
The hole in the side of the pocket is designed to take the full flow through valve A so that no
pressure build-up occurs in the pocket.

The quantity of process fluid entering the reactor for testing can be measured and then used as
part of the normal batch processing, or possibly returned to interim storage for re-use. Testing is
carried out at any suitable point in the batch cycle.
Testing Temperature Loops
The manipulation of process temperatures is not often practicable due to the time it would take
to raise or lower the temperature to the trip value and due to the high temperatures encountered
in chemical processes. A common approach is to remove resistance thermometers or
thermocouples from their pockets and place them in a calibrated bath or block to simulate the
trip point temperature without removing them from the area. Again, this is not always
practicable due to equipment being located in hazardous areas or operating temperatures being
too high.
One organisation removes the elements from the pocket and does just this. They recognise that
with head mounted transmitters it is more difficult to do this [lack of consideration of testing
requirements at the design phase leads to potential inconsistency with principle 4.2.1 (a)]. If the
measurement device is located in a potentially explosive atmosphere, then removal or exposure
of equipment may generate a source of ignition. They also have experience of temperature
elements being too short for their pockets, which could give an artificially low temperature
measurement. This would not be picked up by usual forms of testing, other than a physical
inspection of the element and comparison of its length with the depth of the pocket [inconsistent
with principle 4.2.1 (d), however, adverse consequences would be addressed by comparison of
the element and pocket lengths].
Another organisation operates in a similar way. Testing is generally done on-line by removing
the element from its pocket and inserting it in a bath at a suitable temperature, however, this
cannot be done on all installations. Alternative methods include disconnecting the element and
connecting a decade resistance box or voltage source to drive the input to the trip point.
Alternatively, they would rely on a SMART transmitter to drive itself to the trip point
[inconsistent with principles 4.1.1 (a) and 4.2.1 (a)].
In another example, whether it is a live test or shutdown test, the end-user connects a decade
box to the head of a 3-wire RTD probe. They realise that there may be a problem with pocket
sensitivity and that this method does not test the pocket/probe interface and that they should
check the response and calibration of the system [currently inconsistent with principle 4.1.1
(d)].
An end-user ensures that all temperature probes are mounted in pockets with breakaway
couplings. To test a loop, the process control is placed in to manual mode, the probe is removed
and a measurement of resistance or voltage at ambient temperature is checked against a
standard. This suggests that the control sensor is also being used for trip duty. The logic solver
is tested, by injecting a signal equivalent to the trip point. There is no duplicate system installed
and it is recognised that they are running blind whilst this is ongoing, so plan to install
duplicate and comparison units.
An example of the testing of a process gas heater was provided. Elements installed in pockets
are tested on-line, as they form part of triple redundant systems with 2 out of 3 voting. They use
a thermocouple / PT100 simulator from the connection at the head, and check for ingress,
integrity and connection security. When on line, they check for differences in readings between
the three instruments to detect drift. To improve confidence and reliability, they would like to
change the thermocouples regularly in addition to simulation, and check contact with the end of
the pocket.
A further end-user's normal on-line test is to inject a current, voltage or resistance signal to
simulate temperature and so test the operation of the safety system. The signal can be injected
on some types of probes in front of the electronics and so only the sensing element is not tested.
On some other probes the signal is injected after the electronics, particularly where the

10

transmitter is built-in to the probe, and hence the probe will not be included in the test [lack of
consideration of testing requirements at the design phase leads to inconsistency with principle
4.2.1 (a)]. The probe can be compared to another temperature probe in the same line as a
method of testing the response of the primary element. However, common mode failure may be
an issue where both probes could suffer from coating, contamination or environmental
conditions.
An example provided by another organisation involves the use of a pyrometer installation to
measure the temperature of a converter bed, the normal operating temperature of which is
greater than 900oC. There is no practicable means of recreating operating conditions in a test
situation and testing in anger could be hazardous, so testing is done by injecting a current signal
into the trip amplifier of the SIS. There are two temperatures on the bed, so confidence in the
measurement is provided by comparison. Periodically, a hand-held optical pyrometer is used
through an inspection glass to confirm the temperature of the bed corresponds with the
measurement [consistent with principle 4.1.1 (b)].
The measurement of temperature in the remainder of the plant is carried out using RTD probes
mounted in pockets. Approximately 50% of these have the transmitter separate to the probe, so
a resistance box can be connected to the transmitter and the corresponding resistance value to
the trip point simulated. Where a transmitter is built into the head, a current signal is injected at
a suitable point. It is realised that these test modes do not test the sensing element [lack of
consideration of testing requirements at the design phase leads to inconsistency with principle
4.2.1 (a)], so on critical duties the probe would be removed, tested and calibrated on a regular
basis. There is significant confidence in the measurements, as duplicate or other measurements
slightly downstream accompany many systems.
An alternative approach to reliability was reported by another end-user. During shutdowns the
elements are replaced on a regular basis with new ones and the old ones tested in batches for reuse at a later date [inconsistent with principles 4.1.1 (a) and 4.2.1 (d)].
The following example of temperature measurement shows how the process fluid can be used
for the test.
Figure 3 shows a batch reactor. There are three process materials used for the reaction. It is
during the reaction with all three present that there is potential for a reaction runaway. There is a
high temperature trip using the sensor TT1. Independent temperature sensors are used for
control.
The proof test procedure for this reactor was designed around the use of only one the liquids
normally added to the reactor, thereby removing the risk of reaction. Following completion of
the test, the plant operators could then add the other materials and produce a batch of product.
There are two benefits from this. One is that the trip is tested from the process fluid right
through to the actuator [consistent with principles 4.1.1 (a) and 4.2.1 (a)]. The second is that no
additional fluid is introduced into the reactor for the test and the fluid used for the test can be
used to make product. However, there is a need to include a contribution for human error into
the likelihood for a runaway in the reactor [principle 4.7.1 (a)].
One example of where errors can occur is illustrated in the following example. It is common
practice to replace faulty SMART transmitters by uploading the faulty transmitter configuration
to a hand held device and downloading it to a replacement spare unit. With a certain make of
transmitter, this overwrites everything but the burnout direction. One end-user had around ten of
these transmitters which had incorrect burnout directions because of this feature. Where this
method is used for any transmitter, it is recommended to check all the parameters in the
replacement before re-commissioning.

11

TT1

Figure 3 : An example of a temperature SIS


proof testing arrangement
Testing Flow Loops
Flows under control are usually critical to the process, therefore it is not often feasible to
manipulate them for the purposes of proof testing, however, there can be exceptions.
One end-user echoed this, reiterating that it is inherently difficult to test in-line flowmeters
using the process fluid due to upset of process conditions. They invariably inject a signal into
the electronics to simulate a trip condition and test the safety function, but realise that this does
not test the wetted end of the sensor [principle 4.2.1 (a)]. This holds true both for on-line and
off-line testing.
Another end-user confirmed this, reporting that it is difficult to test or calibrate an in-line
flowmeter whilst it is still installed in the line. The usual method of proof testing would be to
inject a signal to simulate the flow measurement and so test the rest of the safety function as in
the previous example. This, however, does not prove that the flowmeter is working correctly or
is accurate [inconsistent with principle 4.2.1 (a)]. The flowmeter can be taken out of the line and
tested on a proven flowmeter test rig but this usually requires a shut down. Another method is to
use the flowmeter to fill a calibrated tank or compare it with another flowmeter, but any
differences in density of the test fluid and actual operational fluid has to be taken into account.
If the SIS is based on a simple DP cell and orifice plate installation, the most common approach
is to inject a differential pressure signal, simulating the flow, into the cell, however, this does
not test the impulse lines and isolation or equalisation valves for possible blockage [inconsistent
with principle 4.2.1 (a)]. The end-user providing this example would expect blockage to
become apparent during normal operation by manifesting itself in an obviously incorrect
reading. Regular maintenance and calibration of the sensor instrumentation gives the end-user
confidence in the reading from the instrument [consistent with principle 4.1.1 (b)].
One end-user recounted an incident when a flow switch on a scrubber vent system was changed
for a device designed to give a remote indication of the flow. The reason for the change was that
the previous flow switch was very unreliable. The new instrument worked too well, as there
was a small period (which was not realised in the HAZOP) in the scrubbers cycle when the
system had no flow and the previous switch did not detect this. Every time the cycle got to this
12

point, the reactor associated with the scrubber system would trip. On further investigation this
was revealed and the trip system was moved to the fan shaft by means of a proximity switch to
prevent this happening, and the flow measurement was returned to a measurement duty only.
This modification is being extended to another seven similar systems.
One end-user declared that all their flows are tested by simulation, via either the electronics or
injecting current signals [inconsistent with principle 4.2.1 (a)]. In some instances, when
conditions allow, a calibrated, in-line, portable flowmeter is installed to give confidence in the
accuracy of the measurement [consistent with principle 4.1.1 (b)].
An example was given by one end-user of a stabiliser addition system, where the flow is only a
matter of litres per minute. These can be tested on-line as there would be minimal process upset.
Trips on pump seal systems are never tested in anger but are always simulated to prevent
damage to the equipment. For other flow trip system measurements, such as electromagnetic
and vortex shedding flowmeters, it was estimated by this end-user that 95% of these are
simulated by either using the electronics (30%) to simulate the trip signal or injecting a current
signal (65%) at a suitable point. Only 5% of systems are tested by manipulating the process
variable. This is due mainly to the difficulty of testing this type of instrumentation [inconsistent
with principle 4.1.1 (a)].
For more complex flow installations employing such devices as electromagnetic, vortex
shedding and coriolis flowmeters, the measurements are generally duplicated by diverse
measurements in series for comparison [consistent with principle 4.1.1 (b)]. Current injection or
the outputs of SMART devices are then used to test the logic solver. The end-user reiterated an
important point that the equalising and isolation valves of DP systems must be returned to their
original positions when reinstating [principle 4.2.1 (f)].
Discussion with another end-user centred on a DP installation. This was again treated as if it
were a pressure installation. Vortex shedding and electromagnetic flowmeters are tested by
using the test facility of the device or by injecting a current signal at the flowmeter output
[inconsistent with principle 4.2.1 (a)]. The end-user does, however, recognise that this is not a
complete test.
On a hydrogen flow to a hydrochloric acid burner, the process connection is a one inch Annubar
tube. Due to the nature of the process, the Annubar and DP devices, and temperature and
pressure transmitters are removed and all equipment sent to the manufacturer for verification
and calibration [inconsistent with principle 4.2.1 (d)]. The safety system is then tested by
simulation of the current signal. This end-user pointed out that the system is old and the
reliability of the computation equipment needs to be reviewed and probably eventually replaced.
Another end-user example concerned a heat-exchanger associated with a reactor shell coolingwater installation which employs dual redundant in-line electromagnetic flowmeters. During an
on-line test they use the software override facility and monitor alternative instruments. To verify
the measurement they use the comparison between these instruments. They also check that the
outlet temperature is of the correct order for the cooling water flow [consistent with principle
4.1.1 (b)]. They would like to improve the installation by including a positive displacement
totaliser. They consider that removing and checking the meter on a test rig would increase
reliability, however, a bypass would be needed and is considered uneconomic at the moment.
The findings of another end-user were that the calibration of in-line flowmeters relies upon the
correct operation of their electronics, so they prefer to inject a current with the HART protocol
removed. They recognise the reliability of HART, and the stigma associated with the corruption
of electronic instruments. They find that this gives them an increase in reliability and confidence
in the measurement.

13

Others (e.g. pH, density, speed etc.)


The majority of end-users did not provide examples of analysis instrumentation used on trip
duties. Most felt that a lot of the instrumentation was not reliable enough for this purpose and
only went down this route as a last resort. Of the few who did, there are examples below.
On one end-user's flare stack, on-line testing of analysers is possible due to dual redundancy.
They use calibrated test gases injected into the sample impulse lines at a point near the
analysers. The sample lines are proved by small flowmeters, used to set the sample flow-rate
and alarm and trip on sample flow failure [consistent with principles 4.1.1 (a) and 4.2.1 (a)].
On pH control of a brine solution, the electrode system is situated in a bypass line. To test the
system, the process control is placed in manual and the meter is buffer checked to test the trip
and alarm points. The end-user recognises the shortcomings of the system and has recently
installed a duplicate system using HART diagnostics to improve the loop reliability and made it
a two out of two trip system.
Another end-user employed such a two out of two pH system on a bottoms analyser. This
system is critical to product quality as product de-colouring or polymerisation can occur if the
pH is not within tolerance. The system is calibrated every week using buffer solutions and the
trip (final product to storage) is proof tested every three months using buffer solutions. The two
out of two system gives confidence that the system will not trip if the electrodes become
unserviceable on one of the installations.
Testing Actuators (Valves and Motors)
There was a wide and varied approach to the way that valves were tested. Some were not tested
at all, some were only partially tested and, in most cases, only significantly tested during a plant
shutdown. The most satisfactory way to test a final element is to check that it has the desired
effect on the process under operating conditions. This is not always considered practicable due
to the potential for process upset or shutdown. Some end-users indicated that they would use
plant shutdowns or outages to test selected systems on a rotational basis [potentially inconsistent
with principle 4.4.1 (b)]. Such an activity would require planning to avoid unnecessary
disruption of production and consequential damage to equipment.
During discussions, one end-user indicated that they tested trip valves on-line by blocking the
solenoid vent with a pressure gauge and operating the valve. This caused the valve to move
slightly and also gave an indication on the pressure gauge of solenoid operation [inconsistent
with principle 4.2.1 (a) if this is the only proof test of the valve]. This system was thought to
work well though the installation and subsequent removal of the gauge would need to be very
carefully controlled [principle 4.2.1 (f)].
One end-user stated that they need a valve to shut-off tightly within five seconds. The nature of
the process is that this could not be tested on-line, so it was tested during a shutdown. Although
they understood that this was not testing the valve under process conditions, it was as close as
they could practicably get without tripping the plant every time a test was scheduled
[inconsistent with principles 4.1.1 (a), 4.1.1 (d) and 4.4.1 (b)].
One end-user carried out a real test on critical shutdown valves on a rotational basis by actually
tripping the plant. The philosophy used when the plants are on-line is to have multiple input test
routines, then test the valve with one of these inputs on a rotational basis, when the process or
plant conditions allow [potentially inconsistent with principle 4.4.1 (b)]. They hope to improve
valve diagnostics by adding valve position feedback in the future.
The most general approach was to test valves off-line for many of the reasons stated above. One
end-user does not close or open shutdown valves during on-line testing. These would be tested
with a bypass in operation. During a planned shutdown, a full test is carried out, including the
operation of the associated valves. This off-line testing has the disadvantage that the valve is not

