Modul-Plus Manual
Modul-Plus Manual
Revision No.1
Dated: JAN 06
Issued By
Approved
IJR
KS
Technical Dept
Table of Contents
Page
Contents
Introduction
5-7
8
9-13
14-15
Unvented Systems
16-20
21
22
Anode Protection
23
Immersion heaters
24
25
26
27
28
Notes
29
Introduction
Introduction
These instructions have been written to give a brief description of the F Modulplus Calorifier, its installation, commissioning, operation and subsequent maintenance.
The installation of calorifiers and their ancillary equipment is normally carried out by a heating
engineer. For the purpose of this manual he is regarded as the installer, and, as such, it is his
responsibility to ensure that he has read and understood the contents of this manual before
installing the calorifier.
It is essential that each calorifier has all services permanently connected to it before commissioning is requested.
The installation should be in accordance with
current I.E.E. regulations, relevant British Standard and Codes of Practice, Building Regulations and Local Authority Bylaws.
Commissioning/Combustion Report
A note should be entered below by the person responsible for the plant, giving the boiler, calorifier
model and its output and reference K number, as indicated on the nameplate.
Output l/hr:
K Number:
Date of installation:
General Details
The construction of the F Modul plus is in the form
of a series of horizontal bottles, linked in modular
fashion, and comprising a high grade stainless
steel inner vessel with a rippledwall to enhance
heat exchanger efficiency. This is surrounded by
a mild steel primary water jacket, which is encased
with steel sheet insulated panels. The assembly
is mounted on two base channels running from
front to back. On all seven models, the secondary
flow and primary inlet are from the top and the secondary return, cold feed and primary outlet connections are at the bottom.
Performance of the seven F Modul plus models
covers a range of outputs up to an hourly rating of
10,000 litres/hour. Higher outputs can be provided
by arranging the units in modular formation. For
most typical applications (other than process water generation) the key requirement is for adequate
quantities of hot water over a relatively short period. On this basis, the F Modul plus will provide
significantly higher flow rates than its continuously
hourly rate.
Key Features
Minimum floor area, fits through standard
doorway.
Primay Details
Contents Flow rate
Resistance
Contents
continuous
peak
continuous
litres
l/s
mbar
litres
l/10 mins
l/hour
l/10 mins
l/hour
F21
30
2.27
120
230
405
1750
455
1960
12
F31
45
1.94
120
345
495
1800
555
2550
24
3.33
430
545
2400
625
3300
30
F41
60
2.92
440
460
800
3400
875
4150
80
F51
75
2.22
300
575
950
3200
1080
4350
120
3.33
720
140
F32
90
4.55
220
7.05
595
690
mbar #
1035
3950
1185
5250
1136
4546
1170
5800
33
1227
5682
1250
6600
39
F42
120
5.46
446
920
1727
6800
1740
8100
93
F52
150
4.44
340
1150
1900
6400
2160
8700
130
5.83
610
2015
7400
2315
10000
150
* Resistance is for primary ow rate listed
+ For DHW outputs below 60oC, external blending to a lower temperature is recommended.
# Resistance at the peak 10 minute draw off rate. For resistance at other draw off rates See Graphs on page 6.
Pressures
Standard Model Pressures
System
Test Pressures
Operating
Test Pressures
Pressure Bar
Bar
Bar
Bar
Primary Side
4.48
6.90
6.90
10.0
Secondary Side
5.87
11.73
9.66
15.0
** To meet the requirements of M&E3, high pressure primary water units can be tted with a bursting disc.
Weights
Model
Dry Weight kg
Total weight kg
F21
269
165
529
F31
319
215
709
F41
380
265
900
F51
455
315
1105
F32
491
370
1271
F42
605
470
1645
F52
730
570
2030
Chloride.
The maximum allowable chloride content of DHW cold feed water is 100mg/litre,
(or up to 200 mg/litre where optional sacricial anodes are tted).
Litres (kg)
o
C
o
C
kJ/kgoC
Legionellae The safe temperature for storage is now considered to be a minimum of 60 C to prevent the risk of
o
legionella bacteria contamination. For kitchen and similar duties requiring 60oC water, the supply can be direct from the
calorier. For washing and showering duties which require a 42oC supply, mixing or blending with cold water, external to the
calorier, is required and will increase the secondary output listed on page 5 by about 25%.
When temporarily operating the primary side only, the pressure should not
exceed 1 bar g and the secondary side should be vented.
