Bhel (Transformer) Major Training
Bhel (Transformer) Major Training
Bhel (Transformer) Major Training
POWERING PROGRESS
STUDY ON TRANSFORMERS
A PROJECT REPORT
SUBMITTED IN PARTIAL FULFILLMENT OF THE
INDUSTRIAL TRAINING
OF
MECHANICAL AND AUTOMATION ENGINEERING
BY
SOURABH SINHA
UNDER THE GUIDANCE OF
MR. SANJAY KUMAR
(SENIOR PRODUCTION ENGINEER IN TRM DEPTT.)
BHARAT HEAVY ELECTRICALS LIMITED,BHOPAL,INDIA.
Guided by:-
Submitted by:-
Mr.Sanjay Kumar
SourabhSinha
Enrollment No.A12405411019
TRM Division.
Transformers
DECLARATION
I Sourabh Sinha declare that this project report entitled report on a original piece of work
and submitted by me to words partial fulfillment of my B.Tech (MECHANICAL
ENGNEERiNG) graduate program (industrial training), under the guidance of
Mr. Sanjay Kumar (Sr.Poduction Eng.) TRM division BHEL, BHOPAL.
_________________
SOURABH SINHA
Enrollment No.- A12405411019
B.TECH (MECHANICAL ENGG.)
AMITY UNIVERSITY, NOIDA(U.P.)
Acknowledgement
"There are times when silence speaks so much more loudly than words of praise to only as
good as belittle a person, whose words do not express, but only put a veneer over true
feelings, which are of gratitude at this point of time."
I would like to express my sincere gratitude to my industrial mentor Mr. Sanjay Kumar for
his vital support, guidance and encouragement, without which this project would not have
come forth. I would also like to express my gratitude to the staff of the Transformer
Department for their support during the making of this project.
____________
Submitted by:Sourabh Sinha (A12405411019)
B.TECH (MECHANICAL ENGG.)
AMITY UNIVERSITY, NOIDA(U.P.)
ABSTRACT
BHEL manufactures the heavy machineries and it makes the product according to the
customers requirement and the requirements are like weather it can work in humid, high
temperature, low temperature and some of the requirements are like it could work in nuclear
plants and many more conditions.
The development of the Indian heavy electrical machinery industry is directly linked to the
Performance of the Power sector in India. With Indias development, the need for more and
Better Power supply has become essential for industries to grow. Thus with increasing focus
on capacity expansion in the Power sector, the heavy electrical machinery manufacturing
industry is expanding vigorously.
TABLE OF CONTENTS
SR. NO.
SECTION
01.
INTRODUCTION
02.
CORE PUNCH
03.
INSULATION
04.
WINDING
05.
06.
TECHNICAL DIVISION
07.
INSTRUMENT
CHAPTER 2
08.
BCM
CHAPTER 3
09.
CPM
CHAPTER 1
TRM
PAGE
TRM
TCB
Transformer
Capacitor
Bushing
TRANSFORMERS
Power Transformers upto 420kV class, 50/60 Hz 930 MVA, 3-phase Bank.
Power Transformers upto 420kV class, 50/60 Hz 400 MVA, 3-phase Unit.
HVDC Converter Transformers and Smoothing Reactors.
500 MVA, 500kVDC, 3 winding, 1- Phase. Convertor Transformer.
254 MVAR, 360mH, 1568A, 500 kVDC 1 Phase Smoothing Reactor.
INSTRUMENTS TRANSFORMERS
Current transformers up to 400 kV.
Capacitor voltage Transformer up to 420 kV.
REACTORS
Gapped core Shunt Reactors up to 420 kV class, 125 MVAR 3 Phase Unit.
Series and Neutral Grounding Reactors.
Controlled Shunt Reactor up to 420 kV class, 80 MVAR 3 Phase Unit.
Major Consumers of BHEL:
National
International
NTPC
TNB, Malaysia
PGCIL
PPC, Greece
NJPC
MEW, Oman
NHPC
OCC, Oman
NLC
GECOL, Libya
NPCIL
NEEPCO
New Zealand
APTRANSCO
APGENCO
JPPCL
ALL State Electricity Boards
Tanzania etc
CORE PUNCH
Ferrous
Material
M/C
Comp
CRGO
Lamination
Preparation
B.O. Insulation
Component
In House
Insul. Comp.
