J8
J8
J8
SLQS Journal
Editorial Committee
Dhammika T. Gamage
NDT(Civil Eng.), ICIOB, ACIArb, AAIQS, AIQS-SL, FIIE(SL), IEng, FACostE, FCInstCES
Lakshman Gunatilake GCGI, MBA (Sri J.), FCMI, FQSi, MCInstCES, ACIArb, MIIE(SL), IEng, PMP
Manju Sri Adikari BSc. (Hons), MRICS, MCIArb, MIIE (S.L.) I Eng, GCGI (UK)
Nishantha Fernando, BSc(QS) Hons, MRICS, MAA
Prasanna Pushpajith DipSurv., MSc, MRICS, ACIArb
Sudeera A. Widanage., BSc(QS) Hons, MRICS
Editorial Policy
We, the editorial committee reserve the right to select, reject, edit, and excerpt articles at our sole discretion. We will
publish no article which, in the opinion of the editorial committee, can be reasonably interpreted as insulting or offensive
to any individual or group. We will not return unsolicited manuscripts. The opinions expressed in articles contained in the
SLQS Journal are the opinions of individual authors and not necessarily those of the SLQS Journal editorial committee.
Articles are provided for the general interest of the quantity surveying and contract administration community, but the
information contained therein does not constitute legal advice and should not be relied on as such. Neither the SLQS nor
the individual authors assume any responsibility for the accuracy of information reported.
The editorial committee assumes no responsibility for failure to report any matter inadvertently omitted or withheld from
it. The mode of citation utilised within the articles and for the bibliography would be the Chicago method.
Email your own creations to [email protected] with your passport size photograph and brief profile of yourself which
should not be more than 35 words.
June 2012
SLQS JOURNAL
CONTENTS
Page
Editorial
Four Reasons for Adopting Adjudication Process in UK Construction Industry
Murugesu Sathiyaseelan LLM (with Merit), FRICS, MCIArb
13
16
19
24
The Steps an Arbitrator should take before and During a Full Oral Hearing
Priyankara Premarathna, HND QS, ACIArb
27
31
40
Prevention Principle
Senerath Wetthasinghe LL.M., AIQSSL, AAIQS, MQSi, FCIArb
46
52
SLQS JOURNAL
June 2012
Editorial
Dear Sri Lankan Quantity Surveyors,
As we start experiencing summers burn in the UAE, Europe and North America are being buffeted by the heat of
desperately flailing economic waves. The emerging BRICS economies are also about to experience theburn of the
same global economic waves, with India being the first of the member nations to feel the heat.The professionals
associated with the UAEs construction industry one of the most impacted by the global economic downturn cannot think of any easy shelter from this scorching heat. Therefore, we, as sound contract administrators, have a
duty to deliver with due diligence, in order to avoid any actions that could further worsen the existing crisis. On
that note, we hope the 2012 Olympics will bring a cooling breeze to the economic shores of the UK.
We are pleased that we managed to release the overdue 8th Volume of this journal and hope that it brings you as
much gratification as the ones preceding it.
Murugesu Sathiyaseelans promotion of the adoption of adjudicationas a most cost-effective and speedy alternative
to lengthy arbitration and litigation can be considered one of the more appropriate topics to whisper within the
construction industry. Similarly, Dr. Chandana Jayalaths article complements the sentiments expressed earlier
perfectly. Likewise, Sampath Marasingheges proposal is another effective tool to eliminate the fear of undue
encashment of performance securities.
While Prasanna Jayaweeracomprehensively discusses procurement routes and strategies in general, Asanka
Sanjaya Kumara focuses on the specific desire for lump sum building contracts among UAE clients. The articles
by Senarath Wetthasinghe, C. J. Quickson and Priyankara Premaratna display an excellent trend in career
progression, towards construction dispute resolution, with the first in particular being a comprehensive treatment
of the Prevention Principle. The article by Saman Welagedaraprovides a look at regular contract administration
practices.Vajira Kosala Hettiarachchis well-written article goes on to add further merits to the Samaratunga
Formula. Kidneswaran Kajananthas article has so cleverly documented Prof. Sams seminar that it evokes the feel
of the very auditorium in which the seminar used for the article was delivered.
On a cheerful note, you may once more see a new name, that of Mr. Sudeera A. Vidanage, amongst the members
of the editorial committee, whose thanks go to him for his commitment to delivering this excellent reference to
you.
To bring this editorial to its terminus, we ask all our readers to recall that this journal is your property. As such,
its performance is indeed your concern and all feedback and articles are not only appreciated, but an active part
of being a member of the SLQS and the construction community. We anticipate your academic pleasure and
hope that you assist us in ensuring it for future readers as well, by providing high-quality articles of your own in
the near future.
On behalf of the editorial committee,
Dhammika T. Gamage
June 2012
SLQS JOURNAL
Four Reasons for Adopting Adjudication
Process in UK Construction Industry
Murugesu Sathiyaseelan LLM (with Merit), FRICS, MCIArb
Executive Surveyor working with Gardiner & Theobald since August 2003, Counsellor and APC Panel
Chairman of RICS UAE
Is it a speedy process?
June 2012
SLQS JOURNAL
Adjudication is a dispute resolution process employed in
the construction sector which as per 23(2) Pt 1 Scheme
(The Scheme for Construction Contracts Regulations
1998) and Section 108(3) of the Act (Housing Grants,
Construction and Regeneration Act 1996) states that:
After the Act came into force many criticisms that as per
the statutory rights the adjudication has to be carried out
within a narrow time frame which could be unreasonably
tight so as to result in injustice. Parliament is aware of
this.
