Procedures For Connecting Switchgear and PSA

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 3

Procedures for Connecting

Switchgear and PSA


Tie In Procedures
Dated: 08th April 2014
Document No TIP-Sub-R1A-Rev00
PO No 6510521318
Client Saudi Electricity
Job Order No 7-00014
Project Name Installation of HMI at 7 substations in Riyadh
Plant RIyadh Sub R1A
Tie In Procedures for Transformer Feeders GCB3A, GCB2A, GCB3B, GCB2B, Tie
Breaker and Incomer-1 and Incomer-2
Reference Documents
1. IO List
V21-R1A-IO-STATUS-001 Rev 01, V21-R1A-IO-CONTROL-001 Rev 01
2. Approved Red Marked Schematics for the Switchgear
3. PML Meter Daisy Chain Drawing V21-R1A-DS-001 Rev01

Make sure the Breaker Transformer Feeder is in Open Condition


Make sure both the disconnect Switches are open and both the
Grounding Switches are closed to put the breaker under modification
under test position (tags to be discussed with POD/ESO engineers
before operation)
Open the MCB for Closing Circuit and Tripping Circuit on the Switchgear
Side and Tag it
Open the MCB DC-1 and AC-1 and AC-Aux inside V21-R1A-PSA-001 and
Tag it
Existing Selector Switch will be replaced with the new Selector Switch
using the following steps
o Tag each and every wire of the existing selector switch
properly for Local/Remote contacts and verify from the
drawings.
o Open the control cables from the existing selector switch and
pull out the existing selector switch from the switchgear
panel, install the new selector switch and carefully following
the approved RED MARKED modified drawings for the panel,
put back the Local and Remote contacts to the new selector
Switch on the same positions of Local and Remote matching
each other.
o New Selector Switch will be used on the same location and
same cut-out as the original.
Saudi Aramco: Company General Use

o One Extra Contact (apart from the contact being used in the
scheme) from Local and Remote shall be taken to the
Terminal Block as per the RED MAREKD Modified drawings for
the switchgear.
o One Contact from PSA and SCADA each shall be wired to the
terminal block as per RED MARKED Modified drawings.
Install new Terminal Block Strip along with all accessories i.e. CChannel, Tag Carrier, Protective Strip and Terminal Numbering, End
Plates and End Stoppers
Local / Remote / PSA and SCADA and Breaker Open / Close Status
Signals shall be taken to the designated Terminal Block No referring to
Approved Red Marked Drawings
25Core 22AWG Status Cable shall be used to carry these signals from
the terminal blocks installed inside the switchgear to the terminal
blocks inside the PSA Panels consulting the IO List and Approved Red
Marked Modified Drawings
Modify the existing switchgear scheme to accommodate and segregate
Local, Remote, PSA and SCADA positions in Close and Trip Circuit using
Approved Red Marked Modified Drawings
14Core 14AWG Cable shall be used to run the control signals from
terminal blocks of the switchgear to the terminal blocks of the PSA
panel consulting the IO List and Approved Red Marked Modified
Drawings
PML meters shall be daisy chained as per the Daisy Chain Approved
Connection Diagram and signals brought to PSA Panel V21-R1A-PSA002 via 22AWG 3 Core Wire.
Lock Out Relay Connection and 94 Operated Connection of the
respective Feeders shall be wired to the Digital Input of the PML Meter
as per the IO List
Perform Continuity Test / Loop Check for the modified circuit from
Switchgear to PSA panel and highlight in as-builts
With the breaker still in test mode (i.e. Disconnector open and
Grounding closed), turn on the MCB for Tripping and Closing Circuit.
Turn on the MCB DC-1 and AC-1, AC-Aux inside the PSA Panel and
power on the IO Controllers DPAC-1 and DPAC-2
Using the IO list, check the status of Direct / Remote / PSA / SCADA
selector switch.
Each position of Selector Switch should light up its respective LED (IO
List to be used as reference) and Digital Input which will be viewed
from HMI
Check the Lock Out Relay Operation and check the status on PSA Panel
from HMI by jumping the contact of the Lock Out Relay. Special
Cautious measures to be taken that Lock Out Relay should not trigger
any other Breaker

Saudi Aramco: Company General Use

Opening and Closing of Circuit Breaker while still in test mode (i.e.
Disconnector open and Grounding closed) via Local, Remote, PSA and
SCADA
Do the testing of opening and closing against the positions as per the
reaction matrix below

Saudi Aramco: Company General Use

You might also like