Acr 2006
Acr 2006
ACR 2006
ACR 2006
Assessment, Cleaning, and Restoration
of HVAC Systems
An Industry Standard Developed by the
National Air Duct Cleaners Association
ACR 2006 Committee Roster
Bill Lundquist - Chairman
Terry Bray
Doug Groen
Brad Kuhlmann
Greg Long
Patrick ODonnell
Channing Starke
Project Management
Sufka & Associates, Inc.
Technical Editor
John Schulte
Published by
NADCA National Air Duct Cleaners Association
1518 K Street, NW, Suite 503
Washington, DC 20005
Copyright 2006 by NADCA
All rights reserved.
No part of this publication may be reproduced in any form
mechanical, electronic or otherwise - without the
prior written permission of the publisher.
Printed in the United States of America.
Page i
Notice
All questions or other communications relating to this document should be sent to NADCA Headquarters, addressed to
the attention of the Standards Committee Chairman. For the procedures to request that the NADCA Standards
Committee issue Formal Interpretations relating to the content of this document, use the form on the last page of this
document to write to the Standards Committee Chairman, National Air Duct Cleaners Association, 1518 K Street, N.W,
Suite 503, Washington DC 20005.
Page ii
Page iii
Page iv
Foreword
Assessment, Cleaning, and Restoration of HVAC Systems (ACR 2006) is an industry standard that has evolved from
guidelines, industry standards of care, and research originating from the National Air Duct Cleaners Association (NADCA)
along with other organizations dedicated to HVAC system hygiene, remediation and restoration. This standard
establishes criteria for evaluating the cleanliness of HVAC system components, and for cleaning and restoring systems to
a specific cleanliness level as described in Section 13.
ACR 2006 provides recommended inspection frequencies for HVAC systems. HVAC components that should be
evaluated during inspections are described to assist users of this standard in determining when cleaning may be
necessary.
In the assessment sections, ACR 2006 describes the areas of the HVAC system to be evaluated for contamination levels
and the types of contaminants identified. Assessment information may then be used to select appropriate safeguards
such as environmental engineering controls to protect the indoor environment during cleaning. The Guideline section of
this document provides examples of several types of containment engineering strategies that may be employed in
conjunction with an HVAC system cleaning project to control the migration of particulate, unwanted gasses, and vapors.
In the cleaning and restoration sections, ACR 2006 defines acceptable cleaning methods and criteria for cleaning tools
and equipment. Cleaning encompasses the removal of contaminants in order to restore HVAC systems to a specific
cleanliness level as described herein.
ACR 2006 addresses considerations for mold and biological contaminants and the cleaning of fiber glass insulation, duct
liner and duct board. This document also provides requirements for creating service openings within HVAC systems;
safety and health considerations for remediation workers, employees, and occupants; and procedures for monitoring
cleaning projects as they progress.
The Standard also provides methods to verify HVAC system cleanliness. Three separate methods are defined and
have been updated to address mold remediation clearance.
The term HVAC system cleaning is used exclusively throughout this document instead of the common term air duct
cleaning. The requirements of this document encompass the entire HVAC system and its components. To ensure
optimum system performance and environmental conditions, the entire HVAC system should be maintained at the highest
cleanliness levels possible and at an acceptable hygiene condition as described in this Standard.
A Note Regarding Service Openings
The National Air Duct Cleaners Association (NADCA) recognizes the need for service openings in HVAC system
components, including air ducts, to facilitate inspection and/or cleaning. NADCA has expanded ACR 2006 to define
minimum requirements for the proper construction and installation of service openings. This document should be cited in
Project Specifications for HVAC system cleaning projects to insure proper access and closure of system components.
In nearly all HVAC system cleaning projects, it will be necessary to make new service openings in duct walls in order to
insert cleaning and inspection equipment. The creation of service openings, and their subsequent closure, requires
craftsmanship and professional skills. Where possible, access to duct interiors should be made by dismantling the ducts
or through existing openings such as supply diffusers, return grilles, duct end caps, and existing service openings.
This Standard applies to the majority of HVAC systems, regardless of the type of duct construction. Service openings
created in any type of system component must meet or exceed the requirements defined herein.
