Hi All,
1. After doing the cost estimation (Easy Cost Planning) for the service line in BOS, the
values are not transferred to the Calculated Costs (ISKO to ISK9).
In the pricing procedure VS0000 these conditions are manual conditions. In the document,
do we need to maintain them manually?
2. Getting an error 'No Service lines exist that can be costed'. For the outline level 'dummy
material' service lines are not maintained.
Thanks & Regards,
K.Rajendra Prasad Rao
Rajendra Prasad Rao Kondaveete 25 posts since Nov 25, 2013
Re: Bill of Service - Pricing Conditions Dec 11, 2013 11:53 AM
Hi Maria,
Thanks for providing configuration document. I checked and found that
1. All the mandatory settings are done, as per the document.
2. We are using cost determination for services, the required mandatory settings are defined.
I am getting the same errors. Please find below the steps I followed.
VA21 --> Create Quotation
Document Type: QBOS
Material: D01
Unit of Measurement: AU (Activity Unit)
Item Category: QBOS
Pricing Procedure: ADBOS1 Bill of Services
Pricing Procedure for Service Lines: VS0000
Service specifications are created as shown below
Before doing the calculations for cost estimate, if we check the pricing procedure in Analysis
pricing for the service line, I found that the pricing procedure VS0000 is determined.
Then I did the cost estimate for service line, Costing Variant PC0X
Clicked the back button till I reach the service overview screen. Here, I am getting the error No
Service lines exist that can be costed
The below screen is not same as before (please check the 2nd image).
No Pricing Procedure...
When I tried to add condition, I got the below F4 options. These conditions are not available in the pricing
procedure VS0000. These conditions are defined in MM under External Service Management --> Maintain
Conditions for Service.
If I go to the cost estimate and check the errors and come back to the service line overview
getting the message The cost estimate has been transferred. (no changes done in the cost
estimate)
Thanks for providing the valuable suggestion. OSS message opened and the issue is resolved.
I want to reward with points....don't know how to do. Let me know.
Thanks & Regards,
K. Rajendra Prasad Rao