Decommissioning in The North Sea - Demand Vs Capacity - Low-Res

Download as pdf or txt
Download as pdf or txt
You are on page 1of 100

Decommissioning in

the North Sea


Review of Decommissioning Capacity

Decom North Sea


Review of Decommissioning Capacity | October 2014

2
Boskalis

Decom North Sea


Review of Decommissioning Capacity | October 2014

Contents
Executive Summary

1 Introduction

Topside and Substructure Removal 55


7.1 Overview

57

7.2 Activity

58

1.1 Background and Context

7.3 Supply Chain

60

1.2 Drivers and Influencers

7.4 Health Check

63

Topsides and Substructure


Recycling

65

Analysis of Supply Chain Approach 17

7.1 Overview

67

2.1 Analysis Approach

18

7.2 Activity

68

2.2 Resource Breakdown Structure

19

7.3 Supply Chain

70

2.3 Programme

18

7.4 Analysis

74

Market Forecasts

23

3.1 Market Forecasts of Expenditure

24

3.2 Market Forecasts of Activity

4
5

1.3 The North Sea in Numbers

10

1.4 Decommissioning Approaches

14

8 People

77

30

Context and Considerations

81

Critical Supply Chain Elements

39

Appendix A: References

87

Well Abandonment

45

Appendix B: Criteria Scoring

91

5.1 Overview

47

Appendix C: Resources

95

5.2 Activity

48

5.3 Supply Chain

50

5.4 Health Check

52

Contents

Decom North Sea


Review of Decommissioning Capacity | October 2014

Executive Summary
The O&G Decommissioning sector offers a significant
socio-economic opportunity in terms of job creation
in the Scottish, UK and European supply chains,
and an opportunity for North Sea based firms to
export expertise to other parts of the world. This
report, prepared by Arup and commissioned by
Decom North Sea (DNS) and Scottish Enterprise,
seeks to provide an overview of the scale and
nature of the decommissioning market in the next
decade highlighting areas where there are potential
bottlenecks in the supply chain.
There is a need to continue to develop the existing
O&G and decommissioning supply chain to
meet future increases in demand associated with
Decommissioning in the North Sea. This offers
a significant opportunity to the supply chain in a
growth market, and will require a range of highly
skilled and high value capability. A range of activities
will require innovation in terms of technical and
management approaches to drive down the costs
of decommissioning. There are other areas that
will need significant growth in capacity to meet the
demands of the market.

Executive Summary

The analysis focuses on critical supply chain


elements which are resources that are fundamental
to delivering decommissioning projects, and
which would have the most significant effect on
the deliverability of the these projects if there were
capacity constraints. The critical supply chain
elements that have been identified are:

rigs/rigless abandonment infrastructure,

removal vessels for topsides and substructure,

ports/harbours/yards for recycling and

skilled engineering and operational resources


serving all aspects of the sector.

These are the areas where the supply chain,


operators and Government will need to work closely
to ensure that the opportunities are realised. For
other resources the supply chain is more likely to
be able to naturally respond without major external
intervention.
A capacity health check for the critical supply chain
elements considers available capacity and investment
lead time, investment commitment, pressures/
synergies from other industries and capability. The
study drew from the experience and expertise of a
number of significant firms currently operating within
the North Sea decommissioning market. There
was broad consensus amongst this group that the
industry needed to evolve to efficiently deliver the
activity needed over the next 40 years.

Decom North Sea


Review of Decommissioning Capacity | October 2014

A Changing Mind Set

Contracting and Procurement Strategy

The approaches and philosophy of the Exploration


& Production (E&P) market are currently largely
implemented in the decision making processes of
the decommissioning market. There is a need for the
market to evolve an approach to decommissioning
that is distinct from that of exploration and production
activity. Recognition of the different drivers and
success criteria of E&P versus decommissioning
should enable the market to evolve an approach that
is optimised for their respective projects.

Rigidity in contracting and procurement structures


developed to support the E&P market can inhibit
operators and the supply chain from adapting to
meet the demands of the decommissioning market.
Adapting existing procurement strategies to reduce
requirements for proof of previous experience will
allow new entrants to the market who may introduce
innovative methods.

Smoothing the Peaks


Creating accurate estimates of decommissioning
expenditure across the North Sea is challenging.
Estimates have been produced in isolation by a
range of organisations from the bottom up. These
show a broad range in expenditure on a year by
year basis and over the next decade. Operators
are likely to have significantly more flexibility to
manage procurement and programme decisions for
decommissioning activities than in E&P, where a race
to production is imperative. Consequently, the market
is unlikely to procure services in the peaks suggested
by the predicted estimates as the cost to procure
resources would increase i.e. the market will smooth
out the peaks.

Driving Innovation, Driving Down Costs and


Regulation
Innovation can play a role in delivering
decommissioning in a more cost effective manner.
The nascent market has limited experience focusing
on decommissioning activities and is at a stage
where it can incorporate lessons learnt along with
developing new approaches to reduce costs.
The uncertainty in the timescales of the market
opportunity is limiting commitment to drive and invest
in innovation. The supply chain cites the stop/start
nature of the industry as a barrier to investment.

Executive Summary

Decom North Sea


Review of Decommissioning Capacity | October 2014

Decom North Sea


Review of Decommissioning Capacity | October 2014

1.0 Introduction

Decom North Sea


Review of Decommissioning Capacity | October 2014

1.1 Background and Context


The Cost

The Scope

Projected North Sea decommissioning activity


estimates vary, with the most conservative estimates
predicting the market will require over 30bn of
expenditure before 2040 in the UK Continental Shelf
(UKCS) alone[1]. As ageing assets reach the end of
their economically useful life it is expected that the
next 5 to 10 years will see a significant increase in
activity, increasing up to an estimated annual spend
in excess of 2.5bn per annum[1],[2],[3].

North Sea O&G resources are extracted from


the North Sea and proximate areas including the
Norwegian Sea and Atlantic Ocean. This area is
collectively known as the North Sea within the O&G
industry. Four countries have O&G resources rights
which they exploit in the North Sea. These are
the United Kingdom, Norway, Denmark, and the
Netherlands, and it is this area that is the focus of this
study.

The Opportunity

The Contributors

The Decommissioning Sector offers a significant


socio-economic opportunity in terms of job creation
in the Scottish, UK and European supply chains,
and a foundation from which North Sea based firms
can export expertise to other parts of the world. To
take full advantage of this opportunity, the industry
must build on its existing capacity and capability
to service the complex and demanding nature of
decommissioning work in the North Sea.

This report uses a number of existing sources of


information to assess the likely scale of demand for
decommissioning services. It then draws on Arups
knowledge of the Sector, along with the expert
views of a range of industry leaders in the field, to
identify and assess critical areas of capability and
capacity. Particular thanks go to the following for their
invaluable insight and contributions:

The Objectives

CNR International

This report, prepared by Arup and commissioned by


DNS and Scottish Enterprise, seeks to provide an
easily understandable and concise overview of the
scale and nature of the decommissioning market. In
particular, highlighting areas where there are potential
bottlenecks in the supply chain which might impact
decommissioning activity levels.

Halliburton

Aker Solutions

Marathon Oil
Royal Boskalis Westminster N.V.
Seaway Heavy-lifting
Weatherford International
Wood Group

Note: All references can be found in Appendix A

Introduction | Background and Context

Decom North Sea


Review of Decommissioning Capacity | October 2014

1.2 Drivers and Influencers


The market drivers are complex and there are many
technical, commercial and regulatory influences
which will affect the manner in which the market for
decommissioning activity is realised. Understanding
the opportunities and challenges presented by
North Sea O&G decommissioning is best informed
by reviewing the market as part of a much more
extensive whole, including E&P and other competing
industries.

Regulation
A range of international and national legislations
impact the North Sea Decommissioning Sector.
Of these, OSPAR is particularly significant in terms
of influencing decommissioning approach.
OSPAR Decision 98/3 prohibits leaving offshore
installations wholly or partly in place unless further
derogation are granted. However, it provides
certain derogations to concrete structures and the
footing of large steel jackets weighing more than
10,000 tonnes, from the fundamental principle
that decommissioning should result in full removal
of the installation. Derogation is not automatically
available and is subject to a detailed assessment
and consultation procedure to determine if there are
significant reasons to allow the installation (or part
thereof) to remain in situ. Furthermore, no derogation
is available to steel installations constructed after 9
February 1999 (being the date that Decision 98/3
came into force).
As a result of the OSPAR ruling, the North Sea will
lead global decommissioning practice from a total
removal perspective.

The Other Industries


Decommissioning offshore installations is one
component of offshore industrial activities occurring
in the North Sea. These include E&P, offshore wind,
marine renewables, power and communications
networks, and port and harbour developments.

This broader appreciation will provide a greater


understanding of where it competes for resources
with other offshore activities, and where possible
synergies exist, notably in the area of transferable
skills.

The Global Industry


In terms of expenditure, the North Sea represents
an important but modest part of an extensive global
O&G industry, including onshore and offshore activity
across upstream, midstream and downstream
Sectors.
The resources supporting the North Sea market tend
to be highly mobile and operate in a global, rather
than local market. The cycles of the global activity
will influence the availability of certain North Sea
resources.

Asset Life Cycle


Decommissioning is the final chapter of a whole
asset lifecycle, which often stretches back many
years to initial fabrication and installation, through
maintenance, refurbishment and production,
then into the late life asset management cycle,
including cessation of production and ultimately
decommissioning. The design and management
of the asset through its long life cycle will influence
the approach to decommissioning and provides
important context for the market.

Interdependent Systems
Individual offshore O&G assets, be they platforms,
pipelines, wells or utilities, often interact with and
are interdependent upon one another to a greater
or lesser degree. While these can introduce
additional complexities to the decommissioning
process, they can offer opportunities to increase
the decommissioning process efficiency through
integrated management of systems and processes.

Understanding the opportunities and challenges


presented by North Sea O&G decommissioning
therefore needs to be considered in the context of
these wider activities.

Introduction | Drivers and Influencers

Decom North Sea


Review of Decommissioning Capacity | October 2014

1.3 The North Sea in Numbers


Installations in the North Sea
450

Number of Installations

One of the main challenges in determining the supply


chain requirements stems from the heterogeneity of
the types and designs of structures present in the
North Sea. This renders a consolidated approach
to removal difficult, if not impossible. Indeed, North
Sea infrastructure varies across geographies due
to a range of factors including the nature of the
resources being exploited, the geological conditions,
water depth, the technology available and metocean
conditions.

400
350
300
250
200
150
100
50
0

The Installations

Denmark

Netherlands

UK

Norway

Country

There are more than 1500 registered installations in


the North Sea including small fixed steel installations
of less than 100 tonnes, large heavy concrete gravity
base or fixed steel installations weighing up to 0.5
million tonnes, floating steel, concrete installations
and subsea steel infrastructure[4].

Fixed Steel

Floating Concrete

Floating Steel
Others

Concrete Gravity Based

Source: OSPAR[4]

North Sea Installation Types


(excluding subsea steel)

Excluding subsea steel, there are 715 installations


in the North Sea: the vast majority of these
installations are fixed steel (83%) and located
in the UKCS (53%)[4].

Others 3%
Concrete Gravity Based 4%
Floating Steel 11%
Floating Concrete >1%

The Age

Fixed Steel 82%

The North Sea has an ageing asset base, with


the first field having commenced production in
1967. The peak ten year period was from 1984
to 1993 when an average of 20 installations were
commissioned each year. The yearly peak occurred
in 1993, with 38 commissions[4]. The average over
the last ten years has been just over 7.5 a year with
a peak of 13 a year[4].

Source: OSPAR[4]

The average age of North Sea installation is 25


years. The UKCS has the oldest average asset base,
whilst Denmark owns the youngest assets. There are
currently 245 assets over 30 years old across the
North Sea[4].

Average age of North Sea Installations


28
27

Average Age

26
26

25
24
24

23

24

22
21

22

20
19
Denmark

Netherlands

Country

10

Introduction | The North Sea in Numbers

Norway

UK
Source: OSPAR[4]

Decom North Sea


Review of Decommissioning Capacity | October 2014

Decommissioning
Only 12% (88) of North
Sea installations have been
decommissioned to date,
reflecting the nascent nature of
the decommissioning market[4].
This includes 55 fixed steel
installations, 22 floating steel,
3 concrete gravity base and 7
others.
Of the 88 installations that have
been decommissioned, only
seven have had derogations
granted to allow infrastructure
to remain in place. These have
been associated with installations
in NW Hutton, Frigg and
Ekofisk. These were all concrete
gravity base infrastructure with
substructures over 200,000
tonnes. The only exception
NW Hutton was a fixed steel
installation where the jacket and
topside were removed and the
footings of the jacket were left in
situ.

Installations by Age. Source: OPSAR[4]

Introduction | The North Sea in Numbers

11

Decom North Sea


Review of Decommissioning Capacity | October 2014

The Geographies
UKCS Southern North Sea, Danish and Dutch Sectors are
generally characterised by comparatively shallow water (less
than 60 meters), relatively moderate metocean conditions,
and exploit gas resources. They have comparatively light
installations[4].

Fixed and Floating Steel Infrastructure Weight


in the North Sea
UNITED KINGDOM
Topside
3,068,000 tonnes

The Norwegian Sector and UKCS Central and northern


North Sea have deeper water and more exposed metocean
conditions. The platforms are larger and heavier[4].
The Norwegian Sector has proportionally larger installations
in tonnage terms compared to other countries. This is
because the majority are large deep water installations.
Norway has a larger percentage of heavy concrete gravity
base infrastructure when compared to the UKCS.
The UKCS area contains a mix of platform sizes with lighter
installations predominately in the southern area and heavier
installations moving north.
Despite having a similar number of installations to the
Norwegian Sector, the Dutch Sector only has a small
proportion of the total installation tonnage, as the majority
are small installations.

Substructure
1,687,000 tonnes
NORWAY
Topside
985,000 tonnes
Substructure
675,000 tonnes
NETHERLANDS
Topside
215,000 tonnes

Infrastructure Weight in the North Sea

Total Weight (Te) Millions

10

Substructure
127,000 tonnes

9
8

DENMARK

7
6

Topside
155,000 tonnes

5
4
3

Substructure
87,000 tonnes

2
1
0
Fixed Steel

Floating
Concrete

Floating
Steel

Topside

Concrete
Gravity Based

Others

Subsea Steel

Substructure

Source: OPSAR[4]

12

Introduction | The North Sea in Numbers

Source: OPSAR[4]

Decom North Sea


Review of Decommissioning Capacity | October 2014

Topside Weight of Installations greater than 30 years old. Source: OSPAR[4]

Introduction | The North Sea in Numbers

13

Decom North Sea


Review of Decommissioning Capacity | October 2014

1.4 Decommissioning Approaches


The manner in which assets can be decommissioned is subject to a Comparative Assessment. This assessment
is used to make recommendations to the regulatory authority. It considers the technical feasibility, environmental
and social impact, economic and health & safety implications of all viable decommissioning approaches in
determining the optimal approach. The decommissioning approaches associated with the main infrastructure
elements are influenced by the original installation design, and the strategy implemented by the operator.

Well Abandonment
Running, Make Safe & Preperation
Subsea & Site Remediation
Topsides & Substructure Recycling
Operator Project Management & Monitoring
Topside & Substructure Removal

Topsides
Several methods are used for removing installations. The main classifications include:
Piece Small - the installation is dismantled offshore by cutting or dismantling into small sections that are
shipped onshore in containers.
Heavy-lift - whole modules are removed in the reverse of the installation sequence and loaded on to flat-top
barges or a crane vessel for transport to the decommissioning yard.
Reverse Float Over - the topside is removed in an approach that is a reversal of a float over installation
process. Here, the whole topside is cut from the jacket and taken ashore in one piece, with the installation
partly floating during transport.
Single Lift - the topsides and/or jacket are removed in one piece and transported to the decommissioning
yard.

14

Introduction | Decommissioning Approaches

Decom North Sea


Review of Decommissioning Capacity | October 2014

Substructures
The main classification of substructures includes:

Steel Installations

Floating Installations (concrete or steel)

Concrete Gravity Bases

The majority of substructures will require total removal.


For platforms with the option to apply for a derogation,
they can be partially removed or left in place if
approved.
The main classifications include:
Heavy-lift [as explained in the section above]
Reverse Installation [as explained in the section
above]
Single Lift [as explained in the section above]
Buoyancy where buoyancy tanks are installed on
the jacket legs to force the platform to the surface

Wells
Plugging & Abandonment (P&A) is the process by
which a well is closed permanently, usually after
either logs determine there is insufficient hydrocarbon
potential to develop the well, or after production has
ceased. Abandonment must be done in a way that
protects the downhole and surface environment in
perpetuity.