There are two general types of service openings: removable duct access doors and permanent closure panels. Duct
access doors are designed so they can be re-opened without dismantling or altering the system. Permanent closure
panels are pieces of HVAC system material that are sealed and/or fastened permanently upon closure of the service
opening. Depending on the methods used to seal permanent closure panels, it may be possible to remove and re-install
them. Permanent closure panels sealed with gasketing may be removed and re-installed; whereas those closure panels
sealed with mastic or caulking should not be removed. If new service openings will be used in the future for inspection or
cleaning, then removable duct access doors may be most appropriate.
Page 1
The location and size of new service openings is heavily dependent upon the equipment and methodologies the HVAC
system cleaning contractor will use in the project. However, there are certain strategic locations in most systems where
service openings are made to facilitate inspection. Visual inspection of interior HVAC system surfaces is required as
noted in this Standard.
The most common locations for service openings in air ducts include:
Adjacent to turning vanes
Adjacent to dampers (balancing, fire, control, back draft, splitter, etc.)
Mixing & VAV boxes
Adjacent to in-duct electric heat strips
Duct transitions, offsets, and changes of direction
Adjacent to heating, reheat, & cooling coils
Adjacent to all other in-duct mechanical components & sensors
Each of these locations may require one or more service openings to properly access the ducts for cleaning and
inspection. The tools used in the installation of the new service openings should be industry-specific for the type(s) of
duct material and construction techniques commonly found in HVAC systems. Proper installation of new service openings
is dependent on the use of the right tool(s) by trained personnel. Nothing in this Standard is intended to prevent the use
of new methods, materials, or technologies in the installation and closure of service openings, provided that they meet the
requirements prescribed by this Standard.
Poorly constructed service openings may have a negative impact on the HVAC system. An air duct system, when
improperly altered, may compromise the systems structural integrity and fire-rating integrity. Improperly installed service
openings may act as a site for duct leakage. An improperly created or sealed service opening may affect indoor air quality
by serving as a conduit that can expose both the HVAC system and the indoor environment to contaminants. These
potential threats to the safety of the building and its occupants are just two of the reasons for this Standard.
In some areas, the creation of a service opening in an HVAC system may require special licensure from the state or
locality. Most state construction industries are regulated by a licensing board or commission authorized by the state
government, and such organizations should be contacted directly for information about a particular states requirements.
This Standard includes a new chapter in the appendix titled Guidelines for Constructing Service Openings in HVAC
Systems. The information provided in this chapter is intended as a guideline to assist in the further understanding of
HVAC service system opening construction methods, but its contents are not considered requirements under this
Standard unless specified below.
It is highly recommended users of this document consult applicable federal, state and local laws and regulations. NADCA
does not, by the publication of this document, intend to urge action that is not in compliance with applicable laws and this
document must never be construed as doing so. The most stringent requirements of this Standard and applicable federal,
state, and local regulation must apply to the assessment, cleaning, or restoration of HVAC systems. The disclaimer at the
conclusion of this document provides additional important information regarding use of this standard.
Page 2
Introduction
Maintaining clean heating, ventilation and air-conditioning
(HVAC) systems is an important part of sustaining
acceptable indoor air quality (IAQ). When an HVAC system
is a source of contaminants introduced into occupied
spaces, properly performed system cleaning services
should take place to reduce or eliminate contaminant
introduction.
ACR 2005, the third edition, went further than any previous
NADCA standard. It covered the same essential elements
of assessment and cleaning detailed in the previous
documents and also provides more detailed requirements
for managing HVAC system cleaning projects, including
clearly defined conditions that require cleaning. ACR 2005
was revised such that its requirements were in accordance
with the latest standard for mold remediation published by
the Institute of Inspection, Cleaning and Restoration
Certification (IICRC), S520 - Standard and Reference
Guide for Professional Mold Remediation. By working in
cooperation with representatives from IICRC and other
industry organizations to update the ACR standard, the
2005 edition was a standard that could be utilized not only
as a standard for professional HVAC system cleaning
contractors, but also as a comprehensive reference source
for consumers, facility administrators, engineers, mold
restoration contractors, general contractors, architects, or
HVAC project design consultants.
Page 3
General
1.1
Scope
Purpose
Application
Definitions
Page 4
Page 5
Page 6
Page 7
Page 8
Table 1
HVAC Cleanliness Inspection Schedule
(Recommended Intervals)
Building Use
Classification
(See Section 4.1)
Airhandling
Unit
Supply
ductwork
Return
ductwork
/ Exhaust
Industrial
1 year
1 year
1 year
Residential
1 year
2 years
2 years
Light Commercial
1 year
2 years
2 years
Commercial
1 year
2 years
2 years
Healthcare
1 year
1 year
1 year
Marine
1 year
2 years
2 years
3.2
3.2.1
AHU Inspections
Page 9
3.2.2
3.3.4
3.4
3.5
Page 10
Compromised Performance
4.1
Page 11
4.1.1
4.1.8
Industrial
Residential
Buildings classified as residential use include standalone homes, apartment buildings, and condominiums
where people reside.