Fabrication
Component
Assembled
Core
Core
Building
To Next Process
Slitting Machine
Cropping Machine
Stacking / Arranging
Setting (Job)
Core Building
Clamping
Lifting
Tapping
Curing
Lamination Size
M4
0.27 mm
1.00 W/Kg
MOH
0.27 mm
1.00 W/Kg
ZDKH 90
0.27 mm
0.90 W/Kg
ZDKH 85
0.23 mm
0.85 W/Kg
BINA Power
ZDKH - 85
TATA Mundra
MOH
PG Sujalpur
MOH
INSULATION SHOP
i.
ii.
iii.
iv.
v.
vi.
Materials Used:
Press Board (1mm 50mm)
Perma Wood
Bakelite (2mm 25mm)
Fiber Glass (0.5mm 4mm)
Card Sheet / Gasket (for tanking) (3mm 12.5mm)
GUM Fevicol & Dendroid
COIL WINDING
PICC / CTC
Moulded Comp.
B.O. Insul.
Component
In House
Insul. Comp.
Wound Coil
Coil
Winding
To Process
M/S
From
Dimension
01.
Silvassa
7.00 x 2.05 mm
02.
Manipal
10.05 x 1.40 mm
03.
Mandideep
1.90 x 7.50 mm
04.
Japan
2.05 x 9.60 mm
05.
Coil Pre-Heating:
100 oC (min 95 oC oven temperature)
Duration 3 Hours
Types of Winding:
Disc and Interleaved
Helical, Spiral and Inter-Wound Helical
Copper Conductors:
PICC Bunched
GLUED
CTC-GLUED
2.00 x 4.15 mm
Wound Coil
Coil
Assembly
Moulded Comp.
Assembled Coil
To Process 4
B.O. Insul
Comonent.
In House
Insul. Comp.
TAP
HV
LV
HV
TAP
High insulating
Low Viscosity
Low Surface Tension
Optimum Cooling Point
Low Decomposition
Material used: SRBP Synthetic Resin Best Paper
TECHNICAL DIVISION
(VAPOR PHASE DYING PLANT)
Capacity
Autoclave Size
Max Loading
Transformer Rating
: 430 KW
: 12500 x 6000 x 6000
: 450 Ton
: 750 MVA, 765 KV
Process:
It is a process of proper drying of insulation of transformer by a perfectly controlled
automatic process, with lowest possible paper de-polymerization and energy consumption.
Basic Equipment of Vapor Phase Drying (VPD) plant:
a.
b.
c.
d.
e.
f.
g.
h.
i.
j.
Evaporator system.
Condensation system.
Autoclave.
Vacuum system.
Solvent Pumping system.
Heating system for evaporator and autoclave.
Heat recovery system.
Distillation equipment.
Special water extraction measuring equipment.
Computer aided process.
The whole process is carried out in % stages, which is as explained below:
R1: Preparation:
In this first stage, the oven is prepared for the process. The job is let inside the
chamber by means of crane. All the instruments and devices are checked for correct
operation. The oil filling pipe is placed in position. Thermocouple is attached to the core
of the transformer for temperature monitoring; drain plug is connected by steel pipe, etc.
Finally, the door is closed and clamped by hydraulic pump.
High insulating
Low Viscosity
Low Surface Tension
Optimum Cooling Point
Low Decomposition
Advantages of VPD:
01. Fast, uniform heating up of the material to be dried.
02. Substantial reduction in the drying cycle of the transformer compared to conventional
process.
Sr.
Conventional Process
VPD Process
1st Process
12 to 15 days
5 days
2nd Process
07 to 08 days
3 days
BCM
Following are the products of Bushing Manufacturing Division:
Assembly
Processing
Leakage Test
Testing
Pinking
The top cover consists of pack assembly which accommodated washer / stud.
Force is applied by compressor and nut is tightened to hold the complete bushing.
Entire assembly is carried out in five stages, which are explained below:
Stage 01: Assembly of bushing in horizontal position
-
Top Porcelain.
Core condenser bushing.
Top cap.
Bottom porcelain.
Sealing item.
Stage 02: Assembly of bushing in Vertical position
Spring pack.
Top cap setting / adjustment.
Stage 03: Vacuum & Impregnation processing
In N2 pressure test, the bushing is filled up with N2 gas at 1.5 Kg/cm2 and kept under
observation for 12 hours. If any leakage exists, theres a fall in the inside pressure, it is then
identified and rectified. The bushing is then sent to the processing plant for moisture removal
and oil filling.