In order to determine the manner by which a well


can be abandoned, data is collected from the well
to determine its current condition. Depending on the
age and history of the well and the quality of records,
it can be challenging to accurately determine the well
state. This creates risk in selecting the appropriate
abandonment approach. An approach which can
only be operated in good conditions may reduce
costs if conditions turn out to be favourable but
lead to significant additional costs if conditions are
unfavourable.

Pipelines
OSPAR have not made any recommendation for
pipelines, and therefore there is no obligation to
remove them. Agreement must be obtained from
the regulating authority on the appropriate approach
through consideration in a comparative assessment.
Key issues to be considered are pipeline cleanliness,
stability, extent of burial and impact on other users of
the sea.
There are diverging precedents in the North Sea.
Indeed, some pipelines have been decommissioned
in situ, while others have been removed to shore.
Generally, the smaller pipelines which can be more
easily removed without significantly disturbing the
seabed are recovered. O&GUK have produced
guidelines on the decommissioning of pipelines.

All wells must be plugged and abandoned according


to regulations once no longer in use and their
connecting platform is being decommissioned. P&A
involves plugging off the well generally with cement
plugs and salvaging all recoverable equipment. The
standards applied in terms of expected integrity vary
between jurisdictions. The North Sea has some of
the worlds most stringent regulations. In this region,
responsibilities for well integrity are enduring and any
future failure must be remedied by the operators.
There is a diversity of well infrastructure in the North
Sea which is determined by a variety of technical
factors associated with the well including type,
location, status and geology. Wells are associated with
a range of E&P life cycle activities including exploration
(identifying resource), appraisal (determining
commercial viability) and development (extracting
resource). Wells ready to be P&A may have been
suspended through installation of a temporary cap.
Alternatively, they may be associated with a depleted
reservoir.

Introduction | Decommissioning Approaches

15

Decom North Sea


Review of Decommissioning Capacity | October 2014

Boskalis

16

Decom North Sea


Review of Decommissioning Capacity | October 2014

2.0 Analysis of Supply Chain Approach

17

Decom North Sea


Review of Decommissioning Capacity | October 2014

2.1 Analysis Approach


The approach to the analysis of the decommissioning
supply chain taken in this report is explained below.

Market Forecasts of Expenditure Trends


A review of existing industry estimates of overall
anticipated decommissioning expenditure was
undertaken to understand the likely range of activity
over the next 5 to 10 years in the North Sea.
This information is found in Chapter 3.

Critical Supply Chain Elements


This involved identifying the critical supply chain
elements on which the detailed assessment
was undertaken. Critical supply chain elements
are resources that are fundamental to delivering
decommissioning projects, and which would have
the most significant effect on the deliverability of the
decommissioning projects if there were capacity
constraints. It is on these elements that a detailed
activity analysis was undertaken. This information is
found in Chapter 4.

Market Forecasts of Activity Trends


These estimated the level of activity expected for
each of the critical supply chain elements which
was informed by the overall expenditure trends. This
information is found in Chapter 3.

Supply Chain Capacity Review


This consisted of a detailed review of the capacity of
the existing supply chain for the critical supply chain
activities. This information is found in Chapters 5 to 8.

18

Capacity Health Check


A capacity health check analysis was essential to
determine the critical supply chain elements. The
analysis considered the following parameters:

Available Capacity & Investment Lead Time - the


existing capacity of skills and resources against
expected activity and the duration it takes to
build any capacity shortfall.

Investment Commitment - the progress and


commitment made by the supply chain to build
new capacity to meet any shortfalls.

Pressures/Synergies from other industries - the


opportunity or threat of analogous industries.
This can result from competition from resources/
skills, or supporting the investment case to build
capacity.

Capability - the competence of the industry to


support the decommissioning market.
It is distinct from capacity as it does not relate
to the volume of capable resources to meet
the predicted demand. The classification of
capability is derived from the assessment
commissioned by DNS and Scottish Enterprise[5].
In this report, the industry and supply chain was
consulted on their perceived capability to provide
decommissioning services as per the Oil & Gas
UK (O&GUK) Work Breakdown Structure (WBS).

Each critical supply chain element is attributed a


score of Low to High (Low, Low/Medium, Medium,
Medium/High, High) for each parameter. The scoring
is based on subjective criteria which are detailed in
Appendix B. The capacity health check is found in
Chapters 5 to 8.

Analysis of Supply Chain Approach | Analysis Approach

Decom North Sea


Review of Decommissioning Capacity | October 2014

2.2 Resource Breakdown Structure


A common language in decommissioning has been developed by O&GUK through the production of their WBS.
Activities associated with the decommissioning programme have been characterised in 11 categories which are
defined.
This report uses an aggregated version of the O&GUK WBS which focuses on the resource requirements. Some
O&GUK categories have been combined where there is commonality in the resources that support the activities.
This categorisation has been termed in this report as the Resource Breakdown Structure (RBS) to differentiate it
from the O&GUK WBS.
The relationship between the 2013 O&GUK WBS and the RBS can be seen in the figure below.

Work Breakdown Structure


Operator Project
Management &
Monitoring
Well Abandonment

Facility Running / Owners Costs (Pre NU/NUI)

Operator Project Management

Facilities / Pipelines
Making Safe
Topsides Preparation

Well
Abandonment

Running, Making
Safe & Preparation

Topsides Removal

Substructure Removal

Topside &
Substructure
Removal

Subsea Infrastructure

Site Remediation
Topsides and
Substructure Recycling
Monitoring

Subsea & Site


Remediation

Topsides &
Substructure Reuse
& Recycling

2013 O&G UK WBS

The resources associated with each element of the RBS are


detailed in Appendix C.

Arup
Resource Breakdown Structure

Analysis of Supply Chain Approach | Resource Breakdown Structure

19

Decom North Sea


Review of Decommissioning Capacity | October 2014

20

Decom North Sea


Review of Decommissioning Capacity | October 2014

2.3 Programme
The decommissioning programme commences with the management of the asset during late life, and lasts all the
way to the monitoring of the seabed once the asset has been decommissioned. The diagram below shows the
RBS activities in a programme format.
The programme duration depends on the technical complexity of the project as well as a range of commercial
considerations. A typical project is often carried out in parts with several periods of inactivity, rather than a
continuous activity flow and so individual project programmes can vary significantly.

Hydrocarbon
Free

Late Life Operations and


Asset management

Well Abandonment
Facilities, Pipelines
Making Safe
Topside
Preparation
Topside
Removal
Substructure
Removal

CoP

Subsea Infrastructure

Site Remediation
Topsides & Substructure
Reuse or Recycling

Monitoring

Facilities Running, Owners Costs

Analysis of Supply Chain Approach | Programme

21

Decom North Sea


Review of Decommissioning Capacity | October 2014

22

Decom North Sea


Review of Decommissioning Capacity | October 2014

3.0 Market Forecasts

23

Decom North Sea


Review of Decommissioning Capacity | October 2014

3.1 Market Forecasts of Expenditure

The UKCS is likely to be the largest sector


of the North Sea decommissioning market,
although Norway is expected to contribute
a significant proportion of activity as the end
of the decade approaches. Denmark and the
Netherlands are likely to contribute a much
smaller proportion of activity.

Annual Estimated North Sea


Decommissioning Expenditure
3,000

Estimated Expenditure (M)

Available market forecasts indicate that the


overall decommissioning expenditure in the
North Sea could be between 1.1bn and
2.6bn per annum, and is estimated to
reach over 17bn for the period between
2014 to 2022[1], [3].

2,500

2,000

1,500

1,000

500

0
2014

2015

2016

2017

OGUK Insight 2013 Report


UK

2018

2019

Mackay 2013
Norway

2020

2021

2022

Mackay 2013
Denmark & Netherlands

Source: Oil & Gas UK[1], Mackay Consultants[3]

Annual Estimated North Sea


Decommissioning Expenditure
Estimated Expenditure (M)

2,000
1,800
1,600
1,400
1,200
1,000
800
600
400
200
0
2014

2015

2016

2017

OGUK Insight 2013 Report


UK

2018

2019

Mackay 2013
Norway

2020

2021

2022

Mackay 2013
Denmark & Netherlands

Source: Oil & Gas UK[1], Mackay Consultants[3]

24

Market Forecasts | Market Forecasts of Expenditure

Decom North Sea


Review of Decommissioning Capacity | October 2014

Predicting Decommissioning Activity

Profile of Market Activity

Accurate estimation of decommissioning expenditure


is challenging. Forecasts have been produced by a
number of organisations to estimate the profile of
decommissioning expenditure in the North Sea over
the next decade. These estimates are substantially
diverse both in the short and long term.

There are further limitations in decommissioning


estimates which are built from a bottom-up analysis
based on individual operators independently
declaring their expected decommissioning schedule.
These estimates suggest that activity will ramp up in
the next decade with a number of peaks and troughs
in activity.

The estimates are underpinned by assumptions


of the costs of decommissioning activities and the
programme in which activities are delivered. There is
inherent uncertainty in both areas:

The timing of decommissioning activities is


informed by an economic analysis which
considers the revenue generated from the asset
in terms of productivity and market value of the
resource, the costs to operate and maintain
the infrastructure and the capital costs of
decommissioning. Current trends have seen
O&G prices increase, while technology innovation
has allowed for improved extraction, increasing
the life span of ageing infrastructure
The costs of decommissioning generally have
not to date been reliably predicted, due to the
nascent stage of the industry. The evolving
market has significant potential to reduce costs
through applying innovative approaches that
reduce costs and simplify operations.

However, the market is inherently different to that of


E&P activities. In E&P programmes, delays directly
impact the timing of subsequent revenue flows
and programme drivers are highly significant in
procurement decisions, resulting in an industry that
has a peaking profile.
For decommissioning, programme delays defer
capital expenditure and often have a relatively less
significant detrimental impact on project economics.
As a result, operators are likely to have higher
flexibility to manage procurement and programme
decisions, and are unlikely to procure in peak periods
so there will be a flattening of the peaks and troughs
with the decommissioning market flexing.

Data from the Norwegian, Danish, and Dutch Sectors


are significantly less detailed and less robust than
data from the UKCS. Although these Sectors have
fewer installations than the UKCS, they cumulatively
represent almost half of the O&G infrastructure in the
North Sea.

Market Forecasts | Market Forecasts of Expenditure

25

Decom North Sea


Review of Decommissioning Capacity | October 2014

Interaction with the Wider Supply Chain


The vast majority of resources utilised by the decommissioning market are not wholly specialised to those
activities. A number of critical supply chain elements support other offshore industries such as E&P, offshore wind,
subsea cabling, and marine renewables. The mobility of resources means that the impact potential of local and
global activities on decommissioning supply should be considered. Indeed, decommissioning spend over the next
decade is expected to be a small proportion of overall O&G market, both in the North Sea and globally. Therefore
expenditure in this area is likely to be a key influencing factor in the delivery of North Sea decommissioning.

Forecasts of Expenditure in the UKCS

However, there is significant uncertainty with


regards to the spend that will actually be
incurred, due to confidence in the estimates
of both costs and timing of individual
programmes. Comparison of O&GUK
analysis with other trend analysis shows
a significant range in both the annual and
average forecasts. The largest annual variance
is over 1.2bn and average range is over
0.5bn[1],[2],[3],[6].

2,000

Estimated Expenditure (M)

O&GUK undertake a comprehensive survey


of estimated spend and activity in the UKCS.
Their members estimate that 10.4bn of
expenditure will be incurred by 2022[1]. This is
approximately 30% of the decommissioning
costs in the UKCS estimated to 2040[1]. This
spend is associated with the decommissioning
of 2,300km of pipelines, over 130 installations
and 800 wells[1].

Forecast Annual Average UKCS Expenditure


(2014 - 2022)
1,800
1,600
1,400
1,200
1,000
800
600
400
200
0

Annual Average
OGUK Insight 2013 Report

Kemp 2014

Oil and Gas UK Activity Report 2014

Mackay 2013
Source: Oil & Gas UK[1][6],
Prof. Kemp[2] Mackay Consultants[3]

Overall Average

Forecast Annual UKCS Decommissioning


Expenditure
Estimated Expenditure (M)

2,500

2,000

1,500

1,000

500

2014

2015

2016

2017

2018

2019

2020

2021

OGUK Insight 2013 Report

Kemp 2014

Oil and Gas UK Activity Report 2014

Mackay 2013

2022

Source: Oil & Gas UK[1][6], Prof. Kemp[2] Mackay Consultants[3]

26

Market Forecasts | Market Forecasts of Expenditure

Decom North Sea


Review of Decommissioning Capacity | October 2014

Resource Breakdown Structure Average


UKCS Expenditure (2014 - 2022)

Expenditure in each of the six RBS


categories is biased toward Well
Abandonment which accounts for 46%
of the average spend over the period.
Two categories; Running, Making Safe
& Preparation as well as Topside &
Substructure Removal, account for a
further 40% of spend, with the remaining
categories accounting for only 14%[1].

Topside & Substructure Reuse & Recycling


1%

Subsea & Site Remediation

5%

Topside &
Substructure Removal

Operator Project Management & Monitoring

8%
Well Abandonment

Within each of the RBS categories, trends


of spend proportion vary over time as the
overall projects profiles change from a
bias to early stage activities (such as Well
Abandonment), to later activities (such as
monitoring)[1].

22%

46%

18%
Running, Making Safe
& Preparation

Source: Adapted from Oil & Gas UK[1]

100%

1,600

90%

1,400

80%

1,200

70%
60%

1,000

50%

800

40%

600

30%

400

20%

200

10%
0%

2014

2015

2016

2017

2018

2019

2020

2021

2022

Estimated Expenditure (M)

Percentage of Total Expenditure

Estimated Annual UKCS Expenditure

Operator Project
Management & Monitoring

Well Abandonment

Running, Making Safe


& Preparation

Topside & Substructure Removal

Subsea & Site Remediation

Topside & Substructure Reuse & Recycling

Total Expenditure
Source: Adapted from Oil & Gas UK[1]

Market Forecasts | Market Forecasts of Expenditure

27

The data shows that the overall trends in peaks


and troughs is not applicable to all RBS elements.
Topside & Substructure Recycling and Operator
Project Management & Monitoring are relatively
consistent through the period. Whereas Well
Abandonment shows a sharp decline to 50%
of its peak to 2022. Topside & Substructure
Removal grows to a peak near the latter end
of the programme. This shows that the overall
trends relating to growth and decline will not be
consistent across all elements of the RBS[1].

Estimated Expenditure (M)

Decom North Sea


Review of Decommissioning Capacity | October 2014

Estimated Annual UK Continental Shelf


Decommissioning Expenditure
700
600
500
400
300
200
100
0

2014

2015

2017

2016

2018

2019

2020

2021

2022

Operator Project
Management & Monitoring

Well Abandonment

Running, Making Safe


& Preparation

Topside & Substructure Removal

Subsea & Site Remediation

Topside & Substructure Reuse & Recycling

Source: Adapted from Oil & Gas UK[1]

Norway has 19% of the North Sea installations,


and approximately a third of the number in the
UKCS[4]. There is a paucity of data regarding
the likely decommissioning expenditure for the
Norwegian Continental Shelf (NCS) as compared
to the UKCS.
The Norwegian Climate and Pollution Agency
(NCPA) estimates the costs of decommissioning
the entirety of the current infrastructure in the
NCS to approximate 160bn NOK (16bn)[7].
This represents about half of the UKs estimates
to 2040. While the Norwegian Oil and Gas
Association (NOGA) has predicted conservative
estimates up to 2018, analysis undertaken by
Mackay suggests a total spend of 7.3bn up to
2022, which represents over 55% of the total
NCS estimated spend[8],[3].

Estimated Expenditure (M)

Forecast of Expenditure in Norway

Estimated Annual Norwegian Continental Shelf


Decommissioning Expenditure
1,200
1,000
800
600
400
200
0

2013

2014

This is a more front loaded profile than for the


UKCS, which expects only 30% of costs incurred
to 2022. The assets based in the UK are on
average older than in the Norwegian Sector,
which suggest significantly different assumptions
of asset life have been made in the two Sectors.

28

Market Forecasts | Market Forecasts of Expenditure

2015

2016

NOGA

2017

2018

2019

2020

2021

2022

Mackay 2013

Source: Mackay Consultants[3], NCPA[8]

Decom North Sea


Review of Decommissioning Capacity | October 2014

Forecast of Expenditure in Denmark


and Netherlands
There is little information on decommissioning
forecast in the Dutch and Danish Sectors.