M3 / h / 3.6 = l/s
Width
a
530
530
530
530
885
885
885
6 Electrical box
7 Electrical connection
Front View
Side View
T & P Valve on
Unvented Systems
T & P Valve on
Unvented Systems
Type F42
3. Technical data
Rear View
3
2
12
2"2BSP Male
2BSP Male
2"1BSP Male
1"F21-F51 = DN50 PN6
F32-F52
F21
- F51= =DN65
NWPN6
50
F32 - F52 = NW 65
Height
b
1615
1615
1800
2160
1615
1800
2160
Dimensions
Connections
1. Secondary Flow
1 Hot water
2. Cold Feed
2
Cold water
3. Circulation
4. Primary
Flow
3 Circulation
5. Primary
Return
4 feed
6. Control panel
5
return
7. Electrical Connection
F21
F31
F41
F51
F32
F42
F52
Type
3.3 Dimensions
4 200 690 / 01
Delivery
Positioning / Clearance
Position the calorifiers as required, ensuring that
side and inspection opening clearances are adequate.
At least 400mm side clearance is required for
fitting the casings. If this space is not available,
the calorifier insulation and casings must be fitted before positioning the calorifier.
Ensure that the calorifier is level using a spirit
level along the top calorifier bottle.
Assembly Instructions
Assembly Instructions
Mounting the support rails
Ensure that the dimensions between the top casing rails and the base channels are as per H.
Hole A.
Hole B.
10
Assembly Instructions
Do not fasten too tightly as this will effect the insulation properties of the matress.
Fit the pipe insulation (9) and secure using tension springs.
Fit the bottle end covers (10) at both ends.
Figure B
Figure D
Assembly Instructions
Figure E
Figure A
Figure C
11
For instructions on how to fit the casings please see page 12.
12
Assembly Instructions
Fit the front base panel (11) from the front. Then the middle and rear base panels (12) are
placed in position from the side, between the plinth channels.
(ii) The front side panels (13) are first placed in the bottom guide rails (Fig. A) and then attached
to the top casing rails. Push the side panels (13) back against the casing rails as far as it
goes.(Fig B)
(iii) Fit the other side panels (14,15). Join the front side panels (13) to the bottom guide rails with
spring clips (16, Fig. C). Push the side panels (14,15) up against the front side panels so that
there isnt a gap and then fix the panels at the back to the bottom guide rails with the spring
clips.
(iv) Fit the C-clips (17, Fig. D) to the cubicle retaining rails.
(v) Now the front lids (18.19) (on the F31, 32, 51, 52 models) or the front lid (on the F21, 41, 42
models) should be put in place. Then fit the other lids (20). Do not tighten the fixing screws at
this stage.
(vi) Fix the back panel (21) in position using the self-tapping screws.
(vii) Fit the support panel for the electrical control panel (22) and fix to the mounted screws with
dome nuts (23).
(viii) Mount the cable gland (24) in the support panel with the plastic counter-nut. Blank off the other
holes with blank grommets (25).
(ix) Push into position the electrical control panel (26). Beforehand, please route the capillaries to
the rear, through the opening in the support panel (22).
(x) Carefully Insert the thermometer and thermostat sensors into the immersion pocket (27) of
the corresponding bottle. Do not remove the plastic clip until the sensor bundle is inserted half
way into the immersion pocket. The sensor for a limit thermostat (on unvented systems) must
be mounted in the topmost bottle.
Assembly Instructions
13
Before attempting to wire the unit, always refer to the relevant wiring diagram.
14
Installation
Piping layout
For the general design of water circuits refer to
current British Standards and Codes of Practice.
A simple pumped primary flow and return, adequately vented, is all that is needed. Secondary
Recommended Primary
primary Systems
systems (open vented).
Recommended
B
Primary
from
Main Headers.
Primary ConnectionsConnections
from Main Headers. Temperature control
by pump.
Temperature control by pump.
1
AAV
AAV
Secondary
Water
Primary
Water
4 (if Required)
Primary
Water
Secondary
Water
5
3
AAV
3
6
Key
Anti-thermal
loop
6
3
15
2
3
Primary
Water
AAV
Secondary
Water
Flow
3
Primary
Water
4 (if Required)
Secondary
Water
Boiler
6
Flow
Anti-thermal
loop
Boiler
Boiler
Return
Key
Return
Vent
Cold
water
mains
Vent
Valve
AAV
3
4
Primary
Water
Water
Primary Water
Secondary
Water
Secondary
Secondary
Water
Water
Primary
Cold
Feed
2
6
11
Secondary
Return
Secondary
Circulating
Pump
Key
(1) Relief valve adjacent to calorifier.
(2) Spring loaded non-return valve.
(3) Isolating valves.
(4) Open vent.
(5) Unvented system kit.
(6) Secondary drain valve.
