0% found this document useful (0 votes)
654 views18 pages

BOQ Template

template

Uploaded by

marklester
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
654 views18 pages

BOQ Template

template

Uploaded by

marklester
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 18

Community Market Place _Standard BoQ TEMPLATE

Item
N0.

Description of works

Unit

Spec.

QTY

Unit
Cost

Total
Cost

1.10 Substructure work


Allow for clearing the site from any debris, trees,roots
1.11 etc, filling hollows and levelling.

LS

0.00

1,12 Excavation of found trench 0.4m x 0.5m depth.

M3

0.00

M3

0.00

1.14 above ground level.

M3

0.00

R.C (1:2:4 mix) in ground beam


(0.4m
x0.15m ), with 4N0. Y12 re-bars & R6 links @
1.15 300 mm c/c.
200 mm thick stone hardcore filling well
1.16 compacted and leveled.

M3

0.00

M3

0.00

M3

0.00

Mass concrete in 50 mm thick blinding layer


1.13 (1:4:8 mix ) under the foundation wall.

Rubble stone foundation wall in cement & sand


mortar 1:4 ( 0.8 m x 0.4m wide) min. 15cm

75mm thick murram or other approved backfill


1.17 material, well compacted and leveled.

Total for Item 1.10


1.20 Bill of materials for Item 1.10

0.00

(Substructure works)

1.21 Ordinary portland Cement

Bags

0.00

1.22 River sand or other approved sand

tonne

0.00

1.23 Stone ballast (20mm size)

tonne

0.00

1.24 Foundation stone

tonne

0.00

1.25 Hardcore stone

tonne

0.00

1.26 Murram or approved backfill material

tonne

0.00

1.27 Re-bar Y12

Pcs

0.00

1.28 Re-bar R 6

Pcs

0.00

Pcs

0.00

Pcs

0.00

Kg

0.00

Kg

0.00

Truck

0.00

1.29
1.30
1.31
1.32
1.33
1.34
1.35

White timber 12x1


White timber 2x1
Wire nails 3
Binding wire
Water
Total materials
Transport cost
Labour Costs
Total transport & labour

0.00
%

0.00

0.00
0.00

Total for I tem 1.20

0.00

2.10 Superstructure works including conc. floor slab


Mass concrete (1:3:6 mix ) in conc. floor slab 50 mm
2.11 thick.

M3

0.00

40cm thick rubble stone walling in cement & sand


2.12 mortar 1;4 mix

M3

0.00

20cm thick cement block walling laid in cement &


sand mortar 1:4 mix ( rate to include making of
2.13 blocks)

M2

0.00

R.C (1:2:4 mix) in two level conc. ring beams


(40 cm x15 cm ), each with 4N0. Y12 re-bars &
2.14 R6 links @ 250 mm c/c.

M3

0.00

M3

0.00

M3

0.00

R.C (1:2:4 mix) in 20 cm x 20 cm column shaft,


each with 4N0. Y12 re-bars & R6 links @ 200
2.15 mm c/c.
R.C (1:2:4 mix) in display tables (1m x 0.7m x
2.16 0.05m x 12 N0. ).
Total for Item 2.10

0.00

2.20 Bill of materials for Item 2.10 ( Superstructure works )


2.21 Ordinary portland Cement

bags

0.00

2.22 River sand or other approved sand

tonne

0.00

2.23 Stone ballast (20mm size)

tonne

0.00

2.24 Re-bar Y12

Pcs

0.00

2.25 Re-bar R 6

Pcs

0.00

Well cured Sand /cement hollow blocks (size


2.26 40x20x20 cm)

Pcs

0.00

2.27 Walling stones

tonne

0.00

2.28 Water

Truck

0.00

2.29 White timber 12x1

Pcs

0.00

2.3 White timber 2x3

Pcs

0.00

2.31 White timber 2x1

Pcs

0.00

2.32 Wire nails 3

Kg

0.00

2.33 Binding wire

Kg

0.00

Total materials
2.34 Transport cost
2.35 Labour Costs
Total transport & labour

0.00
%

0.00

0.00
0.00

Total for Item 2.20

0.00

3.10 Roof work


Roof with timber rafters covered with N0. 28 GCI
3.11 sheets with two coats anti- rust paint

M2

0.00

Supply and fix 200mm x 20mm fascia board,


3.12 including two coats enamel paint

LM

0.00

Supply and erect 75 mm diam black steel pipes (or


class A pipes), to include two coats gloss paint, for
3.13 verandah roof support.