14

being tested under operating conditions, however, this is seen by the end-user as the limit of
practicability [inconsistent with principle 4.1.1 (a)].
Another end-user contended that valves can often only be tested when the plant is being shut
down or actually shut down. Tests are generally limited to tripping the valve and observing that
it moves to the open or closed position. They realise that they can only carry out limited checks
on the effect on flows through the valve if there is no bypass. It is rarely possible to check that a
tight shutoff has actually been achieved [inconsistent with principle 4.1.1 (d)]. An exception to
this could be a pressure-proving scheme around gas valves on burners. To improve the test
philosophy, the use of SMART positioners to confirm that valves actually close (via travel and
torque feedback) is being considered. The same end-user (this was echoed by two other endusers) believed that it is not always necessary to overhaul valves, suggesting that this could be
an expensive and often pointless rebuild which might result in a badly rebuilt, faulty valve
going back into service. They think a better technique to use is to remove the valve from the
plant, carry out a visual inspection, leak test, function-test and then flow scan the valve when it
is back in-situ [consistent with principles 4.1.1 (b) and, potentially, 4.1.1 (a) but potentially
inconsistent with principle 4.2.1 (d)].
One end-user admitted that their valves were not tested and that this would be their main area
for improvement [principle 4.2.1 (a)]. They plan to establish a log that will automatically log
the operation and travel times of key shutdown valves via open and closed limit switches during
both routine and non-routine shutdowns. They will also begin routine visual inspection and
maintenance to assist improvements in reliability.
One end-user's approach is to trip the valve from the initiator and record the closure time, check
the leakage rate using downstream instrumentation, then overhaul any valves showing
unsatisfactory results during a shutdown [consistent with principles 4.1.1 (a) and 4.1.1 (d)].
This is one of the most comprehensive tests that were discussed during all of the interviews but
they are fortunate that they have a process that allows this.
One end-user prefers to overhaul and test their critical valves on a regular basis [inconsistent
with principles 4.1.1 (a) and 4.2.1 (d)]. They say that this does give them the confidence in the
safety loop function when combined with on-line input testing.
An example was provided for a chlorine gas system. A trip demands a shut-off seal, but this
installation uses a conventional control valve for this function at present and the process needs
to be off line in order to test it, however, tight shut-off cannot be verified under test conditions
[inconsistent with principle 4.1.1 (d)]. To improve this they are going to install a dedicated
shutdown valve to provide tight shut-off and employ a partial stroke testing facility to enhance
its reliability.
Another example was provided for a natural gas system. An emergency gas injection system to
the process must provide gas, via a double block and bleed arrangement, when demanded.
Testing of the system is carried out by performing gas injection on the live process. The
technician tests the system and position switches are used to confirm valve operation. The test
could be improved by including a visual inspection of the valve position, although this would
make it a two-man operation [consistent with principle 4.2.1 (a)].
With periods between plant shutdowns being extended, emergency shutdown valves (ESDV)
may remain in the open position, without movement, for lengthy periods. Experience has shown
that after extended periods without movement, there is a tendency for the valve to stick. This
would result in the shutdown system failing to operate in the event of a genuine demand on the
shutdown system, despite all other tests on the system being completed satisfactorily. A
manufacturer of valve equipment contended that the application of Smart Valve Monitoring
(SVM) can monitor the ESDV for faults based on comparing an original full closure fingerprint
of the ESDV assembly and components, such as solenoid valves, against a partial stroke test.
Their system can perform all tests at the ESDV designed closure speed without shutting the
plant down. It can also include tests for connectivity between itself and a Safety PLC and claims

15

a 95% diagnostic coverage factor. In some cases, due to the speed of the test, full closure of the
ESDV may be possible, resulting in a claimed 99% diagnostic coverage factor. The regular use
of the partial test, in combination with other system tests will help to ensure that the ESDV will
move when it is required, and that the ESD system is maintained in a fully operative state.
These tests can be initiated and monitored by remote signals from the likes of a DCS or SCADA
system. The use of such technology is being piloted by a major end-user at the moment and they
hope to derive benefits form this. It is hoped that benefits will include the reduction of
maintenance costs due to less frequent overhaul, reduction of spurious shutdowns due to
malfunction or equipment failure, or even inadvertent inhibition of the ESD signal for long
periods.
In the case of motors and drives it is most common practice to trip the drive from the initiator
and check that the motor stops and that any secondary trips are operated. In general, it seems to
be more acceptable to trip an on-line machine, reset the system and then restart the machine,
than to trip then re-open a valve. These seem to be similar concepts, unless the consequence of
tripping a valve has a more serious effect on the process. Where a motor is tripped by a SIS, it is
generally done under process conditions when possible. If it is not, the off-line test consists of
removing the fuses, but leaving the control fuse in place and watching the contactor operate.
4.1.4

Conclusions and Recommendations

Approaches to the proof testing of "wetted end" components are common, however the rigour
varies. Amongst others, common approaches are:

manipulation of process variables;

pressure injection;

current, voltage and resistance simulation;

use of SMART features;

comparison with alternative measurements;

valve closure;

inspection and overhaul.

Items that pose particular testing difficulties are valves and in-line flowmeters. The sealing
capabilities of valves under operating conditions are rarely tested due primarily to the impact on
process operation. Whilst it is the case that some processes may present significant risk during
shutdown and start-up it is also the case that SIS should provide the specified safety functions
with the specified integrity. Proof testing is an integral part of the demonstration of function and
integrity and must therefore be given the attention which it deserves, however, where proof
testing is likely to prove difficult then the design phase of SIS should seek to provide the
specified functions and integrity in a manner which accommodates these difficulties. It is during
the design phase of a chemical process that consideration should be given to the facilities that
will be required to ensure the specified integrity of valves without necessarily demanding
process shutdown. Consideration should therefore be given to specifying valve features that
reduce the probability of malfunction and seat failure or to the targetted use of the proven
capabilities of SMART positioners.
In-line flowmeters present little opportunity to apply proof tests that realistically manipulate the
process variable. Differential pressure systems allow process variable simulation but introduce
additional process connections and the potential for loss of containment or process
contamination. The use of alternative or portable measurements to corroborate in-line flow
measurements should be considered, particularly during the design phase of SIS. An interesting
statistic provided by an end-user was that only 5% of flow systems are tested by manipulating
the process variable. This is a subjective figure, however, it suggests that "wetted-end" testing
of flow SIS may not be particularly rigorous.
16

The simulation of process variables and process conditions was common and is a necessity in
cases where the risk associated with manipulation of process variables is not considered to be
acceptable. Good practice in the application of simulation techniques would involve the
comparison of sensor outputs with alternative process measurements, preferably diverse, to
corroborate the measured value.
The use of SMART devices during proof testing should be treated with caution. The generation
of current signals by digital electronics is no substitute for the testing of an instrument's ability
to accurately measure a process variable. The use of such simulation should be accompanied by
corroboration of the sensor reading unless sufficient diagnostic coverage can be demonstrated.
4.2

CONTENT OF PROOF TEST PROCEDURES

4.2.1

Statements of Guiding Principles

Purpose and Scope of Proof Testing


(a) Proof testing should be designed to expose any reasonably foreseeable unrevealed fail-todanger fault conditions in all components including process sensors, logic solvers and final
elements, and in the means of connecting the SIS to the process.
Overrides
(b) Where overrides are applied to SIS, they should be subject to strict controls to ensure their
safe application and timely removal.
Partial Testing
(c) Where the partial testing of SIS or components of SIS is adopted, the impact on process
operation, functional safety and overall test coverage should be established by assessment
and additional controls should be applied where necessary.
System State on Trip Initiation
(d) SIS installations should be tested as found and should not be disturbed during proof testing.
Calibration
(e) All test equipment used for proof testing SIS should be calibrated and the calibration should
be traceable to recognised national standards.
(f) SIS should be returned to their as-found state following testing and any necessary repair.
4.2.2

Rationale

Proof testing forms part of the routine actions that are required to maintain the required
functional safety (as designed) of SIS. Their purpose is to reveal dangerous faults that would
otherwise remain unrevealed and adversely affect the integrity of the SIS. Proof tests are
executed using written test procedures, the content and accuracy of which govern the
effectiveness of the test. The content of procedures addresses many issues, defining the scope of
the testing, the test equipment to be used and the procedural controls to be adopted. Test
procedures must also remain accurate throughout the lifecycle of SIS, particularly where change
is encountered. The procedures communicate the required actions to the tester and should do so
in a manner that takes account of human factors and seeks to minimises the risk of error and
violation.

17

ANSI/ISA-S84.01-19962, the EEMUA Alarm Guide3 and Kletz4 provide published guidance on
the scope and content of proof tests. Guidance on human factors is provided by references 5 and
6.
4.2.3

Research Data

The research revealed that industry is aware of the attributes of effective proof testing, although
its implementation is variable. The research further suggested that consideration of the content
of a proof test procedure tends to be dominated by the following issues:

scope and coverage of the proof test;

overrides;

partial testing;

trip initiation during testing;

calibration of test equipment;

the use of diagnostic facilities.

Scope and Coverage of the Proof Test


There was a unanimous view from interviews and workshops that proof tests should test all
components of SIS, including the process measurement, the logic solver and the actuating
device or "final element". Additionally, one end user workshop emphasised that the connection
to the process in the form of impulse lines, orifice plates and dip pipes was vitally important as
were services to the SIS, such as power, air and bubble gases, and external influences such as
lagging, trace heating and environmental conditions. All interviewees reported executing "endto-end" testing although one interviewee and one end user workshop reported difficulties with
ageing and inherited systems, particularly where existing pipework arrangements were
considered to preclude complete testing. The example procedures obtained during the research
indicated examples of measurement simulation, such as current injection, rather than true
process measurement.
All interviewees initially reported little difficulty in testing measuring elements and logic solver
inputs, referred to by the supplier workshop as the "wetted end", although none reported
explicitly inspecting the physical condition of process connections even though both end user
workshops and one interviewee highlighted their importance. Further interviews and
questionnaires revealed that difficulties were, in fact, encountered. One interviewee reported
difficulties in achieving complete coverage of ageing or inherited systems, being able to test the
field devices only [inconsistent with principle 4.2.1 (a)]. A batch operator reported difficulty in
testing "inter-unit" trips where a number of production units would have to be aligned
[inconsistent with principle 4.1.1 (a)]. An end user workshop reported that the majority of
problems relate to impulse lines clogging but left an open question on how to test for these
occasions. A workshop also stated that functional performance, such as the response of
transmitters and the travel time of valves, should be tested.
The testing of the final element attracted much comment during all interviews and workshops.
There was a clear division between operators of continuous processes and operators of batch or
campaign processes. In general, continuous process operators perceived a conflict between the
desire for high plant availability and the testing of final elements whilst batch process operators
were generally able to take advantage of inter-batch downtime. Two interviewees reported the
examination and testing of valves under workshop conditions, however, the supplier workshop
commented that valves should be tested under process conditions [consistent with principles
4.1.1 (a) and 4.2.1 (d)]. Notwithstanding the impact on plant availability, there was general
acceptance that the final element is the least reliable component of a SIS and demands robust
testing.

18

The research indicated a preference for on-line testing amongst the continuous plant operators
and support for this approach from the supplier workshop. This is not a surprising situation as
manufacturing organisations seek to minimise plant downtime and suppliers seek to develop
and market technologies that aim to satisfy this desire. It is also the case that start-up and
shutdown tend to be the most hazardous periods of plant operation. Within the continuous
industries, the general pattern of proof testing involves the on-line testing of measuring and
initiating devices complemented by full "end-to-end" testing during maintenance activities,
however, two interviewees reported the use of duplicate valves and manual bypass
arrangements to allow full on-line testing [consistent with principle 4.1.1 (a)]. Of those two, one
interviewee reported that the provision of full on-line test facilities allowing operation of the
final element without process interruption is a recently adopted standard. Again, batch operators
reported taking advantage of inter-batch downtime.
ANSI/ISA-S84.01-19962 and the EEMUA Alarm Guide3 provide comprehensive guidance on
the coverage of proof testing.
Overrides
The subject of overrides and bypasses was an integral part of the consideration of coverage yet
generated sufficient discussion to warrant consideration in its own right. The need for overrides
and bypasses was unanimously reported as arising from a wish to carry out routine testing
without adversely affecting production. Nine interviewees specifically reported the use of
override or bypass facilities with only one reporting no bypasses being used on shutdown
systems. Of the nine, seven reported that input overrides are provided as a matter of course
whilst two emphasised that overrides are the exception to the rule. Two interviewees in the
refining and petrochemical sectors reported the use of process bypasses for final element testing
under strictly controlled conditions [consistent with principle 4.2.1 (b)]. An instance of the use
of overrides was reported by a batch operator, indicating that the use of overrides is not
restricted to continuous processes. One example encountered involved the use of duplicate
valves or valve trains whilst another involved the use of manual bypass valves around trip
valves, controlled by the use of Castell key systems. One interviewee from the chemical
industry reported that the provision of process bypasses is not deemed to be cost effective. One
interviewee reported tests on two-out-of-three systems being carried out without overrides. The
supplier workshop suggested that overrides should be designed out and one interviewee
explicitly stated that the emphasis is to design systems to allow testing without overrides.
Overrides were highlighted as an area of concern by all workshops and the need for strict
controls to ensure their safe application and timely removal was unanimously stressed. Typical
controls reported were management authorisation, alarm generation, continuous indication and
the continued functioning of process alarms during the override period. Override switches were
unanimously reported as being key-operated and manual process bypasses were reported as
being subject to mechanical interlocks. Valve jamming / clamping and pneumatic solenoid
bypass arrangements were also reported as a means of override. Management procedures for the
control of overrides and bypasses were stressed by three of the interviewees. One interviewee
reported that bypass authorisation requires the signature of the Site Director and is valid for a
twenty-four hour period. Another interviewee reported the adoption of two classes of override
based on risk and vulnerability with the higher risk overrides requiring the dual authorisation of
both Shift and Operations Management. The same interviewee reported the use of unique keys
for each override to which access is strictly controlled.
Both end user workshops stated that overrides should be time-dependent, with one interviewee
reporting that overrides associated with a DCS will accommodate a re-alarm function after six
hours to ensure that they are not overlooked [consistent with principle 4.2.1 (b)]. One end user
workshop and one interviewee stressed that process alarm functionality is maintained
throughout override periods. An end user workshop reported that the application of overrides is