The Dutch Sector of the North Sea has a


similar number of installations to that of
Norway. However the depths are relatively
shallow and generally platforms are much
smaller than those in the Norwegian
Sector.
Denmark has only 8% of the installations
compared to the UKCS. Analysis by
Mackay identified only five fields expected
to be decommissioned in the period
to 2022[3]. This means that overall
expenditure is expected to be on a minor
scale.

Estimated Expenditure (M)

Estimated Annual Danish and Dutch Continental


Shelf Decommissioning Expenditure
180
160
140
120
100
80
60
40
20
0

2013

2014

2015

2016

2017

2018

2019

2020

2021

2022

Source: Mackay Consultants[3]

As such, the anticipated expenditure is


expected to be significantly less than the UK
and Norwegian Sectors.

Market Forecasts | Market Forecasts of Expenditure

29

Decom North Sea


Review of Decommissioning Capacity | October 2014

3.2 Market Forecasts of Activity

There is limited publically available information


on individual installation decommissioning
programmes. It is therefore not possible to build
this understanding from the bottom-up. However,
analysing the general characteristics of the North
Sea Sectors provides insight into the infrastructure
that could be removed in the coming decade.

Removal Requirements of Fixed Steel and


Concrete Gravity Base Topsides in the North Sea
4.0

Weight (Te) Millions

Market expenditure provides an understanding


of the likely levels of overall activities predicted
in the North Sea. However, to understand the
requirements of the supply chain it is necessary to
understand the characteristics of the infrastructure
that is planned for removal in more detail.

3.5
3.0
2.5
2.0
1.5
1.0
0.5
0

Denmark

Nertherlands

Fixed Steel Installations


Substructures

Norway

Steel Activity

The largest steel substructure is the 45,300


tonne YME MOPUStor installation[4]. However,
the majority of substructures are significantly
lighter, with 64% under 2,000 tonnes. The largest
topside for a fixed installation is the 53,000
tonnes Gullfacks C[4]. Again, the majority of
substructures are significantly lighter with 62%
under 3,000 tonnes.

Weight of Fixed Steel and Concrete


Gravity Base Topsides
Number of Substructures

The UK and Norway have an estimated 4.5


million tonnes of steel associated with fixed steel
or concrete gravity base topsides which will all
eventually need to be decommissioned[4].
The other North Sea countries account for only
0.6 million tonnes or 12% of the total North Sea
steel removal requirements[4].

Source: OSPAR[4]

400
350
300
250
200
150
100
50
0

<1,600

1,600-4,000

4,000-8,000

8,000-16,000 16,000-58,000

>58,000

Weight (Te)
South (Refers to areas
below 55 degrees LAT)

North (Refers to areas


above 55 degrees LAT)
Source: OSPAR[4]

Weight of Fixed Steel Substructures


Number of Substructures

Fixed steel installations and the topsides of


concrete gravity base installations are most likely
to require a removal vessel to decommission
the topside and substructure either by lifting
or reverse float over (a method where a vessel
is semi-submerged and positioned under the
platform, and the lift is achieved by de-ballasting
the vessel). The remaining installations are either
self-propelled or can be towed requiring less
onerous intervention.

UK

Fixed Steel and Concrete Gravity


Based Installations Topsides

400
350
300
250
200
150
100
50
0

<1,600

1,600-4,000

4,000-8,000

8,000-16,000 16,000-58,000

>58,000

Weight (Te)
South (Refers to areas
below 55 degrees LAT)

North (Refers to areas


above 55 degrees LAT)
Source: OSPAR[4]

30

Market Forecasts | Market Forecasts of Activity

Decom North Sea


Review of Decommissioning Capacity | October 2014

The decade from 1984 to 1993 was the


period when the most infrastructure by weight
was installed in the North Sea on an annual
average basis with over 240,000 tonnes of steel
installed every year[4]. This volume of activity is
commensurate with estimated activity over the
next decade. This suggests decommissioning
activity could be comparable to peak installation
activity.

Estimated Annual Steel Removal


in the North Sea
400

Weight (Te) Thousands

Across the North Sea, steel decommissioning is


estimated to average around 150,000 tonnes per
annum up to 2019 and over 270,000 tonnes per
annum between 2020 and 2022. Excluding steel
associated with floating installations, this figure
could be around 100,000 tonnes per annum up to
2019 and over 150,000 beyond.

350
300
250
200
150
100
50
0

2014 to 2019
inc. Floating

UK (North - Refers
to areas above 55
degrees LAT)

2014 to 2019
excl. Floating

Norway

2020 Onwards
inc. Floating

2020 Onwards
excl. Floating

UK (South Refers
to areas below 55
degrees LAT)

All Others

Source: O&G UK[1],[9] ,NCPA[7]

In the UKCS, it is estimated that nearly 440,000


tonnes of steel associated with topsides and
substructures will be removed in the period
between 2014 and 2022[1]. This equates
to approximately 9% of the existing steel
infrastructure in the UKCS.
The timing of decommissioning activities in the
Norwegian Sector is considered more uncertain
with limited published analysis available. The
NCPA have estimated that between 50,000 to
80,000 tonnes of steel a year will be removed until
around 2020[7]. The Agency then expects a steep
increase to around 200,000 tonnes after 2020.
This estimate seems surprisingly high as it equates
to the removal of nearly 50% of the existing steel
infrastructure in the Norwegian Sector by 2022.
The Dutch and Danish Sectors are even less
quantified, but likely to only contribute a small
proportion of total North Sea steel removal activity.
Estimates made by Arup suggest a total removal
of the order of 30,000 - 40,000 tonnes between
2014-2022, or 5-7% of their existing infrastructure.

Market Forecasts | Market Forecasts of Activity

31

Decom North Sea


Review of Decommissioning Capacity | October 2014

Well Abandonment
Platforms vs Subsea

Rigs vs Rigless

Wells are either co-located with a platform and have


been drilled from a permanent installation to which
the well is directly connected, or subsea and drilled
from a mobile installation and tied back to a local
platform. Platform wells may be abandoned using the
platform as an operational base. If the original drilling
rig is still present, it can be refurbished and reused to
abandon the well. Alternatively, a rig can be retrofitted
to the platform, or a rigless alternative can be used.
Platform-based operations are significantly more
flexible and lower cost than their mobile alternative.
Encountering unexpected conditions is also generally
less of a concern than for subsea wells, as operations
are more easily suspended.

Wells can be abandoned using either rig or


rigless approaches. A rig based approach uses
vessel or platform drilling rigs, adapted to recover
downhole equipment and plug the wells. Rigless
alternatives can be utilised for some or all parts
of P&A operations to reduce the number of
expensive rig days. However, the condition and
type of well dictates the potential to use a rigless
approach. Currently rigless operations have been
biased towards platform based operations due to
technology constraints and operators risk appetite.
Due to the limitations of rigless methodologies, costs
can dramatically increase if unexpected conditions
are encountered and a rig needs to be deployed to
complete the abandonment. Technology innovation
and increased demonstration of rigless approaches
is likely to reduce these risks and increase their use in
the future with consequential cost reductions for web
abandonment activities.

Subsea wells can also be abandoned using a mobile


rig such as a drill ship, semi-submersible or jack-up
vessel. A light-weight intervention vessel can also
be used if a rigless methodology is opted for. The
water depth and metocean conditions of well location
both influence the appropriate methodology and
subsequent vessel requirements.

32

Market Forecasts | Market Forecasts of Activity

Decom North Sea


Review of Decommissioning Capacity | October 2014

Wells in the North Sea

Activity
UK

It is estimated that there are more than 8,200


wells in the North Sea that are active or
suspended and awaiting P&A. The majority of
these are located in the UKCS, accounting for
61% of wells [9] [10] [11] [12] [13].

Netherlands
Norway
550
Denmark

There is significant publicly available data


from the UKCS in terms of the technical
characteristics of well infrastructure and
planned decommissioning activity which
can be used to inform the understanding
of demands on the supply chain. The other
Sectors have a paucity of data. It is therefore
necessary to make assumptions in terms
of the relative activity based on known data
in terms of geographical characteristics,
infrastructure volume, spend and activity
profiles.

2330
5000

375

Source: DECC[10], NPD[11], DEA[12], NLOG[13]

Wells to be
Decommissioned
in the UKCS (2014 - 2022)

Activity in UKCS
It is estimated that there are close to 5,000
wells requiring abandonment in the UKCS
of which around 18% (more than 800) will
require abandonment in the next
decade[9], [1]. Approximately 80% of all wells
in the UKCS are associated with a platform,
but the next decade will see a proportionately
larger number of subsea wells to platform
wells being abandoned, compared to the long
term[9].

Subsea
Wells
910

Subsea
Wells
258

Platform Wells
552

Platform Wells
3725

Source: Oil & Gas UK[1]

Source: Oil & Gas UK[9]

UKCS Wells to be Decommissioned


4,500
4,000

Number of Wells

Of the wells expected to be decommissioned


in the next decade, there is a relatively
consistent and even split between wells in
the South and Central North Sea compared
to the Northern North Sea. This is the case
for both subsea and platform wells. This will
influence vessel selection as water depth
and metocean conditions differ across these
regions.

Total UKCS Wells to


be Decommissioned

3,500
3,000
2,500
2,000
1,500
1,000
500
0
Subsea Wells

Completed NNS

Well type
Suspended NNS

Completed SNS / CNS / IS

Platform Wells

Suspended SNS / CNS / IS


Unclassified

Source: Oil & Gas UK[9]

Market Forecasts | Market Forecasts of Activity

33

Decom North Sea


Review of Decommissioning Capacity | October 2014

Wells by Abandonment Methodology

Analysis undertaken by O&GUK also estimates the


number of wells that might be undertaken using
rig-based and rigless approaches[9].
It considers that only 6% of wells will definitely
require intervention with a rig. A further 19%
could be abandoned using rigless methodologies
if anticipated technological advancements are
made; otherwise they would likely need a rig.
In total 66% of wells could be removed using
current rigless based technology, and the vast
majority of these are platform wells which lend
themselves more readily to this approach.

Group 5 - Plugged Wellbore


Requiring Annulus Plugs
Group 1 - Rig Required
Group 2 & 3 - Future Rigless

6%

9%

Group 4 - Rigless

19%

In the next decade, it is expected that


approximately a third of wells adandoned from
the UKCS will be subsea wells[9]. This is a higher
ratio than for the total asset base where a fifth of
wells are subsea[9]. Subsea wells are more likely
to require a rig-based intervention than platform
wells. Moreover, it is likely that the demand for rig
equipment for well abandonment will be higher
over the next decade than in the longer term.

66%

Source: Oil & Gas UK[9]

UKCS Wells to be Decommissioned

Subsea
Wells

Platform
Wells

500

1000

1500

2000

2500

3000

3500

4000

Group 1 - Rig Required

Group 2 - Future Rigless with


Entire Completion

Group 3 - Future Rigless Partial


Completion

Group 4 - Rigless

Group 5 - Pluged Wellbore Requiring


Annulus Plugs

Source: Oil & Gas UK[9]

Well P&A Durations for the UKCS (2014 - 2022)


14.00
12.00

Duration (Years)

10.00
8.00
6.00
4.00
2.00
0.00
Group 1
Rig Required

Group 2 & 3
 uture Rigless
F

Group 4
Rigless

Adandonment Method
Platform Wells Total Duration

Group 5
Plugged Wellbore
Requiring Annulus
Plugs

Subsea Wells Total Duration


Source: Oil & Gas UK[9]

34

Market Forecasts | Market Forecasts of Activity

Decom North Sea


Review of Decommissioning Capacity | October 2014

Activity in Norway

Activity in Netherlands

There are over 2,300 active wells in the Norwegian


Sector of which only 140 have been suspended[11].
There is limited information regarding the planned
decommissioning programmes for these wells, or if
they are associated with platforms or subsea.

There are nearly 500 active wells in Dutch waters


of which approximately 10% are suspended[13].
There is limited information regarding the planned
decommissioning programmes for these wells, or if
they are associated with platforms or subsea.

The nature of the Norwegian Sector water depths


means that the wells are likely to all be in deeper
waters, therefore requiring intervention by semisubmersible vessels or drill ships, rather than jack-up
vessels.

The nature of the Dutch Sector water depths


means that the wells are likely to be all in shallower
waters requiring intervention by jack-up vessels or
lightweight intervention vessels (LWIV) rather than
semi-submersible vessels or drill ships.

The Norwegian volume of activity could be assumed


as roughly half of the UK activity inferred from
the knowledge that they have only 40% of the
infrastructure, but that their spend and steel removal
activity profile suggest a more aggressive spend
profile than the UK. In the absence of published
data, it could be assumed that Norway has similar
characteristics to the UK in terms of demands for rigs
versus rigless solutions. However, further analysis
of the characteristics of the wells may affect those
assumptions.

In the absence of published data, it could be


assumed that the Dutch Sector would have similar
characteristics to the UK in terms of demands for
rigs versus rigless solutions. Further analysis of
the characteristics of the wells may impact those
assumptions.
The spend profiles combined with the proportion of
infrastructure suggests that activity will represent less
than 10% of the level occurring in the UKCS.

Activity in Denmark
There are nearly 380 active wells in Danish waters[12].
Denmark has been focusing on the P&A of
suspended wells which has resulted in only a very
small number remaining suspended, all of which have
P&A plans approved by the Danish Energy Agency
(DEA). Across the Danish North Sea, only 3 subsea
wells exist with all remaining wells being platform
based.
The nature of the Danish Sector water depths means
that the wells are likely to be all in shallower waters
requiring intervention by jack-up vessels rather than
semi-submersible vessels or drill ships.
Activity in Denmark is likely to be more biased
towards rigless approaches than the overall UK profile
due to the low number of subsea wells. However,
the spend profiles combined with the proportion of
infrastructure suggests that activity will represent less
than 10% of the level occurring in the UKCS.

Market Forecasts | Market Forecasts of Activity

35

Decom North Sea


Review of Decommissioning Capacity | October 2014

Published Plans
There is a paucity of published data on decommissioning dates from operators. Data published by OSPAR and
the North Sea regulators identifies a total of 32 installations likely to cease production and/or be removed in the
coming decade [4], [14], [15], [16]. These include 29 fixed steel installations and 3 concrete gravity base. 67% of the
platforms are located in the deeper and more exposed waters in the northern areas of the North Sea.

UK

Norway

Denmark

Netherlands

Miller
Brent A
Brent B
Brent C
Brent D
Goldeneye
Kittiwake A
Thames AV
Thames AR
Thames AP
Brae A
Brae B
Brae East
Murchison
Little Dotty
Big Dotty

Albuskjell F
Edda
Ekofisk A
Ekofisk G
Ekofisk S
H-7
Hod
Huldra
Valhall PCP
Vest EkoFisk
YME MOPUStor

Cecilie
Dagmar
Rolf
Svend

Q8-B
K10-B

Weight of North Sea Platforms Expected to


be Decommissioned (2014 - 2022)

The following plots show the relative topside


and substructure weights for the 32 identified
platforms. The larger the circle, the sooner the
platform is planned for removal.
Topside Weight (Te)

1,000,000

100,000

10,000

1000

100

100

1000

10,000

100,000

1,000,000

Substructure Weight (Te)


Concrete Gravity Based

Fixed Steel
Source: OSPAR[4], NPD[14], DEA[15], DECC[16]

36

Market Forecasts | Market Forecasts of Activity

Decom North Sea


Review of Decommissioning Capacity | October 2014

The weight distribution of these 32 installations,


as shown in the graphs, show a broad spread
of installation sizes. This is despite the fact
that the overall North Sea asset stock includes
a significantly higher proportion of smaller
installations in the more sheltered areas of the
southern North Sea. This suggests that the early
demands for decommissioning are going to be
more evenly spread across all the weight ranges,
with a disproportionately higher demand for
larger capacity vessels depending on the removal
method.

Weight of Topsides for Platforms Expected


to be Decommissioned
9

Number of Topsides

8
7
6
5
4
3
2
1
0

<1,600

1,600-4,000

4,000-8,000

8,000-16,000

16,000-58,000

Weight (Te)
South

North

Source: OSPAR[4]

Weight of Fixed Steel Substructure for Platforms


Expected to be Decommissioned
9

Number of Substructures

The identified platforms equate to approximately


1.2 million tonnes of infrastructure of which
540,000 tonnes is fixed steel or concrete gravity
base topsides. This equates to an annual
removal of approximately 54,000 tonnes of steel.
These figures are about two thirds of the values
identified by O&GUK and NCPA up to 2020.
This suggests that there are plans for additional
platforms to be decommissioned in the next
decade, which are not in the public domain and
these estimates appear conservative.

