QC PROCEDURE - BORED PILE WORK
CHECK
RANDOM CHECK
S SURVEYOR
Flow of Activities
Check item
Method of measure
Check Frequency
Position
Theodolite
All
As per drawing
Bore location sequence
Casting record
All
Radius 3m from casted bore pile which
less then 2 days strength
Embankment
Visual
All
To retain the water flow to adjacent
Collection pit
Visual
All
To pump back to collection pit
Rebar fabrication
Visual
All
As per drawing
Concrete cover
Visual
Random
Sufficient spacer and cover i.e.75mm
Tremie Pipe
Visual
Random
Clean condition
Casing
Reference peg
All
Verticality 1/100. Final position + 75mm
Water in bore hole
Visual
Random
Water level min. 2m above ground water
level i.e.RL -3m or up to ground level to
control
Drilling bar
Spirit Level
Random
Verticality 1/500
Drilling depth
Tape
All
As per design requirement
Sediment
Time
All
Toe depth
Record
Length
Pre - Installation
Specification/Criteria
Record
Check list
SV SUPERVISOR
S SURVEYOR
QC
SV
REMARK
Check list
Check list
Check list
Bore piling
Check Sheet
Allow min.30min for sediment to settle
before final bore hole cleaning
Check list
All
min.200 above bore hole toe
Check list
Record
All
As per specification
Check list
Lapping
Measure
All
As per specification i.e. 40D
Check list
Joint
Visual
Random
Spot weld
Install tremie pipe
Nos. of pipe
All
max. 200mm above toe level
Water plunger
Visual
All
Before casting
Concrete
Slump
Random
Slump 16 + 2
Travel time
Batching record
Random
Max. 2hrs
Tremie pipe
Tape
Random
Min.1.5m below concrete upper surface
Casting height
Tape
All
Cut of level + 1m
Extract casing
Visual
Random
Remove soon after complete casting
Cleaning tremie pipe
Visual
Random
Soon after remove from concrete
Curing
Casting record
All
Min.7 days strength before allow for
excavation
Back fill blind hole
Visual
All
After concrete age >12 hrs
Rebar installation
Check Sheet
Concreting
Cleaning & Curing
Excavation & pile head
treatment
Check Sheet
Check Sheet
INSPECTION CHECKLIST - BOREPILING WORK
PROJECT : SENAYAN SQUARE OFFICE TOWER 3
DATE :
SUB-CONTRACTOR :
PILE NO.
NO.
ITEMS TO BE CHECKED
Pre-Installation
a) Peg position
b) Bore location 6m from new casted pile
c) Collection pit
d) Rebar cage
e) Concrete cover ; 75mm
Bore piling
a) Casing position
b) Kelly bar verticality
c) Toe Level ; RL -30m
d) Base cleaning min.30min after
e)
Rebar Installation
Acceptable
CRITERIA /
CH'K METHOD
YES
Theodolite
Record
Visual
Dwg
Measure
NO
DATE
Sign :
Sign :
Offset line
Spirit Level
Actual :
Measure
Record
Actual :
Measure
Cage 1 : 12m
Cage 2 : 12m
Cage 3 :
f)
g)
Tremie pipe
- Cleanliness
- Top level
- Tremie total length
- Toe depth max.200mm above toe
Bore hole water level
min. 2m above ground water level
Visual
Measure
Record
Calculate
Measure
Sign :
3
Concreting G30N
a) Concrete Slump ; 18 + 2
b) Time
c) Top level ; min.1 x above cut off level
d) Concrete Volume
Actual :
Actual :
Actual :
Water level : 3m
Bore hole water level :
Sign :
Slump test
Time
Measure
Record
Actual :
Start :
Actual :
Dwg :
Differences % :
OTHER COMMENT IF ANY ;
Page 1 of 2
KI/FORM/QC/BP Rev.1
Page 1 of 2
KI/FORM/QC/BP Rev.1
ORK
Form Ref. : KI/FORM/QC/BP/01
REMARKS
( STS )
( KI )
Time :
Time :
Lapping 1 :
mm
Lapping 2 :
mm
hole water level :
Finish :
Actual
Page 1 of 2
KI/FORM/QC/BP Rev.1
Page 1 of 2
KI/FORM/QC/BP Rev.1