19

reviewed and that copies of override records are displayed in the control room for daily review
[consistent with principle 4.2.1 (b)].
Partial Testing
In the context of this research, the partial testing of SIS describes two situations; the testing of
system components at different times and frequencies or the testing of sub-sets of functions of
single components.
Whilst the need for complete testing of all components of safety-related systems was
unanimously supported it was equally unanimously recognised that production pressures,
particularly associated with continuous processes, significantly affect the ability to carry out
such tests in their entirety at the appropriate frequencies [inconsistent with principle 4.4.1 (b)].
The research found that it is common practice amongst continuous operators to use overrides to
allow the on-line testing of measuring and initiating devices and to schedule the testing of logic
solvers and final elements to coincide with production outages. Only two interviewees reported
routinely testing final elements in-line.
Providing less agreement was the partial testing of individual components. The discussions
concentrated on valves, although the shortcomings of injection testing of sensors was stressed
by one interviewee citing an example of a proof test procedure which specifies the use of
thermocouple simulators, arguably a partial test. All workshops raised the issue of partial
operation of valves. The supplier workshop questioned the usefulness of partial closure tests and
commented that partial stroke testing with feedback is of limited use but that the deployment of
effective intelligent diagnostic facilities could improve the usefulness of the information
gathered. One end user workshop suggested that process constraints dictate that certain valves
can only be operated through a small range of their travel and commented that risk assessment
is necessary to establish the impact on process operation, however, concern was raised that
similarly rigorous risk assessment might not be applied to the impact on functional safety. The
other end user workshop recognised the option of partially operating valves but stressed that
valves can fail to seal, particularly in harsh environments, and cited an example of pebbles
being found on inspection. Recognising this possibility, one interviewee reported leak testing all
safety-related valves on a two to eight year basis [consistent with principle 4.1.1 (a) but
potentially inconsistent with principle 4.4.1 (b)]. One interviewee reported limiting the opening
travel of a ball valve during testing to avoid breaking of the seal. This was due to asset and
environmental issues and was risk assessed.
The partial stroking of safety block valves has been examined in an article by Angela Summers
and Bryan Zachary7 which proposes that failure mode and effects analysis (FMEA) and data
from the Offshore Reliability Data (OREDA) Handbook8 can be used to demonstrate that the
maximum percentage of failures which can be detected by a partial stroke test is 70%. The
FMEA and reliability data must be applicable to specific SIS, however, the article demonstrates
an objective approach to partial testing.
Trip Initiation
The issue of appropriate methods of initiating SIS emerged as a common theme throughout the
research. Both end user workshops and three interviewees specifically highlighted the need to
ensure that the initiation of safety-related systems under test should be consistent with
operational conditions.
Initiation by driving the process variable to its demand condition clearly provides the most
accurate evaluation of the SIS and two interviewees reported striving for this situation. The
EEMUA Alarm Guide3 recommends driving the alarmed process variable into the alarmed state,
however, this does not imply that the process itself should be driven into a hazardous state. If
processes are driven into potentially hazardous states and SIS do not operate as expected, there
is a real possibility that hazardous situations may arise, indeed an end user workshop cited two

20

examples of organisations being criticised by the HSE for raising vessel levels in order to test
trips.
The use of simulation techniques was reported by an end user workshop and the use of
thermocouple simulation was evident in an example proof test procedure. One interviewee
reported investigating the use of equipment suppliers' own in-built test capabilities for some
sensors, such as RF admittance level probes, in order to initiate SIS on-line without driving the
process variable to the demand condition. The use of alternative process fluids was raised by a
workshop, however, one interviewee suggested that adopting this approach over using the actual
process fluid must be justified [consistent with principle 4.1.1 (a)].
An end user workshop commented that proof testing can disturb equipment such as temperature
sensors and questioned whether installations should be tested as found. SIS should indeed be
proof tested as found in order that any fault conditions are recognised and installations are not
unnecessarily disturbed. To further illustrate this point, Kletz4 describes a situation where a trip
was removed from its case before testing but when it was required to operate in anger, a pointer
fouled the case and could not move freely [the incident illustrates inconsistency with principle
4.2.1 (d)].
Calibration
Six interviewees representing all industrial sectors explicitly stated that all test equipment is
calibrated and that the calibration is traceable to national standards. The necessity for traceable
calibration was supported by all workshops.
Diagnostics and Diagnostic Coverage
Three interviewees reported interest in the application of intelligent diagnostic facilities and inbuilt test facilities, with two interviewees trialling such facilities with a view to improving
production availability. Both end user workshops perceived benefit from the use of diagnostics,
but both cited reluctance to implement such technologies. One workshop reported confusion
over the relationship between diagnostic coverage and proof testing whilst the other reported
difficulty in obtaining diagnostic coverage data from suppliers. Not surprisingly, the supplier
workshop proposed benefits from the use of intelligent diagnostics.
It is not the intention of this research to provide a detailed examination of diagnostic coverage.
However, it is useful to reiterate that the purpose of proof testing is to detect unrevealed faults at
the time of testing whilst diagnostic coverage allows the detection and remediation of fail-todanger fault conditions between proof tests. The perceived benefit for industry is that the
application of diagnostic techniques where none previously existed has the potential to decrease
the proof test frequency and the scale of routine testing, however, it does not necessarily render
components any more reliable.
4.2.4

Conclusions and Recommendations

Scope and Coverage of the Proof Test


The research suggests that the achievement of complete proof test coverage of SIS is a
unanimous desire of the chemical industry but that there is some recognition that it is not being
fully realised. The process connection is an integral component of a SIS and may possess
dangerous failure modes, often attributable to blockage or deposition, which could cause the SIS
to fail on demand. Such failure modes should be detectable by proof tests. Nevertheless, there is
strong evidence that comprehensive "end-to-end" testing is practicable and is being undertaken.
With respect to proof test coverage, the following recommendations are made:

proof testing should test all components of SIS which could lead fail-to-danger
conditions;
21

proof test procedures should address the condition of process connections, particularly
impulse lines;

proof test procedures should address the condition of any necessary services such as
power, instrument air, gas supplies, trace heating etc.

Overrides
Overrides of SIS in the form of input overrides or final element bypasses are common in the
chemical industry. Interviews and workshops suggested that considerable care is taken over the
use of overrides and, whilst there is considerable pressure to maintain production during proof
testing, there is recognition that the inappropriate application of overrides can render SIS
inoperative. There is evidence that overrides are being avoided where practicable, for example
during the testing of multiple channel SIS. There is also evidence that procedural controls are
put in place where overrides are applied and that the application of overrides is reviewed.
When used in the presence of adequate controls overrides provide a means of maintaining both
functional safety and process availability, however, if deployed without controls they have the
potential to significantly undermine functional safety. Opinion varies over whether overrides
should be provided within standard well-proven designs and controlled by robust wellunderstood operational practices or whether they should be avoided where possible. They are
certainly a recognised feature of manufacturing processes, being addressed by publications such
as ANSI/ISA-S84.01-19962. Ultimately, functional safety must not be compromised by the
application of overrides so, whether they are favoured or not, they must only be applied after
consideration of risk.
Based on the research, the following recommendations are made:

the application of overrides and bypasses should be subject to a process of risk


assessment which should be documented and reviewed where modification occurs;

the application of overrides should be subject to robust control processes involving


authorisation by personnel competent to assess the risk involved.

Partial Testing
The research suggested that the proof testing of components of SIS at different frequencies and
times is common practice. Specifically, it is common to test initiating devices on-line and to test
the associated logic and final elements during planned outages. This is an entirely appropriate
approach to the maintenance of functional safety provided that the combination of on-line and
off-line tests lead to adequate coverage at an adequate frequency and adequately represents the
operating environment. Less common, but present nevertheless, is the partial testing of
individual components in the form of measurement simulation and the partial stroking of valves.
Such partial testing arises when the complete testing of components is not deemed to be
reasonably practicable and must be subjected to rigorous justification. Based on the research,
the following recommendation is made:

where partial testing of SIS or their components is adopted, its justification should be
documented and it should be explicitly addressed within the demonstration of
achieved functional safety.

Trip Initiation
The methods of initiating SIS are many and varied but whatever the method it must provide
adequate confidence that the SIS would be initiated if required under operating conditions. A
distinction must be drawn between manipulation of the process variable and manipulation of the
process. Manipulation of the process variable without driving the process into a potentially
hazardous situation should be achieved where reasonably practicable. Manipulation of the

22

process may be necessary to provide a realistic test of functionality but this must be
accompanied by a risk assessment to ensure that the probability of achieving an unsafe state
remains acceptably low. Equally, any departure from realistic operating conditions during proof
testing must be accounted for within the safety integrity assessment of the SIS. Based on the
research, the following recommendations are made:

a method of SIS initiation should be adopted which adequately establishes that the SIS
would operate under operating conditions;

where reasonably practicable, SIS initiation should be via manipulation of the process
variable using process fluids. The provision of facilities for achieving this should be
considered during design of SIS;

the initiation of SIS should not involve placing the process in a state where failure of
the SIS under test could lead to a hazardous situation;

SIS should be proof tested as found rather than being disturbed, thereby reducing the
potential for unrealistic tests, loss of as found system failure data and introduction of
faults on system reinstatement.

Calibration
The research established unanimous agreement that traceable calibration should exist for all test
equipment, therefore, the following recommendations are made:

calibration records should exist for all test equipment and should be traceable to
national standards;

the recording of test equipment serial numbers and calibration due dates should form
part of proof test procedures.

Diagnostics
The research identified varying amounts of uncertainty and confusion over the use of diagnostic
facilities and over the application of the term "diagnostic coverage" to proof testing. An exercise
to establish the extent of the implementation of diagnostic coverage, together with examples of
good practice would be of benefit to industrial users.
4.3

FORMAT OF PROOF TEST PROCEDURES

4.3.1

Guiding Principles

(a) The written proof test protocol should take account of recognised human factors in order to
reduce the potential for errors and violations.
(b) The written proof test protocol should be subject to formal document control procedures.
4.3.2

Rationale

A proof test is a set of sequential actions which, when correctly executed, will verify the correct
operation of a SIS at the time of testing. The procedure to be followed by a tester is generally
presented as written text and the format of the written procedure can introduce weaknesses into
proof testing. The involvement of human beings has the potential to introduce behavioural
issues, such as error and violation, where an error is an unintentional deviation from a procedure
and a violation is a deliberate deviation from a procedure. Both error and violation can influence
the effectiveness of proof tests and lead to an undesirable outcome, therefore test procedures
should be constructed and presented in such a way that the potential for error and violation are

23

minimised. Guidance on producing procedures that minimise the potential for error and
violation can be found in references 5 and 6 respectively.
It is also imperative that the test procedure describes a sufficient examination of the SIS and is
recognisable as the currently applicable version. In short, it should be generated in line with the
principles of Quality Management. Clause 9 of ANSI/ISA-S84.01-19962 provides guidance on
minimum general content of a test procedure, which covers preparation for test, the test and
expected results and reinstatement after test.
4.3.3

Research Data

The research found some differences of opinion over the general approach to proof test
procedures. One interviewee reported a preference for generalised procedures executed by
experienced people whilst four reported a preference for explicit procedures to minimise the
need for specific knowledge. Three interviewees specifically reported the use of generic
procedures although only two interviewees specifically reported the deployment of generic
designs. An end user workshop offered the general view that proof tests need to be more
prescriptive, suggesting that the Electrical Engineering community benefits from such
prescriptive procedures. The other workshop explicitly recommended that proof test procedures
should be presented as a collection of sequential steps with each step being verified.
A debate restricted to the pros and cons of detailed and generic procedures fails to address the
accepted issues associated with human factors as described by references 5 and 6. Proof test
procedures should be based upon an understanding of the task and the users. Thought must be
given to those who will use proof test procedures and the level of information they need,
therefore, the competence of the tester must be understood and procedures must be supported by
training in order to promote their effective use.
The examples of test procedures collected from nine interviewees demonstrated a common
approach of describing each sequential step. Of the eight, three demonstrated the use of a tick or
comment facility for each step with one of the three providing a separate results sheet for each
test allowing the recording of the result of each test. The remaining five examples did not
provide the facility to verify each step. Six of the examples provided sign-off facilities for the
tester with four of the six allowing for counter-signature.
Three interviewees specifically reported the provision of additional information in support of
proof test procedures. Such documentation includes cause and effect charts, sequential flow
charts, system descriptions and function diagrams. One interviewee stated that test protocols do
not normally reference or include the design intent, although newer procedures have a short
section detailing the purpose of the test and the equipment upon which it is being performed.
Appendix 3 reproduces examples of test procedures, or sections thereof, which illustrate
elements of good practice. The example of Appendix 3.1 is presented in a structured manner
with a title page providing an overview of the test, precautions and preparation followed by a
procedure broken down into clearly defined steps. The use of short sentences is evident, as is
the use of highlighted text to provide warnings and draw attention to important information.
Lower case font is used throughout; research has shown that test written entirely in uppercase
font is slower and more difficult to read.
The examples of Appendices 3.1 and 3.2 provide mechanisms for the tester to verify the
successful completion of test steps with the latter providing the facility to describe the test
results in the form of a code for input to and manipulation by a database application. Both
examples demonstrate simple revision control. Appendix 3.3 reproduces an example of a
document control sheet that clearly defines the responsibilities and definitions associated with
approval of the proof test procedure.
The trend appears to be to ensure that test procedures are sufficiently detailed to eliminate the
requirements for experienced technicians to be involved in testing, however, the assumption that

