012-MS For Wall Cladding, Roof Cladding & Life Line Installation PDF
012-MS For Wall Cladding, Roof Cladding & Life Line Installation PDF
012-MS For Wall Cladding, Roof Cladding & Life Line Installation PDF
Project
LINDE ENGINEERING
Shell Project No: HP-3000-QAT
2MH127
Tag/Item Number(s):
N/A
Unit(s):
ASU
PCWBS:
Contractor Project No :
Project Rev.: O
Page 2 of 15
5887
19.04.2008
AG
EE
ZG
ICC
29.03.2008
AG
EE
ZG
IFR
28.03.2008
AG
EE
ZG
IIR
Date
Description
GAMA
Rev.
Project
Rev
No.
No.
Status
ORIGINATOR
Document Title:
LINDE ENGINEERING AG
Contractor
LOC470
Gama Qatar Co. W. L. L.
GAM
MTS
GEN
GTL
012
Org.
Code
Doc.
Type
Disc.
Code
Geogr.
Area
Seq.
No
Rev.
No
Vendor Code
Rev No.: O
GAM-MTS-MEC-GTL-012
Doc. Title
Q A T A R
Date/Rev. No :
TABLE OF CONTENTS
1
INTRODUCTION ____________________________________________________________________ 5
1.1
GENERAL ____________________________________________________________________ 5
1.2
SCOPE ______________________________________________________________________ 5
REFERENCES _____________________________________________________________________ 5
DEFINITIONS ______________________________________________________________________ 5
RESPONSIBILITIES _________________________________________________________________ 5
RESOURCES ______________________________________________________________________ 6
EQUIPMENT & MANPOWER _______________________________________________________ 6
5.1
5.1.1
5.1.2
MATERIALS __________________________________________________________________ 6
5.2
6
6.1
6.1.1
6.1.2
6.1.3
6.1.4
7
EQUIPMENT _______________________________________________________________ 6
MANPOWER _______________________________________________________________ 6
6
6
6
7
7.2
7.3
HSSE ____________________________________________________________________________ 7
10
ATTACHMENTS ____________________________________________________________________ 8
10.1
10.2
T-4.250.953 Rev. O
Page 4 of 15
GAM-MTS-MEC-GTL-012
Doc. Title
Q A T A R
Date/Rev. No :
1 INTRODUCTION
1.1 GENERAL
This document describes the methods proposed to be used for wall cladding, roof cladding &
Life installation works for the workshops, warehouses at TSF & ASU area that shall be carried
out as part of ASU Construction works of Qatar Shell GTL Plant (Pearl) in Ras Laffan
Industrial City (RLIC) of Qatar including similar works.
1.2 SCOPE
The cladding & Life erection works shall take place at TSF Area. The construction & erection
activities shall be carried out by GAMA QATAR.
2 REFERENCES
T-4.129.853
T-4.129.867
T-4.129.865
T-4.129.868
T-4.219.611
T-4.234.080
T-4.234.084
T-4.234.542
T-4.219.622
:
:
:
:
:
:
:
:
:
3 DEFINITIONS
Company
Contractor or LINDE
Sub Contractor
Contract
QCP
ITP
QA/QC
HSSE
JSA (RA)
FSI
:
:
:
:
:
:
:
:
:
:
4 RESPONSIBILITIES
Engineer / Supervisor shall;
Be responsible for safe execution and quality of the work.
Monitor the site activities and ensure the job is progressing according to the project
schedule and specifications.
Coordinate with QA/QC inspector for inspection of activities.
T-4.250.953 Rev. O
Page 5 of 15
GAM-MTS-MEC-GTL-012
Doc. Title
Q A T A R
Date/Rev. No :
5 RESOURCES
5.1 EQUIPMENT & MANPOWER
A list of equipment and manpower is given below.
5.1.1 EQUIPMENT
Mobile cranes
Manlift
Hand tools
Rigging gear (Slings, shackles, etc.)
Surveying equipment and instruments
Safety Belt with double Lanyard
Trailer
5.1.2 MANPOWER
Site Manager
Foreman
Surveyor
Surveyor Helper
Helper
Rigger
HSSE Personnel
Banks men
5.2 MATERIALS
Fasteners
Sheeting & Flashings
Cladding materials
6 METHOD OF EXECUTION
6.1 PRE-COMMENCEMENT WORKS
6.1.1 WORK PERMIT
The erection operation of cladding & life line erection will starts with a request for
a permit to work.
