3.0 Inspection & Test Plan
3.0 Inspection & Test Plan
3.0 Inspection & Test Plan
SYSTEM DOCUMENT
QUALITY DETAIL PROCEDURE
DOC. NO : EJ/SSB/B11LQ/1.4.3/08
DATE
: 13/04/10
REV. NO
: 0
SAMPLE
INSPECTION AND TEST PLAN (ITP) PROCEDURE
THIS DOCUMENT PRESCRIBES COMPANY PRACTICE AND IS FOR INTERNAL USE ONLY.
IT SHALL NOT BE REPRODUCED IN WHOLE OR IN PARTS OR RELEASED TO A THIRD PARTY WITHOUT
PRIOR CONSENT FROM THE HEAD OF RESPONSIBLE DEPARTMENT.
PREPARED BY
COMMISSIONING ENGINEER
REVIEWED BY
MANAGER, COMMISSIONING
NO. :
APPROVED BY
PROJECT MANAGER
UNCONTROLLED
COPY
CONTROLLED COPY
Page 1 OF 10
QUALITY MANAGEMENT
SYSTEM DOCUMENT
QUALITY DETAIL PROCEDURE
DOC. NO : EJ/SSB/B11LQ/1.4.3/08
DATE
: 13/04/10
REV. NO
: 0
REVISION
PURPOSE OF ISSUE
DATE ISSUE
ISSUED BY
A
B
0
31/03/2008
06/06/2008
07/06/2008
...................................................................
(SIGNATURE)
...................................
(DATE)
Page 2 OF 10
DESCRIPTION
PAGE
1.0
PURPOSE
4 OF 10
2.0
SCOPE
4 OF 10
3.0
REFERENCE
3.1
Procedure
3.2
Guideline
4 OF 10
4.0
RESPONSIBILITIES
5 OF 10
5.0
DEFINITION
5 OF 10
6.0
PROCEDURE FLOWCHART
6 OF 10
7.0
PROCEDURE DETAILS
7.1
Identify the Inspection & Testing (IT) Requirement
7.2
Develop IT Checklist and Plan
7.3
Identify & Mobilize the Required Resources
7.4
Implement the IT Plan
7 OF 10
8.0
RECORDS
9 OF 10
9.0
ATTACHMENTS
10 OF 10
PERFORMANCE MEASUREMENT
10 OF 10
10.0
Page 3 OF 10
1.0
PURPOSE
This procedure defines the necessary measures to ensure that adequate inspection & test plans
is in place, that activities for the construction materials, equipment and services are monitored,
and that essential controls during the fabrication, construction, installation, and commissioning
phases of the project are in conformance to the quality requirements.
2.0
SCOPES
This procedure applies to the entire duration of the contract, each individual project, and
subcontractors or suppliers hired to supply services to perform the inspection & testing works.
3.0
REFERENCE
3.1
Procedures:
1.
2.
3.
4.
5.