24

there is a best way to present a proof test procedure irrespective of the attributes of the tester is
an indication of poor practice and a lack of understanding of the potential impact of human
factors [inconsistent with principle 4.3.1 (a)]. An appreciation of the competence of the tester is
an integral part of the construction of proof tests. Providing too much information may lead to
less use of the procedure if it becomes too difficult to follow whilst too little information may
mean that an inexperienced person will not be able to carry out the task.
A clear example of a violation arising from an inadequate proof test procedure was encountered
during an end user workshop and involved a tester who tested a SIS differently to the written
procedure because the written procedure was not workable [inconsistent with principle 4.3.1
(a)]. The SIS was tested in this way for a number of years but when the tester left the company
the new staff reverted to the written procedure. The ongoing violation of the proof test
procedure could have been prevented or stopped in a number of ways, for example, by
involving the tester in the production and maintenance of the procedure or by undertaking a
robust validation process prior to fully implementing the procedure.
4.3.4

Conclusions and Recommendations

The research suggests that consideration of the format of proof tests appears to be based on
authors' perceptions of testers' competencies rather than on objective understanding. The
approach should be adequate provided that the perceptions are correct and the attributes of the
tester community remain stable over time, however, this is unlikely to be the case in an
environment where skilled personnel are reported as being in short supply and there is an
increasing reliance on temporary contract personnel. The lack of evidence of proof test
procedures being designed for defined user groups coupled with the lack of evidence of the
competence of user groups being maintained accordingly, increases the potential for error and
violation in the execution of proof tests.
The absence of a single test procedure that exhibits all of the attributes associated with good
practice suggests that proof test procedures could be generally improved. Whilst many attempt
to apply approvals and gather similar information, the styles vary. The chemical industry would
benefit from a structured approach to procedure writing based on the need for validation, data
recording and an appreciation of human factors. References 5 and 6 and related publications
should be reviewed by authors of proof test procedures and used as the basis of a common
approach.
Based on the research and on the consideration of human factors by reference 5, the following
recommendations are made:

the design of proof test procedures should be based on a firm understanding of the test
and the requirements and competence of the tester;

ownership should be promoted by involving testers in the preparation and


maintenance of procedures;

proof test procedures should be presented in a consistent format, including, for


example:

the purpose of the procedure;


precautions which must be observed to avoid potential hazards;
special tools or equipment needed;
initial conditions which must be satisfied before starting;
references to other relevant documents such as data sheets, manuals etc.;
procedural steps to perform the task safely and efficiently;
actions to be taken on discovery of a fault;

warnings should be clear and conspicuous and precautions reiterated in procedural


steps;

25

the style of proof test procedures should promote ease of use by:

keeping sentences short and precise;


using positive active sentences such as 'open valve A then valve B";
using normal lower case text rather than ALL CAPITAL LETTERS;
retaining open spaces and avoiding cluttered pages;

proof test procedures should be subject to strict document control.

4.4

PLANNING AND SCHEDULING

4.4.1

Guiding Principles

(a) Proof testing should be an integral and explicit part of the planning and scheduling of the
safety management system.
(b) The timing of proof tests should be dictated by the need to demonstrate and maintain
functional safety and should not be compromised by operational or business considerations.
4.4.2

Rationale

The proof testing of at least some components of SIS requires those components to be taken out
of service for some time. This is not necessarily a problem for batch and campaign
manufacturing organisations as advantage can be taken of inter-batch downtime, however, no
such opportunities exist for continuous process manufacturing organisations and the need for
proof testing often conflicts with the need to maintain high levels of plant availability. Proof
testing may be scheduled to coincide with planned equipment downtime, provided that it results
in sufficiently frequent proof testing.
4.4.3

Research Data

All participants in the research reported the routine testing of SIS, although, the rationale and
planning behind the routine testing varied. The frequency of routine proof testing was set by one
of three means; reliability analysis, the application of standard rules and, in one case, a
subjective historical decision. A common practice, reported explicitly by six interviewees, was
to calculate maximum allowable intervals between tests then apply standard testing based on
these limits [consistent with principle 4.4.1 (b)]. Standard intervals for partial or complete proof
testing were three months, six months, one year and two years. One interviewee reported the
allocation of test frequencies based on classification of the SIS and therefore on a standard
design. Another interviewee reported establishing test frequencies through reliability analysis
but applied a maximum allowable period between tests of two years. One interviewee reported
adopting a twenty-six month period between tests for a long established installation based on
the historical decisions of an Operations Manager [potentially inconsistent with principle 4.4.1
(b)].
The planning of proof testing is carried out by a variety of resources. Five interviewees
explicitly reported the use of computer-based maintenance scheduling systems, with one being
dedicated to SIS. There were reports of planning being carried out by engineering teams,
process teams, maintenance teams and planning teams.
The research revealed a unanimous aspiration to execute proof testing without impacting on
production. This was particularly obvious amongst continuous process manufacturing
organisations but was also evident amongst batch and campaign manufacturing organisations,
with one batch manufacturer reporting being driven by pressures to minimise disruption to
production. A workshop reported a "constant battle" between production and downtime for
testing [inconsistent with principle 4.4.1 (b)]. The general approach was to schedule the proof
testing of some or all of the components of SIS to coincide with planned production outages

26

such as shutdowns, overhauls or batch changes. Only two interviewees reported addressing the
conflict between production and proof testing by striving for full on-line testing. Eight
interviewees explicitly reported scheduling proof tests to coincide with shutdowns or overhauls,
however, one of the eight reported difficulty in matching resource availability to plant
availability implying an opportunistic rather than planned approach. A further one of the eight
explicitly reported taking advantage of unplanned outages where practicable and rescheduling
subsequent proof tests accordingly.
Two further approaches to minimising production disruption were encountered. A fairly
common practice, reported explicitly by four interviewees and one workshop, was the grouping
of proof tests which could be conveniently executed as a single activity, concentrating
disruption into a single time window. Such a group might include all SIS associated with a
single plant item such as a vessel or reactor. Another approach, reported by two interviewees
and one workshop was the alignment of proof tests with statutory inspections made under
regulations covering pressure vessels, nominally performed on a biannual basis [potentially
inconsistent with principle 4.4.1 (b)].
There was evidence that proof test intervals are being stretched to maximum theoretical limits,
for example, a workshop reported a case of the period between routine shutdowns being
extended to two years resulting in the existing proof test frequencies being reduced accordingly,
thus invalidating the basis of the SIL [inconsistent with principle 4.4.1 (b)]. There is now
pressure from external authorities to return the proof test frequencies to justifiable values.
The supplier workshop raised the issue of "occasional use" systems such as research and
mothballed batch facilities, suggesting that these may tend to require SIL3 systems and require
regular testing. In this case, the proof testing of SIS could be carried out prior to operation then
at the appropriate frequency during operation. This is an example of the need to address proof
testing requirements during development of a maintenance regime.
4.4.4

Conclusions and Recommendations

Proof testing is an integral component of the maintenance of the safety of an operating plant and
should therefore be fully integrated into maintenance regimes. Indeed, given the relatively high
frequency of the tests and the potential impact on production, the scheduling of proof tests
should account for a significant amount of maintenance planning effort. Additionally, care must
be taken to ensure that production pressures and mathematical proofs do not override practical
considerations and lead to undetected reductions in functional safety.
The following recommendations are made:

proof test frequencies should be based on objective and justifiable criteria and any
alignment of proof testing with planned outages should be justified, particularly where
the time between outages exceeds twelve months;

proof testing should be treated as an integral component of the safety management


system planning activities.

4.5

RECORDS OF PROOF TESTING

4.5.1

Statements of the Guiding Principles

(a) The results of proof testing should be recorded and maintained for the purposes of periodic
reporting, audit and historical analysis.
(b) Data arising from proof testing should be collated, reviewed and acted upon in order to
maintain or improve functional safety.

27

4.5.2

Rationale

The records of proof tests are required to enable the review of the design basis and performance
of SIS and to demonstrate compliance with safety requirements. The initial reliability analysis
of a SIS is based on data such as required risk reduction, component failure rates, component
fail-to-danger rates and operational demand rates, gathered from a number of sources. Although
performed by competent personnel, the application of these figures to particular situations may
involve some judgement and the review of data collected during proof testing affords an
opportunity to validate the design basis of SIS or to modify SIS design in line with actual
process and SIS performance.
4.5.3

Research Data

Recording
The research found that the results of SIS proof tests and details of failures under test are widely
recorded but that the data generated is rarely subjected to analysis or reporting. Typically, test
records indicate whether the test was successful and provide a description of any faults found,
details of any corrective action taken and details of the tester. Two interviewees reported that
failure data is not normally gathered [inconsistent with principle 4.5.1 (a)]. Interviewees
unanimously reported the completion and retention of test records in paper form with the
records generally being held by a local Engineer. In some cases the completed test procedure
constituted the record of test whilst in other cases separate results sheets were preferred. An end
user workshop reported strong views to move towards common electronic repositories for test
records. The same workshop queried the length of time that records should be kept and
suggested that the retention period of results should be specified on each test procedure based
on frequency of test.
Only four interviewees reported the transfer of pertinent information from paper records to
electronic formats for the purpose of subsequent analysis and reporting. One interviewee
reported that alarms associated with safety-related systems are logged by a central information
management system allowing reporting of SIS initiation but suggested that no further analysis
was performed. One interviewee reported the use of plant item record sheets to capture and
collate test information associated with major plant items. Another reported that failure data is
held and analysed to provide reliability norms [consistent with principle 4.5.1 (b)]. The
allocation of fault codes was explicitly reported by two interviewees and observed in an
example test procedure provided by another (reproduced in Appendix 3.2). The use of codes
allows simple analysis and reporting using database and spreadsheet applications.
The supplier workshop suggested that strict reporting of component faults would improve the
credibility of reliability data but suspected that many components are considered to be throwaway items and that their failures are not reported [inconsistent with principle 4.5.1 (a)]. This
suspicion was supported by an interviewee who stated that the visibility of operational
downtime takes precedence over SIS analysis. The supplier workshop also raised the possibility
of using intelligent devices to record component and system performance and some evidence of
data gathering using intelligent valve positioners was presented at an end user workshop. An
end user workshop also commented that key reliability data is not available for ageing or
inherited systems, however, the research suggests that the data is available somewhere but is
simply not collated into a useable form and is not easily traceable.
Traceability was a key issue at both end user workshops with one workshop reporting the
examination of a paper trail by the Regulatory Authority. The other workshop presented a
general view that the Regulatory Authority does not give credit for past experience, however,
the research suggested that the quality of record keeping and general traceability of data is
insufficient to formally demonstrate valid previous experience.

28

Review
The research identified the following review processes relevant to proof testing:

the review and reporting of overdue tests;

the review of SIS component failures under test and the associated remedial actions;

the review of SIS component failures in operation;

the review of SIS and process performance against the assumptions of the risk and
reliability analysis;

the review of the quality of proof test execution.

Seven interviewees representing all participating industrial sectors explicitly reported the
analysis and reporting of overdue proof tests to senior management, some via computer-based
maintenance management systems. Reporting, review and action was on a monthly or quarterly
basis. An end user workshop suggested that the number of overdue tests could be used as a key
performance indicator (KPI).
The approach to the review of failures under test varied greatly involving, for example, formal
quarterly reporting to senior management, ad-hoc review based on the experience and
judgement of the tester or no review at all. One interviewee reported that the E/I Manager
reviews reported failures, suitably coded and grouped to identify trends and reports the findings
to senior management via a quarterly report [consistent with principle 4.5.1 (b)]. One
interviewee explicitly reported the use of a computer-based maintenance management system to
store condition reports. One interviewee reported the instigation of root cause analysis
investigations of failures under test [consistent with principle 4.5.1 (b)], one interviewee
reported reliance on the local quality management system and four interviewees reported review
of failures under test by local E/I Engineers. One interviewee reported a feedback mechanism
which relies wholly on testers bringing concerns to the attention of maintenance management
which then has the opportunity to review areas of concern [potentially inconsistent with
principle 4.5.1 (b)]. In this case, the appreciation of trends and concerns remains with the
Maintenance Engineer [inconsistent with principle 4.5.1 (a)]. Two interviewees reported
identifying and reviewing fail-to-danger figures [consistent with principle 4.5.1 (b)]. No
interviewees reported reviewing repair times, however, one interviewee reported reviewing
process availability losses. Five interviewees explicitly reported the use of formal incident
investigation procedures to address failures of SIS under test or on demand during operation.
The review of SIS performance was reported by four interviewees whilst one reported plans to
instigate such reviews in the future and two reported a general review of critical equipment and
process hazards. Two interviewees explicitly reported reviewing SIS fail-to-danger rates whilst
one reported reviewing demand rates. In these cases it was reported that design and testing of
SIS were modified accordingly [consistent with principle 4.5.1 (b)]. One interviewee reported
that a formal review of the test frequency is required after a maximum of five tests and involves
the review of the records of previous tests.
The review of the quality of execution of proof tests was raised by three interviewees. One
interviewee reported a formal review of the execution of proof tests after a maximum of five
tests whilst another explicitly defined the responsibility for such reviews. Another interviewee
reported the instigation of such reviews at a local level by plant Engineers.
Examples of the output of reviews were few. One interviewee reported that experience revealed
very few complete or catastrophic failures of shutdown systems against a slightly higher
incidence of out of tolerance failures. Another interviewee reported only one SIS failure to date,
involving a calibration error. A review of fail-to-danger rates was undertaken in an attempt to
demonstrate that proof test frequencies could be reduced, however, the exercise revealed that
frequencies were at or near their lower limits.