Oven
Start vacuum
o
100 C /
96 hours minimum
0.005 mBar pressure /
48 hours
Temperature 60 C
24 hours
Start oil filling
Drop by Drop
18 20 hours
Stop Heating
Soaking
24 hours
100 C /
72 hours minimum
0.005 mBar pressure /
48 hours
Oven
Start vacuum
o
Temperature 60 C
24 hours
Start oil filling
Drop by Drop
18 20 hours
Stop Heating
Soaking
24 hours
Temperature 60 C - 65 C
Vacuum
12 hours
48 hours
24 hours
Soaking Duration:
Rating
Duration
420
KV Bushing
16 Hours minimum
245
KV Bushing
12 Hours minimum
145
KV Bushing
08 Hours minimum
72.5 KV Bushing
04 Hours minimum
KV Bushing
04 Hours minimum
52
Bushing Testing:
Routine and type tests are carried out on bushing according to the requirement and
customers demand. A typical routine test observation on 420 KV bushing is shown below.
The basic device for testing is Schering Bridge, and the parameters C3 and R3 are measured:
Parameter
KV
Capacitance C3
Tan delta
Partial Discharge (internal)
10
122
255
364
420
364
255
122
10
The applied voltage on bushing is increased from 0-420 KV and reduced to zero
again, and readings are taken as shown above. Upon reaching 420 KV, an overvoltage of 630
KV is maintained for a period of one minute and the same parameter readings are taken.
CPM
Following Products are manufactured at the CPM Division:
Sr. No.
01.
Product
Shunt Capacitors
Rating
6.6 KV - 500 KV
02.
Series Capacitors
33 KV - 400 KV
03.
Filter Capacitors
up - 500 KV
04.
Surge Capacitors
up - 40 KV
05.
CVTs
33 KV - 1200 KV
06.
07.
Motor Capacitors
Roof Capacitors
3.3 KV - 11 KV
2000 volts dc
Purpose
improvement of power
Factor
reactive compensation
and voltage regulation
different types of
harmonics filtering
(HVDC)
protection of generator &
Transformers
measuring line metering
& power line carrier
Communication
improving power factor
traction locomotive
Shunt Capacitor banks with all film dielectric impregnated with non PCB Impregnate of
desired ratings from 6.6 to 400 kV complete with manual / automatic control equipment for
Industrial and power system application.
Pole mounted Capacitors for mounting in line with Rural Electrification scheme up to 11
KV
Roof Capacitor in Traction Motor application: 4 microfarad, 2 KV DC
Series capacitors for Reactive compensation and voltage regulation in power system from
33kV to 400 KV
Capacitor to improve power factor of traction substations suitable for Railway
Electrification.
Surge Capacitor for protection of Rotating Machine and Generator transformers winding
15 kV and 40 kV, 0.125 micro farad.
AC filter Capacitor for Harmonic filtering suitable for HVDC application up to 500 kV.
Coupling capacitors / CVT up to 800 kV class for Power line carrier communication
application, meeting and protection.
Element Winding
Testing 4.5 KV
Element Stack Assembly
Pack Testing
Soldering and Wiring
Boxing
VP Plant
Rack / Dispatch
Material
Purpose / Dimension
01.
Polypropylene film
as a dielectric- 9 to 18 microns
02.
Aluminum Foil
5 microns
03.
as liquid dielectric
04.
Bushing
Testing:
Well Equipped Capacitor test & ultra high voltage laboratory to cope up
with routine & type test requirements as per latest Indian & International for Power
capacitor & coupling capacitor.
TEST
PROCEDURE
1.
Measurement of
Capacitance.
2.
measurement at rated
voltage.
3.
4.
terminals.
for 10 sec.
container.
5.
Test of Discharge
device.
6.
Sealing test
TEST
PROCEDURE
1.
2.
measurement at elevated
Temperature
test.
container.
3.
container.
5.
Test.
o a labelling scheme,
o the inclusion in energy advice and audit programmes and
o the provision of a toolkit for buyers
would particularly address those market actors who lack information and knowledge or who
tend to follow traditional purchasing routines that do not lead to least-costsolutions. This
particularly affects small and medium industry and commerce, but also some smaller
electricity distribution companies, engineering firms, energy service companies, energy
consultants and planners.
REFERENCESES:
1.
2.
3.
www.Google.com
www.yahoo.com
www.scribd.com