8
7
6
5
4
3
2
1
0

<1,600

1,600-4,000

4,000-8,000

8,000-16,000

16,000-58,000

Weight (Te)
South

North

Source: OSPAR[4]

Market Forecasts | Market Forecasts of Activity

37

Decom North Sea


Review of Decommissioning Capacity | October 2014

38

Decom North Sea


Review of Decommissioning Capacity | October 2014

4.0 Critical Supply Chain Elements

39

Decom North Sea


Review of Decommissioning Capacity | October 2014

Identification of the critical supply chain elements


has been based on Arups experience and view
of the status of the industry and informed through
consultation with the industry expert panel.
The following critical supply chain elements have
been established as those most likely to impact
on the delivery of cost effective decommissioning
programmes, with potential to require market
intervention to ensure their capacity is secured.

Resource
Breakdown
Elements

Critical Supply
Chain Elements

Operator Project
Management &
Monitoring

None
Considered
Critical

Well
Abandonment

Drilling Rigs
or Rigless
Alternatives

demands from other maritime and other


industries

Running
Making Safe &
Preparation

None
Considered
Critical

known shortages either in the past or expected


in future, are specialised and not easily
substituted by alternatives, and

Topside &
Substructure
Removal

Removal
Vessels

Subsea & Site


Remediation

None
Considered
Critical

Topsides &
Substructure
Reuse &
Recycling

Ports, Harbours
and Yards

They are parts of the supply chain which are known


to have:

challenges in growing capacity

The critical supply chain elements identified are show


in the table referenced to the resource breakdown
structure.

Generic Critical
Supply Chain
Elements

Engineering
Skills
Operational
Skills

Rigs and Rigless Alternatives for


Well Abandonment
Rigs or rigless alternatives have been identified as
a fundamental aspect of the well abandonment
process and cannot be replicated through another
process. This resource has significant pressures from
E&P activities as the same infrastructure is utilised
for drilling activities and is mobile across the global
market. This market is volatile and the spot prices for
this infrastructure is vulnerable to market demand.
The capacity floats to meet an unpredictable demand
and decommissioning activity will need to compete
within this challenging market.

40

Critical Supply Chain Elements

Decom North Sea


Review of Decommissioning Capacity | October 2014

Removal Vessels for Topside and


Substructure Removal

Engineering and Operational Skills for all


areas of Decommissioning

Removal vessels are a critical part of the


decommissioning process and their cost and
availability will have a substantial impact on the overall
costs of the process. It is likely that vessels with
lift capacities of up to 500 tonnes and significantly
higher will be utilised by the market regardless of
the approach to removal. They are not unique to the
decommissioning market and are utilised for E&P as
well as offshore wind markets.

Skills capacity is an issue that crosses all aspects of


the decommissioning process, and was commonly
cited as a potential concern and constraint. The
challenges to grow skills capability are distinct to
investment in a physical resource such as a vessel
or port. They require a collaborative effort between
schools, universities, operators, supply chain and
Government.

The capital costs of a new vessel are significant,


and vessel operators will require a substantial
commitment to invest in new capacity. The latest new
specialist heavy lift vessel, the Pieter Schelte was
over 10 years in development and was supported
by an investment case from markets other than
decommissioning. Although smaller vessels for piece
small operations will be significantly less expensive
and quicker through the planning process, they
would need to be developed in greater volume to
deliver the same level of work of the larger vessels.

Ports, Harbours and Yards for Topsides and


Substructure Recycling
Although operators could potentially utilise ports,
harbours and yards from the global market to carry
out decommissioning activities, this would likely be
at a significant cost penalty to decommissioning.
This is not because it would impact recycling costs,
which are only a small proportion of overall costs, but
because it would impact on removal costs through
increasing vessel costs. It would also reduce the
potential for local socio-economic benefits through
creation of jobs in the North Sea local markets.
The capital cost of upgrading major infrastructure can
be substantial and generally requires high investment
certainty to make commitment. In addition to this
the timescales can be extremely protracted, with the
duration to realise significant new infrastructure from
design and development to construction potentially
taking up to a decade for a contentious development.

Other Resources
There are a significant number of other resources
associated with the decommissioning processes
which are detailed in Appendix C. These resources
offer a significant opportunity to the supply chain
as the market grows. They will require a breadth of
highly skilled and high value capacity and capability.
A range of activities will require innovation in terms
of technical and management approaches to drive
down the costs of decommissioning. Examples
include development in cutting tools, or improved
logistics management of offshore operations. There
are other areas that will need significant growth in
capacity to meet the demands of the market, such as
a growth in survey capability or support vessels.
There will undoubtedly be constraints in supply of
many of these resources depending on the level of
market demand. However these areas are of lower
capital investment and lead time when compared
to the aspects considered as critical supply chain
elements. The supply chain is more likely to be able
to naturally respond to these opportunities without
any market intervention. As such, although they are
considered as significant opportunities, they are not
assessed in detail as part of this exercise.
A health check of the four critical supply chain
elements identified above is provided in Chapters
5 to 9 where each element is considered within the
context of the expected activity and in light of current
capacity. Engineering and operational skills are
considered separately in Chapter 4, as these skills
are somewhat transferrable across the RBS.

Critical Supply Chain Elements

41

Decom North Sea


Review of Decommissioning Capacity | October 2014

42

Decom North Sea


Review of Decommissioning Capacity | October 2014

5.0 Well Abandonment

43

Decom North Sea


Review of Decommissioning Capacity | September
October 2014
2014

Well Abandonment

Skills

44

Well and P&A Project


Management

Engineering (P&A)

Operations Support

Rig Upgrade Capabilities

Infrastructure and
Equipment

Supply Chain

Rigs

Drilling Contractors

Rigless Solution

Light Weight Intervention


Vessels

Specialist Consultants and


Contractors

Vessel Operators

Transport Vessels

Rig/Rigless Contractors

Waste Management

Rig and Rigless Design


Services

Waste and Scale Treatment


and Storage

Abandonment Materials,
Expanding Cement,
Resins, Silicone Rubber

Hazardous Waste Handling


and Disposal Routes

Specialist Well Inspection


and Intervention services

Specialist Services i.e.


Wireline

Well Abandonment

Decom North Sea


Review of Decommissioning Capacity | October 2014

5.1 Overview

Well P&A can be done using mobile rigs mounted


on a vessel, platform rigs or rigless solutions on a
lightweight intervention vessel. These resources are
all considered critical supply chain elements. The
selected appropriate approach is dictated by the
type and condition of the well.


There are over 8,200 active or suspended wells
in the North Sea, all of which will eventually need
to be plugged and abandoned[9] [10] [11] [12] [13]. In the
UKCS it is estimated that over 800 wells will be
abandoned in the next decade[9]. An extrapolation
of data considering infrastructure and expected
spend in Denmark, Norway and the Netherlands
suggests that there could be up to a 70% increase
in activity from the other Sectors. The majority of this
additional activity will be in the deeper waters of the
northern areas of the North Sea.
The number of working years required to abandon
wells in the UKCS over the next decade have been
estimated. It is predicted there are;
4.5 years which require mobile drilling rigs such
as jack-up vessel, semi-submersible or drill
ship.
Approximately 10 years which require platform
rigs.
Approximately 7.5 years which require rigless
platform solutions.

Less than 2 years of subsea rigless operations


which require intervention vessels but not
mobile drilling rigs.
These durations are exclusive of any weather related
or other non-productive downtime.
Considering P&A activity in isolation the market
capacity for mobile drill rigs appears to be adequate
for both jack-up vessels and semi-submersible
vessels/drill ships. However, there is greater
uncertainty when considering platform rigs and
rigless solutions, where there is more uncertainty
regarding the potential for capacity constraints.
Mobile drilling rigs, temporary platform rigs and
rigless intervention systems are all mobile resources.
P&A contractors operate globally, following market
opportunities in E&P and P&A in the worlds
producing regions. Although it is expected that there
will be sufficient supply chain capability to meet
the demands of abandonment activity in isolation,
the competition for E&P resources has potential
to cause a constraint in an already highly utilised
supply chain.

Estimated UKCS Expenditure


700

46%

Million per year

600
500
400
300
200
100
0
2014 2015 2016 2017 2018 2019 2020 2021 2022

Well Abandonment | Overview

45

Decom North Sea


Review of Decommissioning Capacity | October 2014

5.2 Activity
Well P&A can be done using mobile rigs mounted
on a vessel, platform rigs or rigless solutions on a
lightweight intervention vessel. These resources all
consider critical supply chain elements.

Number of Wells in the North Sea


UK
Netherlands
Norway

Currently, there are more than 8,200 wells in the


North Sea that are either in production, injection
or that have been suspended and awaiting P&A.
The majority of these are located in the UKCS, and
account for 61% of wells.
There is significant data available from the UKCS
in terms of the technical characteristics of well
infrastructure and planned decommissioning activity
which can be used to inform the understanding of
demands on the supply chain. The other Sectors
have a paucity of data and it is necessary to make
assumptions in terms of the relative activity based on
known data in terms of geographical characteristics,
infrastructure volume, spend and activity profiles.

46

Well Abandonment | Activity

550
Denmark

2330
5000

375

Source: DECC[10], NPD[11], DEA[12], NLOG[13]

Decom North Sea


Review of Decommissioning Capacity | October 2014

UKCS and Other North Sea Regions

Wells to be Decommissioned
in the UKCS (2014 - 2022)

It is estimated that there are approximately 5,000


wells requiring abandonment in the UKCS of
which around 18% (more than 800) will require
removal in the next decade[1].

Subsea
Wells
258

O&GUK estimates that it will require over 140


working years of activity to abandon all the wells
currently in the UKCS, without any working
downtime[9]. Of this, 80 years are expected
to require rigs (based on current technology
capability). The majority of this activity (55 years)
is associated with platform wells which may be
able to utilise existing or refurbished rig capability.
However, a large proportion are likely to require
a temporary rig. The remaining 25 years are
associated with subsea wells, which are more
likely to need a mobile drilling rig or LWIV.

Platform Wells
552

Source: Oil & Gas UK[1]

Total UKCS Wells to


be Decommissioned
Subsea
Wells
910

Using this as a basis to consider activities in the


next decade (where 18% of wells will be removed)
and assuming current technical capabilities, there
are[9]:

4.5 years which require mobile drilling rigs


such as jack-up vessel, semi-submersible or
drill ship.

Approximately 10 years which require


platform rigs.

Approximately 7.5 years which require rigless


platform solutions.

Platform Wells
3725

Less than 2 years of subsea rigless


operations which require intervention vessels
but not mobile drilling rigs.

The next decade will see a larger proportion of


subsea wells removed than platform wells.
As such these statistics are likely to underestimate
the number of mobile drilling rig years and
overestimate the number of platform rig years.
In the rest of the North Sea, contribution of activity
from the Norwegian, Dutch and Danish Sectors
will increase the demands on the supply chain.
An extrapolation of data considering infrastructure
and expected spend suggests that there could
be up to a 70% increase in activity from the other
Sectors. The majority of this additional activity will
be in the deeper waters of the northern areas of
the North Sea. Extrapolating between the balance
of rig and rigless solutions is not possible due to a
lack of available data.

Source: Oil & Gas UK[9]

UKCS Well P&A Durations


Subsea
Wells Total
Duration

Platform
Wells Total
Duration

20

40

60

80

100

120

140

160

Working Years
Group 1 - Rig Required

Group 2 - Future Rigless with


Entire Completion

Group 3 - Future Rigless Partial


Completion

Group 4 - Rigless

Group 5 - Pluged Wellbore Requiring


Annulus Plugs

Source: Oil & Gas UK[9]

Well Abandonment | Activity

47

Decom North Sea


Review of Decommissioning Capacity | October 2014

5.3 Supply Chain


Historical E&P and Future P&A in the North Sea
800
700

Number of Wells

600
500
400
300
200
100
0

Pre 60 1963

Mobile Drill Rigs

Within the UKCS, approximately half of the


working requirements are in the Northern North
Sea, and as such there is likely to be an equal
distribution between jack-up vessels versus
semi-submersible vessels /drill ship requirements.
An increase in activity in the Norwegian Sector
will increase the requirements on drill ships and
semi-submersible vessels. As this equates to
approximately 50% of the UKCS activity, it is
likely to affect the overall availability of these
vessels. Although Dutch and Danish Sectors
will be biased towards jack-up vessels, they
have a significantly smaller proportion of vessel
requirements. As such overall, it is assumed there
is a bias towards the need for semi-submersible
rather than jack-up vessels in terms of overall
activity.

48

Well Abandonment | Supply Chain

1971

1975

1979

1983

1987

1991

1995

1999

2003

2007

2011

2015

2019

2023

Total North Sea E&P

Total North Sea P&A

E&P in the UKCS

E&P in Norway

E&P in Denmark

E&P in Netherlands

P&A UKCS

P&A Others
Source: DECC[10], NPD[11], DEA[12], NLOG[13]

North Sea Mobile Drill Rigs


Number of Drill Rigs

Drill ships and semi-submersible vessels are


adapted to work in deep water and harsh
exposed environments. Jack-up vessels are a
lower cost option which are optimal for shallow
water and are more weather sensitive in the
period in which they are mobilised for operations.
Jack-ups for abandonment have a broader
water depth envelope than their heavy-lift
counterparts, but are still limited to about 150
meters. Generally, jack-ups are suitable for the
Southern, Central and Irish Sea in the UKCS as
well as Dutch and Danish Sectors. Drill ships and
semi-submersible vessels are usually deployed
in the UKCS Northern North Sea and Norwegian
Sectors.

1967

60

3000

50

2500

40

2000

30

1500

20

1000

10

500

Drillship

Jackup

Semisub

Rig Type
Number of Rigs

Average Operating Depth (m)

Drilling activity peaked in the decade following


the mid-1980s with an annual of 540 wells
drilled a year in that period. Currently drilling
activity is lower than the peak activity, but still
substantial with 470 wells a year or nearly 90%
of peak activity[10], [11], [12], [13]. If drilling continued at
the same rate over the next decade, estimated
abandonment activities in the same period will
represent an increase in activity of 30%. This will
put increasing pressures on the supply chain for
mobile and platform drilling rigs.

Average Rated Water Depth (m)


Source: Rigzone[17]

Decom North Sea


Review of Decommissioning Capacity | October 2014

Rigzone catalogues that there are 97 mobile drill


rigs currently operating in the North Sea, which
represents around 12% of the global fleet[17]. These
are relatively evenly split between semi-submersible
vessels and jack-ups. Even when factoring in weather
and other unproductive time, a fleet this size could
easily support the 4.5 rig years of adandonment
required in the next decade from the UKCS. The
additional estimated 70% increase of activity from the
other sectors is unlikely to cause a constraint.
However, utilisation of mobile rigs is currently
high, with global utilisation of jack-ups and semisubmersible vessels averaging between 79 to 88%
last year[18]. The incremental increase in abandonment
activity when considered in the back drop of E&P
activity, could potentially cause a constraint on mobile
rigs, unless greater numbers of the global fleet are
deployed in the North Sea.

Platform Rigs

Rigless Intervention Systems


Rigless interventions are associated with about 40%
of the total working days of all P&A activities. Rigless
interventions are estimated to mainly be associated
with platform wells, but also with a smaller number of
subsea wells. For these operations, the availability of
rigless systems must be considered.
There is also a significant number of additional wells
that could be abandoned using a rigless solution if
technology innovation was stimulated. Indeed, rigless
solutions are significantly shorter and lower cost than
rig-based alternatives and could offer a more cost
effective alternative to operators.
The market is likely to want to move towards using
rigless options where risk-based analysis concludes
that it is the most cost effective approach. Availably
of rigless solutions has the potential to become
a constraint in the future, especially if the market
confidence increases in its viability.

The requirement of drill rigs for platforms is estimated


to be more than double the requirement of mobile
drilling rigs in terms of working days. The capability
of the market to refurbish existing platform rigs will
dictate the required capacity for additional rigs to
be temporarily installed on the platform. Again, as
platform rigs are in demand for drilling activity, there
will be a competition for this resource and it has the
potential to become a constraint.