29

The identification and reporting of incidents was a common issue for the workshops with all
workshops suggesting that a formal approach to incident and failure reporting and analysis
should be adopted. The supplier workshop highlighted the availability of intelligent field
devices, which can provide data to information management systems for the purpose of analysis
and review.
A reliability problem that was identified by one end-user involved the regular breakdown of
transmitters on a compressor due to excessive vibration. This was picked up by the trip test
records system [consistent with principle 4.5.1 (b)], and the installations were modified to
include flexible connections to the process.
4.5.4

Conclusions and Recommendations

The research suggested that a significant amount of data is not recorded, and that the data which
is recorded, is rarely reviewed or in a form which allows easy analysis. The ability to review
SIS performance against design data or to provide data in support of claims of past operating
experience is similarly rare. Evidence of effective SIS performance was anecdotal, in some
cases based on the experience of long-serving personnel. The inability to reproduce or review
performance data raises doubt over whether the demonstration and improvement of functional
safety of SIS are considered a priority.
The lack of performance data could be attributed in part, to the treatment of many components
as throwaway items. It was suggested that many malfunctioning components are simply
replaced and discarded leaving their true reliability unreported.
Recording
Although records of tests are generally kept they are rarely kept in a form which facilitates
future analysis. The time required to be invested tends to preclude the analysis of recorded data,
however, failure to record data could lead to maintenance problems in the future and many of
the perceived historical issues could be overcome in the medium term by effective reporting and
analysis. Additionally, traceable records could be used to influence Regulatory Authority
perceptions and practices.
The following basic data should be recorded:

the steps undertaken during testing;

the results of steps;

details of all faults;

details of corrective actions including time to repair and effectiveness of remedial


action;

the duration of the test (start time / end time);

details and signature of the tester;

validation details and signatures.

Additional recommendations are made as follows:

the purpose of making, retaining and tracing records should be understood;

the procedure for the generation, retention and retrieval of records should form part of
the general procedures covering the management of SIS;

any initial processing of the data, such as the input to database systems and the
allocation of fault codes, should be carried out immediately after testing.

30

Review
The research suggests that a significant quantity of data is generated by proof testing but that
most is not reviewed. With only two examples of the review of fail-to-danger figures and no
reported reviews of repair times, it appears that there is significant reliance on assumptions
made during the SIS design process. It further suggests that effective review of such data is
practicable and can provide information that can be used to validate or modify SIS, leading to
the maintenance or improvement of functional safety. The availability of desktop spreadsheet
and database applications provides the ability to store, organise and review data, however, the
ability to review data generated by proof testing depends largely on the quality of recording at
the time of proof testing. A formal yet manageable approach to recording and review is
therefore required.
A formal approach to capturing and reviewing proof test data brings two main benefits. Firstly,
it provides evidence of efforts to continually improve safety management procedures and
maintain functional safety. Secondly, it will, over time, increase the quality of information such
as fail-to-danger rates, demand rates and repair times on which the design and operation of new
and existing SIS are generally based. This will allow proof test intervals to be optimised and
will help to alleviate some of the concerns over ageing and inherited systems.
Based on the research, the following recommendations are made:

the purpose and benefits of effective recording and review should be understood and
the requirements defined by the safety management system;

the review of proof test data should be facilitated by organising recorded data
immediately after proof testing, for example, by inputting it into database applications
and allocating fault codes.

4.6

COMPETENCE

4.6.1

Guiding Principles

(a) Personnel participating in all aspects of the proof testing process should be demonstrably
competent to carry out their allotted tasks.
(b) The responsibilities for all aspects of proof testing should be clearly identified and
communicated.
(c) Documented verification by competent persons should be applied to the appropriate stages
of the proof testing process to ensure that each test is sufficient in terms of content and
execution.
4.6.2

Rationale

The need for people to be competent to carry their allotted tasks is a fundamental and obvious
prerequisite for the avoidance of unsafe situations, particularly when the tasks involve the
maintenance of safety-related systems. With respect to proof testing, there is a need to ensure
that those individuals involved in the design of SIS, in the writing of proof test procedures, in
the execution of proof tests and in associated approval processes recognise their responsibilities
and are demonstrably competent. There is also a need to ensure that appropriate standards and
competencies are applied to proof testing via a structured approval process.
The need to formally identify and measure competence has been addressed by the collaborative
publication, Competency Guidelines for Safety-Related System Practitioners9. Appendix B of
that document provides guidance on competency assessment relating to the maintenance and
modification of safety-related systems.

31

4.6.3

Research Data

Competence
Whilst some views were expressed on the need for appropriate competence to be deployed in
the design of SIS and in the writing of the associated test procedures, the interviewees and
workshops concentrated upon the competence applied to the testing activities. The research
found that although there was unanimous agreement that appropriate competence is essential,
there is little evidence that it is addressed in a formal manner. Only four interviewees reported a
formal approach to competence, the majority reporting no formal processes for the specification,
establishment, recording and maintenance of SIS proof testing competence. Two interviewees
reported the provision of formal training, a further three reported the provision of initial training
but no interviewees reported the provision of refresher training.
An interview highlighted a structured approach to competence assessment and certification
[consistent with principle 4.6.1 (a)]. The process involves all staff and contract Instrument
Technicians attending a training course explaining the corporate and local requirements for
proof testing of safety systems. After the training, technicians are certified to work on safety
systems subject to limitations of authorisation and confidence in understanding of the
underlying principles. There are two levels of certification; Part A covers general principles and
mainly focuses on the field side whilst Part B contains several sections and addresses specific
plants (in Manufacturing Groups) and also covers calibration and issue of test equipment.
Contract Technicians are generally certified to Part A, however, established contract
technicians, may be certified to specific sections of Part B.
There was evidence of differing opinions over the true meaning of 'competence' as applied to
proof testing. For example, a suggestion was made that test procedures should not rely on the
knowledge of the technician performing the test to ensure correct execution whilst it was also
suggested that the competence of persons carrying out proof testing is a key factor in
determining effectiveness. Additionally, eight interviewees reported reliance upon general
technical qualifications to demonstrate competence in proof testing with one interviewee
making no distinction between the testing of SIS and the testing of other instrumented systems.
One interviewee commented that compliance with standards and procedures is most threatened
by the loss of competent personnel.
The use of third party contractors in proof testing was reported by eight interviewees with five
explicitly reporting avoiding the practice. Of those who use third parties, only one interviewee
reported doing so as a matter of course, using preferred suppliers to test all SIS, whilst the
remainder reported using third parties to supplement permanent resources during periods of
high demand. Only one interviewee reported applying the same formal competency certification
to contract staff as is applied to permanent staff, however, only long-term contract technicians
would be certified to the higher level of competence. One interviewee reported an almost total
reliance on the experience of permanent staff due to very low staff turnover, and is concerned
about the risk of key staff leaving and the difficulty of succession planning. Another interviewee
reported the retention of experienced personnel to be a key concern.
The subject of competence generated significant discussion at the workshops. It was suggested
by the supplier workshop that users seem to ask for SIS information as part of the general
documentation package for equipment based on little understanding of the principles of
IEC615081. It was also suggested that, whilst warranties require that equipment be maintained
by competent personnel, there is little definition of 'competent' in this context.
One end user workshop suggested that a general movement towards using contract technical
personnel rather than permanent staff reflected a change in the nature of industry and it was
further suggested that a rapidly changing workforce leads to difficulties in controlling
competence. The workshop observed a trend towards ensuring that proof test procedures are
sufficiently detailed to eliminate the requirement for experienced technicians to be involved in

32

proof testing. To arrest the slide in expertise the workshop suggested the possibility of requiring
NVQs for proof testing and of specifying competency requirements within proof test
procedures. It was also suggested that the use of process operators to perform proof tests
appears to be a growth area and questions were raised over whether competency issues have
been adequately addressed.
The other end user workshop suggested that management structures can lead to ignorance of
competencies, especially when technicians responsible for executing proof tests respond to a
Maintenance Manager who may not be able to judge technical competence.
Responsibility
Thirteen interviewees were able to explicitly name the appointed role responsible for the
operation and testing of SIS whilst one senior engineer was not aware of such an appointment
[inconsistent with principle 4.6.1 (b)]. Of the thirteen, eleven reported that proof testing is the
responsibility of a senior Responsible Engineer whilst two reported that proof testing is the
responsibility of Operations Management. For large installations, the Responsible Engineer
generally has the power to delegate responsibility to local plant Engineers. One interviewee
reported the use of a responsibility matrix to communicate responsibilities [consistent with
principle 4.6.1 (b)]. Making asset owners responsible for the execution of proof testing was
cited as an effective mechanism for managing any conflict between routine proof testing and
plant availability.
The supplier workshop cited an example of the responsibility for the provision of probability of
failure on demand analysis being passed to a supplier without all of the necessary data, implying
a lack of appreciation of accountability by the user [potentially inconsistent with principle 4.6.1
(b)]. An end user workshop stressed the need to distinguish between responsibility and
accountability, a particularly important aspect of the practice of delegation. In this context, the
Duty Holder may delegate responsibilities associated with proof testing to suitably competent
persons but remains accountable for the successful execution of the proof testing process. The
same workshop stressed the need to clearly define ownership, roles and responsibilities.
Additionally, an example was encountered of plant Engineers delegating testing to a
maintenance group but having no control over who performs the tests [inconsistent with
principles 4.6.1 (b) and 4.6.1 (a)].
An attendee at the other end user workshop reported that the Operations / Asset Manager has the
responsibility to ensure that proof testing is carried out but often delegates to the Engineering
group. The workshop stressed that someone must be clearly appointed to own trip testing and
control which personnel can execute the tests, suggesting that company procedures should
define who has responsibility for taking decisions in the event of failures during proof tests. It
was further suggested that only the asset owner should be authorised to give dispensation from
carrying out proof testing.
Approval
The research identified the following approvals relating to proof testing:

approval of the proof test procedure;

approval of the proof test execution;

approval of proof test deferrals;

approval of overrides and bypasses.

33

Three interviewees and both end user workshops reported the practice of having an independent
person witness the first implementation of a proof test to ensure that it is practicable and clear
and to ensure that any relevant feedback from the tester is captured. A further three interviewees
reported the independent approval of proof test procedures by Responsible Engineers or by a
combination of engineering and operations personnel [consistent with principle 4.6.1 (c)]. One
interviewee suggested that the designer should witness the initial test, however, design
personnel have often moved on by the time of commissioning, especially when large design
contractors are employed. Nevertheless, the feedback of operational practicalities to design
personnel was supported by both end user workshops [consistent with principle 4.5.1 (b)].
Competence and independence were raised as key issues. There was general agreement that
approvers should be competent and should bring a level of objectivity through independence,
however, whilst stating that approvals and peer reviews should be carried out by demonstrably
competent personnel, one end user workshop observed that the number of such people has
diminished significantly. This indicates that skill shortages may become a significant issue.
Independent approval of the execution of proof tests was evident from four interviews and two
example procedures, however, the nature of the independent approval varied from operations
personnel to maintenance personnel to engineering personnel. The purpose of the independent
approval of execution was generally to show that the outcome of tests had been reviewed.
An example of an incident attributable to a failure to adequately validate a test procedure was
given during an end user workshop and involved a tester who tested a SIS differently to the
written procedure because the written procedure was not workable. The SIS was tested in this
way for a number of years but when the tester left the company the new staff reverted to the
written procedure. The suggested learning from the workshop was that feedback from testing is
essential in order to initiate change where it is necessary, however, a robust validation process
involving approval by appropriately competent personnel could have prevented the ongoing
violation of the proof test procedure [principles 4.6.1 (c)].
The approval of proof test deferrals and dispensations was raised by an end user workshop,
which agreed that it should be considered as a guiding principle. This is covered generally by
principle 4.6.1 (c)..
4.6.4

Conclusions and Recommendations

Competence
There is limited evidence of formal controls associated with the competence of those individuals
responsible for proof testing, particularly those responsible for its execution. There is a general
view that generic technical qualifications coupled with some initial training is sufficient to
ensure the maintenance of functional safety, especially where the tasks involved can be
expressed in a prescriptive manner. Where prescriptive procedures are employed, care must be
taken to ensure that human factors are taken into account.
There is recognition that an industry trend towards outsourcing has the potential to reduce the
competence applied to proof testing unless appropriate controls are put in place, although,
examples of effective controls are few. The provision of initial training for new or contract
personnel appears to be common practice although its future provision will depend on the
maintenance of a core of permanent expertise in an environment where the retention of such
expertise is already proving difficult. Experienced and skilled personnel are also more likely to
identify and act on issues which less experienced personnel may miss, particularly during
exceptional or unexpected conditions.
Based on the research, the following recommendations are made:

a competence profile for proof testing should be generated by the Duty Holder which
details the necessary knowledge, training and experience required;

34

the competence necessary to perform a proof test should be specified within the proof
test procedure;

records of those deemed competent to test SIS should be retained;

personnel regularly engaged in proof testing should receive refresher training;

succession planning should be adopted in an effort to maintain access to sufficient


competent personnel;

where the maintenance of competence is an issue, periodic audits of proof testing and
related issues by experienced and skilled personnel (internal or external) should be
undertaken.

Responsibility
Large organisations were found to exhibit clearly defined management structures, which lead to
clear definitions and communication of individual responsibility. Smaller organisations
recognise the need to define roles and responsibilities but do not necessarily experience the
same pressures of scale to adopt a formal approach. Whatever the practical pressures, the need
to maintain the functional safety of SIS is paramount and structures and processes should be
deployed accordingly. To this end, the roles and responsibilities associated with the proof
testing of SIS should be clearly defined and communicated. The following recommendations are
made:

the responsibility for proof testing should be assigned to a nominated role who should
be clearly informed of, and accept, their responsibilities and accountabilities;

any delegations of responsibility should be made in a structured manner to suitably


competent persons who should be informed of, and accept, their responsibilities;

roles and responsibilities should be clearly documented and communicated.

Approvals
It is extremely important to recognise that approval is a process of verification and validation,
not simply the application of a signature. The questions;
"what are we trying to demonstrate?" and
"what does approval mean in this case?"
should be asked, before deciding which documents should be approved by whom. In the context
of proof testing the process of approval should ensure that:

the proof test procedure describes a sufficient test of a SIS;

the proof test procedure is safe to apply to the process or equipment under control;

the outcome of the proof test has been reviewed and any appropriate actions initiated.

It is therefore necessary to ensure that the correct competencies are brought to bear, for
example:

an experienced Engineer or technician would be able to assess the sufficiency of a test;

the asset owner or plant manager should be able to assess the safety of the test in the
operating environment;

a Maintenance Engineer might be best placed to ensure that any necessary corrective
actions are undertaken.