8
Cold
water
5
mains
Cold
Feed
7
3
6
10 1
3 2 12 3
9
33
Secondary
Return
10
3
Key
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
16
Unvented Systems
Definition
Unvented
Kit.
Unvented System
System kit
11
Expansion relief
valve c/w tundish.
Expansion
Cold Vessel.
water
mains
Check
valve.
PRV.
10 1
6
9
3
10
Key
Strainer.
1. Expansion Relief Valve
2.
3.
4.
5.
Cold
Feed
As shown in the above diagram, an unvented system kit A temperature and pressure relief valve should be
fitted directly in the calorifier as a thermal protection
comprises of the following components: Strainer (this is optional, but good practice, to prevent to prevent the DHW reaching 100 deg C.
A hand reset limit stat should be fitted in the calorifier
debris passing through the valves)
Pressure regulating valve (PRV), this allows the to prevent the DHW overheating.
pressure to be reduced and controlled at a preset Balanced Unvented Systems
pressure. A pressure gauge is supplied to indicate
Some systems may be fitted with blending valves or
system pressure.
mixers that require a balanced hot and cold water
Double check valve, this prevents the expanded water supply. When sizing the strainer, the PRV, and check
back-feeding into the mains supply and additionally valve care must be taken to ensure they can pass the
seals the system.
flow rates at the required pressure.
An expansion vessel should be fitted between the non Hoval standard unvented system kits are sized to
return valve and the calorifier to take up expanded reduce incoming pressure to 3 bar at a flow rate that
water during heat-up.
meets the peak output of the calorifier only.
17
Unvented Systems
A separate Strainer and PRV can be fitted to both
the hot and cold water services to give balanced
system pressures. Alternatively, a larger Strainer
and PRV can be installed to cope with both hot
and cold water demands.
Unvented
System
Unvented
SystemKit.
kit
Unvented System kit
Expansion relief
valve c/w tundish.
Cold
Expansion
ColdVessel.
Please note that these kits are only sized for the
cold feed going into one of the F Modul plus
calorifiers.
PRV.
Key
Strainer
F21 & F31
P.R.V.
Double
Check
Valve
water
water
mains
mains
Check valve.
33
4 4
211
33
88
55
66
77
99
10 1
10
1
33
1010
Key
Cold
Feed
Expansion
Relief
Valve &
Tundish
T&P
Relief
Valve
80 litre
HP80-6T
HP130-6T
Expansion
Vessel
1.1/2
1.1/2
1.1/2
130 litre
F32
1.1/2
1.1/2
1.1/2
130 litre
2 x 1 HP130-6T2
240 litre
2 x 1
HP240-6T2
18
Unvented Systems
Multi-calorifier Installations
Temperature
and Pressure
Relief Valve
Temperature
and Pressure
Relief Valve
Pressure
Reducing
Valve
Isolation valve
Cold
Feed
Strainer
Double
Check
Valve
Isolation valve
Cold
Feed
Strainer
Drain cock
by installer
Expansion
Relief Valve
and Tundish
Isolating
Valve
Isolating
Valve
Expansion
Relief Valve
and Tundish
Expansion
Vessel
Drain Cock
By the
Installer
Expansion
Vessel
Pressure
Reducing
Valve
Drain cock
by installer
Joining Pipe.
Double
Check
Valve
Drain Cock
By the
Installer
Temperature
and Pressure
Relief Valve
Temperature
and Pressure
Relief Valve
Pressure
Reducing
Valve
Strainer
Cold
Feed Isolation valve
Drain cock
by installer
Double
Check
Valve
Isolating
Valve
Drain Cock
By the
Installer
Drain cock
by installer
Expansion
Relief Valve
and Tundish
Isolating
Valve
Expansion
Relief Valve
and Tundish
19
Unvented
Systems
Unvented
Systems
BalancedBalanced
Hot and Cold
water
supplies.
Hot and
Cold
water supplies.
Unvented
SystemSystem
with balanced
Unvented
with balanced
hot andhot
cold
water
services.
and cold water services.
Temperature
and Pressure
Relief Valve
Temperature
and Pressure
Relief Valve
Isolation valve
Expansion
Vessel
Drain cock
by installer
Pressure
Reducing
Valve
Isolation valve
Cold
Feed
Strainer
Cold
Feed
Strainer
Pressure
Reducing
Double
Valve
Check
Valve
Expansion
Relief Valve
and Tundish
Isolating
Valve
Isolating
Valve
Double
Check
Valve
Drain Cock
By the
Installer
Expansion
Relief Valve
and Tundish
Drain Cock
By the
Installer
Balanced
hot andhot
cold
water
Balanced
and
cold water
services
using two
PRVs.
services
using
two PRVs.