3.2
Procedure
Procedure
Procedure
Procedure
Procedure
Q.P.03-0
Q.P.05-0
Q.P.07-0
Q.P.08-0
.E.P.01-0
Corrective Action
Control of Monitoring & Measuring Devices
Control of Non-Conforming Materials/ Works
Material handling, storage, packing & delivery
Preliminary Project planing- Workpack Preparation
Guidelines
Guidelines
Guidelines
Guidelines
Guidelines
Guidelines
Guidelines
Guidelines
Guidelines
Guidelines
Guidelines:
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
Guideline
Guideline
Guideline
Guideline
Guideline
Guideline
Guideline
Guideline
Guideline
Guideline
Q.G.2-1
Q.G.2-2
Q.G.2-3
Q.G.2-4
Q.G.2-5
Q.G.2-6
Q.G.2-7
Q.G.2-8
Q.G.2-9
Q.G.2-10
on
on
on
on
on
on
on
on
on
on
Radiography Testing
Hydrostatic Testing
MPI Testing
Ultra- Sonic Testing
Visual Inspection
Mechanical Equipment Testing
Electrical Equipment Testing
DCS Testing
Alarm & Shutdown System Testing
Fire & Gas Detection System Testing
Page 4 OF 10
4.0
RESPONSIBILITIES
1. Head of Project (HOP) / Project
Manager
2. Quality Management
Representative (QMR)
3. QC/QA Engineer
4. QA/QC Inspector
4. Commissioning Engineer
5.0
DEFINITIONS
1
Inspection
Test
Page 5 OF 10
6.0
PROCEDURE FLOWCHART
The detail procedure in section 7 must read referring to this Flowchart
START
RESPONSIBILITY
ACTION
1. Identify IT
requirements during
Workpack
development
1. Develop IT checklist
& plans for the
project
QA/QC Inspector/
Commissioning Engineer
QA/QC Inspector/
Commissioning Engineer
IMPLEMENT IT PLAN
OK
RE-DO
NO
YES
APPROVE IT RECORDS
END
Page 6 OF 10
7.0
PROCEDURE DETAILS
7.1
7.2
7.3
7.2.2
QA/QC Engineer to consolidate the planning for all the IT and commissioning
activities in the project IT plan together with procedures that describe the
quality objectives, the extent of inspection, witness point and frequency, and
the acceptance criteria including the method for disposition of non-conforming
materials/ works.
QA/QC Engineer to identify the necessary resources required to execute all the
IT and commissioning activities. The resources include manpower, tools and
equipment such as the monitoring & measuring devices, and out sources
services from a third party Inspection Company for all the Non- Destructive
Test (NDT) works such as the Radiography Testing (RT) and MPI testing.
7.3.2
Page 7 OF 10
7.4
Characteristic of IT
The QA/QC Engineer Inspector shall perform periodically the IT activities at
appropriate stages to permit inspection such as dimension, NDT, visual,
performance test among other tasks in accordance with documented
procedures and guidelines describes in the IT plan. There shall be no random
IT allowed.
7.4.2
7.4.3
Receiving Inspection
7.4.2.1
7.4.2.2
7.4.2.3
In-process IT
7.4.3.1
7.4.3.2
Page 8 OF 10
7.4.4
7.4.5
Evaluate IT Record
7.4.4.1
7.4.4.2
Approval of IT Records
7.4.5.1
7.4.5.2
7.4.6
7.4.6.2
HOP to submit the approved IT report to the clients Focal point for
their further review and final approval.
P/N:
8.0
RECORDS
Records of Inspection & Testing Log shall be maintained by QMR for a period of 3 years
Page 9 OF 10
9.0
ATTACHMENTS:
Attachment 1
Attachment 2
Attachment 3
Attachment 4
Attachment 5
Attachment
Attachment
Attachment
Attachment
Attachment
Attachment
:
:
:
:
:
:
6
7
8
9
10
11
Attachment 12 :
Attachment 13 :
Attachment 14 :
ITP for Mechanical, Piping & Pipeline Work of Material Receiving, Storage
& Issuing Work
ITP for Welding Procedure Specification, Procedure Qualification and
Welder Qualification
ITP for Mechanical, Piping & Pipeline Work of Piping Fabrication &
Installation Work
ITP for Mechanical, Piping & Pipeline Work of Blasting, Painting, Wrapping
& Insulation Work
ITP for Mechanical, Piping & Pipeline Work of Mechanical Equipment
Installation
ITP for Mechanical, Piping & Pipeline Work of Pipe Laying Work
ITP for Instrument & Electrical Work of Above Ground Cable Laying Work
ITP for Instrument & Electrical Work of Underground Cable Laying Work
ITP for Instrument & Electrical Work of Termination of Cable
ITP for Instrument & Electrical Work of Equipment Installation
ITP for Instrument & Electrical Work of Loop Check & Precommissioning
Work
ITP for Instrument & Electrical Work of Calibration Work
ITP for Instrument & Electrical Work of Impulse Line and Air Tubing Work
ITP for Duplex Welding
2.
-END-
Page 10 OF 10