The Macob Civil Engineering Ltd v Morrison
Construction 1999 case which was the first enforcement
case to come before the court. In this case paragraph 14
[defines the above statement?] and also states that the time
frame for adjudicator is very tight (see s.108 of the Act).
SLQS JOURNAL
Also, it is worth reproducing the passage (paragraph 8)
from another case of Costain Ltd v Strathalyde Builders
Ltd 2004 - Judical control of adjudicators decision:
June 2012
June 2012
SLQS JOURNAL
Conclusion
The
Macob Civil Engineering Ltd v Morrison
Construction case asserted that the following intentions
of Parliament were achieved:
June 2012
SLQS JOURNAL
Demystifying a Mechanism to Deal with
Open Market Vacillations
Dr. Chandana Jayalath
D.Sc, M.Sc, B.Sc (QS) Hons, PG Dip (Cons Mgt), PG Dip (Intl Mediation), FRICS,
FIQS (SL), MCIArb
Consulting Engineering Group, Doha, State of Qatar
[email protected]
SLQS JOURNAL
3.
4.
5.
6.
10
June 2012
SLQS JOURNAL
a fixed number); no stock outs occur and materials are
ordered and produced in a lot [of batch?] and the lot is
placed into the inventory all at one time. The unit cost is
constant and no discounts are given for bulk purchases.
The purchasing cost per unit is unaffected by the quantity
ordered and the carrying cost depends linearly on the
average inventory level. This approach to determine
EOQ which involves optimizing costs of holding stock
against costs of ordering stock has been subject to much
controversy. In addition to concerns about the validity
of some assumptions, more recently, criticisms emerged
of the underlying rationale of the approach itself. In
order to keep the EOQ model relatively straightforward,
it is necessary to make assumptions related to stability
of demand, existence of fixed identifiable ordering cost,
and the cost of stockholding and so on. While none of
these assumptions is often strictly true, at times these
assumptions do pose severe constraints to the model.
Although the most fundamental criticism of the EOQ
approach comes from Japanese inspired JIT philosophies,
it would be too difficult a task for construction commercial
managers to find out representative costs of ordering and
stockholding in the light of these cost variables.
Where the forces of supply and demand tolerate the
price equilibrium, obligating the contractor to procure
materials from sources designated by the employer is
not only a gross intervention into contractors internal
transactions which are commercial by nature but also an
intervention in the supply chain. The theory of supply
and demand as an organizing principle for explaining how
prices coordinate the amounts produced and consumed
applies to price and output determination in the market
on the condition that no buyers or sellers are large enough
to have price-setting power. Market equilibrium occurs
where quantity supplied equals quantity demanded at a
price below equilibrium, and when there is a shortage of
quantity supplied compared to quantity demanded, it
poses a price hike-up in the accredited sources more than
in the open market. According to Milton Friedman and
many other monetarists, market economies are inherently
stable if left to themselves. Friedman effectively claims
that the social responsibility of business should be to use
its resources and engage in activities designed to increase
its profits (through) open and free competition without
deception. In Adam Smiths view, the ideal economy
is a self-functioning market system that automatically
satisfies the economic needs of the populace. Smith
describes the market mechanism as an invisible hand
June 2012
that leads all individuals, in pursuit of their own selfinterest, to produce the greatest benefit for society as
a whole. Demand-and-supply analysis can be used to
explain the behaviour of any type of market including
construction which is oligopolistic in nature for many cost
significant items. An intervention in the supply chain by
a major construction client (contributing a considerable
proportion of the gross domestic product (GDP) through
accreditation) is therefore a serious concern. In a nutshell,
large scale procurement through accredited sources can
be detrimental in the long run.
Another pitfall in such a mechanism is that the BOQ
items with materials supplied by accredited suppliers shall
be priced in two different places in the tender document:
supply cost to be priced under a separate schedule and
all other cost elements under respective BOQ items. This
method of pricing Bill of Quantities not only changes
the standard way of pricing (inter alia based on pricing
preambles) but also makes the evaluation of variations
difficult. This is an unnecessary infiltration of the pricing
strategies the contractors may employ from project to
project on different bases. Duplication of the costing of
materials may occur since the cost of a particular material
can be included under several bill items, except in a very
few cases. Instructing the bidders to be careful about
duplication would not suffice. Restricting premature
ordering from compensation is another drawback, which
is again an intervention in the contractors procurement
policy, forgetting the principle of economies of scale
which any prudent contractor follows in materials
procurement. This restricts the benefits of premature
bulk purchases for many forthcoming projects and in
line with replenishment of stocks at site level so that the
accredited suppliers price may have gone up more than
other sources in the market.
Thus, in devising a defect free mechanism, care must
be taken not to disturb the freedom of business. For
instance, the contractor has the liberty to procure
materials from a source of his own choice while the
employer also reserves the right to specify the source
of procurement in some instances. It is the duty of the
contractor, not the employer, to establish the basic prices
against the specified materials under specified bill items
forming part of the tender. Prices could be ex-factory,
imported or open market as the case may be, and it is
a pre-tender function of the consultant to specify the
materials, compute the input proportions and list them
11
June 2012
SLQS JOURNAL
in the tender document and verify the base prices with
a tender price break-up in support. Care must also be
taken in specifying materials eligible for compensation
since the use of materials may differ according to the
type of project. A reference list of construction material
would be in the case of residential building projects
of steel, cement, concrete, sand and stone whereas in
infrastructure projects it would be of concrete, timber
material, sand and stone, bridge columns, expansion
joints, asphalt products, drainage pipes, pre-fabricated
concrete components, etc. Therefore, price adjustment
clauses must be approached with care and should be
diligently drafted, specifically identifying the individual
building materials most at risk of price fluctuation. The
consultant should also check the authenticity of the
escalation information as a post-contract function. Also,
the consultant must keep records of variances in prices so
that a claim for contract price adjustment in a deflation
can be made on the employers behalf. Once the price
difference has been identified, it shall be a separate claim
in its own right.