Temperature
and Pressure
Relief Valve
Temperature
and Pressure
Relief Valve
Isolation valve
Cold
Feed
Strainer
Cold
Feed
Pressure
Reducing
Valve
Strainer
Pressure
Reducing
Double
Valve
Check
Valve
Expansion
Vessel
Expansion
Vessel
Drain cock
by installer
Isolating
Valve
Double
Check
Valve
Drain Cock
By the
Installer
Drain Cock
By the
Installer
Expansion
Relief Valve
and Tundish
Isolating
Valve
Expansion
Relief Valve
and Tundish
19
20
Unvented Systems
Expansion
Vessel
Isolation valve
Strainer
Pressure
Reducing
Valve
Cold
Feed
Drain Cock
(By the
Installer)
Lock Shield
Valve (By the
Installer)
Double
Check
Valve
Isolation valve
Vessel Efficiency = Max Pressure (Bar Abs) - Min Pressure (Bar Abs)
Max Pressure (Bar Abs)
Where:
Fault Finding.
Symptom
Possible Cause(s)
Remedial Action
Blockage in strainer
Blockage in PRV
Wrong PRV pressure setting
21
Commissioning
Flush all swarf, filings and other debris out of (1) Light the boiler (refer to the appropriate boiler
the system, preferably using a proprietary flushing agent. Do not wash particles into the calorifier,
this could cause subsequent corrosion.
Once the secondary side is fully flooded and
sealed, fill the primary system completely and
treat the water with a good corrosion inhibitor
(e.g. Fernox). Corrosion inhibitors are not used
in secondary (tap) water.
Ensure that all joints are water tight and all
pipework is vented.
Check that all electrical connections are complete and correct.
Ensure that the thermostat(s) are wired up and
the sensor probes are fitted in the stat pocket.
The thermostat may be wired into the boiler controls to activate the pumps or a motorised valve.
The control thermostat can be adjusted to operate between 30 deg C and 80 deg C and is usually set to 60 deg C.
operating instructions).
(2) Adjust the calorifier thermostat to the required
operating temperature.
(3) Check that the thermostat is operating correctly.
(4) Ensure that the primary pump is working or
primary primary circuit is established.
(5) Check that the operating temperature remains
constant.
Operating Instructions
The calorifier thermostat when wired to the primary circulating pump or diverting valve provides
completely automatic control. It is necessary only
to adjust the thermostat if the occasion demands.
22
Draining Down
Periodic Inspection
The user is advised to carry out periodic inspection between main servicing periods and it is recommended that the specialist servicing company
also carries them out.
Note: Before opening the inspection
covers always ensure you have a
new inspection cover joint. Each
bottle has two covers (one at each
end, (e.g. 20 on a F52 calorifier).
Model
ALL F Modul plus
23
Anode Protection
Periodic Inspection
Units fitted with sacrificial magnesium anodes (3) Carefully rest the new anode in the slot on
should be checked on a twice yearly basis to the plastic support pipe.
assess the deterioration of the anode.
(4) Screw the new anode to the socket in the
To inspect the anodes follow the procedure be- inspection cover and replace rubber gaskets and
carefully fit the covers.
low:Note: Before opening the inspection
covers always ensure you have a
new inspection cover joint. Each
bottle has two covers (one at each
end, (e.g. 20 on a F52 calorifier).
Example - F31
Magnesium Anode
Part Description
Magnesium Anode
Inspection Cover
Rubber Door Joint
Plastic Support Pipe
Cat Number
628998
628996
414008
528289
24
Immersion Heaters
Immersion heaters
Operation
General
Maintenance
All prevailing site safety regulations shall be
adhered to at all times.
Equipment is to be fully isolated from the
electrical supply and locked off before and whilst
any work is being carried out.
Installation
Routine Maintenance
3 Monthly
6 Monthly
Earth Connection
An earth connection is provided inside the terminal box.
Annually
25
26
Fault finding
Symptom
Possible Cause
Action
A. Primary Water
Circuit Inefficient
Symptom
Possible Cause
Action
A. Secondary water
temperature not as
setting on thermostat.
(4) Electrical fault in control system. (4) Refer to appropriate control system part document.
(5) Calorifier scaled up.
(6) Calorifier not large enough for load (6) Change calorifier or add calorifier / buffer vessel.
imposed.
(7) Low primary temperature.
Electrical Diagrams
27
28
Electrical Diagrams
Notes
29
Conservation of Energy
Protection of the Environment
Hoval Limited, Northgate, Newark, Notts NG24 1JN
Telephone: 01636 672711 Fax: 01636 673532
e-mail: [email protected]
web: www.hoval.co.uk