Well Abandonment | Supply Chain

49

Decom North Sea


Review of Decommissioning Capacity | October 2014

5.4 Health Check


Capability = Low / Medium
Accenture[5] consider well adandonment aligned with the 2011 WBS which considers P&A of wells, rig upgrades and rigless options
among others with an average capability for these three of 2.5 out of 5.
Rig upgrades were rated the lowest capability with P&A and rigless options performing better.
Accenture conclude that the market for associated well services such as drilling, completions and interventions has extensive
knowledge, tools, technology, experience and capability. Well Abandonment has been widely identified as a phase requiring focus
and there are multiple organisations, events and publications that provide a forum for discussion, debate and knowledge sharing.
The presence of global players in the UKCS provides a source of knowledge, technology and experience of complex well situations
and well abandonments from other regions.
However, while the market for wells services is mature, the specific capability and experience for plugging & abandonment is not as
strong. The entry costs for new wells companies in the UKCS are too high, in part due to the cost of compliance to local regulations.

Estimated volume of supply against demand = Low / Medium


Considering P&A activity in isolation the market capacity for mobile drill rigs appears to be adequate for both jack-up vessels and
semi-submersible vessels/drill ships.
There is more uncertainty when considering platform rigs and rigless solutions where there is more potential for capacity constraints.
Rigless solutions are significantly shorter and lower cost than rig-based alternatives and could offer a more cost effective alternative
to operators. There are a significant number of additional wells that could be abandoned using a rigless solution if technology
innovation is stimulated.
The market is likely to want to move towards using rigless options where risk-based analysis concludes that it is the most cost
effective approach. Availably of rigless solutions has potential to become a constraint in the future if the market confidence increases
in its viability.
The lead time to development of rig-based solutions is less than five years to commission and construct new capacity. For rigless
solutions, where innovation and demonstration is required this lead time could potentially be even longer.

Pressures and/or synergies from other industries = Low / Medium


Mobile drilling rigs, platform rigs and rigless intervention systems are all mobile resources. P&A contractors operate as a global
resource, following the market opportunities from E&P and P&A in the worlds O&G producing regions. Anecdotally well contractors
prefer to support new field development, as it is less cost driven and more programme focused than decommissioning.
Currently drilling activity is 470 wells a year or nearly 90% of peak activity which occurred in the 1980s.
Although there is expected to be sufficient supply chain capability to meet the demands of abandonment activity in
isolation the competition for E&P resources has potential to cause a constraint in an already well utilised supply chain.

Investment Status = Low / Medium


Contractors are reluctant to make commitments to new rigs and rigless systems without certainty
in terms of timing of the North Sea decommissioning market. In the Gulf of Mexico an idle iron
policy had been implemented which places a deadline on abandonment activity. This policy
decision has given market certainty and stimulated technology innovation in bringing forward
more rigless solutions. In the North Sea further innovations are necessary to de-risk rigless
solutions.

Overall Status = Red


There is a high potential for well abandonment resources to cause a supply chain
bottleneck based on the considerations detailed above.

50

Well Abandonment | Health Check

Decom North Sea


Review of Decommissioning Capacity | October 2014

51

Decom North Sea


Review of Decommissioning Capacity | October 2014

Jan Berghuis

52

Decom North Sea


Review of Decommissioning Capacity | October 2014

6.0 Topside & Substructure Removal

53

Decom North Sea


Review of Decommissioning Capacity | September
October 2014
2014

Topside & Substructure Removal

Skills

54

Infrastructure and
Equipment

Detailed Engineering
(Topsides and
Substructures)

Removal Vessel

Transportation Barges

Naval Architecture

Anchor Handling Tug


Supply (AHTS) Vessels

Offshore Operations

Transportation

Construction Support
Vessels (CSV)

Safety Standby Vessels


(SSBVs)

Survey Vessels

Rock Dumping / Backfill


Vessels

Topside & Substructure Removal

Supply Chain

Heavy-Lift Vessel
Contractors

Support Vessel Contractors

Engineering Consultancies

Specialist Consultancies

Decom North Sea


Review of Decommissioning Capacity | October 2014

6.1 Overview

83% of installations in the North Sea are fixed steel


and 4% concrete gravity base[4]. They will require
a vessel to remove the topside and substructure,
either by lifting or reverse float over. The remaining
installations are either self-propelled or can be
towed requiring less onerous interventions. The
construction vessels utilised to remove topsides and
substructures are considered to be critical supply
chain elements.

The market is not consolidated on a single approach


to decommissioning for topsides and substructures,
and the methodology is influenced by a range of
technical and commercial factors, such as the
weight and design of the installation and the market
availability of vessels. As a result, there is a diverse
range of vessel types that can be utilised by the
market. These include large heavy-lift vessels which
operate in deep waters and exposed conditions in
the Northern North Sea, and to sheer leg, and jack-
up vessels which are more suited to the shallow and
benign waters of the Southern North Sea.

The market peak for installation in the North Sea


occurred in the decade from 1984 to 1993[4]. In this
period, an approximate average of 240,000 tonnes
of steel was installed every year[4]. This activity level
is equivalent to estimates of steel removal over the
next decade, which are approximately 150,000
to 260,000 tonnes a year. This suggests that the
demand for decommissioning resources in the next
ten years will be comparable to the period of peak
activity which occurred 30 years ago.
The North Sea has significantly greater numbers of
smaller and lighter platforms than heavier and larger
platforms. However, published plans suggest that
the early demands for decommissioning are going
to be spread more evenly across all the weight
classes with a disproportionately higher demand for
larger capacity vessels.
The availability of suitable heavy-lift vessels to
decommission the larger platforms in the northern
area is likely to create the biggest constraint. In
southern areas, where platforms are generally
smaller, there is a larger fleet of vessels that could
remove topsides in a single lift, though this reduces
for categories above >1,600 tonnes.

Estimated UKCS Expenditure


160

22%

Million per year

350
300
250
200
150
100
50
0
2014 2015 2016 2017 2018 2019 2020 2021 2022

Topside & Substructure Removal | Overview

55

Decom North Sea


Review of Decommissioning Capacity | October 2014

6.2 Activity
The vessels that are required to remove substructures
and topsides are critical supply chain elements.
The type and location of installation will impact on
the vessels and approach to removal.

Fixed Steel
83% of installations in the North Sea are fixed steel
with a combined weight of 4.4 million tonnes[4].
There are 535 fixed steel installations with
substructures which range from 100 tonnes to over
45,000 tonnes and topsides which range from 70
to 53,000 tonnes[4]. The average substructure weighs
3,500 tonnes and topside 4,300 tonnes.
All fixed steel installations with a substructure under
10,000 tonnes will require removal under OSPAR
regulations. This applies to 91% of installations.
The remaining 9% may apply for a derogation to
leave some or all of the substructure in place.
Both substructures and topsides will need to be
removed from site using removal vessels through
either single lift, multiple lift, piece small or reverse
float over methodologies.

Concrete Gravity Base


4% of installations in the North Sea are concrete
gravity base substructures[4]. Each structure has a
greater average weight than a fixed steel installation
and in total they weigh 7.4 million tonnes, almost
double the weight of all the fixed steel installations.
OSPAR regulations allow the possibility of a
derogation to leave concrete gravity installations in
situ at the end of their life. Technical and commercial
constraints have meant that all concrete gravity base
platforms decommissioned to date have obtained
permission to leave their substructures in situ. It is
likely that operators will continue to seek derogations
for concrete gravity base installations in the
absence of further regulator intervention or technical
advancements.
It is also likely that the topsides will be removed from
site and recycled in a similar method to large fixed
steel installations, although these can be technically
more challenging than their fixed steel equivalents.

Other Installations
The remaining 13 % of installation types are
predominantly floating technology. Although they
can range in weight (up to 100,000s tonnes), they
are more straight forward to decommission, either
because they can self-propel, or because they can
be towed from site[4]. The requirements for vessels
will be less onerous than for fixed steel and concrete
gravity base.

Activity Focus
The critical supply chain is focused on the removal
of fixed steel and the topsides from concrete gravity
base installations with removal vessels carrying out
either a single lift, multiple lift, piece small or reverse
float over.

56

Topside & Substructure Removal | Activity

Decom North Sea


Review of Decommissioning Capacity | October 2014

Estimated Annual Steel Removal


in the North Sea

Volume of Activity

Published data from the North Sea operators


and regulators suggests that the fixed steel
and concrete gravity base topsides planned
for removal are proportionately distributed to
the heavier weight classes and biased toward
northern North Sea platforms[4], [14], [15], [16].

Weight (Te) Thousands

350
300
250
200
150
100
50
0

2014 to 2019
inc. Floating

2014 to 2019
excl. Floating

UK (North Refers
to areas above 55
degrees LAT)

Norway

2020 Onwards
inc. Floating

2020 Onwards
excl. Floating

UK (South Refers
to areas below 55
degrees LAT)

All Others
Source: OSPAR[4]

Weight of Topsides for Platforms Expected


to be Decommissioned
9

Number of Substructures

However, this estimate includes removal of


floating installations, which make up nearly 40%
of the steel weight in the North Sea, which do
not need a heavy-lift removal vessel[4]. Pro-rata
adjustment of these weights estimated to remove
floating installations suggest annual requirements
for lift vessels might be on average a little less
than 100,000 tonnes until 2020 and 160,000
tonnes beyond to 2022.

400

8
7
6
5
4
3
2
1
0

<1,600

1,600-4,000

4,000-8,000

8,000-16,000

16,000-58,000

Weight (Te)
South (Refers to areas
below 55 degrees LAT)

North (Refers to areas


above 55 degrees LAT)

Source: OSPAR[4]

Weight of Fixed Steel Substructure for Platforms


Expected to be Decommissioned
9
8

Number of Topsides

Overall estimates of activity and steel removal


are discussed in detail in Chapter 3. In total, an
average of 150,000 tonnes of steel (up to 2019)
and over 270,000 tonnes (from 2020 onwards) is
estimated to be removed annually from the North
Sea[1], [7]. The decade from 1984 to 1993 was the
period when the most infrastructure by weight
was installed in the North Sea on an annual
average basis (amounting to over 240,000 tonnes
of steel installed per annum)[4]. This volume
of activity is commensurate with estimated
activity over the next decade suggesting
decommissioning could be comparable to the
peak installation activity.

7
6
5
4
3
2
1
0

<1,600

1,600-4,000

4,000-8,000

8,000-16,000

16,000-58,000

Weight (Te)
South (Refers to areas
below 55 degrees LAT)

North (Refers to areas


above 55 degrees LAT)

Source: OSPAR[4]

Topside & Substructure Removal | Activity

57

Decom North Sea


Review of Decommissioning Capacity | October 2014

6.3 Supply Chain


Vessels with lifting capabilities can be used to
decommission both topsides and substructures using
single lift, multiple lift or piece small approaches.
Semi-submersible vessels can also be used for
removal of topsides for a reverse float over.
Each vessel has an operational envelope which
is dictated by a range of criteria including crane
capacity, deck area, draft, transit speeds, weather
working windows and water depths. This envelope
influences the projects in which they can feasibly be
deployed, and the manner in which they are utilised.
Sheer leg and jack-up vessels are commonly
deployed in the southern North Sea or Dutch Sectors
where water depths, weather conditions and platform
sizes are suited to their operational capability. Heavylift vessels have a broader operational envelope
and are more frequently deployed in the UK Central
and Northern North Sea and Norwegian Sectors.
Although they could work in the Southern North
Sea, it is unlikely that they would be as commercially
viable as the alternatives. On this basis, available
vessels have been classified as either southern or
northern.
The chosen approach of decommissioning a
structure (single lift, multiple lift, piece small) is
influenced by the market availability of vessels, and
technical constraints associated with the structures
weight and configuration.

58

Topside & Substructure Removal | Supply Chain

Decom North Sea


Review of Decommissioning Capacity | October 2014

Topside Approach

Vessels

Single lift requires a vessel with lift capacity to lift the


entire topside structure. For the very large structures,
the number of vessels capable of this approach are
limited. A number of the smaller topsides deployed in
recent years were installed as a single lift, and would
potentially suit this method of decommissioning.

A range of construction vessels are used to


decommission both topsides and substructures,
particularly where large single or multiple lifts are
undertaken. Vessels have a range of crane capacities,
deck area, draught, transit speeds which influence
the projects in which they can be deployed, and the
manner in which they are utilised.

Multiple lifts and piece small give more flexibility


in terms of vessel selection and vessel capability.
However, there is a balance to be struck in terms of
the economics and health and safety implications
of multiple lifts and operations offshore. Historically,
the larger platforms were constructed in a modular
format and some of the older platforms may lend
themselves better to a reverse installation in multiple
lifts.

Substructure Approach
Fixed steel substructures do not lend themselves
easily to removal in parts. Although it may be
technically feasible to slice a substructure for
removal in sections, the cost and health and safety
implications often make this less viable than a single
lift approach.
For the very large steel substructures, total removal
becomes highly technically and commercially
challenging. Consequently, OSPAR regulations allow
a route for operators to seek a derogation to leave
footings in place. As stated, concrete gravity base are
significantly heavier and again, the approach to date
has been to seek a derogation to leave the entire
substructure in place.

Matching vessel capacity to North Sea installations


has a number of challenges, in part due to the range
of installations, technical characteristics and vessel
types. Although vessels will have a stated maximum
working capacity, the specific technical constraints
of the lift and vessel characteristics can significantly
reduce the practical capacity.
A review of vessels with lift capabilities of over 500
tonnes identified 80 vessels with a total combined
nominal capacity of over 200,000 tonnes[19]. However,
only 2 vessels, the Siapem 7000 and Thialf, have the
capability to lift beyond 10,000 tonnes. The majority
have significantly lower lift capacity[19].
These vessels operate in other sectors, serving
offshore wind, E&P as well as other marine industries.
In addition, a significant proportion are not working
in Europe and are serving the global market. It
is expected that only half of these vessels with a
combined nominal capacity of less than 100,000
tonnes are likely to work in the North Sea and
be pursuing decommissioning activity. Moreover,
practical lift capacity is generally less than the nominal
lift capacity (assumed to be 80% on average). As
such, the total combined capacity of 80,000 tonnes
is considered more realistic.
These vessels are shown in the figure overleaf
grouped by weight class. The majority of vessels
are in the lower weight classes, and these are
predominantly vessels suited to working in the more
benign conditions in the southern North Sea. The
larger lift capacity vessels are generally more suited to
the exposed areas in the northern North Sea.

Topside & Substructure Removal | Supply Chain

59

Decom North Sea


Review of Decommissioning Capacity | October 2014

The graphs shows the number of vessels by


weight class plotted alongside the substructures
and topsides which have been identified for
decommissioning. This provides a picture of the
match of vessel capacity against substructure
demand. This is a simplified overview, as vessels
in lower classes can decommission installations in
higher weight classes if they proceed via piece small
or multiple lift methodologies. Moreover, vessels in
higher weight classes can remove those in lower
weight classes, although there may be commercial
barriers.
The graph only shows decommissioning projects
which are in the public domain (these equate to
approximately 60% of steel removal requirements)
identified by the O&GUK and the Norwegian
Government. As such it will under estimate vessel
requirements based on current estimated activity.
In the northern areas, to match the weight class
and lift weight i.e. carrying out a single lift, there is
limitation in the heavier weight classes. Indeed, as
none of the >16,000t cranes are ready for market,
the heavier topsides planned to be decommissioned
in the near future will need to be removed by piecesmall or multiple lift. For the lighter platforms, single
lift will be more feasible.
In southern areas, there are significantly more single
lift opportunities, though there are some limitations in
the above >1,600 categories.

Number of Vessels

25
22

20

15

10
10
5

5
3

<1,600

1,600-4,000

4,000-8,000

8,000-16,000

>16,000

Weight (Te)
South

Number of Vessels and Installations

However, the Pieter Schelte is likely to only be


commercially viable if it were deployed on a
programme of work, rather than individual projects.
Allseas has been contracted by Shell to remove the
Brent Field topsides and substructures commencing
in 2015/2016[20]. The vessel is also equipped with
pipeline laying capabilities, as the vessel operator
wants to spread risk by serving other markets.

Decommissioning Vessels By Weight Class


and Working Class

North

Source: 4coffshore[19]

Installations to be Decommissioned and


Vessel Availability (2014 - 2022) - North
14
12
10
8
6
4
2
0

<1,600

1,600-4,000

4,000-8,000

8,000-16,000

>16,000

Weight (Te)
Topsides and Substructures to be Decommissioned

Available Vessels
Source: OSPAR[4], 4coffshore[19]

Installations to be Decommissioned and


Vessel Availability (2014 - 2022) - South
Number of Vessels and Installations

There are three new ultra large vessels currently


under development which have a significantly higher
lifting capacity than the existing market range.
The most advanced of these is Allseas Pieter Schelte
(48,000 tonne lift capability) which is due to be
operational in 2015. Were this vessel to be deployed
in a programme of activity, it could make sufficient
inroads into meeting the next 10 years worth of
decommissioning requirements.

