INFRA-STRUCTURE Design
Consultant:
Perunding RekaCeKap Sdn Bhd
11A-3 (2nd floor), Jalan USJ 21/7
47630 UEP Subang Jaya
Selangor Darul Ehsan
Earthworks
Water Supply
Sewerage
Irrigation
Water Resources
EARTHWORK
Scope of earthwork involves:
Site clearance
Construction of temporary site access
General earthwork (cut & fill)
Construction of wash trough
Construct of silt trap & earth drain
Construction of slope/retaining system
Erosion and sedimentation control
EARTHWORK scope
Site clearance
Cut/Fill
Temporary Access
Basement Excavation
EARTHWORK - scope
berm drains
retaining system
EARTHWORK scope
Sedimentation control
Check dam
Silt Fence
SITE VISIT
EARTHWORK - Design
Platform/level design
Volume calculations BALANCE design
Slope/retaining system analysis & design
Erosion and sedimentation control plan
(ESCP)
Gabion Wall
Crib Wall
RC Wall
RE Wall
EARTHWORK PLAN:
SILT TRAP
SILT TRAP
EARTHWORK SECTIONS:
VIEW A
VIEW B
VIEW B
ROAD - Design
Road structure
follow local authorities
or JKR standard
ROAD - Design
Road Junction
-
ROAD - Design
ROAD - Design
Road Signage
follow local authorities
or JKR standard
DRAINAGE
Urban Stormwater Management Manual for Malaysia,
published by Department of Irrigation and Drainage.
Landscape/open space
Underground system
Landscape/park
Overflow outlet
UNDERGORUND OSD
Open Space
OSD
IN
OU
T
Culvert (Box)
Covered drain
Main drain
Unlined Drain/river
SEWERAGE
SCOPE OF SEWERAGE RETICULATION
WORKS INVOLVES
INVOLVES::
Design external sewerage reticulation serving the
development
Connect to existing sewer reticulation OR propose
NEW sewage treatment plant (STP) or sewage pumping
station (NPS)
SEWERAGE
Sewerage Network
SEWERAGE
Design compliance (3)
Guidelines for Developers on the Design and
Installation of Sewerage System.
M.S. 1228 : 1991 Code of Practice for Design
and Installation of Sewerage System.
Population Equivalent (PE) refer to SPANs
Table
SEWERAGE
Basic PE table base on type of premises
PE Tabulations
SEWERAGE
Sewerage Planning Proposal (PDC/1)
1. Connect to existing sewer main
2. Construct own STP (Advice on reserve &
set back compliance)
3. Construct New Pump Station (NPS)
advise on land reserve & set back
compliance
SEWERAGE
Buffer Zone Requirement
- Open plant > 30m
- Enclosed plant >10m
- Pump station > 20m
SEWERAGE PLAN:
IN
OU
T
SEWERAGE RETICULATION
HDPE Pipe
VCP Pipe
Concrete Pipe
Mechanical STP
extended aeration plant
WATER SUPPLY
Scope of external water reticulation works involves:
Design external
development
water
reticulation
serving
the
WATER SUPPLY
Incoming main
Suction, pumping
or reservoir, if
required
WATER SUPPLY
Design Guidelines
SPANs Guidelines UNIFORM TECHNICAL GUIDELINES
WATER RETICULATION AND PLUMBING
Water Demand calculations refer to SPANs Table
WATER SUPPLY
Design compliance
1.
2.
3.
4.
5.
6.
7.
8.
9.
WATER SUPPLY
Design HARDY CROSS Method
The network analysis for water distribution system is using
Hardy Cross method and Hazen-Williams equation:
Hf = 10.7 Q1.85
C1.85 D4.87
whereHf = frictional head loss (m)
C = pipe roughness coefficient, 100
Q = flow in pipe (m3/s)
D = internal diameter of pipe (m)
WATER SUPPLY
Design result table
WATER SUPPLY
SUCTION TANK, PUMPING STATION & RESERVOIR
The need depends on the location, water demand of the
development.
Elevated reservoir =
2/3 Storage
Pump house
Suction Tank =
1/3 Storage
WATER SUPPLY
SUCTION TANK, PUMPING STATION & RESERVOIR