This document summarizes the inspection and testing of electrical work including conduiting and underground piping/sleeves at the AOC Building of King Khalid International Airport. It lists inspection items for switchboards, circuit breakers, main cables, transformers/motors, earth systems, battery systems, and operation and testing tools and equipment. The inspection covers for damage, safety, identification, protection, ventilation, maintenance testing and proper operation. Test reports are required to be according to relevant standards and manufacturer recommendations.

Uploaded by

msmkhan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
158 views3 pages

Checklist 5

This document summarizes the inspection and testing of electrical work including conduiting and underground piping/sleeves at the AOC Building of King Khalid International Airport. It lists inspection items for switchboards, circuit breakers, main cables, transformers/motors, earth systems, battery systems, and operation and testing tools and equipment. The inspection covers for damage, safety, identification, protection, ventilation, maintenance testing and proper operation. Test reports are required to be according to relevant standards and manufacturer recommendations.

Uploaded by

msmkhan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 3

King Khalid International Airport.

T5
Certificate of Inspection & Test for Electrical Work
Electrical Conduiting & Underground Piping/Sleeves
Location :

Building :

AXIS 1-10/ A-O

AOC Bldg.

Floor:

Room:

GROUND FLOOR

Drawing Number :

SDD-AOC-

AS PER ATTACHED
HIGHLIGHTED DRAWING

CIT No.

, Rev.00

ELW-CIT-RBX.-.

S/
N

SubCon
(QA/Q
C)

INSPECTION or TEST

TAJ
CONST

JV
(QA/Q
C)

SAUD
CONSU
LT

Date

(i) No visible damage to impair


safety.
(ii) Safe access and adequate
clearance space provided.
(iii) Work done properly recorded in
log book.

A.
)

B.
)

C.
)

SWITCHBO
ARDS
CIRCUIT
BREAKERS

MAIN
CABLES

TRANSFOR
MERS/
MOTORS

Document
Revision

(iv) Every circuit breaker provided


with a legible and durable
identification label.
(v) An up to date schematic diagram
displayed.
(vi) All accessbile live parts
screened with insulating plate or
earthed metal.
(vii) All exposed conductive parts
effectively earthed.
(viii) Earthing system effectively
connected.
(ix) Warning notice displayed at
main bonding connections.
(x) All protective devices are
functioned properly and correctly
set.
(xi) Padlock facilities for shutter
provided.
(xii) Maintenace test carried out
according to relevant recognised
standards and manufacturers
recommendation, where
appropriate, with test reports.
(insulation resistance test, pressure
test, ductor test, oil dielectric
strength test etc.)
(i) No visible damage to impair
safety.
(ii) Cables protected against
mechanical damage and suitably
supported.
(iii) All exposed metal parts
including the armour effectively
earthed.
(iv) Maintenance test carried out
according to relevant recognized
standards and manufacturers
recommendation, where
appropriate, with test reports.
(Insulation resistance test, pressure
test etc.)
(i) No visible damage to impair
safety.
(ii) All accessible live parts screened
with insulating plate or earthed
metal.

ELWMS-019
0

ITP-019
0

CIT-ELW-1.18
0

King Khalid International Airport.T5


Certificate of Inspection & Test for Electrical Work
Electrical Conduiting & Underground Piping/Sleeves
Location :

Building :

AXIS 1-10/ A-O

AOC Bldg.

Floor:

Room:

GROUND FLOOR

D.
)

EARTH

E.)

BATTERY
SYSTEM

F.)

OPERATION
AND
TESTING
TOOLS
AND
EQUIPMEN
T

Document
Revision

AS PER ATTACHED
HIGHLIGHTED DRAWING

Drawing Number :

SDD-AOCCIT No.

(iii) Proper ventilation provided to


avoid excessive temperature rise.
(iv) Maintenance test carried out
according to relevant recognized
standards and manufacturers
recommendation, where
appropriate, with test reports.
(Insulation resistance test, pressure
test etc.)
(i) A warning notice SAFETY
ELECTRICAL CONNECTION- DO NOT
REMOVE AND ARABIC
Provided at all main
earthing and bonding connection.
(ii) Earthing conductors of adequate
size.
(i) Condition of Battery System.
(ii) Voltage of each battery cell
measured.
(i) Proper operation tools and
equipement provided for switching
and isolation use.
(ii) Suitable self- test high voltage
tester provided for verifying
equipment dead

ELWMS-019
0

ITP-019
0

, Rev.00

ELW-CIT-RBX.-.

CIT-ELW-1.18
0