EE 868-Lab Assignment 2
EE 868-Lab Assignment 2
EE 868-Lab Assignment 2
1 Objective
In this laboratory you will use the PSCAD example case provided to study and verify the
following:
(a) Settings of the Time Overcurrent Relays.
(b) Verification of Primary, Backup Protection and their Coordination.
(b) Effect of CT saturation on the operating times.
2 Introduction
The case provided shows a 230 kV substation feeding a 33 kV radial distribution network.
Coordinated over-current (inverse time) relays at the breakers B12, B23 and B34 are used
to discriminate the faults at different locations and provide backup protection.
Bus 1
230 kV
Transformer
230/ 33 kV
Bus 2
33 kV
Bus 3
33 kV
Bus 4
33 kV
B12
Generator
Fault
P+jQ
Fault
P+jQ
Fault
P+jQ
You may recall that the settings of the time overcurrent relays are adjusted in such a way
that the breaker nearest to the fault is tripped in the shortest possible time, and then the
remaining breakers are tripped in succession using longer time delays, moving backwards
1
towards the source. We will use the following principle for coordinated operation of the
overcurrent relays:
For any relay X, backing up the next downstream relay Y, is that X must pick up
(a) For one third of the minimum fault current seen by Y and
(b) For the maximum fault current seen by Y but no sooner than 0.3 s after Y should
have picked up for that current.
All the relays in the PSCAD case provided use the IEC standard inverse current
characteristics and the curves are provided at the end of instruction sheet. As explained in
the class the inverse time relays can be adjusted by selecting two parameters- the pick-up
or the plug settings (tap settings) and the time dial settings (or time multiplier settings
TMS).
Laboratory Exercise
1. Bypass all relays using the bypass switches on the control panel. Record the
maximum fault currents seen at the Bus 2, 3 and 4. Use the timed fault logic to
apply the fault at 2.0s for a period longer than the simulation run to record the
fault currents. Keep the fault resistance at 0.001 .
2. Again bypass all relays using the bypass switches on the control panel and this
time apply line-line and line-to-ground permanent fault at Bus 2, 3 and 4. Record
the fault currents seen by the relays for the two types and note the minimum value
(note that the minimum fault currents are obtained for line-line or line-ground
faults). Use the timed fault logic to apply the fault at 2.0s for a period longer than
the simulation run to record the fault currents. Keep the fault resistance at 0.001
.
3. Use the obtained fault currents to determine the appropriate CT ratios and the
relay settings for the three breakers (follow the method that was explained to you
in the class).
Laboratory Exercise
1. Put all relays back into operation by reverting the position of the bypass switches.
Apply a solid permanent three-phase fault on Bus-4. Examine the fault current
values, primary relay operation and its operating time. Check whether the
operation of primary protection is as expected and according to your settings.
2. Repeat step 1 with fault resistance of 20 .
3. Repeat step 1 with A-B and A-G faults. Keep the fault resistance at 0.001 .
4. Remove the fault at Bus-4. Repeat step 1 for faults at Bus-3 and Bus-2.
5. Bypass the relay at breaker (B34) and apply a solid three-phase fault on Bus-4.
Examine whether the backup protection (B23) clears the fault. Record the
operating time of the backup relay and verify it with it with hand calculations
using the graph provided.
6. Bypass the relay at breaker (B23) and study the operation of backup protection
(relay at breaker B12) by applying a solid three-phase fault on Bus-3. Examine
whether the backup protection clears the fault. Record the operating time of the
backup relay.
3
4 Effect of CT Saturation
In this part of the laboratory we will briefly investigate the effect of CT saturation on the
operating times of the overcurrent relays. CT saturation strongly depends on the fault
current levels, CT secondary burden and the presence of dc offset currents in the
waveform, size of the CT core.
Laboratory Exercise
1. Revert all relays back into operation. Change the burden of the CTs of relay at
B34 to 5 . Apply a solid three-phase fault at Bus-4. Observe the primary and
secondary currents of the CT at B34. Observe the relay operating time and
compare with the values obtained in Section 3. Comment on your observation.
2. Change the fault type to an asymmetrical type of fault (A-G). Apply the fault at
2.0s and record the relay operating time. Repeat the simulation now with fault
applied at 2.0042 s and compare the relay operating time with the previous case.
Comment on your observation discuss with your instructor.
5 References
1. W.D. Stevenson, Elements of Power System Analysis, Fourth Ed., McGrawHill, 1989.
2. J.M. Gers, E.J. Holmes, Protection of Electricity Distribution Networks, 2nd Ed.,
The Institution of Electrical Engineers, 2004.
3. T. Davies, Protection of Industrial Power Systems, Pergamon Press, 1984.
4. Walter A. Elmore, Protective Relaying Theory and Applications, Second
Edition, Marcel Dekker Inc. (On-line book available through library), 2004.