Capital Investment
Capital Investment
%
A
B
C
Cost of
Capital
D
E
F
Incremental Revenues
Incremental Costs
Taxes
Depreciation considerations
Investment in Working Capital
Cost Savings
EVALUATION TECHNIQUES
A)
Payback Period
Year 0
Year 1
Year 2
Year 3
Proj. A
--------(3,000)
1,000
2,000
3,000
Payback = 2 years
Proj. B
--------(3,000)
2,000
1,000
4,000
Payback = 2 years
Both projects have a payback of two years, so the payback method indicates that the two
projects are equally desirable.
Problems:
1)
2)
Project B returns $1,000 a year earlier than Project A and also returns an additional $1,000 in the
last year.
Present Value (or Discounted) Payback, which utilizes the present value of each year's cash
flow, overcomes the first problem, but not the second.
B)
Year 0
Year 1
Year 2
Year 3
Proj. A
--------Cash Flow PV of CF
(3,000)
(3,000)
1,100
1,000
2,420
2,000
3,000
2,254
Proj. B
--------Cash Flow
(3,000)
2,200
1,210
4,000
PV Payback = 2 years
C)
PV of CF
(3,000)
2,000
1,000
3,005
PV Payback = 2 years
We need a methodology that takes into account all of the cash flows as well as the time
value of money. Net Present Value is one such technique:
NPV = PV of Cash Inflows - PV of Cash Outflows
Required Rate of Return = 10%
0
(4,000)
1,000
2,000
3,000
816
4,000
1,000
Return of Investment
(600)
-------3,400
(1,660)
-------1,740
(2,826)
-------(1,086)
0.7513
--------816
Year 1 Investment
Return of Investment
Year 2 Investment
Return of Investment
Surplus Return
PVIF10%,3
Present Value
Less: Interest
(400) (10%*$4,000)
-------Return of Investment
600
Cash Flow - Year 2
Less: Interest
Return of Investment
Cash Flow - Year 3
Less: Interest
Return of Investment
2,000
(340) (10%*$3,400)
-------1,660
3,000
(174) (10%*$1,740)
-------2,826
The problem with NPV is that there is no consideration of cost, or what is referred to as size
disparity.
Proj. A
Proj. B
-------------Present Value of Inflows
1,050
125
Cost
(1,000)
(100)
-------------Net Present Value
50
25
If these are mutually exclusive projects (i.e., choose one or the other, but not both), the NPV
criterion says to choose Project A. While Project A increases the value of the firm by twice the
amount of Project B, it costs ten times as much. The NPV does not indicate how efficiently
money has been invested.
Capital Rationing - the allocation of a scarce resource, in this case money.
D)
Profitability Index
PV of Inflows
PV of Outflows
PIA = 1.05
PIB = 1.25
The interpretation of PI is that of the amount of money in today's dollar terms that you get per
dollar of investment. This indicates how efficiently you have invested money.
E)
Another measure of the efficiency of investment is the Internal Rate of Return. When
someone asks what rate of return an investment is earning, they mean the Internal Rate of
4,000
(222)
Year 1 Investment
Return of Investment
3,778
(1,266)
Return of Investment
Year 2 Investment
Return of Investment
2,512
2,512
Surplus Return
1,000
(778) (19.44% * $4,000)
222
2,000
(734) (19.44% * $3,778)
Return of Investment
1,266
3,000
(488) (19.44% * $2,512)
Return of Investment
2,512
Hence, it is the rate of interest earned on the funds that remain invested within the project. This
is the economic interpretation of the mathematical solution.
Project A
Project B
Year 0
Year 1
Year 2
(15,000)
(48,000)
10,000
30,000
10,000
30,000
Year 3
0
0
NPV @ 10%
PI @ 10%
IRR
2,355
4,066
1.16
1.08
21.5%
16.3%
PI @ 10%
IRR
Which project is better? The major difference is the costs of the projects.
Year 0
Project C
(10,000)
Year 1
Year 2
8,000
5,600
Year 3
0
NPV @ 10%
1,901
1.19
24.9%
Project D
(10,000)
17,000
2,772
1.28
19.3%
Which project is better? The major difference is the timing of the cash flows.
Note that all three measures agree as to whether a project is acceptable or not. The
conflict is in the ranking of the investment proposals.
