OTC 21228 Emergency Pipeline Repair Equipment: Site Integration Tests and Post SIT Engineering
OTC 21228 Emergency Pipeline Repair Equipment: Site Integration Tests and Post SIT Engineering
OTC 21228 Emergency Pipeline Repair Equipment: Site Integration Tests and Post SIT Engineering
Abstract
Since the onset of Deep Water Response to Underwater Pipeline Emergencies (DW RUPE) JIP in 2005, we have been
reporting on progress of the development of a repair system designed to repair ANSI 1500 class pipelines in the 10-inch to 241, 2 , 3, 4 , 5 , 6
OTC 21228
SIT Activities
The functional specifications for the DW RUPE inventory were created after a failure mode and consequence analysis
(FMECA) defined the types of repair required for the system. These functional specifications were used as input for the
design of the tools and equipment, and the factory acceptance tests (FATs) proved that individual components performed to
specifications.
Although interfaces were maintained for all components of DW RUPE throughout the acquisition phase, testing of the entire
repair suite was needed to ensure the various components were compatible and sufficient space was available for ROV
operations.
The SITs were conducted in November 2009; the setup and instrumentation diagram is depicted in Figure 1.
Test and improve the operation and maintenance (O&M) manuals for the IBF and PLF, and add photographs
of the actual assembly process to the manuals
Test and validate the finite differences Excel program developed by Stress to assist with the positioning of
the IBFs and PLFs
Measure the time and resources required for the assembly of the system for future scheduling purposes
Help define what markings to stencil on the IBF and PLF to assist with the assembly and safe operation
Better understand the logistics of mobilization (shipping preparedness, packaging and palletizing, knowledge
of weights and volumes, tools required for assembly of the units, etc.)
Ensure ROVs have room to move around the frames and tools
Check the lifting arrangement for the frames, center of gravity, correct fit of rigging, padeyes, etc.
OTC 21228
Preparedness for mobilization: O&M manuals and general documentation for all equipment is currently available to
co-owners on a web based library at http://dwrupe.org
The spreadsheet based pipe lifting calculation tool accurately predicted the lifting parameters
The assembly process was timed and resources and skill sets defined for a future mobilization
Markings and labels were stenciled
In order to reduce the time to assemble the IBFs and PLFs, larger sub-assemblies were defined and stored in a
preassembled state (Figure 4)
The lifting arrangement had to be modified since the ROV
lifting hooks were too to the horizontal drive mechanisms
(Figure 5)
IBFs traverse mechanism ACME thread was made longer. It
was noticed that the IBFs and PLFs may not be placed so the
pipeline is exactly on the centerline. While the PLF already
has a long traverse, the IBFs were originally made with a
short traverse range (Figure 6)
Path Forward
To help maintain the systems efficiency and prevent obsolescence, a
continuous improvement program is in place for DW RUPE. Every
year, changes, improvements and modifications are submitted for
approval.
Grapple Design modifications: The original grapple design is based on a single rod standard double action hydraulic
cylinder, which requires volume compensation since the rod side displaces less hydraulic fluid than the piston side, is
vulnerable to leaks or punctures, and does not allow for a mechanical override. It was decided to convert the grapple
to a mechanical system composed of an ACME thread actuated by a hydraulic motor, with an ROV bucket in case of
a hydraulic failure (Figures 7, 8)
Reinforcement and tighter diameter tolerance for the IBF
to Connector guide post (Figure 9)
Add transponder buckets to the IBFs and PLFs
Modifications to the hydraulic system (hard piping,
routing of hydraulic lines)
Extend lifting slings to accommodate an as built shift of
the IBF center of gravity.
Modify IBFs and PLF lifting arrangement to ease the
ROV handling of the heavy slings
Future Development
DW RUPE has two divisions:
OTC 21228
DW RUPE continues to actively research new sealing systems and seal materials for connectors, where the primary
issue is control of the thermal expansion of the seals under high temperature pipeline conditions.
The Flowline Division is currently under development. Flowlines have greater challenges, such as high pressures
and temperatures, removal of hard coating, and thicker pipe wall, typically in diameters ranging between 4-inch and
12-inch nominal.
OTC 21228
Acknowledgements
The authors wish to acknowledge the insight and interest of the DW RUPE co-ownership, namely Mike Stark (Enterprise),
Leith McDonald (BP), Don Beesley and Kaya Alptunaer (ENI) and Bill Dick (Enbridge), and the following contractors for
their contribution during the SIT:
Lee Avery and Bruce Morris (Quality Connector Systems), Noah Teichmiller (Oceaneering International, Inc.), Mike
Hargrave (Cutting Underwater Technologies).
References
1
GE Oilfield
Technology
Magazine
OTC 19207
OTC 17772
4
5
6
IOPF
October 2009
May 2008
May 2006
October 2005
September 2006
October 2007