35

It is equally important to recognise that the process of approval can be a time-consuming


activity, particularly the approval of proof test procedures associated with large assets.
Nevertheless, the process of ensuring that SIS proof testing provides the appropriate functional
safety is not optional and the accountability for functional safety cannot be delegated by the
Duty Holder, therefore, the provision of appropriate resources and budgets must be planned.
Involvement in the process of verification and validation allows design personnel to appreciate
the practicalities of testing SIS which they design and, where applicable, the proof test
procedures which they write. It also allows operations and maintenance personnel to appreciate
the design intent of the SIS. Such involvement may be possible where design personnel remain
available to a site or facility but may be not be possible where third parties are involved.
Based on the research, the following recommendations are made:

a robust process of verification and validation should be applied to the design and
execution of proof test procedures;

the involvement of competent people in the design of proof tests should be maximised,
for example, the experience of operations personnel could significantly benefit the
design process;

the initial execution of a proof test should be independently witnessed leading to


modification where necessary;

the purpose of every approval should be defined and understood;

personnel should be demonstrably competent to provide approvals.

4.7

AWARENESS OF HAZARD AND RISK

4.7.1

Guiding Principles

(a) The written proof test protocol should describe all identified hazards associated with
undertaking the test together with the any necessary precautions.
4.7.2

Rationale

Although the purpose of proof testing is to maintain functional safety, the very action of testing
has the potential to expose the equipment under control and the tester to risk. It is therefore
important that those involved in the execution of proof tests take precautions to minimise risk.
The equipment owner has a duty of care to ensure that the action of proof testing does not lead
to an unsafe state. In order to achieve this, the hazards and risks must be understood and suitable
precautions put in place. Risk can be minimised by ensuring that proof testing is carried out by
informed, competent personnel, following well structured risk-assessed procedures.
The proof test procedure is the means of providing the tester with an awareness of the risks
associated with the test and must therefore be written in a manner which the tester understands
and which clearly and conspicuously conveys warnings and precautions. Human factors must be
considered; references 5 and 6 provide further guidance.
4.7.3

Research Data

Only three interviewees reported carrying out formal risk assessments of proof test procedures
[suggests general inconsistency with principle 4.7.1 (a)] with a further two stating reliance upon
risk assessments associated with the issuing of permits to work. Of the three interviewees which
reported risk assessment of proof tests, two reported that it was done as a matter of course
[consistent with principle 4.7.1 (a)]. Of those two, one reported that all procedures are risk

36

assessed by a multi-functional team, the other reported that the precautions taken during testing,
specifically the quantity and level of authorisation required for overrides, are based upon an
assessment of risk and vulnerability.
The research revealed two distinct views on the minimisation of risk during proof testing. One
approach is to provide prescriptive, unambiguous procedures, which fully define the necessary
activities and constrain the tester to a set of actions which are unlikely to result in an unsafe
state. For example, one interviewee reported that test procedures are written in a clear and
concise way to minimise the need for specific knowledge of a system and reduce the risk of
making mistakes. The second approach is to provide less detailed procedures and rely upon the
expertise of the tester. For example one interviewee reported that tests are not generally detailed
exhaustively but the expertise of technicians is recognised and equipment suppliers' manuals are
used where necessary. Of those interviewees which specifically addressed this issue, three
reported generating prescriptive proof test procedures whilst one reported reliance upon the
expertise of the tester. The common feature of these approaches is the reliance on someone's
competence; that of the tester, the author or the assessor(s) of the proof test procedure
[potentially inconsistent with principle 4.3.1 (a)].
The supplier workshop suggested that proof test procedures should include a description of the
safety function and an explanation of the process of SIL determination. Whilst a description of
the safety function could help the tester to understand the purpose of the SIS and the risks
associated with its testing, a description of the SIL determination process may be less useful.
One end user workshop suggested that risk assessment should be undertaken in order to
understand and, by implication, communicate the hazards associated with proof testing to the
tester.
Of the nine example proof test procedures obtained, four provided a mechanism for explicitly
defining the precautions to be taken and for providing the tester with additional information
[consistent with principle 4.7.1 (a)]. None of the examples explicitly defined the process hazard
being addressed by the SIS, however, one of the examples used bold typeface to describe
precautions and the reasons why they were being taken [consistent with principle 4.7.1 (a)].
Examples of sections of procedures, providing supporting information that were encountered,
are:

purpose;

scope;

initiating variable(s) / items actuated;

references;

definitions;

pre-requisites / process conditions for testing;

preparation (including test equipment requirements);

notes (free format).

The proof test procedure of Appendix 3.1 uses a title page to provide a subset of this
information in tabular form.
4.7.4

Conclusions and Recommendations

A key consideration in the execution of proof testing is the avoidance of unsafe states during the
testing. To this end, all personnel involved in proof testing, including the tester and the
equipment owner, should be aware of the risks associated with their actions and with the
necessary precautions. The awareness of risk and hazard, together with a description of the
associated precautions, should be provided in a conspicuous manner to complement the general
competence of the tester. To this end, the following recommendations are made:
37

a risk assessment of each proof test procedure should be carried out to identify
potential hazards to the equipment under control, to the tester and to the wider
operating environment;

the differences between the testing environment and the operating environment should
be clearly understood by those managing and executing proof testing;

the risks associated with each test should be summarised in the proof test procedure
together with the associated precautions;

warnings should be conspicuous, using bold typeface or other means of attracting the
attention of the tester;

a brief description of the purpose of the proof test and the equipment under control
should be included in the proof test procedure enabling the tester to fully understand
the impact of the test;

the risks associated with the proof test should be reviewed after any change to the SIS
and the proof test procedure should be modified accordingly.

4.8

MANAGEMENT OF CHANGE

4.8.1

Guiding Principles

(a) Management of change should explicitly require consideration of the impact of change on
proof testing.
4.8.2

Rationale

Change is common in the process industries. Well-managed change has the potential to improve
safety and business performance, however, poorly managed change has the potential to
undermine the functional safety provided by SIS. It is therefore essential that the full impact of
change on SIS is properly considered in its widest context. The impact of change on the testing
regimes of SIS, from timing of routine tests to the detailed stepwise procedures, is as important
as the impact on system design, though arguably less obvious to those charged with
implementing the change.
Change Management is a recognised issue throughout industry, indeed it is a fundamental
element of a Quality Management System (QMS). Whilst a documented QMS applies strict
change control to product-related activities the same pressures of certification do not necessarily
apply to SIS and their related documentation. Guidance, however, does exist, for example,
ANSI/ISA-S84.01-19962 provides specific guidance on the management of change, specifically
within clause 10, "SIS Management of Change". With respect to proof testing, it states that all
changes to operating procedures, process safety information and SIS documentation (including
software) shall be noted prior to start-up, updated accordingly and that all SIS documentation
shall be revised, amended, reviewed, approved and be under the control of an appropriate
document control procedure. The UKOOA guidelines10 also promote a rigorous change
management system.
4.8.3

Research Data

The research highlighted a number of initiators of change which impact on the operation and
testing of SIS, namely:

process modifications;

chemistry modifications such as catalyst changes;

product changes;

38

batch changes (one organisation reported that one loop can have up to 6 sets of
settings);

small scale manufacturing improvement projects;

large scale capital projects;

SIS improvements based on a review of operational data;

proof test procedure modification based on feedback from testers;

organisational changes due to divestments, acquisitions and mergers (seven


interviewees reported some form of organisational change resulting in the need to
adopt, or otherwise deal with, systems and procedures from new or past owners);

proof testing itself, where temporary measures such as overrides are introduced.

An additional issue, put forward as a potential initiator of change, was the perceived increased
pressure to address ageing and inherited systems. This was raised in the end user and supplier
workshops. Notwithstanding the existing duties of end users, the emergence of IEC615081 has
raised concerns over its impact on those systems that have been inherited or have been in
service for many years.
The research suggests that procedures controlling the management of change are widely
adopted, indeed all of the organisations interviewed operate some form of documented change
management procedure with nine interviewees explicitly reporting change management as being
based on some form of risk assessment. With respect to proof testing, only three interviewees
explicitly refer to proof test procedures within their change management procedures [suggests
general inconsistency with principle 4.8.1 (a)]. Additionally, an end user workshop commented
that although "modification forms" are completed for set point changes, they are not always
completed for a change to the procedure for a trip test [inconsistent with principle 4.8.1 (a)].
Notwithstanding the reported current practices, the research showed an overwhelming belief by
end users and equipment suppliers that the operation and testing of SIS, and especially
supporting documentation, should be subject to rigorous change management.
Although all interviewees adopt change management procedures, some differences in approach
were noticeable. The research suggested that strict adherence to a widely deployed QMS within
the pharmaceutical industry delivers a robust approach to change management and more
particularly to the control of documentation such as operating instructions and instrumentation
test procedures. Two interviewees reported a "standard design" approach to SIS, with one
organisation going as far as to prohibit any change to the design of a SIS once the standard
design has been deployed. As stated previously, only three interviewed organisations explicitly
address proof test procedures via their change management procedure with the remaining
organisations relying upon the competence and experience of discipline Engineers to address the
impact of change on proof test procedures.
The competence of personnel involved in the change management process was identified as a
key issue through interviews and workshops. One interviewed organisation reported that its
recommended approach to the modification of proof test procedures is to involve the author of
the test procedure in addition to those with responsibility for testing. An end-user workshop
reported evidence of the person carrying out the test writing up any changes to the proof test
procedure, a situation which must be backed up with appropriate checks to ensure that the proof
test remains appropriate in the wider context. Another organisation reported that training,
including any special requirements for maintenance or testing, is provided for all site personnel
when any major change is made. An end user workshop commented that peer review is an
essential part of the approvals process and must include all disciplines and questioned whether
the person who approves a change is always competent to assess that change, particularly with
respect to technological judgements. To illustrate the need for appropriate authorisation of

39

change, Kletz4 suggests that set points should be changed only after authorisation in writing at
an agreed level of management.
Interviewees and workshops highlighted the scope and coverage of change management
processes. One organisation commented that every change is managed through a standard
change control process with inputs from operations, quality, all engineering disciplines and
others. Two interviewees specifically mentioned that original risk assessments and design intent
are referenced when executing changes to SIS, ensuring that the purpose of the SIS remains
clear. The point was made by one interviewee that the like-for-like replacement of components
should not constitute a change. The validation of changes was raised by an end user workshop
which suggested that although it was common for the initial performance of a proof test to be
witnessed, it was not necessarily as common for this to be done if the test method were changed.
The control of SIS documentation emerged as a key issue. A common suggestion for a guiding
principle was that SIS documentation should be properly controlled with the appropriate
expertise and review processes being deployed where change occurs. However, concern was
raised via an end user workshop over the amount of approvals that may be necessary and the
point was made that some end users do not enjoy the benefit of a large engineering resource.
Whilst this is a genuine concern, the employment of sufficient resource remains the
responsibility of the Duty Holder. An example of a robust SIS-specific change control
procedure was encountered requiring approval, by both Engineering and Operations
Management, however, even in this case, the interviewee reported a general problem with
availability of personnel. An end user workshop commented on the need to ensure that the
information for the trip settings for different batches should be stored in one place only. On this
subject, five interviewees reported using, or planning to use, electronic document handling
techniques to ensure version control of "master" proof test procedures and other SIS
documentation.
4.8.4

Conclusions and Recommendations

Although evidence of the use of formal change management procedures was widespread, only
three interviews revealed explicit reference to the need to assess the impact on proof test
procedures. There was evidence of reliance on Instrument Engineers to gauge the impact of
changes on instrument maintenance documentation and therefore, by implication, on proof tests.
Even changes to plant maintenance frequencies can have an impact on proof test procedures,
especially where they have been based on specific planned outages.
The following recommendations are made on the basis of the research:

changes to proof tests must be based on an unambiguous statement of required


functional safety;

change management procedures should explicitly state a need to consider the impact
of change on proof tests;

testers and the original authors should be involved in modifications to proof tests to
ensure that tests remain practicable and consistent with the design intent. Where
original authors are unavailable, other suitably competent design authorities should be
nominated;

changes to proof tests should be accompanied by appropriate training, especially for


testers and operators.

40

5.

SEARCHES

The following sections present the findings of searches of information available in the public
domain. In general, specific references to proof testing are rare, hence little information relevant
to the research was encountered.
5.1

LOSS PREVENTION JOURNAL

The following documents were reviewed:


Vol.7 1,4;
Vol.8 4,5,6;
Vol.9 1,2,3,4,5,6;
Vol.10 1,2,3.
The literature was reviewed with respect to any specific references to proof testing and any
contribution it may have had towards any incident, e.g., bad practice, failure to carry out etc.
It was found that the articles in the journal were mainly of a mathematical and process
modelling nature and that no reference was made to proof testing either in the articles or the
references used.
5.2

IChemE LOSS PREVENTION BULLETIN

Literature from incident bulletins from the last several years was reviewed with respect to any
specific references to proof testing or maintenance and any contribution it may have had
towards the incident.
In bulletin 143, an analysis of past incidents, the frequency of primary causes of incidents where
it was possible that proof testing elements were involved were reported as follows:

equipment or mode of operation modified 7.9% (37);

safety instrumentation failures 5.8% (27);

wrong equipment opened up or operated 3% (14);

shut valve passing fluid flow 1.9% (9);

control or motor operated valve stuck 1.3% (6);

control valve bypass left open 0.6% (3).

5.3

MISCELLANEOUS LITERATURE SEARCHES

A broad search of publications, journals and conference proceedings was undertaken to extract
and analyse those entries relevant to the research topic under consideration.
The following reference material was reviewed:

Chemical Abstracts 1998 - 2001;

Loss Prevention Bulletin 1999 2001;

Chemical Engineering Journal 2000 2001;

Computing & Control Abstracts 1999 2001;

UKOOA Guidelines for Instrument-Based Protective Systems Issue 2 Nov 1999;

41

Loss Prevention and Safety Promotion in the Process Industries 9th International
Symposium;

EWICS TC7 publications;

Safety Critical Systems Club symposia;

IEE Computing & Control Journal 2000 2001.