Contract rates are not subject to change due to price
escalation, meaning that the rates shall not be revised
depending on the level of fluctuation. Also, a claim on
price escalation is separate from a claim for liquidated
damages by the employer since a delay in procurement
due to delay in progress has a knock-on effect that does
not prejudice the contractors eligibility for contract price
adjustment on open market price escalation. By the same
token, the contractor reserves the right to claim on price
escalation even during the extended period/s since he has
been permitted to complete the work on a new date.
Equally important is the notification procedure to hold
the contractor responsible for notifying the employer
of a price increase and its impact on the contract sum
12
June 2012
SLQS JOURNAL
Performance security and possible
alternative mechanism for performance
security in the economic downturn
Sampath Marasinghege, B. Sc Hons (QS)
Is a Quantity Surveyor graduated from University of Moratuwa, Sri Lanka in 2002. He is currently working
for Damac Properties LLC as a Quantity Surveyor.
Introduction
13
June 2012
SLQS JOURNAL
1. It is a pledge by the guarantor, i.e., the bank, to
indemnify the employer merely when demand is
made upon him by the latter, and
2. It entitles the employer to call upon the guarantor
for payment whether or not there has been default
under the contract provided only that the call is not
fraudulent.
The duration and amount of a guarantee depends upon
the terms on which it is given in the contract. Generally,
in a FIDIC form of contracts, a performance security
remains in force until the contractor has completed the
works and remedied any defects.
14
June 2012
SLQS JOURNAL
Not only main contractors but also most employers
now accept security cheques from their contractors as a
performance security owing to the economic downturn.
The amount of the security cheque is equivalent to the
amount of performance security stated in the contract.
Security cheques can be provided as an undated cheque
or a dated cheque. However, it has to be noted that the
security cheque provided for performance security is a
dated cheque. There is a validity period for dated cheques
set by the Central Bank of UAE (as per current rules, it is
six months from the date of issue) and the dated cheque
needs to be re-issued by the contractor prior to its expiry.
The following advantages can be identified in this
alternative mechanism for performance security:
1. As stated in the aforementioned alternative
mechanism, there are no additional bank charges to
obtain security cheques; and
2. Since the amount of security cheque is equivalent
to the amount of performance security from the
commencement of the project, the employer has an
opportunity to make full payment at any stage of
the project.
However, there are several disadvantages in this alternative
mechanism that can be summarized as follows:
1. Generally, a performance security is an arrangement
under which the performance of one party for
another party is backed up by a third party. In
this alternative mechanism, however, there is no
financial guarantee provided by the third party to
the first party, i.e., the employer, but the second
party. i.e., the contractor provides the guarantee by
himself. There is a financial risk to the employer by
a dishonoured cheques though contractors provide
security cheques;
2. If the security cheque is a dated cheque, it is required
to validate the cheque before its expiry;
3.
Conclusion
15
June 2012
SLQS JOURNAL
Why most UAE clients go for Lump Sum
building contracts
S.M. Asanka Sanjaya Kumara
BSc (Hons), NCT(QS)
Asanka is a Quantity Surveyor graduated from The University of Reading, UK in year 2011. He completed
his National Certificate of Technology course in Quantity Surveying at Technical College, Sri Lanka in year
2005. Asanka has worked as a Quantity Surveyor in Sri Lanka, UAE & Morocco during the last decade. He
is currently working for Depa Interiors, Dubai, as a Senior Quantity Surveyor.
16
June 2012
SLQS JOURNAL
construction errors, and other unforeseen costs that that
the contractor might incur, but has no protection against
under the terms of the contract. When considering those
contingencies, the eventual cost may turn out to be
significantly different from his estimates originally made
for the work. The contractor takes the risk that overexpenditure will result in a smaller profit than expected
or even a loss, in the knowledge that, if all goes well, his
profit may be greater than expected.
Lump sum contracts can be divided into two major parts;
i. Lump sum contracts with quantities are based on
drawings and firm Bills of Quantities (BOQ), and
ii. Lump sum contracts without quantities are usually
based on drawings and specifications together with
schedule of work.
17
June 2012
SLQS JOURNAL
Participants were informed to disregard variation
situations during the survey (assumed there are no
variations). According to the above Figure 1, 93% of
respondents believe cost certainty to be the main reason
for the selection of lump sum contracts if there are no
variations.
The next two highest percentages of 85% & 83%
respectively were received for easy post-contract
management (assumed there are no variations) and easy
to forecast client cash flow.
Less post contract paper work also a major reason for
selecting lump sum contracts if there are no variations.
62% of participants state limited overall project duration
and 60% say to achieve faster construction and limited
post-contract duration as the other factors.
As per Figure 1, 65% and 62% of participants believe that
lump sum contracts will cause post-contract disputes and
it is difficult to manage variations. Therefore, handling
of post-contract variations has been identified as a key
problem of lump sum contracts.