6.1.2 TRAFFIC MANAGEMENT PLAN
Works shall not interrupt any kind of vehicle traffic on any access road leading to
any gates. In case of this kind of activity a revised traffic management plan shall
be provided.
6.1.3 EQUIPMENT AND PERSONNEL
All equipment shall be inspected and approved by the CONTRACTOR, and all
personnel shall be inducted and trained before they commence work on site.
T-4.250.953 Rev. O
Page 6 of 15
GAM-MTS-MEC-GTL-012
Doc. Title
Q A T A R
Date/Rev. No :
8 QUALITY ASSURANCE
A Quality Assurance System shall be operated conforming to related standards.
9 HSSE
All works shall be in compliance with the State of Qatar laws and regulations, Ras Laffan Industrial
City and International standards, codes, LINDE ENGINEERING AG and QSGTL and/or its PMC
requirements and instructions.
In addition all employees and GAMA subcontractor employees on site will have gone through GAMA
Qatar Site Safety Induction, LINDE ENGINEERING AG Site Safety Induction and QSGTL Safety
induction for site safety, health, environmental and security prior to resuming work activities at site.
T-4.250.953 Rev. O
Page 7 of 15
GAM-MTS-MEC-GTL-012
Doc. Title
Q A T A R
Date/Rev. No :
Other training courses will be attended as required by LINDE ENGINEERING AG or QSGTL and/or its
PMC as required.
Risk Assessment will have been prepared by the Risk Assessment Team (RAT) ranking the hazards
associated with project works and control measures to be taken to mitigate the hazards to an
acceptable level.
Each scope work or task will have a completed and approved Job Safety Analysis (JSA) identifying
the potential hazards and control measures that will be implemented to protect people and
environment.
The JSA (RA) will be used by Supervisor as the basis of conducting his daily TSTI meeting and his
weekly Tool Box Talk.
For additional safety requirements for a particular or specific task please refer to the JSA prepared for
that task.
All personnel will have PPE required for their specific tasks in addition to the minimum PPE (coveralls,
safety goggles, safety helmet, safety shoes, high-visibility vests, gloves) at site at all times as
required.
10 ATTACHMENTS
10.1
10.2
T-4.250.953 Rev. O
Page 8 of 15
Job being analyzed: METHOD STATEMENT FOR WALL CLADDING, ROOF CLADDING AND LIFELINE INSTALLATION
Department/Section doing JSA: HSSE & MECHANICAL WORKS
Normal Approvals:
Name
JSA by:
19.04.08
Date
Signature
19.04.08
Date
Approval required for hazardous work detailed in the Linde Work Permit Procedure.
Changing conditions and emergency procedures: Stop work. Switch off equipment. Supervisor directs personnel to nearest and safest muster point considering wind direction. Supervisor counts all employees.
Missing employees are reported to Linde HSSE Dept. When all clear is given, check with Linde HSSE before returning to work.
LINDE EMERGENCY TELEPHONE NO.
HSSE MANAGER:
Pearl HOT LINE :
583 40 72
474 88 88
Note: 1) If any of the tasks involves biological, physical or chemical hazards, then The LINDE Industrial Hygienist must also approve the work.
2) Use additional sheets as necessary.
3) Details on safety (PPE, Hazard etc) and environmental requirements can be found in LINDE and SHELL Safety and Environment Procedures.
Q A T A R
ITEM
1
ACTIVITY
Roof Installation
HAZARDS / POTENTIAL
CONSEQUENCES
1.1 Dropped materials.
Initial Risk
RISK
P C
RANK
Residual Risk
1.1.1
1.1.2
C
HIGH
1.1.3
1.2
Wind Hazard.
1.2.1
1.2.2
1.2.3
C
LOW
1.2.4
1.2.5
1.3
Unprotected edges or
openings.
1.3.1
C
HIGH
1.3.2
1.4
Lifeline failure
1.4.1
2
MED
1.4.2
MAIN
CONTROLS
Install barricades "exclusion zone"
with sign boards indicating roofing
works in progress to prevent
unauthorized entry.
All materials shall be safely
lowered from one level to the next
either by hand-to-hand or by lifting
equipments or by securely
attaching a rope and hauling.
Tools shall be tied by retaining
rope attached to the harness.
100% personal fall protection
system.
