Preguntas para Examen
Preguntas para Examen
1. Which BOM (bill of materials) selection possibilities are available for opening
a production order?
Automatic selection controlled with Customizing settings
Selection using a production version
2. Which statements about the reorganization of planned independent
requirements in SAP ECC are true?
The reorganization only affects planned independent requirements that lie on a
time axis to the past from a specified key date.
The reorganization can be parameterized using a plant-specific reorganization
interval.
3. Which options can you use to convert planned orders into production orders
in the SAP ECC system?
Mass processing
Background processing in a program
Order progress report
4. The company you are advising uses a plant data collection system from
company XYZ and would like to distribute production orders to the terminals on
this system and enter feedback using these terminals. Which integration
possibilities would you recommend so that as little work as possible is required
for the customer to implement this?
The plant data collection interface (PP-PDC)
5. During the implementation of SAP ECC material requirements planning, the
project team defines MRP controller numbers in Customizing under the entry
"Define MRP Controller" that can be assigned to the planners responsible for
the material. Which of the following statements are correct concerning these
MRP controllers?
The MRP controller number is a central selection
A planner responsible for a material can have multiple MRP controller numbers.
6. In the SAP ECC system, you interpret the result of a routing schedule. When
scheduling a routing in the SAP ECC system which of the following time
elements are interoperation times?
Floats before and after production
Move time
7. You enter a new BOM (Bill of Materials) in SAP ECC but forget to enter a plant
reference. Which of the following statements describes what happens when
you try to save it?
When saving the BOM, a group BOM is created which can, under certain
conditions, be assigned to a plant later
8. Which of the following organizational units does the manufacturing,
planning, and execution process use?
Storage Location
Plant
9. What options does the SAP ECC system offer to retrieve the available
capacity for work centers?
Standard available capacity
Interval of available capacity
Shift sequence
10. A user of the SAP ECC system wants a rolling planning time fence (firming
type = 1) to be set up for a material; in other words, new planned orders are
firmed within a planning time fence. When an unforeseen production failure
occurs, it can happen that such firmed planned orders are not being processed
because time passes. What solution would automatically delete firmed planned
orders?
In the material master, an MRP type is used in which the roll-forward
mechanism is activated (Customizing for requirements planning).
11. Following are valid BOM categories
b) Material BOM
c) Equipment BOM
d) Costing BOM
12. Material BOM that is created without plant is called
c) Group BOM
13. If a Header Material is used as a BOM item in the same BOM the BOM is
referred as
a) Repetitive BOM
b) Alternative BOM
c) Multiple BOM
d) Flexible BOM
e) Recursive BOM
Ans:
14. Alternative BOMs are grouped under one internal number and are called
a) Multiple BOM
b) Variant BOM
c) Variable BOM
d) Super BOM
e) Header BOM
Ans: b
15. BOM can be used for the following
a) MRP
b) Costing
c) Inspection data
d) Sales & Distribution
16. The base quantity in the BOM specifies
a) To which amount of the semi finished product the item quantities refer
b) To which amount the item quantities required for two or more finished
products
c) To which amount of the finished product the item quantities refer
17. Work Center is used in
a) Routing
d) Inspection Plans
18. Routing contains information on the following
a) Material Components
b) Operations
c) Capacity for Work Centers
19. Alternative sequences in routing are created with reference to
a) Parallel Sequence
b) Master Sequence
c) Standard Sequence
d) Reference Sequence
Ans: b
20. Work Center requires formulas for the following
a) Move time
b) Scheduling
c) Capacity requirements
d) Cost estimate using activities
Ans: a, c, d
21. Routings are identified by
a) Routing Group
b) Routing Status
c) Group Counter Values
d) Routing Group and Group Counter Values
e) Status and use
Ans: d
22. You can assign work center to only one cost center in a time period.
a) True b) False
Ans:
23. Production Planning Module is integrated with the following modules.
a) Material Management
b) Controlling
c) Quality Management
d) Sales & Distribution
24. Movement Type for Goods Receipt in to Ware House
c) 101
25. Movement Type for Transfer Posting to storage location
c) 311
27.
What are the options for the material staging from a warehouse
management system? (more than one option is correct)
a) Create parts are ordered manually
b) Release order parts are ordered manually
c) Pick parts are provided for the production order in exactly the same quantity
as the requirements quantity
d) Release order parts are ordered automatically
Answer: a, b &c
For the material staging from a warehouse management system, there are
three options for the production order. These options are described here:
Pick parts are provided for the production order in exactly the same quantity as
the requirements quantity
Create parts are ordered manually when a crate is almost empty. Typical
examples are small parts in containers such as screws, nails..
Release order parts are ordered manually: The required quantity is calculated
using the targe quantities of the components in the selected released orders.