Pcs

0.00

Total for Item 3.10


3.20 Bill of materials for Item 3.10 ( Roof work )
3.21 White timber 3 x 2
3.22 White timber 2 x 2

0.00

Pcs
Pcs

0.00
0.00

3.23
3.24
3.25
3.26
3.27
3.28

White timber 6 x1
White timber 12x1
GCI Sheets ( N0.28 )
Roofing nails
Wire nails (assorted)
75 mm diam. Class A steel pipes
Total materials
3.29 Transport cost
3.30 Labour Costs
Total transport & labour

Pcs
Pcs
Pcs
Kg
Kg
Pcs

0.00
0.00
0.00
0.00
0.00
0.00
0.00

0.00

0.00
0.00

Total for Item 3.20

0.00

4.10 Plastering and other finishing


External & internal plastering ,12 mm thick,
4.11 cement / sand mix 1:5, with wood float finish.

M2

0.00

Apply two coats white wash and distemper paint


4.12 to the plastered wall surface.

M2

0.00

M2

0.00

4.13 40 mm thick 1;3 cement/sand floor screed.


Total for Item 4.10

0.00

4.20 Bill of materials for Item 4.10 ( Plastering & other finishes )
4.21 Ordinary portland Cement
bags
4.22 River sand or other approved sand
tonne

0.00

4.24 Water

Trucks

0.00

4.25 Lime

bags

0.00

4.26 Emulsion paint

Litres

0.00

4.27 Gloss paint

Litres

0.00

Total materials

0.00

0.00

4.29 Transport cost

0.00

4.30 Labour Costs

0.00

Total transport & Labour

0.00

Total for Item 4.20

0.00

5.10 Gates, Doors & Windows


Supply and fix wooden panel doors (2.0m x 0.9m)
single leaf, complete with hinges & locks and to
include two coats of gloss paint.

Pcs

Metal

0.00

Supply and fix metal gate ( 3m x 2.5m) complete with


hinges and locks and to include 2 coats of gloss
5.12 paint.

Pcs

0.00

Supply and fix wooden panel windows (1.0m x 1.2m )


complete with wooden frame, hinges & locks and to
5.13 include two coats of gloss paint.

Pcs

0.00

Total for Item 5.10

0.00

6.10 Provisional Items (includes materials & labour )


6.11 Water tank / Plumbing works

LS

6.12 Standard latrine units as per BoQ

LS

6.13 Electrical installation works

LS

0.00
0.00

Total for Item 6.10

0.00
0.00

7.10 Other inputs


7.11 Land

0.00

7.12 Miscellaneus

0.00

Total for Item 7.10

0.00

Grand Total (Bill of materials, provisional items & other inputs

0.00

Grand Total

0.00

(BoQ, provisional items & other inputs)

Note: 1) Ideally the two Grand Totals should be the same, but this is difficult to achieve as long as the estimation methods a
on exactly the same assumptions and criteria.

2) The higher of the two totals should be considered for costing purposes.
Percentage of community contribution

Contribution
Community

CDRD

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

0.00
0.00

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

0.00

0.00

0.00

0.00
0.00
0.00

0.00
0.00

0.00

0.00

s the estimation methods are not based

mmunity contribution

#DIV/0!

ALUMINIUM DOOR & WINDOW


Storey
B1

B2

1ST

2ND

3RD

4TH

5TH

6TH

Code

Description

7TH

TOTAL AREA
TOTAL QTY
TOTAL COST

Specs
Finishes

Dimension, mm
Glazing

Length

Dimension, mm
Height
Width

Unit

Total Area
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

QTY

0
0
0
0

Unit
Cost

Total
Cost

0.00
0.00

You might also like