5.3.1

Method of Search

The method chosen reflected the need to be able to undertake a first-cut analysis of the material
using key words such as safety, protection, trips and alarms in the case of journals,
bulletins and abstracts, followed by a more detailed review of those specific references cited
from the first-cut.
For conference proceedings the first-cut analysis consisted of searching the paper titles for
relevance to the subject under review, and if pertinent the second cut a review of the abstract
followed if required by review of the contents of the paper. For other material (books, trade
association material) the first cut consisted of a search of contents and index for appropriate
subject matter with detailed review of sections and chapters if relevant.
5.3.2

Findings

Many of the publications provide information relating to the maintenance of SIS, however, none
explicitly address proof testing. Some publications provide detailed guidance on the
management of SIS during their operational life and make recommendations that support the
guiding principles developed from the industrial research. The content of these publications is
summarised as follows.
UKOOA Guidelines for Instrument-Based Protective Systems Issue 2, November
1999
Section 7, Operations & Maintenance, provides guidance on responsibilities (7.2), Maintenance
and Testing (7.3), Documentation and Records (7.4), Control of Changes (7.5) and Assessment
of Protective System Integrity (7.6). The document also makes the following comments and
recommendations relating to proof testing.

Each responsible person is accountable for ensuring that the systems continue to
perform to the required performance standards. Specific responsibilities include:
-

ensuring appropriate test procedures are available;

assurance of competency of the operator and maintenance technicians who work


with or on the system;

control of access to the system including use of key words and passwords;

control of overrides;

co-ordinating testing of the system;

control of changes;

ensuring appropriate records are maintained;

accessing results of testing, demands rates, system failures etc.

The maintenance, testing scope, frequency and responsibilities should be clearly


documented.

42

Maintenance overrides should be formally authorised and documented and the status
regularly assessed.

Results of periodic testing should be assessed and appropriate measures taken to


maintain required system integrity.

HSE PES 211


The document provides comprehensive checklists which, whilst not specific to proof testing,
does promote the need for a formal operational management system to include:

fault reporting and analysis;

supervision to ensure the continued adherence to agreed procedures;

training provided appropriate to the tasks to be undertaken and personnel involved;

review of maintenance and test procedures;

prevention of unauthorised access to systems.

CCPS Guidelines for Safe Automation of Chemical Processes


This publication includes a section (6.4.3) on Functional Testing. Whilst this covers testing
prior to operation it provides a complete list of validation requirements to be covered in a test,
which can be taken forward and used in follow-on proof testing. A specimen proforma for
functional test checklists is provided.
Section 6.5 covers testing frequency requirements. In addition to the routine testing it
recommends additional testing:

after upgrading the vendor-supplied operating system;

after major work that changes system communications network configuration;

after major upgrades of hardware components.

Section 6.6 provides guidance on installed test connections and necessary bypasses. It
recommends that written procedures exist that prevent having more than one signal bypassed at
the same time. All instances of bypassing should be documented and the return-to-normal
position should be a requirement prior to signing off that any work has been completed. Where
a SIS allows, changes in positions of all bypass switches should be automatically logged. Only
those bypasses that are truly required for maintenance or testing should be allowed in the system
and no master bypass switches should be allowed.
5.3.3

Conclusions on the Literature Search

Whilst this literature search was extensive it did not reveal specific factors directly relating to
proof testing, nor did it identify any dangerous occurrences or incidents where the root cause
was directly linked to proof testing. However, there are a number of points drawn from the
material, which can underpin the development of the set of guiding principles. The majority of
these apply to management and operational systems, rigorous change control and
responsibilities.
5.4

INDUSTRY INCIDENT DATABASE

The database (on 30 Jan 2001) contained details of 23 incidents. The majority of the incidents
recorded are associated with maintenance problems, modifications or line ruptures, however,
one suggests a lesson that relates to protective systems and is described in Table 4 in a
generalised manner to preserve confidentiality.

43

Table 4 : Summary of findings of a review of the industry incident database


Description of Incident

Relevance to SIS Proof Testing

An incident resulted from a pair of block valves The inability of both block valves to seal
(series) which were both passing when adequately remained an unrevealed
notionally closed and a third valve, intended to dangerous fault.
bleed dilution air into the oxidiser was shut by
the control system.

5.5

MAJOR ACCIDENT REPORTING SYSTEM (MARS) DATABASE SEARCH

The MARS search facility was used to query the database, however, no accidents were reported
as being attributable to proof testing issues.
5.6

HSE PROSECUTIONS DATABASE (HTTP://WWW.HSEDATABASES.CO.UK)

The database (checked on 30 Jan 2001) contained details of incidents from a wide range of
industrial and other sectors. This review focuses on the Manufacturing Sector and the
Extractive and Utility Supply Sector as being most relevant to the chemical industry.
There are 55 incidents recorded for the Manufacturing Sector and 6 for the Extractive and
Utility Supply Sector, covering the period from 1994 to 2000. The majority of the incidents
recorded are associated with unsafe systems of work and no incidents could be directly
attributed to proof testing.
5.7

GENERAL CONCLUSIONS FROM SEARCHES

Documented evidence of causal links between incidents and deficiencies in proof testing is rare,
although references to the general management of SIS are more common. The searches have
identified instances of criticism, corrective action and recommendation associated with the
maintenance of SIS though not with proof testing. Furthermore, the results of the searches do
not suggest a need to develop guiding principles beyond those developed as a result of the
industrial research
The lack of documented evidence might be thought to indicate that weakness of proof testing
practices is not a significant contributing factor to incidents, however, the style and content of
the reviewed publications and databases indicate that reporting mechanisms are simply too
coarse to identify proof testing as a contributing factor.

44

APPENDIX 1 : GUIDING PRINCIPLES FOR PROOF TESTING


Proof Testing Practices (4.1.1)
(a) The proof test of a SIS should reflect real operating conditions as accurately as possible. If
reasonably practicable, the SIS should be initiated by manipulation of the process variable
without driving the process into the demand condition. Any approach which involves
driving the process into the demand state should be accompanied by risk assessment and
additional controls.
(b) Where process variables cannot be safely or reasonably practicably be manipulated,
sufficient confidence in the correct operation of sensors should be gained by other means,
such as comparison with other measurements.
(c) The inherent difficulties associated with testing valves and in-line flowmeters should be
addressed during the design phase of SIS and additional provisions such as corroborative
measurements should be made where necessary.
(d) Proof tests should address the necessary functional safety requirements of SIS, including
functions such as response time and valve leakage class.
Content of Proof Test Procedures (4.2.1)
(a) Proof testing should be designed to expose any reasonably foreseeable unrevealed fail-todanger fault conditions in all components including process sensors, logic solvers and final
elements, and in the means of connecting the SIS to the process.
(b) Where overrides are applied to SIS, they should be subject to strict controls to ensure their
safe application and timely removal.
(c) Where the partial testing of SIS or components of SIS is adopted, the impact on process
operation, functional safety and overall test coverage should be established by assessment
and additional controls should be applied where necessary.
(d) SIS installations should be tested as found and should not be disturbed during proof testing.
(e) All test equipment used for proof testing SIS should be calibrated and the calibration should
be traceable to recognised national standards.
(f) SIS should be returned to their correct state following testing.
Format of Proof Test Procedures (4.3.1)
(a) The written proof test protocol should take account of recognised human factors in order to
reduce the potential for errors and violations.
(b) The written proof test protocol should be subject to formal document control procedures.
Planning and Scheduling (4.4.1)
(a) Proof testing should be an integral and explicit part of the planning and scheduling of the
safety management system.
(b) The timing of proof tests should be dictated by the need to demonstrate and maintain
functional safety and should not be compromised by operational or business considerations.
Records of Proof Testing (4.5.1)
(a) The results of proof testing should be recorded and maintained for the purposes of periodic
reporting, audit and historical analysis.
(b) Data arising from proof testing should be collated, reviewed and acted upon in order to
maintain or improve functional safety.

45

Competence (4.6.1)
(a) Personnel participating in all aspects of the proof testing process should be demonstrably
competent to carry out their allotted tasks.
(b) The responsibilities for all aspects of proof testing should be clearly identified and
communicated.
(c) Documented verification by competent persons should be applied to the appropriate stages
of the proof testing process to ensure that each test is sufficient in terms of content and
execution.
Awareness of Hazard and Risk (4.7.1)
(a) The written proof test protocol should describe all identified hazards associated with
undertaking the test together with the any necessary precautions.
Management of Change (4.8.1)
(a) Management of change should explicitly require consideration of the impact of change on
proof testing.

46

APPENDIX 2 : PROPOSED CHECKLIST FOR USE BY


INSPECTORS

This checklist has been designed to assist Field Inspectors to assess the quality of an
organisation's approach to proof testing.
It is designed as a series of high-level statements that can be used directly or to develop more
detailed questions. The assumption made is that SIS will be one of a number of topics to be
addressed during site visits by inspectors. Therefore, the emphasis is on seeking quick and
effective feedback from the organisation, making a judgement, and if confidence in respect of
the responses is low, seeking further expert support leading to more detailed examination of
evidence. The statements are designed to encourage the collection of evidence to support
responses. This evidence may take a number of forms including:

proof test procedures;

calibration records;

test sign-off sheets;

training records;

change control records;

scheduling tools;

management reviews;

risk assessment reports;

incident reporting procedures;

authorisation levels;

lists of Responsible Engineers;

override and bypass management reviews.

47

Principle : Proof Test Practices and Procedures


Guidance

Inspector's Observations

Proof testing should be carried out in an environment


that is as consistent as practicable with operating
conditions. (Tests performed under maintenance
conditions may not necessarily demonstrate that a SIS
would function under operating conditions).
Proof testing should attempt to manipulate the process
variable. (Note that manipulation of the process
variable does not imply manipulation of the process
under control).
Proof testing should not have the potential to place
process, plant or equipment in a dangerous state.
(Driving process variables, particularly pressure and
level, into high states has the potential to create
hazardous situations if SIS fail to operate).
Risks associated with manipulation of the process
variable should be identified and assessed.
Proof testing should provide adequate confidence in the
correct operation of in-line devices, particularly in-line
flowmeters and safety valves. (Note that the use of builtin simulation facilities alone does not demonstrate a
device's ability to operate under operating conditions)
Proof testing should address dynamic SIS performance
by testing features such as response time and valve
leakage class.
Proof testing should be designed to test all components
of SIS (Evidence could be documentation which shows
that reasonably foreseeable fail to danger faults have
been identified and captured in proof test).
Proof testing should address the condition of process
connections, particularly impulse lines.
Proof testing should be designed to address the
condition of all necessary services such as power,
instrument air, gas supplies, trace heating etc.
The use of overrides and bypasses should be subject to a
documented process of risk assessment.
The application of overrides should be subject to
authorisation by competent personnel.
Access to override initiation facilities should be
controlled.

48

Principle : Proof Test Practices and Procedures


Guidance

Inspector's Observations

Operators should be made aware of the presence of


overrides.
Procedures should be in place to ensure that overrides
are removed in a timely manner.
If partial testing of SIS and component parts is
undertaken, its justification should be documented.
Proof testing should not unnecessarily disturb SIS (SIS
should be tested as found).
SIS failures identified during proof testing should be
repaired in a timely manner.
Calibration records should exist for all test equipment
and should be traceable to recognised national
standards.
Proof testing should be based on a firm understanding of
the test and the requirements and competence of the
tester.
There should be evidence of a culture of ownership of
the proof test procedure, for example the testers should
be involved in the preparation and maintenance of
procedures.
Proof testing procedures should be provided in a
consistent and standard form.

49

Principle : Proof Test Practices and Procedures


Guidance

Inspector's Observations

Proof test procedures should address the following key


attributes:

a clear statement of the purpose and scope;

due consideration and documentation of all


precautions that must be observed whilst
performing the tests in order to avoid potential
hazards;

clear identification of any special tools or


equipment required and evidence that the
personnel are competent to use such
equipment;

any initial conditions which must be satisfied


prior to undertaking the test;

adequate cross references to any other


documents, manuals etc.;

clear and concise procedural steps which


adequately define the tasks necessary to
perform the test safely and efficiently;

any warnings or specific issues that should be


drawn to the attention of the tester should be
clearly and conspicuously stated.

The procedures should promote ease of use by way of:

short, precise sentences and instructions;

use of positive active sentences such as open


valve A then valve B.

(Further guidance on human factors is given by HSE


publication ' HSG48 - Reducing Error and Influencing
Behaviour').
Management systems should encourage active feedback
from testing personnel, designed to highlight issues,
difficulties and anomalies in the proof test.
When undertaking the test for the first time, there
should be a process in place for independent witnessing
of the test.
Proof test procedures should be explicitly referenced by
any formal change control regime. (Evidence suggests
that the revision of proof test procedures after a process
modification relies on the thoroughness of the C&I
Engineer and may be neglected).

50

Principle : Planning and Scheduling


Guidance

Inspector's Observations

There should be evidence that proof testing is a integral


and explicit part of the planning and scheduling of the
safety management system within the organisation.
There should be evidence that that the organisation
plans proof testing in a structured and managed way.
The scheduling of proof tests should take full account of
the availability of competent resources.
What is the longest period between proof tests?
Proof test intervals should not be 'stretched' to the point
of compromising functional safety. (The justification for
claimed SIL should be documented and should specify a
required proof test interval. This can be compared with
the timing of planned maintenance activities.)
Any steps to minimise production disruption due to
proof testing should be taken without compromising
functional safety. (Such steps may include alignment of
proof testing with statutory inspections or the grouping
of tests associated with related equipment into a single
activity.)
The deferral of any proof test should be authorised by a
suitably responsible and competent person and the
justification should be documented.

51

Principle : Records of Proof Testing


Guidance

Inspector's Observations

Records and results of proof testing activities should be


retained and be readily accessible.
Records and results of proof testing activities should be
maintained in a form that facilitates future analysis.
(This does not imply a necessity to create electronic
records).
There should be evidence that the data associated with
the tests is subject to analysis and review. (Such data
should include component failure rates, operational
demand rates etc. Reviews can provide opportunities to
validate the design basis of the SIS or to modify the SIS
in line with actual process and SIS performance).
The organisation should take steps to ensure that those
with responsibility for the management of functional
safety have access to the necessary records and reports.
Records of proof testing should cover:

verification of the satisfactory execution of


proof test steps;

details of all faults encountered (for example,


by the use of specific fault codes to facilitate
later analysis);

details of any corrective actions, including


time to repair and effectiveness of remedial
actions;

duration of test;

signature of tester and validator/approver;

ability to record any recommendations, and


evidence that these recommendations have
been subject to review.