18
16
14
12
10
8
6
4
2
0

<1,600

1,600-4,000

4,000-8,000

8,000-16,000

>16,000

Weight (Te)
Topsides and Substructures to be Decommissioned

Available Vessels
Source: OSPAR[4], 4coffshore[19]

60

Topside & Substructure Removal | Supply Chain

Decom North Sea


Review of Decommissioning Capacity | October 2014

6.4 Health Check


Capability = Low / Medium
Piece Small and Reverse engineering capacity is higher than that of single lift removal. The market for heavy-lift, while relatively
immature for decommissioning, has gained experience from decades of construction in the North Sea. There is more experience in
lower weight categories. For lifts greater than 10,000 tonnes there is extremely limited capacity.

Estimated volume of supply against demand = Low / Medium


There are challenges in determining the capacity of the vessel market to respond to decommissioning opportunities.
The market peak for installation in the North Sea occurred in the ten years from 1984 to 1993. In this period an approximately
average of 240,000 tonnes of steel were installed every year. This activity level is equivalent to estimates of steel removal over the
next decade which are approximately 150,000 to 260,000 tonnes a year. This suggests activity over the next ten years will be
comparable to the period of peak activity which occurred 30 years ago.
In the northern areas, to match the weight class and lift weight i.e. carrying out a single lift, there is limitation in the heavier weight
classes. For the lighter platforms single lift will be more feasible.
In southern areas there are significantly more single lift opportunities, though there are some limitations in the above >1,600
Categories. If there are shortages in the market there is a long lead time to building new capacity, with vessel development and
construction taking approximately 5 years or more. If there is an undersupply, the lead time to developing new capacity could cause
constraints in the medium term.

Pressures and/or synergies from other industries = Medium


Vessels operate as a global resource, following the market opportunities from a range of marine industries such as offshore wind,
and O&G construction.
Jack-up, sheer leg and heavy-lift vessels are in demand from the offshore wind industry for substructure, turbines and substation
platforms. There are significant developments planned in UK waters for projects with construction programmes that last for a
number of years for each project.
The majority of decommissioning vessels are also appropriate for new field development. Anecdotally vessel operators prefer to
support new field development, as it is less cost driven and more programme focused than decommissioning.
Despite this, current North Sea new construction activity is significantly lower than during peak development. Over the ten year
period from 1984 to 1993 there was an average of 20 fixed steel or concrete gravity base installations constructed a year, with a
peak of 38. The average number of fixed steel or concrete gravity base installations constructed over the last ten years has been just
over 7 a year only 35% of the peak. As such there is less demand from E&P activities than historically occurred.

Investment Status = Low / Medium


Vessel operators are reluctant to make commitments to new vessels without certainty in terms of timing of the
North Sea decommissioning market. There has been commitment to development and construction of new
vessels, such as the Pieter Schelte, which can support the decommissioning market. However, these
vessels have generally been justified on the basis of a business case covering a broader market sector.

Overall Status = Orange


There is a moderate potential for topside and substructure removal resources to cause a
supply chain bottleneck based on the considerations detailed above.

Topside & Substructure Removal | Health Check

61

Decom North Sea


Review of Decommissioning Capacity | October 2014

chrishendersonphotography

62

Decom North Sea


Review of Decommissioning Capacity | October 2014

7.0 Topsides & Substructure


Reuse & Recycling

63

Decom North Sea


Review of Decommissioning Capacity | September
October 2014
2014

Topsides & Substructure Reuse & Recycling

Skills

64

Waste Material
Characterisation

Onshore Dismantling

Onshore Environmental

Waste Management

Hazardous Material
Management and Disposal

Infrastructure and
Equipment

Supply Chain

Onshore Cranage

Engineering Consultants

Cutting Equipment

Onshore Yard Operators

Handling Equipment

Onshore Yard Space

Ports and Harbour


Operators

Quayside Strength and


Extent

Civil Contractors

Demolition Contractors

Waste Reuse & Recycling


Contractors

Deepwater Access Channel

Dry Dock

Metal Recycling Facilities


and Logistics

Topside & Substructure Reuse & Recycling

Decom North Sea


Review of Decommissioning Capacity | October 2014

7.1 Overview


Determining capacity of a yard to service the O&G
decommissioning market is a function of a number
of parameters relating to processing capability
such as; footprint, material handling capability, lift/
skidding capability, quayside strength, draught, waste
processing etc. It is also dependent on the weight of
the total installation and the weight and dimension
of any subsections delivered to the facility (which is
dictated by the removal method).

Currently there are 6 facilities with decommissioning


experience in proximity to North Sea infrastructure
with a total footprint of nearly 90 hectares[3], [7], [19], [21],
[22], [23]
. There are at least another 17 that have most
of the required characteristics could support future

decommissioning work[3], [7], [19], [21], [22], [23]. The total
footprint available in these yards would increase the
overall available footprint by ten times. There are
also significantly more facilities that could support
decommissioning with further investment. A number
of these are making upgrades to support the offshore
wind market, which would be suitable for the
decommissioning market.

Estimates by the NCPA suggest that Norway has


a capacity to process 50,000-160,000 tonnes of
decommissioning annually[7]. The UK is likely to have
a similar scale of processing capability based on
comparing facility footprints. The average demand of
steel removal and recycling is estimated at 100,000
tonnes per year, ramping up to 160,000 tonnes a
year[1], [7]. This suggests that, there could be capacity
constraints over the period to 2022, particularly
if the lower range of current Norwegian and UK
port capacity is considered; if further ports are not
developed; and if there is high competing demand for
capacity.
For smaller installations, there is less likely to be
capacity constraints due to the range of viable
facilities capable of lifting and processing installations
of a few thousand tonnes. For heavier installations,
depending on competing demands, there may be
limitations on the available ports capable of receiving
and processing large structures up to 10,000 which
the current generation of large heavy-lift vessels can
deliver. However, there are a range of opportunities
to upgrade current ports to equip them with greater
lifting and processing capability.

1%

Estimated UKCS Expenditure


30

Million per year

25
20
15
10
5
0
2014

2015

2016

2017

2018

2019

2020

2021

Topside & Substructure Reuse & Recycling | Overview

2022

65

Decom North Sea


Review of Decommissioning Capacity | October 2014

7.2 Activity
With pressure to reuse and recycle as much of the infrastructure as possible, capable facilities are required to
respond to the challenge. However, there are a limited number of locations with experience and track record. The
ports, harbours and yards infrastructure that are required to decommission steel installations have been identified
as critical supply chain elements through the assessment and consultation process.

Approach
The activity for topside and substructure recycling consists of transferring the structure from a floating or towed
condition to a reusable or recycled product. The following flow diagram shows the typical process during reuse/
recycling.
Structures to be recycled are taken to a port/yard and either loaded in to a dry dock or lifted/skidded/trailed
onto a quayside. The dry dock capacity, skids, craneage, marine crane access and quay side strength are all
constraints which will affect the capacity of the facility to process the structures. As part of the breakdown and
recycling process, the structure is cut into pieces and waste is segregated into hazardous and non-hazardous
waste. For these activities, yard space, cutting and handling equipment, pollution control, and hazardous
materials control dictate the volume of material that can be processed.
Rather than being recycled, many floating steel structures are reused at subsequent fields. This is often following a
retrofit at a fabrication yard. The average age of North Sea floating structures is 17 years which is much less than
the average life of North Sea fixed steel structure at 25 years[4]. As such, there will be significantly less demand for
ports, harbours and yards associated with floating structures in the short to medium term. The most demanding
need for reuse and recycling of infrastructure will result from the steel associated with fixed steel installations and
concrete gravity base topsides, and is the focus of this chapter.

Recover
from field

Retrofit:
Transport to new
location

Install in
new field

Quayside strengh and


exent

Deep water access


channel

Load - in
Lifted, skidded or
trailed onto
quayside

Load into
dry dock
and drain dock

Dry dock
Dewatering
equipment

transport and installation


contractor

98% Waste:
Recycled into
new products

EPC Contractor

Port operators

Nearshore
operations
Arrives in inner
harbour

Marine spread

Onshore craneage

Waste
segregation
Broken down
using cutting,
controlled
blasting

Hazardous Material
Disposal
Waste Recycling
contractors

Material
characterisation
Secure, segregated
storage areas

Onshore Yard
Operators
Yard Space
Cutting and handling
equipment
Pollution control

66

Waste Recycling
contractors

Hazardous
Waste:
treatment and
disposal

Quayside strengh
and exent
Skids

Material recycling
facilities and logistics

Topside & Substructure Reuse & Recycling | Activity

Decom North Sea


Review of Decommissioning Capacity | October 2014

Volume of Activity

Published data from North Sea regulators


suggests that the fixed steel and concrete
gravity base topsides that will be removed
are equally distributed across all the weight
classes[1], [7]. This is unlike the profile of the
North Sea which is biased towards smaller
platforms. This suggests that the short to
medium term focus for the decommissioning
market will be the larger heavier northern
North Sea platforms, which are reaching
end of life.

Weight (Te) Thousands

400
350
300
250
200
150
100
50
0

2014 to 2019
inc. Floating

2014 to 2019
excl. Floating

UK (North Refers
to areas above 55
degrees LAT)

2020 Onwards
inc. Floating

2020 Onwards
excl. Floating

UK (South Refers
to areas below 55
degrees LAT)

Norway

All Others
Source: OSPAR[4]

Weight of Topsides for Platforms Expected


to be Decommissioned
9

Number of Substructures

Full detail of the estimates of activity and


steel removal requirements are detailed in
Chapter 3. Total estimates of the North Sea
decommissioning steel removal requirements
equate to an average of 150,000 tonnes per
year up to 2019 and over 270,000 tonnes
from 2020 onwards[1], [7]. However, this
includes floating installations which make
up nearly 40% of the steel weight and could
potentially be refurbished or reused at other
fields[1]. If this is assumed to be the case, then
demand for break-up of structures and steel
recycling may be of the order of 100,000
tonnes per year until 2020 increasing to
150,000 tonnes beyond.

Estimated Annual Steel Removal


in the North Sea

8
7
6
5
4
3
2
1
0

<1,600

1,600-4,000

4,000-8,000

8,000-16,000

16,000-58,000

Weight (Te)
South (Refers to areas
below 55 degrees LAT)

North (Refers to areas


above 55 degrees LAT)

Source: OSPAR[4]

Weight of Fixed Steel Substructure for Platforms


Expected to be Decommissioned
9

Number of Topsides

8
7
6
5
4
3
2
1
0

<1,600

1,600-4,000

4,000-8,000

8,000-16,000

16,000-58,000

Weight (Te)
South (Refers to areas
below 55 degrees LAT)

North (Refers to areas


above 55 degrees LAT)

Source: OSPAR[4]

Topside & Substructure Reuse & Recycling | Activity

67

Decom North Sea


Review of Decommissioning Capacity | October 2014

7.3 Supply Chain


Determining the current and future supply chain capacity in the next 10 years is complex due to the technical,
commercial and political factors influencing how the supply chain is utilised. The lead time to build new capacity
and capability will result in limitations in terms of new facilities in the next few years.

Capability
The type of installations in terms of scale and weight
and decommissioning approach (piece small, multiple
lift, single lift) will dictate the required port, harbour and
yard functional requirements. Smaller installations or
piece small approaches will provide for a much lower
barrier to entry for the supply chain. For the very large
installations, or multiple/single lift approaches the
functional requirements are significantly more onerous,
and there are less viable facilities in the current supply
chain.

Depending on the volume of business and continuity


of projects the following characteristics would also be
attractive:

Available and experienced workforce.

Rail and other transport connections.

Facilities for treatment and storage/transport of


hazardous waste including Naturally Occurring
Radioactive Material (NORMs).

Areas for waste segregation.

Located within reasonable proximity to the location


The average topside weight in the North Sea is just
[4]
of the asset that is being decommissioned; and
over 4,000 tonnes . An ideal decommissioning yard to
recycle a topside of this size would require the following A safety focussed and secure licensed worksite.
characteristics:
Smaller lighter substructures and topsides will be more
Draught sufficient to allow access for appropriate
flexible in terms of their functional demands, requiring
removal vessels.
a lesser footprint, draft and lifting capability. The largest
installations will be significantly more limited in terms of
Depths in excess of 15 m provides flexibility for
larger vessels, although this depth is not common. the locations which they can utilise.
Alternative approaches such as use of barges can
Waste Transfer
be utilised where there are draught limitations.

68

There are regulatory barriers in terms of capacity, as


there are limitations in terms of waste that can be
transferred across national boundaries. Waste requiring
disposal cannot be shipped across international
Quayside with a capacity in excess of 40 tonnes
borders. However, waste can be moved across
per m2 and capability for lifting, skidding or trailing international borders if it is destined for recovery.
the topside or substructure; or
Capacity must be considered in terms of constraints in
A dry dock with footprint of approximately 2 ha with North Sea operators considering facilities out with their
continental shelf, especially where there are limitations in
appropriate shape.
recovery of the waste products.
Adequate working space to allow for the topside
footprint and an appropriate working space
estimated to be approximately 2 ha.

Topside & Substructure Reuse & Recycling | Supply Chain

Decom North Sea


Review of Decommissioning Capacity | October 2014

Naturally Occurring Radioactive Material


(NORM)
O&G operations can result in production of an
insoluble NORM scale which can be entrained
in plant such as pipework and valves. Additional
regulations govern the management and disposal
of NORM, with the level of radiation dictating the
manner in which material must be managed.
In the UK, the O&G industrys current activities are
estimated to produce approximately 800 tonnes
of NORM a year, of which less than 150 tonnes is
disposed of, using specialist treatment and disposal.
Comparison of the information on estimated NORM
waste arising and current landfill capacity suggests
that there is no immediate disposal capacity problem
for solid, non-hazardous NORM containing waste[24].
The same can be said for NORM waste that also has
hazardous properties. However, there is only one
landfill site in the UK that can take hazardous NORM
waste, making this disposal route fragile. The growth
of decommissioning activity has potential to impact
on capacity, though there is considerable uncertainty
in terms of the scale of impact due to the scarcity of
experience in decommissioning activity.

Existing Capacity
Determining capacity of a yard to service the O&G
decommissioning market is a function of a number
of parameters relating to processing capability,
such as footprint, material handling capability, lift/
skidding capability, quayside strength, draught, waste
processing etc. It is also dependent on the weight of
the total installation and the weight and dimension
of any subsections delivered to the facility (which is
dictated by the removal method).
At present, there are at least 6 yards available to
service the North Sea that have decommissioning
experience [3], [7], [19], [21], [22], [23]. These yards have a
combined footprint of approximately 90 hectares[3], [7],
[19], [21], [22], [23]
. There are at least another 17 that have
most of the above characteristics and are capable of
carrying out future decommissioning work[3], [7], [19], [21],
[22], [23]
. The total yard space available in these yards
suitable for decommissioning projects is estimated
at over 950 hectares[3], [7], [19], [21], [22], [23]. This would
increase the overall footprint by ten times, compared
to current capacity.

This includes the Lutelandet Offshore yard, under


construction in Norway which is planned to service
the Pieter Schelte vessel and encompasses another
140ha of potential development[25]. A number of
other yards are currently planning on expanding,
through construction of new quays or by developing
additional land for storage for markets other than
offshore decommissioning. For example, Nigg is
planning a new deepwater harbour; while it is aimed
towards the offshore wind market, the facilities would
be suitable for decommissioning work.
The table below details yards in proximity to the
North Sea which have present or future potential to
support decommissioning.

Experienced Yards

Yards with Potential


to Carry out Future
Decommissioning

Greenhead Base
- Peterson UK & Veolia
Environmental Services

Bremerhaven

Seaton Port - Able UK

Delfzijl

Stord Kvaerner

Esbjerg

Vats AF Decom Offshore

Great Yarmouth

Vlissingen
Hoondert Services &
Decommissioning

Hull

Wallsend Peterson UK
& Veolia Environmental
Services

Dales Voe

Humber Port
Kishorn
Lutelandet
Mandal
Nigg
Port of Tyne
Smith Embankment
Sunderland
Thyboron
Vest Adger
Wilhelmshaven

Note: Locations are shown overleaf

Topside & Substructure Reuse & Recycling | Supply Chain

69

Decom North Sea


Review of Decommissioning Capacity | October 2014

Decommissioning Yards.

70

Topside & Substructure Reuse & Recycling | Supply Chain

Decom North Sea


Review of Decommissioning Capacity | October 2014

Decommissioning Yards in
the North Sea

The graph shows some key yard characteristics


and the capability of yards with existing and future
decommissioning experience. The circles represent
yard footprint. A comparison of the number of yards
in each country also shows the capability available
and the geographic spread. The UK is leading in
terms of the current capacity, as well as in terms
of locations with potential capacity to support the
decommissioning market.