Monitor wind speed using
Anemometer.
Crane operations shall be stopped
at greater than 25 knots.
Lifting work must be stopped
during strong wind.
Ensure all roofing sheets to be
secured on the ground and on the
roof.
Full body harness and lanyards
shall be inspected & colour coded.
Harness and safety line to be
used when height more than 1.5
meters.
Ensure lifeline has a design
calculation/Engineering Design.
Ensure lifeline can withstand load
impact as per HSSE procedure.
ADDITIONAL
CONTROLS
1.1.1.1 Remove any unnecessary
materials.
1.1.1.2 Provision of watchman with
whistle & vest to control people
from barricaded area.
LOW
LOW
LOW
LOW
Q A T A R
ITEM
2
ACTIVITY
HAZARDS / POTENTIAL
CONSEQUENCES
Sliding installation. 2.1 Dropped materials.
2.2
2.4
HIGH
Wind Hazard.
2.3
Initial Risk
C RISK
LOW
LOW
MED
MAIN
2.1.1 Install barricades "exclusion zone"
with sign boards indicating roofing
works in progress to prevent
unauthorized entry.
2.1.2 All materials shall be safely
lowered from one level to the next
either by hand-to-hand or by lifting
equipments or by securely
attaching a rope and hauling.
2.1.3 Tools shall be tied by retaining
rope attached to the harness.
2.2.1 100% personal fall protection
system.
2.2.2 Monitor wind speed using
Anemometer.
2.2.3 Crane operations shall be stopped
at greater than 25 knots.
2.2.4 Lifting work must be stopped
during strong wind.
2.2.5 Ensure all roofing sheets to be
secured on the ground and on the
roof.
2.3.1 Warm personnel's about pinch or
crush points.
2.3.2 Two tag lines shall be attached to
control the loads.
2.4.1 All employees shall wear
inspected full body harness fitted
with twin lanyards shall be fitted
with dual action self locking safety
hook for 100% Tie-off.
2.4.2 Ensure 100% fall protection.
ADDITIONAL
Residual Risk
P C
R
LOW
LOW
LOW
LOW
Q A T A R
ITEM
3
ACTIVITY
Using of Manlift.
HAZARDS / POTENTIAL
CONSEQUENCES
3.1 Mechanical Breakdown.
3.2
LOW
Improper use of
equipment
B
3.3
Initial Risk
C RISK
LOW
Untrained personnel.
LOW
MAIN
ADDITIONAL
Residual Risk
P C
R
LOW
LOW
LOW
Q A T A R
ITEM
ACTIVITY
HAZARDS / POTENTIAL
CONSEQUENCES
3.4
LOW
Fall of personnel
3.5
Initial Risk
C RISK
MED
Overturning of Machine
MED
MAIN
3.3.3 Training and practice in this type
of work undertaken is essential.
3.3.4 Ensure that equipment operator is
certified by third party, valid
certificates.
3.4.1 Safety harness shall be provided
for the use of all personnel
working from mobile work
platforms so that in the event of
any advertent movement of the
platform they are working from,
they will not be thrown from it.
3.4.2 Boxes, hop-ups or ladders will not
be used to gain additional height
or reach from the platform of
manlift machine work platform.
3.5.1 Ensure no excessive force by the
operator on the platform by
introducing an element of side
load.
3.5.2 The outriggers or stabilizers, when
fitted, shall be fully extended and
in position, before the platform or
boom is raised.
3.5.3 The platform shall not be
overloaded exceeding the
regulated safe working load.
3.5.4 Ensure the machine will be located
to the most suitable position for
the job to be carried out before
any slewing takes place.
ADDITIONAL
Residual Risk
P C
R
LOW
LOW
LOW
Q A T A R
ITEM
ACTIVITY
HAZARDS / POTENTIAL
CONSEQUENCES
B
3.6
Issuance of PTW
4.1
Initial Risk
C RISK
MED
Vehicle movement
Work Stoppage
MAIN
ADDITIONAL
LOW
3.6.1 Ensure all vehicle movement to be 3.6.1.1 Barricade and secure the
guided by competent banks men
working are with sign boards to
with high visibility vests.
prevent unauthorized entry.
3.6.2 Ensure that each piece of
equipment is fitted with an
automatic reverse alarm and
beacon or strobe light.
LOW
Residual Risk
P C
R
LOW
LOW
LOW