Risk allocation between the client & the contractor in different procurement routes (Figure 2)
(Takashi Saito,1999)
References
1.
2.
18
June 2012
SLQS JOURNAL
Type (b)
A letter of intent incorporating interim contractual
arrangements: As a request by the Employer to the
Contractor, which if actioned by the Contractor, creates
an interim contract between the parties on terms that fall
short of the terms and conditions of the relevant standard
form.
19
June 2012
SLQS JOURNAL
Type (c)
A letter of interim sufficient to form a contract for the
entire project: As a request by the Employer to the
Contractor, which, if actioned by the Contractor, creates
an interim contract between the parties on most or all of
the terms and conditions of the relevant standard form
OR
As a final contract between the parties incorporating
the terms and conditions of the formal, written contract
notwithstanding the failure of the parties to execute the
formal, written contract.
Dividing the Letters of Intent into the above three
categories will depend on the intention of the parties,
which is found by an objective interpretation of:
a. The language of the Letter of Intent
b. The surrounding circumstances, including anything
the parties wrote, said or did subsequent to the
Letter of Intent.
20
June 2012
SLQS JOURNAL
As discussed above, where the cases fall into Type (a), the
effect of the Letter of Intent is to authorize the Contractor
to carry out the work. However, the Contractor will be
entitled to stop work at any time without notice.
21
June 2012
SLQS JOURNAL
Court of Appeal found that the words meant that the
only circumstance in which Harvey would be entitled to
a quantum meruit was if the contract did not proceed
and was not finalised. The contract did proceed and so
Harvey was not entitled to a quantum meruit.
Allen Wilson Shopfitters v Buckingham13 is another case
where HHJ Coulson QC concluded that the signing and
returning of the Letter of Intent by the contractor led to a
contract incorporating the JCT conditions referred to in
the Letter of Intent.
Summary
As discussed above under 3 Types, the more recent cases
show that the court is inclined to find a contract if it
can (at least in construction/engineering cases) since the
court believes this will usually accord with the intention
of the parties (Hall & Towse v Ivory Gate, Durabella v
Jarvis, Jarvis v Galliard).
However, when the Letter of Intent and the surrounding
circumstances show that the parties were continuing to
negotiate about matters that were or that they regarded
as essential to the existence of a contractual relationship
between them, there will be no contract (Durabella
v Jarvis; British Steel v Cleveland Bridge4). The same
will be true if the Letter of Intent expressly states that
there will be no contract between the parties until the
occurrence of a stated event and that event does not occur
or if the Letter of Intent contains some other express term
negativing the existence of a contract (dictum of Steyn LJ
in Trentham v Archital; Jarvis v Galliard).
As discussed above, we can come to a conclusion based on
the cases as follows, how the court / judge will interpret
and act based on the terms, wordings and intention of the
parties used in the Letter of Intent.
The court is well aware that in the construction industry
the parties all too often simply fail to get round to
executing a formal contract incorporating the terms of
a standard form the parties contemplated should govern
their relations.
As in Type (b), where the Letter of Intent indicates an
intention to enter into a contract on a standard form,
where the contractor starts work on the basis of the letter
13
22
June 2012
SLQS JOURNAL
pending something further happening, there is a
simple unilateral right to be paid for work done.
For example, an express provision that pending the
execution of the formal contract, the Contractor is
to be paid a reasonable sum for the work executed
and the Employer is entitled to terminate the Work
at any stage. In some circumstances, however,
such a provision may prevent a contract arising.
Or language that makes it clear the Contractor is
instructed to commence only a limited amount of
work (Eugena v Gelande14 where the judge stated
that as far as the works not covered by the language
of Letter were concerned, Eugena was not entitled
to payment: there was no express or implied term in
the Letter providing for payment and there was no
express or implied request for Eugena to carry out
the work which would found a claim for a quantum
meruit)
Where the proper conclusion is that there is a bilateral
Interim Contract, but one which does not incorporate all
the terms of the standard form referred to in the Letter of
Intent, it seems the court is likely to be ready to conclude
that any relevant terms were incorporated subject to
evidence of a contrary intention, as discussed above in
the cases Hall & Towse v Ivory Gate; Hackwood v Areen.
Where the Letter of Intent results in an Interim Contract
or Contracts for only part of the Works:
(i) The Contractor will be entitled to the payment at
the agreed rates for that part of the Works.
(ii) Where the Contractor carries out additional work,
the question of what further payment, if any, he will
be entitled to will depend on the circumstances.
a. Where a Contractor carries out the additional work
14
15
Held that this amounted to an acceptance by them of the main Contractors counter offer.
23
June 2012
SLQS JOURNAL
Internal Auditors are at Site!
Saman Jayasiri Sirisoma Welagedara
BSC (Hons) , MRICS
Internal Audit Manager
Dubai Properties Group
Dubai
24
Financial reconciliation
Shared savings calculations
Contingency, allowances, credits
Closeout reporting
24
June 2012
SLQS JOURNAL
1. Risk assessment
3. Keep tracking
5. Be wise in justifications
25
June 2012
SLQS JOURNAL
The common reason that It was not in the contract
may not be sufficient for internal auditors. They
may be interested in determining why it was not in
the contract. Be ready for such questions.
