Rasuwagadhi Hydropower Company Limited: Rasuwagadhi Hydroelectric Project (111 MW)
Rasuwagadhi Hydropower Company Limited: Rasuwagadhi Hydroelectric Project (111 MW)
Rasuwagadhi Hydropower Company Limited: Rasuwagadhi Hydroelectric Project (111 MW)
Location/Structure
Desander Caverns
Desander Cavern # 1
Desander Cavern # 2
Desander Cavern # 3
2.0
3.0
4.0
Shape/Size
B x H = 15m x 22.47m
Excavated Length
Excavation (%)
157
157
157
8%
13%
15%
282
282
100%
330
330
100%
Construction Adit # 1
141
141
100%
5.0
5.1
5.2
5.3
Circular/4m Dia.
91
84
90
91
15
90
100%
18%
100%
6.0
6.1
6.2
43
1837
24
76
55%
4%
2897
1049
36%
Horseshoe/6.3m Dia.
Remarks
For 1st layer excavation of pilot tunnel 5m x 5m.
For 1st layer excavation of pilot tunnel 5m x 5m.
For 1st layer excavation of pilot tunnel 5m x 5m.
Location/Structure
Desander Operation Tunnel
Desander Flushing Tunnel
Construction Adit # 1
Desander Cavern # 1
Center Part
Right Part
Left Part
Desander Cavern # 2
Center Part
Right Part
Left Part
Desander Cavern # 3
Center Part
Right Part
Left Part
Desander Inlet Tunnel
Inlet Tunnel # 1
Inlet Tunnel # 2
Inlet Tunnel # 3
HRT from Construction Adit-1
HRT (CA1)-Upstream
HRT (CA1)-Downstream
Shape/Size
Inverted D-Shaped/5m Dia.
Inverted D-Shaped/5.2m Dia.
Inverted D-Shaped/5m Dia.
B x H = 15m x 22.47m
B x H = 5m x 5m
B x H = 5m x 5m
B x H = 5m x 5m
B x H = 15m x 22.47m
B x H = 5m x 5m
B x H = 5m x 5m
B x H = 5m x 5m
B x H = 15m x 22.47m
B x H = 5m x 5m
B x H = 5m x 5m
B x H = 5m x 5m
Circular/4m Dia.
Design Length
(m)
282
330
141
Excavated Length
Exacavation %
(m)
282
100%
330
100%
141
100%
Remarks
157
157
157
157
0
0
100%
0%
0%
157
157
157
157
52
55
100%
33%
35%
157
157
157
157
73
77
100%
46%
49%
91
84
90
91
15
90
100%
18%
100%
43
1837
24
76
55%
4%
Horseshoe/6.3m Dia.
Status of Open Excavation, Jet Grouted Pile Construction and PCC at Undersluice
(Till Date: 25th April 2015)
Open Excavation Status:
S.No.
Start Chainage
End Chainage
1.0
2.0
HD 0+000.00
HD 0+042.00
HD 0+042.00
HD 0+090.00
Start
Elevation
(masl)
1769.50
1768.00
End Elevation
(masl)
Design Qty.
(m)
1767.00
1765.50
4984
6497
Total =
11481
Excavated Excavation
Qty. (m)
(%)
Remarks
100%
80%
89%
4984
5198
10182
Initial Piles Proposed By CWE & Its Work Progress Before Proposing New Piles:
S.No.
Location
Starting
Chainage
End
Chainage
Starting
End Elevation
Elevation (masl)
(masl)
Pile Dia.
(m)
Cement
Qty.
(Tons)
Proposed
Nos. of
Piles
Constructed
Work
Nos. of Piles Progress (%)
Left Side
Middle Portion
Right Side
D/S Key/Cutoff
Remarks
Since these piles
were found to be
insufficient and
most of them were
not as per
design,CWE came
with new proposal.
HD 0+003.20 HD 0+003.20
1771.00
1771.00
0.6
9.5
57
36
26
72%
HD 0+000.00
HD 0+000.00
HD 0+000.00
HD 0+092.00
1771.00
1771.00
1771.00
1765.50
1765.50
1765.50
1765.50
1765.50
1
1
1
1
0.6
2
0.6
0.6
9.5
9.5
9.5
9.5
Total =
66
177
38
32
370
48
152
48
24
308
25
103
32
16
202
52%
68%
67%
67%
66%
End Elevation
(masl)
Cement
Qty.
(Tons.)
Proposed
Nos. of Piles
1782.50
1.0
0.6
9.5
56.0
0%
Impermeable Curtain
Layer Preperation
Impermeable Curtain
Layer Preperation
HD 0+042.00
HD 0+042.00
HD 0+042.00
HD 0+042.00
Newly Added Piles Proposed By CWE & Its Work Progress Till 25 th April 2015:
Starting
Chainage
End Chainage
HD 0+000.00
1782.50
1771.00
1.0
0.6
9.5
13.0
0%
HD 0+000.00
HD 0+000.00
HD 0+026.75
HD 0+092.00
1771.00
1771.00
1769.50
1765.50
1.0
1.0
3.0
9.5
13.2
93.4
61.0
152.0
20
142
33%
93%
HD 0+002.00
HD 0+002.00
1771.00
1.0
9.5
10.0
0%
HD 0+093.80
HD 0+093.80
1765.50
1765.50
2.0
0.6
At Missing
Locations
Only
0.6
9.5
107
36.0
328
0
34
0%
10%
S.No.
Location
Starting Elevation
(masl)
C/C Pile
Pile Depth
Spacing (m)
(m)
Remarks
1.2
1.0
Total =
S.No.
Start Chainage
End Chainage
1.0
2.0
HD 0+000.00
HD 0+002.75
HD 0+042.00
Start
Elevation
(masl)
1769.50
1768.00
End Elevation
(masl)
PCC Thickness
(mm)
1765.50
300
300
Remarks
At Key Groove
Location
Start Elevation
(masl)
1852.00
1840.00
1830.00
End Elevation
(masl)
1840.00
1830.00
1820.00
Excavation
Status
Complete
Complete
On Progress
1786.80
1782.50
On progress
Remarks