EE 868-Lab Assignment 2

Download as pdf or txt
Download as pdf or txt
You are on page 1of 5
At a glance
Powered by AI
The key takeaways are to study and verify the settings of time overcurrent relays, coordination of primary and backup protection, and the effect of CT saturation on operating times using a PSCAD simulation case of a radial distribution network.

The objective is to study and verify the settings of the time overcurrent relays, coordination of primary and backup protection, and the effect of CT saturation on the operating times using a PSCAD simulation case provided.

The overcurrent relays are coordinated such that the breaker nearest to the fault trips first, followed by breakers further away in succession using longer time delays. Specifically, a backup relay X must pick up for 1/3 the minimum fault current seen by the next downstream relay Y and for the maximum fault current seen by Y, but no sooner than 0.3 seconds after Y should have picked up.

EE 868: Digital Techniques for Power System Protection

Laboratory Assignment #2 (Feb. 8 (12pm))


Overcurrent Relay Coordination
Rama Gokaraju
Department of Electrical & Computer Engineering
University of Saskatchewan

1 Objective
In this laboratory you will use the PSCAD example case provided to study and verify the
following:
(a) Settings of the Time Overcurrent Relays.
(b) Verification of Primary, Backup Protection and their Coordination.
(b) Effect of CT saturation on the operating times.

2 Introduction
The case provided shows a 230 kV substation feeding a 33 kV radial distribution network.
Coordinated over-current (inverse time) relays at the breakers B12, B23 and B34 are used
to discriminate the faults at different locations and provide backup protection.
Bus 1
230 kV

Transformer
230/ 33 kV

Bus 2
33 kV

Bus 3
33 kV

Bus 4
33 kV

Feeder line( 15 km)


B23

B12

Feeder line( 10 km)


B34

Generator
Fault

P+jQ

Fault

P+jQ

Fault

P+jQ

Figure 1: A radial distribution network.

You may recall that the settings of the time overcurrent relays are adjusted in such a way
that the breaker nearest to the fault is tripped in the shortest possible time, and then the
remaining breakers are tripped in succession using longer time delays, moving backwards
1

towards the source. We will use the following principle for coordinated operation of the
overcurrent relays:
For any relay X, backing up the next downstream relay Y, is that X must pick up
(a) For one third of the minimum fault current seen by Y and
(b) For the maximum fault current seen by Y but no sooner than 0.3 s after Y should
have picked up for that current.
All the relays in the PSCAD case provided use the IEC standard inverse current
characteristics and the curves are provided at the end of instruction sheet. As explained in
the class the inverse time relays can be adjusted by selecting two parameters- the pick-up
or the plug settings (tap settings) and the time dial settings (or time multiplier settings
TMS).

The pick-up settings


The pick-up settings are used to define the pick up current of the relay. For example, the
tap settings of the electromechanical overcurrent relay that was discussed in the class was
1.0, 1.2, 1.5, 2.0, 3.0, 4.0, 5.0, 6.0, 7.0, 8.0, 10.0, 12.0 A. We will use these discrete
values in the PSCAD simulation case provided as well. This way we can make a
comparison with the hand calculated values from the characteristic curves shown in the
graph paper. However, you should be aware of the fact that the modern relays are of the
digital type and the pick-up settings of IEC characteristics can be varied in a continuous
fashion.

Time dial settings


The time dial setting adjusts the time delay before the relay operates whenever the fault
current reaches a value equal to, or greater than, the relay current setting. In
electromechanical relays, the time delay is usually achieved by adjusting the physical
distance between the moving and fixed contacts, and is also specified as discrete settings.
In Figure 2, a time-dial setting of 0.1 produces the fastest operation of the relay, whereas
a setting of 1 produces the slowest operation for a given current. For digital relays,
similar to the pick-up settings, the time-dial settings can be used in a continuous fashion
but we will assume in this laboratory that the time multiplier settings are discrete.

3 Settings of the Time Overcurrent Relays


Study and familiarize with the PSCAD simulation case provided.

Laboratory Exercise
1. Bypass all relays using the bypass switches on the control panel. Record the
maximum fault currents seen at the Bus 2, 3 and 4. Use the timed fault logic to
apply the fault at 2.0s for a period longer than the simulation run to record the
fault currents. Keep the fault resistance at 0.001 .
2. Again bypass all relays using the bypass switches on the control panel and this
time apply line-line and line-to-ground permanent fault at Bus 2, 3 and 4. Record
the fault currents seen by the relays for the two types and note the minimum value
(note that the minimum fault currents are obtained for line-line or line-ground
faults). Use the timed fault logic to apply the fault at 2.0s for a period longer than
the simulation run to record the fault currents. Keep the fault resistance at 0.001
.
3. Use the obtained fault currents to determine the appropriate CT ratios and the
relay settings for the three breakers (follow the method that was explained to you
in the class).

4 Verification of Primary, Backup Protection, and their


Coordination
Apply the settings that you just determined to the CT models and the overcurrent relay
models in the simulation.

Laboratory Exercise
1. Put all relays back into operation by reverting the position of the bypass switches.
Apply a solid permanent three-phase fault on Bus-4. Examine the fault current
values, primary relay operation and its operating time. Check whether the
operation of primary protection is as expected and according to your settings.
2. Repeat step 1 with fault resistance of 20 .
3. Repeat step 1 with A-B and A-G faults. Keep the fault resistance at 0.001 .
4. Remove the fault at Bus-4. Repeat step 1 for faults at Bus-3 and Bus-2.
5. Bypass the relay at breaker (B34) and apply a solid three-phase fault on Bus-4.
Examine whether the backup protection (B23) clears the fault. Record the
operating time of the backup relay and verify it with it with hand calculations
using the graph provided.
6. Bypass the relay at breaker (B23) and study the operation of backup protection
(relay at breaker B12) by applying a solid three-phase fault on Bus-3. Examine
whether the backup protection clears the fault. Record the operating time of the
backup relay.
3

4 Effect of CT Saturation
In this part of the laboratory we will briefly investigate the effect of CT saturation on the
operating times of the overcurrent relays. CT saturation strongly depends on the fault
current levels, CT secondary burden and the presence of dc offset currents in the
waveform, size of the CT core.

Laboratory Exercise
1. Revert all relays back into operation. Change the burden of the CTs of relay at
B34 to 5 . Apply a solid three-phase fault at Bus-4. Observe the primary and
secondary currents of the CT at B34. Observe the relay operating time and
compare with the values obtained in Section 3. Comment on your observation.
2. Change the fault type to an asymmetrical type of fault (A-G). Apply the fault at
2.0s and record the relay operating time. Repeat the simulation now with fault
applied at 2.0042 s and compare the relay operating time with the previous case.
Comment on your observation discuss with your instructor.

5 References
1. W.D. Stevenson, Elements of Power System Analysis, Fourth Ed., McGrawHill, 1989.
2. J.M. Gers, E.J. Holmes, Protection of Electricity Distribution Networks, 2nd Ed.,
The Institution of Electrical Engineers, 2004.
3. T. Davies, Protection of Industrial Power Systems, Pergamon Press, 1984.
4. Walter A. Elmore, Protective Relaying Theory and Applications, Second
Edition, Marcel Dekker Inc. (On-line book available through library), 2004.

Figure 2: Characteristic curves of type IEC standard inverse overcurrent relays.

You might also like