6. Do reconciliations regularly
26
June 2012
SLQS JOURNAL
Introduction
Preliminary Meeting
27
SLQS JOURNAL
calculated, secured, and paid, including any deposits
to be advanced unless such arrangements have not
been stated in the Contract or the Arbitration
Agreement..
k. To fix the date, time and place of the hearing.
l. To make such other determinations as may be
necessary before the hearing.
m. To decide which of the points referred to in (a) to (l)
above are to be covered by an engagement agreement
and to complete and sign such agreement either at
the meeting or prior to the formal hearing.
n. At the preliminary meeting, the arbitrator shall
disclose any personal interest in the matters in
dispute and any previous relationship with any of
the parties to determine if there is any objection to
his/her continuing to act.
A preliminary meeting is very important due the fact
that arbitration shall be conducted in accordance with
any decisions reached at the preliminary meeting. The
parties will [come to the agreement, committed herein
would be monitored and measured throughout until the
award has been made, enforced, and implemented.?] This
meeting sets the basis for proceeding with the arbitration
in accordance with the applicable law.
Pre-Hearing Meeting/Conference
28
June 2012
SLQS JOURNAL
e. Notice that orders may be made at the prehearing conference that will be binding on all
parties, including parties added at the pre-hearing
conference, with respect to the proceeding, including
setting the dates for a hearing
During the pre-hearing, the tribunal shall check if the
documents that are transmitted are properly lodged,
received, and acknowledged by all parties and copies are
available in bundles in the required number. Minutes of
the preliminary meeting are a vital document too. This
would enable the tribunal to ensure that action has been
taken and complied with.
The tribunal shall issue a pre-hearing conference
memorandum setting out the results of the pre-hearing
conference, setting forth orders, agreements, and
undertakings made at the pre-hearing, and setting out
the dates of the hearing and the issues that are to be
determined.
After the pre-hearing conference has been held, no
substantive issues, other than those set out in the prehearing conference memorandum, may be raised or
addressed without leave of the tribunal.
Hearing
June 2012
29
June 2012
SLQS JOURNAL
In addition to the above-mentioned logistical
requirements, the following procedural requirements
have to be maintained by the arbitrators. Matters of
procedure are normally determined either by the law of
the seat of the arbitration, or by the tribunal itself under
its own inherent jurisdiction (depending on national
law). Procedural matters normally include:
30
i.
UNCITRAL Arbitration Rules (1976) United Nations (UN)
ii. UNCITRAL Model Law on International Commercial
Arbitration ( United Nations Document A/40/17, Annex 1)
iii. Introduction to International Commercial Arbitration, Dr
Emilia Onyema
iv. Construction Arbitration Second edition 1998, Vincent Powel
Smith, John Sims and Christopher Dancaster Publisher:
Blackwell Science
v.
Handbook of Arbitration Practice, Second edition 1993, Ronald
Bernstein, Derek Wood Publisher: Sweet and Maxwell
vi. Law and Practice of International Commercial Arbitration, Third
edition, 1999, Alan Redfern and Martin Hunter Publisher:
Sweet and Maxwell
June 2012
SLQS JOURNAL
Which Procurement Route?
Prasanna Jayaweera
B.Sc (Hons) QS, MRICS, CCC, ICIOB
Abstract
Procurement Strategy and Procurement Route are
two popular terms encountered in the construction
industry. What do they mean? Some may argue that
both have the same meaning. However, it is not so. As
defined by the United Kingdoms Office of Government
Commerce (OGC), Procurement Strategy identifies
the best way of achieving the objectives of the project
and value for money, taking account of the risks and
constraints, leading to decisions about the funding
mechanism and asset ownership for the project. The aim
of a procurement strategy is to achieve the optimum risk,
control and funding for a particular project.
Overall Procurement Strategy includes a number of
aspects like the working arrangement (procurement
route), Tendering Process (Method of contractor selection)
and Form of Contract to be used, etc. Therefore, the
Procurement Route is a part of the Procurement Strategy
that delivers the overall Procurement Strategy.
Selection of a suitable procurement route is of paramount
importance for the success of any development. In this
process, there are a number of parameters like project
objectives, market conditions, internal regulations of the
Employers organization, etc. to be considered. On the
other hand, several procurement routes are available in the
industry. Each of these routes will suit certain situations
and has their own advantages and disadvantages,
including different ways of risk allocation between the
parties. The identification of applicable parameters to any
particular development project, analyzing their priority,
evaluating alternative procurement routes and selecting
the best procurement route to cater to those identified
project parameters is the key to success.
31
June 2012
SLQS JOURNAL
32
Medium priority
Certainty about the project cost.
Cost certainty was also a very important factor
considering the fact that the project budget was
dependent on the Employers business plan.
Therefore, any measures that could give cost
certainty prior to the Employers commitment to the
Contract and control costs of the project effectively
would be of high importance
Price competition and obtaining lowest possible tender
price.
Lowest Priority
Flexibility in accommodating future variations.
It should be possible to accommodate the variations
that would become necessary due to insufficient
tender information from the design team at the
tender stage and variations due to future design
changes. Further, there shall be the flexibility in
catering to the changes that might be initiated by
the potential buyers / investors.
Early involvement of the Contractor and getting the
benefit of his know-how to improve buildability in design
June 2012
SLQS JOURNAL
Figure No. 1 Prioritizing project / Employer requirements and constraints
High Priority
No
Achieving the pre-defined project specific milestones utilization of early design packages and concurrent engineering (refer section 4.4)
Contractual relationships shall be relatively simple (with single point responsibility for construction)
Priority 2 (Medium priority)
Lower Priority
Flexibility for future changes (variations due to Employer changes and design
related changes)
Early involvement of the Contractor and getting the benefit of his know-how to
improve buildability in design
Main advantages
1. Competitive fairness as the complete design provides
a clear equal basis for tenderers.