Note also that the Profitability Index, a measure of efficiency of investment, does not
always agree with IRR in terms of which is the most efficient use of funds.
Year 1
Year 2
Year 3
(886)
100
100
1,100
Year 0
Year 1
Year 2
Year 3
(886)
900
150
55
Cash Flows
NPV @ 10% = 114
PI @ 10% =
1.13
IRR =
15.0%
Project Y
Cash Flows
NPV @ 10% = 97
PI @ 10% = 1.11
IRR =
20.0%
Year 0
Year 1
Year 2
Year 3
(886)
100
100
1,100
1.21
121
1.10
110
Terminal Value =
1,331
Project Y
Cash Flows
Year 0
Year 1
(886)
900
Year 2
Year 3
150
55
1.21
1,089
1.10
165
Terminal Value =
1,309
Since the costs are the same, the terminal values are both relative to the same size of
investment. The $1,331 terminal value of Project X represents a 14.53% rate of return on an
investment of $886 over three years while the $1,309 terminal value of Project Y is a 13.89%
return on the initial investment. The difference in the terminal values of $22 has a present value
of $17 which is the same as the difference in NPVs of the two projects (114 - 97 = 17). Thus, the
terminal value rankings are consistent with the NPV and PI rankings that indicate Project X is
superior to Project Y. Similarly, if the cash flows of each project are reinvested at their respective
IRRs, the following is obtained:
Project X
Cash Flows
Year 0
Year 1
Year 2
(886)
100
Year 3
100
1,100
1.3223
132
1.15
115
Terminal Value =
1,347
Project Y
Cash Flows
Year 0
Year 1
(886)
900
Year 2
Year 3
150
55
1.4400
1,296
1.2000
180
Terminal Value =
1,531
Since the costs are identical, it is clear that Project Y is better since it maximizes future
wealth, and agrees with the rankings of the IRRs. Moreover, the terminal value of $1,347 of
Project X represents a 15% return on the cost of the project, while the $1,531 terminal value of
Project Y is a 20% return on the investment in Project Y.
NON-NORMAL (NON-CONVENTIONAL) PROJECTS
Multiple Internal Rates of Return
Another criticism of the IRR method is that non-normal (or non-conventional) projects
can have multiple IRRs. Consider the following project:
Cash Flows
Year 0
Year 1
Year 2
Year 3
Year 4
(3,000)
2,000
4,500
3,500
(7,200)
Two IRRs exist: IRR1 = 3.2% and IRR2 = 47.16%. Which one is correct? Technically, both of
them provide a solution to the discount rate that yields a Net Present Value = 0. The text
refers to the question of "A borrowing rate or an investment rate?" in explaining why both are
correct. Let's look at the 3.2% solution:
0
(3,000)
2,000
4,500
3,500
(7,200)
(3,000) * (1.032) =
(3,096)
+ 2,000
(1,096) * (1.032) =
(1,131)
+ 4,500
3,369 * (1.032) =
3,477
+ 3,500
6,977 * (1.032) =
Terminal Value =
7,200
+( 7,200)
-0-
In this case, if you only require a 3.2% rate of return, your 3.2% rate of return and your
principal are returned early in Year 2, and you only need to earn a return of 3.2% on the
investment of surplus funds in order to have enough to payoff the cost of $7,200 at the end of
the 4th year. The same is true with the IRR of 47.16%:
0
(3,000)
2,000
4,500
3,500
(7,200)
1,393
+ 3,500
4,893 * (1.4716) =
Terminal Value =
7,200
+( 7,200)
-0-
Because of the higher rate of return (47.16%), it takes longer to receive your rate of return and
principal back (not until almost the end of the 2nd year since more of the cash flow is rate of
return rather than return of principal) and you must now earn a 47.16% rate of return on the
surplus funds to cover the cost of $7,200 at the end of the project life. (Check out the NPV of
this project at 3.2% and 47.16% to verify that you'll get an NPV of zero.)
In short, the economic interpretation (that it is the return on invested funds) is lost
because it also requires that the surplus funds earn the same rate of interest in order to cover
the cash outflow in the last year. In fact, there is an IRR for each time that the cash flows
change sign (in this case only two).