30

Draught (m)

25

Estimates by the NCPA suggest that Norway has


a capacity to process between 50,000 to 80,000
tonnes of steel annually at facilities in Vats, Stord/
Scanmet, and Vest Adger which have permits
to decommission offshore installations[7]. These
facilities have a total footprint of nearly 70 hectares.

For smaller installations, there is likely to be limited


constraints due to the range of viable facilities
capable of lifting and processing installations of
a few thousand tonnes. For heavier installations,
depending on competing demands, there may
be limitations on the available ports capable of
receiving and processing large structures up to
10,000 tonnes which the current generation of large
heavy-lift vessels can deliver.

20

15

10

500

1000

1500

2000

Quayside Length (m)

A 2002 study by Det Norske Veritas (DNV)


suggested that Norway had sufficient capacity to
process up to 160,000 tonnes a year[26]. However,
this included capacity of a number of facilities which
are no longer operating. There is a lack of data on
UK capacity, but it is likely that the UK will have
the potential to match or exceed this processing
capability based on comparing facility footprint.

Potential

Experienced
Source: Mackay Consultants[3], NCPA[7]

Footprint of Decommissioning Yards


250

200

Yard Area (Ha)

The average demand of steel removal and recycling


is estimated at 100,000 tonnes per year ramping
up to 160,000 tonnes a year in the latter half of the
next decade[1], [7]. This suggests that there could
be capacity constraints over the period to 2022,
particularly if the lower range of current Norwegian
and UK port capacity is considered; if further ports
are not developed, and if there is high competing
demand for capacity.

Typical Footprint of a
4,000 tonne topside

150

100

50

Denmark

Germany

Potential

Netherlands

Norway

UK

Experienced
Source: Mackay Consultants[3], NCPA[7]

There are a range of opportunities to upgrade


current ports to allow for greater lifting and
processing capability. However, the lead time
to develop upgrades may cause constraints in
the short to medium term. Moreover, the high
level of investment commitment may discourage
investment, unless there is confidence that
opportunities will materialise in a reasonable
timeframe. The number of yards which can
accommodate the ultra-large vessels, such as the
Pieter Schelte, will be very limited.

Topside & Substructure Reuse & Recycling | Supply Chain

71

Decom North Sea


Review of Decommissioning Capacity | October 2014

7.4 Health Check


Capability = Medium
Accenture[5] consider topside and substructure recycling including offloading, cleaning and handling, deconstruction, recycling and
disposal and possible re-use with an overall capability for the phase of just over 3 out of 5, making it the joint second strongest
capability across the decommissioning supply chain. They assessed the activity with the strongest supply capability is Recycling &
Disposal with 3.43 while, Offloading is the lowest capability at 2.89 out of five.
There is good capability and track record in dealing with piece small decommissioning. However, deep water facilities capable of
hosting large heavy-lift vessels are more limited with large vessels relying on transfer barges.
Steel processing plants are far from available yards, complicating logistics and increasing costs. There are also opportunities for
improving the link between demolition contractors and yards.

Estimated volume of supply against demand = Medium


A review of capacity against demand suggests that, particularly if the lower range of current Norwegian and UK port capacity
is considered, there could be capacity constraints over the period to 2022 if further ports are not developed and if there is high
competing demand for capacity.
For smaller installations there are likely to be limited constraints due to the range of viable facilities capable of lifting and processing
installations of a few thousand tonnes.
For heavier installations, there may be some limitations in terms of facilities capable of receiving and processing structures up to
10,000 tonnes which the current generation of large heavy-lift vessels can deliver.
There are a range of opportunities to upgrade current ports to allow for greater lifting and processing capability. However the lead
time to develop upgrades may cause constraints in the short to medium term. And the high level of investment commitment, may
discourage investment unless there is confidence that opportunities will materialise in a reasonable timeframe.

Pressures and/or synergies from other industries = High


Ports/Harbours/Yards have a variety of uses which may compete with the decommissioning market including O&G fabrication and
refit, ship building and decommissioning, marine renewables and others.
There is potential competition from the offshore wind sector, for fabrication and assembly facilities which could reduce storage space
and berths availability if a high deployment scenario is realised. Recent development activity in this market has been scaled back
suggesting that the demands from the industry is likely to be more modest than initially anticipated.
Analysis undertaken on behalf of The Crown Estates indicated that there is sufficient European capacity for the offshore wind
market[27]. In the UK, there has been progress in developing installation capacity at Belfast, Great Yarmouth, Harwich, Hull,
Merseyside, Mostyn and Teesside. There have also been developments in Belgium at Ostend, in Denmark at Esbjerg and in the
Netherlands at Eemshaven and Vlissingen.
However, generally the locations currently being targeted by each industry do not overlap. It is considered that their
development has potential to offer a synergistic benefit as the overall capability of infrastructure grows, rather than
a risk of competition.
In some areas, ports face redevelopment pressures as they are sought after locations for residential or
commercial enterprises. However, this pressure has reduced in recent years as the property market is
less buoyant.

Investment Status = Medium / High


Investment has been made in a number of facilities in proximity to the North Sea on the basis
of opportunities from decommissioning and other industries.

Overall Status = Green


There is a low potential for topside and substructure recycling resources to cause a
supply chain bottleneck based on the considerations detailed above.

72

Topside & Substructure Reuse & Recycling | Health Check

Decom North Sea


Review of Decommissioning Capacity | October 2014

73
Able UK Ltd

Decom North Sea


Review of Decommissioning Capacity | October 2014

Arup

74

Decom North Sea


Review of Decommissioning Capacity | October 2014

8.0 People

75

Decom North Sea


Review of Decommissioning Capacity | October 2014

North Sea Decommissioning Employment


Estimates
6,000

Employment in Man Years

Common across all elements of the resource


breakdown structure is the requirement to have
skilled manpower to support decommissioning
projects. People, and in particular those with
engineering and offshore skills have been
identified as a critical supply chain element
through the consultation process. People are
elements of the supply chain which are known
to have demands from other maritime and
other industries, have had known shortages,
are specialised and not easily substituted by
alternatives.

5,000

4,000

3,000

2,000

As a nascent market, it is inevitable that there is


1,000
currently a shortage in sufficiently experienced
resources to meet future demand. Building
0
capacity will involve attracting skilled resources
2017
2018
2019
2020
2014
2015
2016
2021
2022
from analogous industries and training new
capability. Knowledge management is a core
Denmark and the Netherlands
UK
Norway
aspect to efficacious advancement of the
decommissioning market. To drive down
Source: Adapted from Oil & Gas UK , Mackay Consultants
project costs, it is critical to ensure that lessons
learned from early projects, both the successes
and failures, are understood and integrated into future approaches. The O&G Sector is generally characterised
by a comparatively mobile workforce that follow opportunities across the sector and geographies. Capturing and
disseminating experiences from a transient workforce will be a challenge.
[1]

Analysis undertaken on the Brent Decommissioning Programme concludes that there is approximately 450,000 of
expenditure per man year of employment[3]. Using this figure in conjunction with the predicted expenditure profile in
the North Sea to 2022, results in an annual average employment of approximately 4,250 people.
Annual average decommissioning activity is predicted to double over the next decade, indicating a need to
substantially grow the workforce capability. The most likely source of these resources is the North Sea E&P
Sector. There are an estimated 271,000 directly employed within the O&G industry across the UK, Norway and
Denmark[28], [29], [30]. These countries all estimate a workforce that will grow at a faster rate than the UK average[28],
[29], [30]
. A significant proportion of these individuals could have directly applicable or transferrable skills to support
decommissioning. Decommissioning employment estimates represents less than 2% of the North Sea E&P
resource. Considered in isolation it is unlikely that resources to support the decommissioning market will be a
constraint.
However, the O&G market and engineering market as a whole are suffering from resource constraints. According
to statistics from the Royal Academy for Engineering, the UK only produces enough science, engineering
and technology graduates to meet two thirds of the required 110,000 new entrants required annually by UK
businesses[31]. Analysis by OPTIO finds that 33% of businesses in the upstream O&G Sector have hard-to-fill roles
including design engineers, marine crew, and mechanical engineers[28]. Skills shortages also exist within the current
workforce, with 24% of businesses with engineering and technical staff citing skills shortages as a particular issue[28].
Arup consultation suggested there is an anecdotal perceived image problem associated with the decommissioning
market, which is not considered as interesting or as financially rewarding as the E&P market. As a result, the
decommissioning market is likely to be vulnerable to competition from the North Sea and global E&P markets.
Research highlights that the age profile of employees in the industry is a key issue[32]. An aging workforce creates a
concern in terms of future reduction in available workforce as older staff retire without the pipeline of new staff filling
their roles. This is particularly critical for the decommissioning market as the first tranche of projects will be older
assets, many of which have suffered from poor record keeping. It is important that the expertise and knowledge held
by older workers is retained within the industry and transferred to new recruits. Other markets such as the nuclear
decommissioning and offshore wind sector may provide resources with transferrable skills that can support the
market. However, these markets are already resource constrained and are unlikely to offer significant potential to
alleviate resource constraints.

76

People

[3]

Decom North Sea


Review of Decommissioning Capacity | October 2014

Health Check
Capability = Medium
As a nascent market it is inevitable that there is currently not sufficient experienced resources to meet future demand. Building
capacity will involve attracting skilled resources from analogous industries and training new capability.
Annual average decommissioning activity is predicted to double over the next decade, indicating a need to substantially grow the
workforce capability. Capturing and disseminating experiences from a transient workforce will be a challenge[1].

Estimated volume of supply against demand = Medium


Annual average decommissioning activity is predicted to double over the next decade, indicating a need to substantially grow
the workforce capability. The most likely source of these resources is the North Sea E&P Sector. There are an estimated 271,000
employed within the O&G industry across the UK, Norway and Denmark. These countries all estimate a workforce that will grow at
a faster rate than the UK average based on the demand. A significant proportion of these individuals will have directly applicable or
transferrable skills to support decommissioning. Decommissioning employment estimates represents less than 2% of this market.
Considered in isolation it is unlikely that resources to support the decommissioning market would be a constraint.
Some capabilities can quickly be established where there is the potential to build on existing capability. However, the lead time to
build professional skills with experience can take up to a decade or more.

Pressures and /or synergies from other industries = Low / Medium


The O&G market and engineering markets as a whole are suffering from resource constraints. There is an anecdotal perceived
image problem associated with the decommissioning market, which is not considered as interesting or financially rewarding as the
E&P market. As a result the decommissioning market is likely to be vulnerable to competition from the North Sea and global E&P
markets.
Other markets such as the nuclear decommissioning and offshore wind Sector may provide resources with transferrable skills that
can support the market. However, these markets are already resource constrained and are unlikely to offer significant potential to
alleviate resource constraints.

Investment Status = Medium / High


There is a recognised drive to increase resource capability and volume across the O&G sector with significant growth in resources
expected in the short term.

Overall Status = Orange


There is a moderate potential for people resources to cause a supply chain bottleneck based on the
considerations detailed above.

People | Health Check

77

Decom North Sea


Review of Decommissioning Capacity | October 2014

Jan Berghuis

78

Decom North Sea


Review of Decommissioning Capacity | October 2014

9.0 Context and Considerations

79

Decom North Sea


Review of Decommissioning Capacity | October 2014

A Changing Mind Set


The decommissioning market is largely served by supply chain who also operate in the E&P Sector. The market is
largely driven by operators who have taken assets through the E&P phases and whose business model focuses
on E&P optimisation. As such, a number of the approaches and philosophy of E&P has been taken through to
inform decision making in decommissioning.
Contributors to the consultation exercise informing this study commonly noted the need for the market to
develop an approach to decommissioning distinct from that of exploration and production activity. Recognition
of the different drivers and success criteria of E&P versus decommissioning will enable the market to develop an
approach that is optimised for their respective projects.
Regardless, the existing operators of installations are critical to understanding the assets and their
characteristics. To develop an effective decommissioning process, their experience should be integrated into the
decommissioning plan.
The table gives examples of the differences in market drivers in E&P versus decommissioning.

Exploration & Production

Decommissioning

Economics driven by achieving first oil

Economics driven by reducing overall costs, with


drivers bias towards defer spend

Projects may not proceed if they do not achieve


investment hurdles

Project legally obligated to proceed

Future market scale uncertain

Future market scale relatively certain

Very mature market which has been evolved since


first activity in the 1960s

Immature market with a small number of projects


and operators having delivered a decommissioning
project to date

Scope of project can vary based on technical and


commercial drivers

Scope of project is largely fixed and includes


removal of all infrastructure (unless a derogation is
granted). Although there is considerable uncertainty
for older facilities in the instance where record
keeping has been poor.

Safety and asset integrity driven, to ensure


operation and production is sustained
uninterrupted

Safety driven. Asset integrity only relevant to


maintain critical functions necessary for the removal
process and limit environmental impact

Perceived by the supply chain as having higher


margins and offering more challenges

Perceived by the market as lower margins and less


interesting

80

Context and Considerations

Decom North Sea


Review of Decommissioning Capacity | October 2014

Smoothing the Peaks

Contracting and Procurement Strategy

Creating accurate estimates of decommissioning


expenditure across the North Sea is challenging.
Estimates have been produced by a range of
organisations which show a broad range in variation
on a year by year basis and over the next decade.
There is inherent uncertainty in terms of the costs of
decommissioning and timing of activities which drive
these variations.

Rigidity in contracting and procurement structures


developed to support the E&P market can inhibit
operators and the supply chain from adapting to
meet the demands of the decommissioning market.

Estimates of expenditure from all sources show large


variations year on year. However there are inherent
limitations in decommissioning estimates, which
are built from a bottom-up analysis of individual
operators independently declaring their expected
decommissioning schedule. The rapid development
of North Sea infrastructure means that a number
of assets will come to the end of their life in similar
timescales. This trend would suggest that there will
also be peaks in the decommissioning activity, which
is reflected in many of the forecasts.
However, the market is inherently different to that
of E&P activities. In E&P programme delays directly
impact the timing of subsequent revenue flows
and so programme drivers are highly significant
in procurement decisions. For decommissioning,
programme delays defer capital expenditure and
often have a less significant detrimental impact on
project economics than in E&P projects.
As a result, operators are likely to have significantly
more flexibility to manage procurement and
programme decisions for decommissioning activities
than in E&P. Consequently, the market is unlikely
to procure services in the peaks suggested by the
predicted estimates as the cost to procure resources
would increase i.e. the market will smooth out the
peaks.

Current procurement procedures generally consider


value, approach and experience. This creates a
bias towards the limited parts of the supply chain
that have existing experience. Adapting existing
procurement strategy to reduce requirements for
previous experience which will allow new entrants to
the market who may introduce innovative methods.
This could allow learning from other markets, such as
the nuclear or salvage industries to be integrated.
There are a range of contracting strategies pursued
by operators which are generally an evolution of E&P
activities. Innovative contracting strategies may allow
contractors and operators to reduce costs through
better allocation of risk and pain-gain mechanisms
to better aligning objectives. Examples could include
well P&A contracts being extended to cover a
programme of wells which could be more efficient
than contracting wells as individual projects. Provision
of a more flexible window during which operations
can be undertaken could allow more efficient
programming of resources.
There are also opportunities for the supply chain
to collaborate more effectively to develop more
comprehensive offerings which respond to
contracting strategies.

Context and Considerations

81

Decom North Sea


Review of Decommissioning Capacity | October 2014

Driving Innovation, Driving Down Costs


and Regulation
Innovation can play a role in delivering
decommissioning in a more cost effective manner.
The nascent market has limited experience focusing
on decommissioning activities and is at a stage
where it can incorporate lessons learnt along with
developing new approaches to reduce costs.
The uncertainty in the timescales of the market
opportunity may limit commitment to drive and invest
in innovation. The supply chain cites the stop/start
nature of the industry as a barrier to investment.
Investment in the Pieter Schelte is a significant
exception, however, opportunities from other markets
provided investment confidence to Allseas.
An example of this is the development of a tested
rigless approach for well P&A, which could
significantly reduce costs. Currently there are
limitations in the number of North Sea operators that
have accepted a rigless solution due to concerns
associated with using novel untested technology.
Also, well P&A contractors are not publically
committing to develop and test equipment due to
the lack of certainty over timing of decommissioning
programmes. In the Gulf of Mexico regulatory
intervention through the Idle Iron policy gave greater
certainty in the pipeline of activity which provided the
appropriate climate for the supply chain to invest in
development of new tools[33].
In the UK the overhaul of the regulatory system
offers opportunities for intervention that will
motivate the market to reduce costs. Alternative
approaches to encouraging the supply chain are
increased collaboration between operators in terms
of identifying clusters of projects which offer a more
attractive contracting opportunity.