2. Relatively low tender preparation costs to the
Contractor.
3. Changes can be easily introduced during design and
full cost impact can be envisaged.
4. The project is clearly defined. Therefore, there is
a greater certainty about the overall cost and time
before the Employer commits himself to contract
and penalties for late completion can be properly
established.
5. Design is fully prepared before commencement of
work on site. Hence proper coordination of different
trades is possible.
6. Construction costs are likely to be lower than other
methods of procurement since the Contractor can
assess the extent of his scope and potential risks at
the tender stage.
7. A detailed basis exists for evaluating future time and
cost variations.
Main disadvantages
1. Slow to start on site. (Construction is not concurrent
with design development).
2. Design risk rests with the Employer.
33
SLQS JOURNAL
3. The time period from the start of design to
completion of the construction is longer than the
other methods.
4. The design process does not get the benefit of the
Contractors involvement with the design team
in achieving compliance with the cost plan or
buildability solutions.
34
June 2012
June 2012
SLQS JOURNAL
2. Difficult to compare tenders and evaluate for
competitiveness where widely differing design
solutions are introduced by the tenderers.
3. Difficult to ensure the required quality of the end
product.
4. Placing a larger risk (both design and construction)
with the Contractor can result in overpricing of the
risks and greater cost to the Employer.
Management Contracting
The Management Contracting procurement route
is characterized by the Employers appointment of a
Management Contractor early in the process to advise
on the design programming and buildability (refer Figure
No. 4). The Management Contractor divides the works
into packages, programmes and obtains tenders for
them.. Then the work packages are let on a competitive
tender basis on lump-sum, firm-price contracts entered
into with the Management Contractor.
Works can be commenced as soon as the Employer
has approved the design proposals. In this method the
Management Contractor is appointed much earlier
than the Contractor in the Traditional Method. He
becomes a member of the design team and contributes
his construction knowledge and management expertise.
Main advantages
1. Facilitates fast rack development.
2. The design process benefits from the Management
Contractors involvement with the design team in
achieving compliance with cost plan or buildability
solutions.
3. Concurrent construction and design is inherent
resulting in overall time saving.
4.
35
SLQS JOURNAL
Construction Management
The Construction Management procurement route is
characterized by the appointment of a construction
manger to advise the Employer on a fee basis (refer
Figure 5). The Employer then independently enters into
Contracts with numerous trades (package) Contractors
rather than with a main Contractor (as in Management
Contracting). This needs closer involvement of the
Employer with the project throughout its life. The lines of
communication between the Employer and the package
Contractors carrying out the work packages are shorter
than with other systems, thus ensuring a faster response
for matters that require the Employers decisions.
As a member of the design team, the Construction
Manager would be expected to co-ordinate the design and
construction programmes and ensure that the interfaces
between trade packages were properly considered. This
arrangement can place the Employer at considerable risk.
The Construction Manger, who is appointed for a fee
with no contractual risk with trade Contractors, will be
responsible for planning, management and co-ordination
of the project and for establishing competitive bids for
all elements of the work. The actual Contracts are then
placed directly by the Employer.
The Construction Manager acts as the main Contractor
but he does not carry out any construction activities;
instead he manages and co-ordinates the performance of
the trade Contractors.
36
June 2012
Main advantages
1. The best price is obtained for each package Contract
through competitive tendering which will help to
control the overall price to some extent.
2. Facilitates fast track development.
3. The design process benefits from the Construction
Managers involvement with the design team in
achieving compliance with cost plan or buildability
solutions.
4. Concurrent construction and design are inherent
resulting in overall time saving.
5. Late changes are easily accommodated as work is let
package by package.
Main disadvantages
1. No cost certainty at the outset.
2. Minimum risk to the Construction Manger and
higher risk to the Employer.
3. No time or cost certainty prior to the Employers
commitment to Contract.
4. Design is not fully prepared before commencement
on site, therefore more potential changes and
variations.
5. The Construction Managers liability to the Employer
for the performance of the works Contract is limited
to the amount recovered from the defaulting trade
Contractors.
7. Needs effective control of time and information.
8. Contractual relationships are complex.
SLQS JOURNAL
June 2012
37
June 2012
SLQS JOURNAL
Figure No Comparison of the Procurement Routes
No
Construction
Management
Traditional
Method
Management
Contracting
10
10
10
10
10
10
10
10
Sub Total
34
26
43
170
130
215
10
10
10
Sub Total
11
19
12
33
57
36
Flexibility for future changes (variations due to buyers / investors changes and design related changes)
10
10
10
Sub Total
19
11
18
19
11
18
Grand Total
222
198
269
Note: Each item is awarded a points score out of ten. A higher score implies greater advantages.
Conclusion
The selection of a suitable procurement strategy is a key
factor in successful project delivery. It has to be done
carefully by analyzing the project requirements and
available procurement routes, their characteristics and
striking a compromise between project requirements. The
project considered in this paper is an advanced phase of
a large mixed use development project. Accordingly, the
38
June 2012
SLQS JOURNAL
priority requirements, including achieving project
milestones and commencing construction early. Though
the Construction Management route is also capable of
catering to most of the project objectives / restraints, it
places a huge contractual burden on the Employer.
Though Management Contracting is recommended as
the most suitable route of procurement for this project,
the Employer is warned about certain disadvantages
inherent in Management Contracting. Therefore, it is
recommended that these disadvantages and risks are
carefully monitored, controlled, transferred through
possible means or any unfavorable impact of these
disadvantages minimized.