Typical examples are laminates, paints
28. Consider a product scenario where there is high product stability, high
repetition rates, and low product complexity. What type of manufacturing do
you suggest?
a) Mass manufacturing
b) Bulk manufacturing
c) Repetitive manufacturing
d) Order based manufacturing
Answer: c
To allow the material to be used in repetitive manufacturing, you set the
Repetitive Mfg indicator in the material master (in the MRP view). This means
that you can use the various production versions of this material for repetitive
manufacturing (that is, you can set the indicator Repetitive Mfg allowed for
version in the production version.)
The BOM defines the planned material consumption for the components. When
you backflush components in repetitive manufacturing, you can define the
issue storage location from which components are to be backflushed in the
status/long text of the BOM item (Production storage location field).
Production lines are usually created as simple work centers in the ECC system.
In the work center, you define the availability of the production line. The
production line created at the work center is entered in the Production line field
in the production version. This same work center is specified in the single
operation of the routing. Production lines that have more than on work center
can be represented in a line hierarchy.
In repetitive manufacturing, the routing define the production rate (quantity
per time unit) used to produce materials on production lines. The production
quantities and their capacity requirements are scheduled and calculated
respectively according to the production rate.
The routing therefore forms the basis of lead time of scheduling. In repetitive
manufacturing often have only one operation. The total production rate of the
line is specified in this operation. It define how many materials per unit can be
produced on this production line. In the singe operation, you enter the
production line as the work center.
30. What is the industry standard that uses COM/DCOM technology to define
manufacturer-independent interfaces for the industrial usage area?
a) SAP COM/COM model
b) SAP OPC
c) SAP OCOM
d) SAP OLE
Answer: b
SAP OPC Data Access (SAP ODA) enables the reading and writing of data points
and event using the OPC server of the ECC system. These functions are also
available with the production order environment.
OPC stands for OLE for Process Control and Openness, Productivity and
Connectivity, and is an industry standard that uses COM/DCOM technology to
define manufacturer-independent interfaces for the industrial usage area. The
OPC standard was designed especially for the process control level.
OPC servers enable you to access different data sources (for example, process
control systems, memory programmable controls, temperature sensors) and
thus provide process data which can be requested by OPC clients.
SAP ECC with the component SAP ODA is an OPC server and client that can
communicate with OPC servers. This considerably simplifies the data exchange
between applications. OPC servers and OPC clients are currently PC-based
systems based on which Microsoft operating system runs.
31. As a production manager how do you enable process operations parallel to
and independent of other operations?
a) Parallel sequences
b) Successor relationships
c) Control sequences
d) Linked sequences
Answer: a
The parallel sequence enables you to process operations parallel to and
independent of other operations. You can copy both parallel and alternative
sequence types from the routing to the order. Parallel sequences are linked to
the standard sequence through predecessor/successor relationships. Parallel
sequences are a special form of overlapping operations. This gives rise to
network-like structures. Order scheduling inserts operation floats according to
the alignment key specifications. In mechanical engineering for assemblies
involving the production of individual components, inspection processes and
preparatory and closing operations.
In the chemical industry for analysis processes that are carried out in parallel to
the production process.
32. What is the difference between regenerative planning and net change
planning?
a) Planning all materials from the planning file, you can only plan materials for
which planning file exists.
b) Planning all materials bases on demand, you plan all materials bases on
previous production
c) Planning all materials parallel, planning all materials from previous planning
file
d) Planning all material online, planning is carried out as a background job
Answer: a
Regenerative planning means you plan all materials from the planning file. Net
change planning means that you can only plan materials for which planning file
exists. This means that they have undergone a change relevant to MRP within a
restricted planning horizon. You can only generate planning proposals within
the horizon. Planning is carried out online or as a background job.
Creation & Conversion of Planned Order in ECC
33. What is the report that collects all important information about a work
center or a hierarchy of work centers of a shift?
a) Shift report
b) Shift transfer report
c) Transfer report
d) Shirt work center report
Answer: a
The shift report is a document that is generated manually by the production
scheduler once data capture for the preceding shift has been completed. The
shift report is used for collecting all important information about a work center
or a hierarchy of work centers of a shift. The shift report thereby facilitates shift
transfer.
The shift report consists of the following parts:
Shift notes
Maintenance notifications
Graphical evaluations
In Customizing for the shift report, you define which information you want to be
part of the shift report and which layout you want to use for the document.
You cannot change the shift report manually.
35. Settlement in product cost controller is based on? (more than one option is
correct)
a) Period-oriented
b) Costs of the product cost controller
c) Order settlement
d) No settlement rule
Answer: a & b
In product-related costs object controlling, all costs are debited and credited to
a product cost controller. Individual production orders do not have cost
segments or settlement rules. All functions in Production and Materials
Management that are relevant to costs( material withdrawal, confirmation,
goods receipt for the production order and goods receipt from production) are
executed on the basis of the production order.
All controlling functions (process cost allocation, overhead allocation, WIP and
variance calculation, settlement) are carried out at the end of the period on the
basis of product costs collector. Thus, the relevant values are determined.
The current costs for a period comprise values for:
Make-to-stock production