82

Context and Considerations

Decom North Sea


Review of Decommissioning Capacity | October 2014

83

Decom North Sea


Review of Decommissioning Capacity | October 2014

84

Decom North Sea


Review of Decommissioning Capacity | October 2014

Appendix A: References

85

Decom North Sea


Review of Decommissioning Capacity | October 2014

Sources of Information
The following sources of information were integrated
into this analysis:
1. Oil and Gas UK (2013), Decommissioning Insight
2013, Available via; http://www.oilandgasuk.
co.uk/cmsfiles/modules/publications/pdfs/
OP082.pdf (Accessed 25th September 2014)
2. Prof. Kemp, A. (2014), Prospective
Decommissioning Activity and Infrastructure
Availability in the UKCS (updated figures),
University of Aberdeen. Not publically available
3. Mackay Consultants (2013), Draft Report for
Decom North Sea, Not publically available
4. OSPAR (2013), Inventory of Offshore
Installations, Available via; http://www.
ospar.org/content/content.asp?me
nu=01511400000000_000000_000000
(Accessed 25th September 2014)
5. Scottish Enterprise, Decom North Sea
& Accenture (2013), Decommissioning
in the UKCS, Available via; http://www.
scottish-enterprise.com/~/media/
SE_2013/Knowledge%20Hub/Publication/
Decommission%20ing%20UKCS%20study.PDF
(Accessed 25th September 2014)
6. Oil & Gas UK (2014), Activity Survey, Available via
http://www.oilandgasuk.co.uk/cmsfiles/modules/
publications/pdfs/EC040.pdf (Accessed 25th
September 2014)
7. Norwegian Climate and Pollution Agency
(NCPA) (2010), Decommissioning of Offshore
Installations, Available via; http://www.npd.no/
Global/Engelsk/3%20-%20Publications/Reports/
endelig%20avvikling%20rapport%20engelsk.pdf
(Accessed 25th September 2014)
8. Norwegian Oil & Gas Association (NOGA) (2013),
Activity Still High In a Still Uncertain World,
Available via; http://www.norskoljeoggass.no/
Global/2013%20Dokumenter/Publikasjoner/
NOROG%20konjunktur_2013_ENG%20(08).pdf
(Accessed 25th September 2014)
9. Oil & Gas UK (2009), North Sea Well
Abandonment Study, Not publically available

86

Appendix A: References

10. Department of Energy and Climate Change


(DECC) (2014), Wells Data Search Tool, Available
via; https://itportal.decc.gov.uk/pls/wons/
wdep0100.qryWell (Accessed 25th September
2014)
11. Norwegian Petroleum Directorate (NPD)
(2014), FactPages Wellbore (Exploration and
Development), Available via; http://factpages.
npd.no/factpages/ (Accessed 25th September
2014)
12. Danish Energy Agency (2014), Wells 1935
2013, available via; http://www.ens.dk/en/oilgas/oil-gas-related-data/wells (Accessed 25th
September 2014)
13. NL Oil & Gas portal (2014), Boreholes Data,
Available via; http://www.nlog.nl/en/pubs/maps/
other_maps/other_maps.html (Accessed 25th
September 2014)
14. NPD (2014), FactPages - Facility (Fixed),
Available via; http://factpages.npd.no/factpages/
default.aspx?culture=en (Accessed 26th
September 2014)
15. Danish Energy Agency (DEA) (2013), Oil & Gas
Production in Denmark and Suboil Use 2013,
Available via; http://www.ens.dk/sites/ens.dk/
files/dokumenter/publikationer/downloads/
danmarks_olie-_og_gasproduktion_2013_uk.pdf
(Accessed 25th September 2014)
16. DECC (2014), Pathfinder, Available via;
https://www.og.decc.gov.uk/pathfinder/
decommissioningindex.html (Accessed 25th
September 2014)
17. Rigzone (2014), Worldwide Offshore Rig
Utilization, Accessed via; https://www.rigzone.
com/data, (Accessed 12th September 2014)
18. Rigzone (2014), Offshore Rig Utilization by Rig
Type, Accessed via; https://www.rigzone.com/
data/utilization_rigtype.asp, (Accessed 12th
September 2014)
19. 4coffshore (2014), Vessel database, Available via;
http://www.4coffshore.com/windfarms/vessels.
aspx, (Accessed 26th August 2014)
20. DecomWorld News (2014), Available via;
http://social.decomworld.com/structures-andmaintenance/shell%E2%80%99s-brent-platformdisposal-and-recycling-contract-goes-able-uk
(Accessed 25th September 2014)

Decom North Sea


Review of Decommissioning Capacity | October 2014

21. Infield (2012) Decommissioning: The North Sea in


Context, Available via; http://www.oilandgasuk.
co.uk/downloadabledocs/1309/5 (Accessed
26th September 2014)

30. NPD (2014), FACTS 2014, Available via; http://


www.regjeringen.no/upload/OED/pdf%20filer/
Faktaheftet/Fakta2014OG/Facts_2014_nett.pdf
(Accessed 25th September 2014)

22. Ports.com (2014), North Sea Ports, Available via;


http://ports.com/sea/north-sea/ (Accessed 26th
September 2014)

31. Campaign for Science and Engineering (2014),


How to Meet Demand for Engineering Skills,
Accessed via; http://sciencecampaign.org.
uk/?p=13510 (Accessed 26th September 2014)

23. Achilles Database (2014), Scandinavia MetalInformation Register, Available via; http://
www.scanmet.no/files/Achillesdocument.pdf
(Accessed 26th September 2014)
24. DECC (2014), Strategy for the Management of
NORM Waste in the UK, Available via; https://
www.gov.uk/government/uploads/system/
uploads/attachment_data/file/335821/Final_
strategy_NORM.pdf (Accessed 25th September
2014)

32. OPITO (2011), Labour Market Intelligence Survey,


Available via; http://www.opito.com/media/
downloads/labour-market-intelligence-2011report.pdf (Accessed 25th September 2014)
33. Bureau of Safety and Environmental Enforcement
(BSEE) (2014), Idle Iron Policy, Available
via; http://www.bsee.gov/Exploration-andProduction/Decomissioning/Idle-Iron/ (Accessed
26th September 2014)

25. Lutelandet Offhore (2014), Decommissioning,


Available via; http://llof.no/Facilities/
PlatformDecommisioning/tabid/2284/Default.
aspx (Accessed 25th September 2014)
26. Det Norske Veritas (DNV) (2002).
Decommissioning of offshore installations.
Assessment of capacity at Norwegian yards in
the period 20012020, Report NO.01-4063
27. BVG Associates (2013) Offshore Wind: A 2013
Supply Chain Health Check, Available via,
http://www.bvgassociates.co.uk/Portals/0/
publications/BVGA%20TCE%20Offshore%20
Wind%20SC%20Health%20Check%201311.pdf
(Accessed 25th September 2014)
28. OPITO (2014), Upstream Oil & Gas Industry
Labour Market Intelligence Summary Findings,
Available via; http://online.fliphtml5.com/jgfa/
czqp/ (Accessed 25th September 2014)
29. Oil Gas Denmark (2013), Denmark An Oil
Nation, Available via; http://issuu.com/firstpurple/
docs/ogd2013_uk-enkeltsidet (Accessed 26th
September 2014)

Appendix A: References

87

Decom North Sea


Review of Decommissioning Capacity | October 2014

88

Decom North Sea


Review of Decommissioning Capacity | October 2014

Appendix B: Criteria Scoring

89

Decom North Sea


Review of Decommissioning Capacity | October 2014

Each critical supply chain element is attributed a


score of Low to High (Low, Low/Medium, Medium,
Medium/High, High) for each parameter. The scoring
is based on subjective criteria which are detailed
below.

Available Capacity and Investment Lead


Time
This criterion considers the existing capacity of skills
and resources against expected activity and the
duration it takes to build any capacity shortfall.

Capability
Capability refers to the competence of the market to
support the decommissioning market. It is distinct
from capacity as it does not relate to the volume of
capable resources to meet the predicted demand.
The classification of capability is derived from
the assessment carried out by Accenture,
Decommissioning in the UKCS, May 2013. In
this report the industry and supply chain was
consulted on their perceived capability to provide
decommissioning services as per the O&GUK WBS.

90

Score

Rational

Low

Very Limited

Low / Medium

Limited / Not Proven / Under


Development

Medium

Established / Proven

Medium / High

Proven Track Record


/ Innovation / Industry
Recognised

High

Best in Class

Appendix B: Criteria Scoring

Score

Rational

Low

Existing Capacity has a


high probability of being
significantly limited and there
is a long lead time from Final
Investment Decision (FID) to
establish new capacity. There
are expected to be significant
long term constraints.

Low / Medium

Existing Capacity has a high


probability of being limited
and there is a moderate
lead time to establish new
capacity. There are expected
to be moderate medium term
constraints.

Medium

Existing Capacity has a


moderate probability of
being limited and there are
moderate lead times from FID
to establish new capacity.
There is expected to be
moderate short to medium
term constraints.

Medium / High

Existing capacity exists and


there is limited need for further
investment. There are at most
limited short term constraints.

High

There is a high probability of


there being an oversupply
in the market. There are no
expected capacity constraints
likely.

Decom North Sea


Review of Decommissioning Capacity | October 2014

Investment Commitment

Pressures/Synergies from Other Industries

This criterion considers the progress and


commitment made by the supply chain to build new
capacity to meet any shortfalls.

This criterion considers the opportunity or threat


of analogous industries. This can result from
competition of resources/skills, or supporting the
investment case to build capacity.

Score

Rational

Low

There are no publically


available sources of the supply
chain building investment
commitment.

Low / Medium

The market has indicated an


interest in building capacity,
but plans have not been made
publically available.

Medium

There market has indicated


an interest in building capacity
and a number of plans are in
development.

Medium / High

There are well advanced


plans to building capacity, but
uncertainty if they will deliver
sufficient capability.

High

The market is making strong


commitment to building
additional supply chain
capacity and there is a high
certainty that new capacity is
due to come on line.

Score

Rational

Low

The resource has an


application in other industries
which is likely to result
in a pressure on the use
of that resource in the
decommissioning market. It is
highly likely that the demands
from the other industry will
take precedence.

Low / Medium

The resource has an


application in other industries
which is likely to result in a
pressure on the use of that
resource. It is not clear which
industry will take precedence.

Medium

The resource has potential for


application in other industries
which may result in a pressure
on the use of that resource in
the decommissioning market.
However, it is highly likely
that the demands from the
decommissioning market will
take precedence.

Medium / High

There are limited pressures


on the resource from other
industries. The resources are
generally specialised for the
decommissioning market.

High

The resource has an


application in another industry
which is likely to support
capacity building and will be
of an overall benefit to the
decommissioning market.

Appendix B: Criteria Scoring

91

Decom North Sea


Review of Decommissioning Capacity | October 2014

92

Decom North Sea


Review of Decommissioning Capacity | October 2014

Appendix C: Resources

93

Decom North Sea


Review of Decommissioning Capacity | October 2014

Operator Project Management & Monitoring

Skills

Project Management Core


Team

Corporate Services

Commercial, Costing and


Economic Support

Decommissioning
Programme Preparation,
Reporting and Close Out

Survey Vessels
Geotechnical data
collection

Supply Chain

Engineering Consultancies

Project Management
Consultancies

Survey Vessels
Geophysical data collection

Integrated Professional
Services

Survey Vessels
Environmental

Legal Advisors

Navigational Aids

Accountants

Engineering Concept
Appraisal
(to support DP)

Survey Contractors

Environmental
Consultancies

Environmental Assessment
(to support DP)

Tier 1 Contractors

Licencing and Consenting

Navigation Consultants

Stakeholder Engagement

Commercial Fisheries
Interface
(Fish Safe, Admiralty
Charts, Legacy Trust)

Navigation Interface

Legal Support

Health and Safety

94

Infrastructure and
Equipment

Appendix C: Resources

Decom
Decom
North
North
Sea
Sea
Review
Review
of of
Decommissioning
Decommissioning
Capacity
Capacity
| October
| September
2014 2014

Well Abandonment

Skills

Well and P&A Project


Management

Engineering (P&A)

Operations Support

Rig Upgrade Capabilities

Infrastructure and
Equipment

Supply Chain

Rigs

Drilling Contractors

Rigless Solution

Light Weight Intervention


Vessels

Specialist Consultants and


Contractors

Vessel Operators

Transport Vessels

Rig/Rigless Contractors

Waste Management

Rig and Rigless Design


Services

Waste and Scale Treatment


and Storage

Abandonment Materials,
Expanding Cement,
Resins, Silicone Rubber

Hazardous Waste Handling


and Disposal Routes

Specialist Well Inspection


and Intervention services

Specialist Services i.e.


Wireline

Appendix C: Resources

95

Decom North Sea


Review of Decommissioning Capacity | October 2014

Running, Making Safe & Preparation

Skills

96

Infrastructure and
Equipment

Supply Chain

Offshore Operations

Standby Vessels

Vessel Operators

Deck Crew

Engineering consultancies

HV and LV Power
Engineering

Support Vessels (anchor


handlers, DSV, Tugs)

Specialist Contractors

Conventional Cutting
Technologies

Survey Contractors

Large Diameter Cutting


Technologies

Tier 1 Contractors

Subsea Disconnection &


Removal Tools

Platform Services

Integrity Management
(structural)

Engineering Down

Engineering Up

Survey Vessels

Detailed Engineering

Health and Safety

Logistics Base Marine,


Aviation and Onshore

Waste Management
Services

NORM Disposal Routes

Contaminant Disposal
Routes

Specialist Sampling
Services

Appendix C: Resources

Decom
Decom
North
North
Sea
Sea
Review
Review
of of
Decommissioning
Decommissioning
Capacity
Capacity
| October
| September
2014 2014

Topside & Substructure Removal

Skills

Infrastructure and
Equipment

Detailed Engineering
(Topsides and
Substructures)

Removal Vessel

Transportation Barges

Naval Architecture

Anchor Handling Tug


Supply (AHTS) Vessels

Offshore Operations

Transportation

Construction Support
Vessels (CSV)

Safety Standby Vessels


(SSBVs)

Survey Vessels

Rock Dumping / Backfill


Vessels

Supply Chain

Heavy-Lift Vessel
Contractors

Support Vessel Contractors

Engineering Consultancies

Specialist Consultancies

Appendix C: Resources

97

Decom North Sea


Review of Decommissioning Capacity | October 2014

Subsea & Site Remediation

Skills

98

Infrastructure and
Equipment

Supply Chain

Vessel Crew

Suction Dredging

Engineering consultants

ROV Pilot & Support

ROV and Support Vessel

Survey Contractors

Offshore Operations

Vessel Contractors

Geotechnical engineering

Diver Support Vessels


(DSVs)

Environmental Consultants

Stone Placement Vessels

Specialist Contractors

Anchor Handling Tug


Supply Vessel (AHTS)

Appendix C: Resources

Decom
Decom
North
North
Sea
Sea
Review
Review
of of
Decommissioning
Decommissioning
Capacity
Capacity
| October
| September
2014 2014

Topsides & Substructure Reuse & Recycling

Skills

Waste Material
Characterisation

Onshore Dismantling

Onshore Environmental

Waste Management

Hazardous Material
Management and Disposal

Infrastructure and
Equipment

Supply Chain

Onshore Cranage

Engineering Consultants

Cutting Equipment

Onshore Yard Operators

Handling Equipment

Onshore Yard Space

Ports and Harbour


Operators

Quayside Strength and


Extent

Civil Contractors

Demolition Contractors

Waste Reuse & Recycling


Contractors

Deepwater Access Channel

Dry Dock

Metal Recycling Facilities


and Logistics

Appendix C: Resources

99

For further information on


this report please contact:

Clare Lavelle
Arup
Scotstoun House
South Queensferry
Edinburgh
EH30 9SE
t +44 (0) 131 331 1999
e clare-m.lavelle@arup.com
Nigel Jenkins
Decom North Sea
33 Albyn Place
Aberdeen
AB10 1YL
t +44 (0) 1224 452170
e njenkins@decomnorthsea.com
Scottish Enterprise
Atrium Court
50 Waterloo Street
Glasgow
G2 6HQ
t +44 (0) 845 607 8787
e enquiries@scotent.co.uk

www.scottish-enterprise.com
www.decomnorthsea.com
www.arup.com
Cover Image: The Thialf, Heerema Crane Vessel Jan Berghuis

You might also like