The above scoring matrix was prepared in order to
demonstrate the suitability of each procurement route.
However, it is advised that the selection of a procurement
method shall not only be based on such a scoring system
but also on some common sense and professional
judgment.
6.0 Bibliography
1. Amos, S.J., 2007, Skills and Knowledge of Cost
Engineering, AACE International.
2. Ivor H. Seeley, 1984, Quantity Surveying Practice,
the Macmillan Press Ltd.
3. Keating Donald, 2001, Keating on Building
Contracts, Sweet & Maxwell Limited.
4. M Skitmore, DE Marsden, 1988, Which
procurement system? Towards a universal
procurement selection technique, Construction
Management and Economics, 1466-433X, Volume
6, Issue 1, pages 71 89.
5. RICS, 2003, The Surveyors Construction
Handbook, Royal Institute of Chartered Surveyors.
39
June 2012
SLQS JOURNAL
On and Off Site Recoveries
Vajira Kosala Hettiarachchi
Quantity Surveyor
Rotary Gulf Limited Electro-Mechanical Works LLC
Abu Dhabi
Introduction
40
June 2012
SLQS JOURNAL
Site Overheads
Actual costs
41
SLQS JOURNAL
In general, interim payments for the preliminaries for
a contractor will be calculated based on the pre-agreed
preliminary split which identified the mobilization,
demobilization and running costs, etc. which is shown
in the above diagram by a dotted line as an average. For
instance, consider any delay that occurs at point C in the
above graph, and the project cost remains constant during
the time period D and curve shifts as shown. In the
event of the Employers culpable delay the contractor will
be paid the actual time related cost which is equivalent
to the rectangular area B. However, the actual cost
incurred due to the delay is equivalent to the rectangular
area A which is much larger than area B.
42
June 2012
June 2012
SLQS JOURNAL
Formulas for recovery of Head Office Overhead
in a delay event
H.O. &
Additional
= Profit % X Contract Sum X
Payment Due 100
Contract Period
(Week)
Period of Delay
3,000,000 x 10 %
300 days
Contract Sum,
Period of
Delay
(Weeks)
30 days
Contract Sum
Contract Period
(Week)
X Period of Delay
(Weeks)
Eichleay formula
Allocable
Overhead
43
June 2012
SLQS JOURNAL
Step 2
Allocable Overhead
Days of Performance
Step 3
Daily contract Head
Days of
Additional
X Compensable Delay = Payment Delay
Office Overhead
Additional
CP
SCP
June 2012
SLQS JOURNAL
45
June 2012
SLQS JOURNAL
Prevention Principle
Senerath Wetthasinghe
LL.M., AIQSSL, AAIQS, MQSi, FCIArb
Director
Cost Engineering Services (Pvt) Ltd
Sri Lanka
46
an implied term,
implied supplement contract,
June 2012
SLQS JOURNAL
waiver, or
estoppel.
47
June 2012
SLQS JOURNAL
wording used in extension of time clauses and have held
that wordings such as events beyond the control of the
employer had rendered the liquidated damages regime
inoperable. As stated by Salmon LJ in Peak Construction
(Liverpool) Ltd v McKinney Foundations Ltd 30:
48
June 2012
SLQS JOURNAL
More recent authority38 suggests that the employers delay
and the contractors delay could be in some circumstances
divisible for the purposes of determining and enforcing
liquidated damages, but remains circumspect in light
of Peaks39 authority. In Rapid Building Group v Ealing
Family Housing40 , Lloyd LJ remarked that:
[I] was somewhat startled to be told in the course of
the argument that if any part of the delay was caused by
the employer, no matter how slight, then the liquidated
damages clause in the contract ... becomes inoperative.
Nevertheless, Lloyd LJ went on to note that:
Thus, the classic case of Peak41 remains dominant, and
authorities seem to suggest that where an act of prevention
goes to part of the delay but not to the whole, the entire
liquidated damages clause will be invalidated. This view
has been reinforced in SBS International Pty Ltd42, where
Besanko J held that, in a situation where delay to the
completion date was caused by the contractor as well
as the principal, it was not open to a court to apply the
liquidated damages clause to the delay specifically caused
by the contractor.
A number of Articles in the UAE Civil Code provide the
same comfort to a contractor that the prevention principle
provides. For example, Article 296 provides that:
Accordingly, despite an agreement between the parties to
the contrary, either party is liable for its harmful acts or
omissions. Harmful acts, it is opined, include financial
and economic harm in addition to physical harm.
49
June 2012
SLQS JOURNAL
prevention principle overrides conditions precedent. This
view has been subjected to strong academic criticism46. In
a paper47 submitted to the Society of Construction Law
(SCL), Hamish Lal critically analyzed this view referring
to the recent Scottish case of City Inn Ltd v Shepherd
Construction Ltd48. In that he argued that if:
(i) the notice requirements did not place an excessive
burden upon the contractor; and
(ii) there were no ambiguity between the clauses
(bespoke49 and standard);
then the notice provision should prevail over the
prevention principle although there may be some debate
about what constitutes an excessive burden upon the
contractor.
Further, in a recent paper50 submitted to SCL, Lal
justifying his aforesaid proposition said:
He further suggested that jurisprudential tensions
between time-bar clauses and the prevention principle
could be better resolved by arbitrators by adopting one of
the following approaches:
50
SLQS JOURNAL
Bills of Quantities, the Civil Code demands immediate
notification thereof from the Contractor (Article 886(1)
of the Civil Code refers). Further, as Articles 258 and
259 of the Civil Code uphold the intention of the parties
if they are clearly defined without any ambiguities, it is
opined that condition precedent clauses in a contract
would be upheld under the UAE jurisdiction.