Many believe this is the primary reason to prefer NPV over IRR as an evaluation tool.
Unfortunately, the concept of a rate of return (such as IRR) is preferred by almost all
practitioners, particularly since it can be compared to the cost of funds or other investment
opportunities.
Another shortfall to NPV is if the risk of the project (or future cash outflow) is higher than
the risk of the average investment for the company. Consider the above example where the
outflow is associated with a great deal of uncertainty about the cost (such as decommissioning a
nuclear power plant). The greater uncertainty implies a higher discount rate be used in
calculating the present value. Yet a higher discount rate makes the present value of the cost
lower, and hence the project more attractive rather than less. One solution to this is to discount
future cash outflows at a separate discount rate from the cash inflows. In fact, the more risky the
future cash outflow, the lower the discount rate that should be employed. This has its own
problems: as shown previously, if NPV assumes cash flows are reinvested at the discount rate,
then an above-average risk project assumes that the (positive) cash flows will continue to be
reinvested in above-average risk projects (i.e., earn a high rate of return) while the aboveaverage risk costs (being discounted at a lower discount rate as mentioned) have a belowaverage cost of capital. Confusing, isn't it?
RELEVANT CASH FLOWS
Incremental Cash Flows
The relevant cash flows for investment analysis is the change in the cash flows that
would occur by accepting a proposal, or what is referred to by the term incremental cash flows.
An opportunity cost is a cash flow given up as a consequence of a decision, and is
generally defined as the next-best-alternative. Since an opportunity cost is a change in cash
flow, it is relevant to the investment decision.
A sunk cost refers to past expenditures. Sunk costs are not relevant since they occurred
in the past and the decision of whether or not to undertake a project does not change the past.
A general (simplified) format for analyzing a capital expenditure that considers all
incremental cash flows is on the following page. Note that the relevant cash flows include those
found on the income statement as well as those that are not on the income statement (such as
working capital). Also, some cash flows are only reflected on the income statement in part (such
as the gain or loss on the sale of an asset).
Intervening Years
E. Incremental Revenues
from new asset
F. Less: Incremental Costs
from new asset
G. Less: Incremental Depreciation
------------------------------------------Change in Taxable Income
Less: Taxes on Tax. Inc. (t)
------------------------------------------Change in Net Income
Plus: Incremental Depreciation
------------------------------------------Incremental Operating Cash Flow
Last Year
I. Salvage of new asset
J. Tax effect of gain or
loss on disposal of
new asset1
K. <Salvage value lost
on old asset>
L. Tax effect of gain or
loss on disposal of
old asset1
M. Recovery of working
capital
Year 2
Year 3
Incremental Revenues
Increased sales
Lost lease payments
595,500
667,500
748,140
Incremental Costs
Labor & materials
Administrative expense
482,000
510,920
541,575
Year 1
Incremental Depreciation
New Machine
MACRS rate
Year 2
Year 3
280,000
20.00%
280,000
32.00%
280,000
19.20%
New Depreciation
56,000
89,600
53,760
Old Machine
MACRS rate
90,000
19.20%
90,000
11.52%
90,000
11.52%
Old Depreciation
17,280
10,368
10,368
Incremental Depreciation
38,720
79,232
43,392
Sale of Equipment
Old machine - Yr. 0
Market Value
Book Value
Gain (loss)
Tax rate
45,000
43,200
1,800
40%
720
8,000
5,184
Gain (loss)
Tax rate
2,816
40%
1,126
50,000
80,640
Gain (loss)
Tax rate
(30,640)
40%
(12,256)
Working Capital
(90,000*48%)
(90,000*5.76%)
(280,000*28.8%)
Year
Required
Change
0
1
2
3
85,000
91,800
99,144
107,076
85,000
6,800
7,344
7,932
Year 1
Year 2
Year 3
595,500
(482,000)
(38,720)
667,500
(510,920)
(79,232)
748,140
(541,575)
(43,392)
74,780
(29,912)
77,348
(30,939)
163,173
(65,269)
44,868
38,720
46,409
79,232
97,904
43,392
83,588
125,641
141,296
( 6,800)
( 7,344)
( 7,932)
( 85,000)
(280,000)
50,000
12,256
45,000
( 720)
(8,000)
1,126
(320,720)
76,788
118,297
295,822