Assignment Pipeline
Assignment Pipeline
Concept analysis of
Gas Field
Marine Special Topic 1 OENA 8588
Krisitan Odland 21180174
5/24/2013
CONTENTS
Contents ................................................................................................................................................................................ II
Figures ................................................................................................................................................................................... II
Table ....................................................................................................................................................................................... II
Introduction .........................................................................................................................................................................1
1 Sketch of two options ...................................................................................................................................................1
Option A - Tieback from wellhead to topsides facilities................................................................................1
Option B - Subsea-to-shore tieback to LNG processing onshore ...............................................................2
2 Advantages & Disadvantages ....................................................................................................................................2
Option A Platform ......................................................................................................................................................2
Option B Subsea to Shore tie-in ...........................................................................................................................3
3 Basic Carbon Steel vs Corrosion Resistant Materials ......................................................................................4
4 Cost estimate for option B ..........................................................................................................................................2
Input data for corrosion calculations....................................................................................................................2
Carbon steel .....................................................................................................................................................................2
Carbon steel + Chemical Corrosion Control .......................................................................................................2
Cost estimate for option B ..............................................................................................................................................2
References .............................................................................................................................................................................3
APPENDIX 1........................................................................................................................................................................... i
Cost estimate - Carbon steel pipe with anti-corrosive inhibitor ................................................................ i
Cost estimate - Corrosion resistant alloy (CRA) ................................................................................................ i
FIGURES
Figure 1 - Sketch of tieback from wellhead to topsides facilities ...................................................................1
Figure 2 - Subsea-to-shore tieback to LNG processing facilities onshore ..... Error! Bookmark not
defined.
TABLE
Table 1 - Platform advantages & disadvantages ...................................................................................................3
Table 2 - subsea-to-tie in.................................................................................................................................................3
Table 3 input data for corrosion calculations ........................................................................................................2
Table 4 calculation of corrosion allowance .........................................................................................................2
Table 5 - Corrosion resistant inhibitor......................................................................................................................2
Table 6 Cost estimate for option b ..............................................................................................................................2
TABLE 7 - DETAILED COST ESTIMATE FOR CARBON STEEL PIPE INHIBITOR ......................... i
II
INTRODUCTION
Two development options are explored for a new gas field:
Option A - Tieback from wellhead to topsides facilities
Option B - Subsea-to-shore tieback with LNG processing onshore
In addition a cost estimate is performed for Option B, and through-life- factors regarding
material selection for pipeline are discussed. There has been some uncertainty regarding
dissimilar information given in lecture 4 and the assessment description. However, following the
initial project description no calculations of corrosion rates & costs are done under section 3.
The platform is suggested to be located roughly 40 50 km southeast from gas field in a depth of
approximately 450 meters (fig.1) for the following main reasons:
1. A safe distance to the gas field in occasion of a gas field blow out.
2. Avoid strong currents up the scarp and rough seabed
3. Be within an economically feasible distance from manifold to platform, regarding
cost of dual flow lines for multiphase gas, electricity supply etc.
4. Avoid having platform in shallow waters where cyclonic storms occurs(< 200m)
Because the location is in a deepwater area, floating production facilities are preferred. A TLP,
SPAR or Semi-submersible could be used. Limiting the complexity of the platforms mooring
system regarding water depth has been considered. The steep slope down slide (50-60 m depth)
may be a challenge for pipelaying and intervention work due to high current velocities and
should be carefully studied.
Hydrate Inhibition
Ease of Inspection
Controls
Route Selection
Disadvantages
Environmental
considerations
Construction
Reliability
Economics
Materials selection
& Corrosion
Hydrate Inhibition
Ease of Inspection
Disadvantages
High CAPEX
Multiphase flows has higher pressure drop than
single phase
Equipment at seabed needs to resist HP/LT, thus
higher material costs
May need: 1) thermal insulation to avoid hydrate
formation & 2) thicker wall to allow corrosion
MEG injection required & multiphase may need to
be heated up to avoid hydrate formation
High maintenance - and repair costs & low
availability
Difficult to access flowlines for intervention and
inspection.
Complex control assembly and is dependant on the
use of wet-mate high-power and/or optical
connectors
Controls
Route Selection
Construction
CRA
Positive
Safety, reliability
and security of
production
Negative
Environment
Negative
Negative
Maintenance &
Inspectability
Negative
Negative
Hazards
Negative
Positive
Positive
No corrosion in general
(low maintenance)
Negative
Negative
Negative
Corrosive material
Easy to weld
Positive
Fabrication &
materials
Positive
393,15
300
0,06
18
6
kelvin
bar
bar
-
CARBON STEEL
The results presented, using deWaard and Lotz equation shows that carbon steel is not a feasible
solution without an anti-corrosion inhibitor. Over a 20 year design life we need a corrosion
allowance equal to 30, 4 mm. All hazards except bottom line corrosion are ignored.
deWaar and Lotz Equation for
F scale
0,045
pH saturated
3,583
pH actual
6
F pH
0,169
Uncorrected V - corrosion
201,42 mm/yr
Uninhibited Corrosion Rate V un
1,52
mm/yr
20 yr lifetime
30,4
mm
TABLE 4 CALCULATION OF NEEDED CORROSION ALLOWANCE
95
0,1
1,52
0,171
3,4
%
mm/yr
mm/yr
mm/yr
mm
CRA
$700,0 mill
$591,0 mill
$1291,0 mill
REFERENCES
Woodgroup Kenny (2013) Lecture slides in the unit Special Topic 1 (OENA8588) at UWA
Lee (2009) - Introduction to Offshore Pipelines and Risers
Owe (2011) - Slide presentation - SUBSEA COMPRESSION - APPLICATION ON ORMEN LANGE
Shell Exploration & Production (2012) - Overview of Ormen Lange Project
http://www.ipt.ntnu.no/~jsg/undervisning/naturgass/lysark/LysarkGupta2012.pdf [22.05.13]
peter osmundsen
APPENDIX 1
COST ESTIMATE - CARBON STEEL PIPE WITH ANTI-CORROSIVE INHIBITOR