1
2
June 2012
51
June 2012
SLQS JOURNAL
Graduated from the University of Moratuwa, Sri Lanka; has more than 6 years of UAE experience in Quantity
Surveying related Contract Administration, currently working as a Quantity Surveyor for DAMAC Properties
Co. LLC
Introduction
The title
The date
52
June 2012
SLQS JOURNAL
The Preamble
53
June 2012
SLQS JOURNAL
Execution
54
Let us look at the terms of the contract. They are the things
stated in the two covenants. As we did not state them
there itself we have to write them in a separate document
and incorporate them, e.g., conditions of contract.
Let us assume a third party has drafted them and sent
them to us for scrutiny and now we have to study and
confirm that our companys interests are protected. In
this juncture, what are the things that one is supposed to
look for? For this purpose, let us have a checklist that can
be used for this purpose. Generally, there are three major
areas that we have to look for to check whether the terms
are clearly stated in the document or not, namely, time,
cost and quality.
Time
1. Commencement date We have to see if the
commencement date is stated properly.
2. Time for Completion
3. If the extension of time clause is present.
4. If the penalty clause is present in the contract.
5. Time control procedure.
6. Taking over procedure.
June 2012
SLQS JOURNAL
Price
1. The type of contract (lump sum, re-measurable,
etc.)
2. Payment application and payment certificate
procedure including time limits,
3. Variations and provisional sums
4. Additional cost claims - entitlements and procedures
5. Price control procedure
6. Final account procedure
Quality
1. Drawings and specifications should be clearly
incorporated
2. Sample requirements and how it should be tested
3. Inspection procedures, approvals and rejections,
rectifications and remedies
4. Quality control procedure
5. Contractors liability to maintain the works after
the substantial completion of the project, defects
liability period, etc.
There are certain things that do not fall into these heads
of time, cost and quality. Some of them are as follows:
1. Insurance
If it is not clearly written into the contract the
employer cannot insist on the contractor submitting
insurances. He cannot say that it is normal practice
because sometimes the employer himself arranges
for such insurances. Therefore, the contractor could
refuse to insure saying to the employer that It is
your site and I am building for you, so you had
better insure them.
2. Bonds
For example, the requirement of a performance bond
should be written into the contract. Otherwise, the
employer cannot ask for it later.
3. Subcontractors
Contractors are responsible for the default of
the domestic subcontractors. In FIDIC type of
contracts the contractors are again responsible for
the default of the nominated subcontractors. But in
JCT type of contracts the employers are responsible
for the nominated subcontractors and they can get
the Extension of Time (EOT) for their default. So, it
should be written into the contract. Otherwise, the
situation would be difficult.
4. Language and the law
5. Termination clauses
6. Who is going to administrate the contract?
7.
55
SLQS JOURNAL
conditions of contract. Further, it is necessary to modify
all the relevant clauses accordingly to suit the agreed
terms between the parties and the type of contract.
Further, we can add any new clauses if we need to do so in
Part II the particular conditions of contract other than
modifying some of those 210 sub-clauses if we considered
the bespoke document of FIDIC 1987 4th edition
conditions of contract for construction.
56
June 2012
June 2012
SLQS JOURNAL
should have been incorporated therein. It doesnt state
what the penalty is or talk about LDs. In addition to that,
the subcontractor should be made available for inspection
of the main contract except the prices and other sensitive,
commercial and confidential matters. Mainly a copy of
the Appendix to tender of the main contract together
with Part II conditions of the main contract should be
provided for the subcontractor during the tender. Further,
the contract says the subcontractor is deemed to have full
knowledge of the provisions of the main contract less
such details of the contractors prices. And it goes on to
state the obligation of the subcontractor. He should not
cause the main contractor to be in breach under the main
contract. And if the subcontractor commits any breaches
of the subcontract he shall indemnify the contractor
against any damages for which the contractor becomes
liable under the main contract as a result of such breaches.
Now we move on to the 6th, 7th and 8th ingredients of
the Contract.
The 6th ingredient of the contract is possibility. A
contract is invalid if parties enter into a contract to do
impossible things.
And then we come to legality, the 7th ingredient. Parties
cannot enter into a contract for any unlawful thing.
And the 8th ingredient of the contract is intention to
create legal relations. In olden days contracts it is stated
Reference:
Prof.
Indrawansa
Samaratunga.
Sound
Contract
Administration - Drafting Contract Agreement, delivered at
Al Futtaim Training Centre, Dubai, for the Sri Lankan Quantity
Surveyors, UAE.
Editors Note:
ActionstrengthLtd(t/aVitalResources)vInternationalGlassEngineeringIN.
GL.ENSpA House of Lords 03 April 2003
Summary: Estoppel; oral contracts; enforceability of oral contract of guarantee under Statute of
Frauds 1677.
Abstract: A has agreed to supply labour to enable I to build a factory for G. A appealed against a
Court decision that that evade the effect of the Statute of Frauds 1677 s.4. A creditor cannot claim
that a guarantor should deny from relying on the Statute of Frauds 1677 s.4 by reason of having
encouraged the creditor to act to his damage by a promise to pay.
Held: Dismissed the appeal, that the oral contract of guarantee between A and G was not enforceable
under s.4 of the 1677 Statute, as a written agreement was required for a contract to be enforceable.
57