52

Principle : Records of Proof Testing


Guidance

Inspector's Observations

The organisation should have in place appropriate


review mechanisms to cover:

reporting of overdue tests;

SIS component failures under test and any


remedial actions;

SIS component failures in operation;

SIS and process performance against the


assumptions of the risk and reliability analysis;

the review of the quality of proof test


execution.

(Such reviews provide evidence of efforts to continually


improve safety management procedures and maintain
functional safety)

53

Principle : Competence
Guidance

Inspector's Observations

Procedures should be in place to ensure that personnel


engaged in the execution and management of proof
testing are suitably competent. (Job descriptions and
training records could provide supporting evidence.)
Competency profiles for proof testing should be
available which detail the necessary knowledge, training
and experience required of testers and approvers.
Records of personnel deemed competent to undertake
proof testing should be maintained.
Personnel regularly engaged in proof testing should
receive refresher training.
The competence necessary to perform the proof test
should be specified within the proof test procedure or
easily accessible to those staff involved in performing
the tests.
If outside agencies are employed to execute proof tests
their staff should be subject to competency assessment
which is at least as robust as that applied to permanent
staff.
The responsibility for proof testing should be assigned
to a nominated role. The person filling that role should
be clearly informed of, and accept, the responsibilities
and accountabilities.
Responsibilities for all aspects of proof testing should
be clearly identified and communicated to the
responsible personnel.
The delegation of responsibility should be managed in a
structured manner.
The approval process should check that:

the proof test procedure describes a sufficient


test of the SIS;

the proof test is safe to apply to the process or


equipment under control;

the outcome of the proof test has been


reviewed and any appropriate actions initiated.

54

APPENDIX 3.1: EXAMPLE OF A FORMATTED PROOF TEST


PROCEDURE
The following example is included to illustrate some, though not all, of the principles of an
effective proof test procedure.
Attention is drawn to the following characteristics:

the use of a title page giving an overview of the proof test and detailing any necessary
preparation and pre-requisites [consistent with principle 4.3.1 (a)];

an estimate of the time to be taken (an implied time limit);

highlighted precautions to avoid a hazardous situation during testing [consistent with


principle 4.7.1 (a)];

a step-by-step approach with each step carrying a unique number;

tick-boxes where the tester is required to confirm an action or status;

boxes for the recording of measured values;

recording of as found details (step 2) [consistent with principle 4.2.1 (f)];

the return to as found conditions (step 6) [consistent with principle 4.2.1 (f)];

document details appearing on each page;

the use of a summary page allowing the detailed recording of any faults [consistent
with principle 4.5.1 (a)];

the requirement for signature by the tester [consistent with principle 4.6.1 (c)];

counter-signature by engineering and operations personnel [consistent with principle


4.6.1 (c)];

signature to confirm that the results of the test have been checked and recorded
[consistent with principle 4.6.1 (c)];

final sign-off by the proof test initiator and the responsible Engineer [consistent with
principle 4.6.1 (c)].

55

A COMPANY

Reference No. :
AAA/AAA/001(j)
Revision No.
:
Date of Issue
:
Page No.
:

CRITICAL INSTRUMENTED
PROTECTIVE SYSTEMS

INSTRUMENT SAFETY METHOD (ISM)


Trip Linkage:
Plant
Section:

Description:
Chemical Plant

Testing Frequency:

26 Weeks

Time Taken:

1hour

Items Actuated:

Initiating Variable(s):

Process Conditions for Testing:

In order to ensure that this test does not create a [hazardous situation], it is essential
to ensure that both stream feed hoppers have been run empty for the last 45minutes.

Preparation:
Agreement for trip testing to be obtained from the Process Manager.
Operator to check that all [processing is] complete before commencing tests as per
instructions above.

Notes:
Obtain a Permit to Work.

56

A COMPANY

Reference No. :
AAA/AAA/001(j)
Revision No.
:
Date of Issue
:
Page No.
:

CRITICAL INSTRUMENTED
PROTECTIVE SYSTEMS

INSTRUMENT SAFETY METHOD (ISM)


Trip Linkage:

Description:

Method:
1)

Make sure that the following drives are running:


[drive 1]
[drive 2]
[drive 3]
Confirm running status from the DCS:

2)

[drive 1]

Yes

No

[drive 2]

Yes

No

[drive 3]

Yes

No

Note the positions of the [drive 3] Fan Inlet and Outlet damper positions.
Inlet V[nnn] - %Open

3)

Outlet V[nnn] - %Open

Slowly close the inlet damper until the fan trips on undercurrent. The damper should be
between 10% open and 20% open. It is acceptable to use the inlet or outlet damper
for this test, but ensure that if either is found to be faulty, that the fault is reported
to process and commented on the results sheet. Note the damper position at the fan
tripped.
Damper Position - %Open

4)

Confirm that the [drive 3] fan has tripped on undercurrent:

Yes

No

5)

Confirm that the [drive 1] has tripped

Yes

No

6)

Return all dampers to their original positions see item 2.

7)

Reset the drives and restart the [drive 1] and the [drive 3],
confirm running on the DCS.
[drive 1]

Yes

No

[drive 2]

Yes

No

[drive 3]

Yes

No

57

A COMPANY

Reference No. :
AAA/AAA/001(j)
Revision No.
:
Date of Issue
:
Page No.
:

CRITICAL INSTRUMENTED
PROTECTIVE SYSTEMS

INSTRUMENT SAFETY METHOD (ISM)


Trip Linkage:

8)

Description:

Initiate a stop of the [drive 2] using the local stop pushbutton, confirm the following
drive trips:
[drive 1]

Yes

No

9)

Reset the drives and leave drives in a running state and fill in the report sheet overleaf.

10)

Sign off the Permit to Work.

58

A COMPANY

Reference No. :
AAA/AAA/001(j)
Revision No.
:
Date of Issue
:
Page No.
:

CRITICAL INSTRUMENTED
PROTECTIVE SYSTEMS

INSTRUMENT SAFETY METHOD (ISM)


Trip Linkage:

Description:

Comments:
Where any faults discovered?

YES/NO

If yes, which loop item(s) were faulty/had failed (please tick relevant box)
Push Button
Ball Valve(s)
Power Supply
Other(s), please specify

Relay(s)
Wiring
Air Supply

SOV(s)
Terminals
Pneumatics

Describe fully the faults/failures for each item (continue on separate sheet if
necessary):

Describe fully the corrective action taken for each item (continue on separate sheet if
necessary)

Signature Test Complete:


Power & Control Technician

Process Technician

Name:
Signature:
Date:

Name:
Signature:
Date:
Return Completed Form Responsible Instrument Engineer

Checked and Recorded:


Responsible Engineer

Comments:

Name:
Signature:
Date:
Revision No:

Note:
Initiator

Name:
Signature:
Date:

Checked (Responsible Instrument Engineer)


Name:
Signature:
Date:

59

APPENDIX 3.2: EXAMPLE OF THE RECORDING OF PROOF


TEST RESULTS

The following example is included to illustrate a structured approach to the recording of results.
Attention is drawn to the following characteristics:

the specification of test equipment;

the requirement to record calibration and corrective actions (step 1) [consistent with
principle 4.2.1 (e)];

the specification of acceptable tolerances (heading panel and step 10);

instructions detailing the action to be taken on discovery of a fault (step 11);

the recording of the test result in the form of a code number allowing future analysis,
reporting and review [consistent with principle 4.5.1 (b)].

60

TRIP & ALARM TESTING


LOOP :

(CLASS A)
SETTING

LIMITS

UNITS

TEST INTERVAL :

PROCESS
INSTS

TEST METHOD
TITLE :
ACTION OF TRIP :
TEST EQUIPMENT :
LOOP NO :
DATE :
*** This Trip/Alarm protects against a SERIOUS hazard ***
Note : This test to be carried out during plant SHUT DOWN.

1.

Ensure that there is a valid PERMIT to WORK for this test. Inform the
Panelman that testing is about to be carried out.
Check calibrate, note values in Comment box and correct as necessary.
Setting :

2.

Panelman to open valves [1], [2], [3], [4], [5].

3.

One man to remain in the Control Room, the other to carry out the outside
work.

4.

Isolate the impulse lines. SLOWLY open the LP vent needle valve to allow
the pressure to fall SLOWLY, the high [process] alarm will be initiated but
continue to allow the pressure to fall until the Extra high [process] trip
annunciator is initiated.

5.

When the annunciator is initiated, note the recorder/indicator reading in the


Comments box.

RESULTS
0
1
2
3

PASS
OPERATED EARLY
OPERATED LATE
DID NOT OPERATE

NOT DONE

TEST RESULT

1
2
3
4
5
9

BLOCKAGE
CALIBRATION ERROR
BREAKAGE
FOUND DEFEATED
WET/STUCK
OTHER

1
2
3
4
5
6
7
8
9

PROCESS LIMITATION
NO ACCESS
NO TEST EQUIPMENT
PLANT IS SHUTDOWN
UNABLE TO DEFEAT
NO I-E EFFORT
NO PROCESS EFFORT
PLANT SHUTDOWN REQD
OTHER

1
2
3
4
5
9

INITIATOR
LOGIC
SOLENOID VALVE
S/D MECHANISM
DESIGN
OTHER

0
1
2
3
4

RETESTED OK
NO SPARES
NO TIME/LAB
NOT KNOWN
NEEDS S/D

OTHER

COMMENTS :

INSTRUMENT : ..............................................................
PROCESS:...................................

ELECTRICAL:..........................................................

61

DATE ........./........../.........

6.

Check that valves [1], [2], [3], [4], [5] have tripped closed.

7.

Recommission the D/P cell.

8.

When conditions are stable, reset the trip using the Reset button.

9.

Ask an authorised person to reset all conditions [1], [2], [3], [4], [5]. Check
that the associated data alarms have returned to normal.

10.

Check and record the zero reading of the transmitter at process pressure. If it
is in error by more than 2.5% of full scale, then the test has FAILED.

11.

If any part of the system failed to operate correctly or if the reading did not
correspond with the required trip or alarm setting within the prescribed limits
then the test has failed. Check each item of the loop. Repair where necessary
and re-test If extensive repairs have to be carried out, inform the Process
Supervisor.

12.

Check that the [process] indication and annunciator(s) have returned to


normal.
Ensure that valve(s) [1], [2], [3], [4], [5] have returned to normal.

13.

Inform the Panelman that testing has been completed.

14.

END of TEST.

62

APPENDIX 3.3: EXAMPLE OF PROOF TEST DOCUMENT


CONTROL

The following example is included to illustrate some of the principles of effective document
control.
Attention is drawn to the following characteristics:

reference to company, plant and unit;

unique document reference number [consistent with principle 4.3.1 (b)];

reference to the specific SIS;

revision history [consistent with principle 4.3.1 (b)];

specific reference to risk assessment [consistent with principle 4.7.1 (a)];

multiple approvals [consistent with principle 4.6.1 (c)];

definitions of the meanings of the different approvals [consistent with principle 4.6.1
(b)];

reference to a controlling procedure for the management of controlled documents


[consistent with principle 4.3.1 (b)].

63

Company Plant Unit


Procedure Number:
SIS Reference Number

DOCUMENT CONTROL SHEET

Document Issue

Date
Risk Assessment No.

Responsibility

Print Name

Signature

Date

Document Owner
Author of change or new procedure
Document Approver (Technical)
Procedure is correctly structured
and technically accurate
Document Approver (Process)
Procedure is correctly structured
and achieves purpose & scope
without adversely affecting process
Document Administrator
(Technology)
Procedure has been risk assessed
and will be filed as master copy

Refer to document number xx/xxx/002 Management of Controlled Documents for explanation


of individual responsibilities.

xxx/xxx/103

Issue A

64

Page of

REFERENCES

INTERNATION ELECTROTECHNICAL COMMISSION (IEC)


Functional safety of electrical/electronic/programmable electronic safety-related systems,
Parts 1 to 7
IEC 61508 :1998 - 2000

AMERICAN NATIONAL STANDARDS INSTITUTE (ANSI)


Application of Safety Instrumented Systems for the Process Industries
ANSI/ISA-S84.01-1996

Engineering Equipment and Materials Users Association (EEMUA)


Alarm Systems - A Guide to design, management and procurement
EEMUA 1999
ISBN 0 85931 076 0

KLETZ, TREVOR
Lessons from Disaster
Institution of Chemical Engineers, 1993

HEALTH & SAFETY EXECUTIVE (HSE)


HSG48 - Reducing Error and Influencing Behaviour
HSE Books, 1999
ISBN 0 7176 2452 8

HEALTH & SAFETY EXECUTIVE (HSE)


Improving Compliance with Safety Procedures - Reducing Industrial Violations
HSE, 1995
ISBN 0 7176 09707

SUMMERS, ANGELA AND ZACHARY, BRYAN


Partial-Stroke Testing of Safety Block Valves
Control Engineering, 2000
Control Engineering On-line
www.controleng.com/archives

DET NORSKE VERITAS


Offshore Reliability Data Handbook - Third Edition
1997

THE INSTITUTION OF ELECTRICAL ENGINEERS (IEE)


Competence Guidelines for Safety-Related System Practitioners
IEE, 1999

10 UNITED KINGDOM OFFSHORE OPERATORS ASSOCIATION (UKOOA)


Guidelines for Instrument-Based Protective Systems Issue 2
UKOOA, Nov 1999
11 HEALTH & SAFETY EXECUTIVE (HSE)
Programmable Electronic Systems in Safety Related Applications: 2. General Technical
Guidelines
HSE, 1987

65

GLOSSARY

DCS

Distributed Control System

E/E/PES

Electrical / Electronic / Programmable Electronic Safety-Related


System(s)

EPICC

European Process Industries Competitiveness Centre

HCF

Humberside Chemical Focus

PFD

Probability of Failure on Demand

PLC

Programmable Electronic Controller

Proof Test

A periodic test performed on a SIS in order to determine unrevealed


failures of all safety-related components (from sensors through to
final elements) which would cause a reduction in the safety
integrity achieved.

QMS

Quality Management System(s)

RF

Radio Frequency

SIL

Safety Integrity Level

SIS

Safety Instrumented System

66

67

Printed and published by the Health and Safety Executive


C30 1/98
Printed and published by the Health and Safety Executive
C1.25
04/02

ISBN 0-7176-2346-7

CRR 428