4.1.3
Light Commercial
4.2
4.1.4.1 Restaurants
Healthcare
Marine
Commercial
4.1.5
Multi-use Buildings
4.2.1
Air-handling Units
Page 12
4.2.2
5.1
5.1.1
5.1.2
Page 13
5.2
5.3.1
Operational Condition
5.3.3
5.4.1
Temporary Controls
Page 14
5.7
5.5
Pressure Differentials
Page 15
5.8
Project Planning
5.9.1
5.8.1
5.10
5.11
Page 16
Table 2
Velocity Requirements for Contaminant Removal
Nature of
Contaminant
Examples
Design
Velocity
in fpm
25003000
30004000
Average
industrial dust
35004000
Heavy dusts
40004500
Collection Devices
6.1.2
Mechanical Agitation
6.1.3
Contact Vacuuming
Page 17
6.1.4
6.2.2
6.3
Service Openings
Component Cleaning
Duct Systems
7.1
Page 18
7.2
Coil Inspections
7.3.1
7.3
7.3.2
Page 19
8.1
Note: Cleaning methods and products must be pretested and determined not to cause damage to, or
erosion of, the coil surface or fins, and must conform
to coil manufacturer recommendations when
available. In order to limit damage to coils it is
recommended that only coil cleaning solutions that
are as close to ph neutral as possible are used. It is
highly recommended that coils be thoroughly rinsed
with fresh water in order to remove coil cleaner
residue from the coil surfaces.
8.2
Surface Treatments
Cleaning Methods
8.3.1
Page 20
9.2
9.2.1
Page 21
10.2
10.4
Flooding/Water-Damage
10.5
Fire/Smoke Damage
10
Page 22
11
Project Monitoring
13
12.1
Cleaning Contractors
11.1
Page 23
13
13.2
13.3
13.1
Page 24
13.3.1.4 Template
The template must be 15 mil thick (0.381 mm) and must
provide a 100 cm2 sampling area consisting of two 2 cm
x 25 cm slots at least 2.5 cm apart.
The standard size openings for the NADCA Vacuum
Test Template are 2 centimeters in width by 25
centimeters in length. At times, templates with slots of
this size may not fit in a space where testing is
necessary or desired. Slots of other sizes may be
utilized, subject to the specifications herein.
Page 25
14
14.1
Applicable Documents
14.2
General Requirements
14.1.2. UL Publications
Service openings shall not hinder, restrict, or alter the
airflow within the duct.
Page 26
Page 27
Reference Documents
Air Conditioning and Refrigeration Institute
ASTM International
E84-00a Standard Test Method for Surface Burning
Characteristics of Building Materials.
Guideline 01
Institute of Inspection, Cleaning and Restoration
Certification (IICRC)
Page 28
Page 29
Chapter 1
Protective Coverings Clean, protective coverings must be used within each work area. Protective
coverings must extend beyond the work area to provide protection of flooring, equipment, and furniture
whenever necessary.
Cleaning Equipment Inlet openings on all vacuum collection devices and negative air machines must
be properly sealed during transport and when the equipment is not in use. Vacuum hose openings must
be sealed during transport. All tools, equipment, and equipment components that enter the HVAC
system from an occupied space must be wet-wiped, HEPA vacuumed, or sealed in a disposable
polyethylene bag during removal from the HVAC system.
Cross Contamination Control Suitable provisions must be made to control contaminant discharge from
the HVAC system and cross contamination into occupied space during the cleaning process. This may
require temporary sealing of existing duct joints, seams and other system components.
Page 30
Work Above Ceilings Above ceiling work area must be completely isolated from occupied spaces
within containment barriers utilizing 6-mil fire retardant polyethylene sheeting or equivalent. These
barriers must be sealed airtight where they meet the ceiling, floor, and walls.
Containment Area Floor The containment must have a two-layer floor utilizing 6-mil fire retardant
polyethylene or equivalent. The floor material must extend at least 6 inches (15.2 centimeters) up the
containment side walls. The floor material must be sealed to side walls with two layers of duct tape in an
airtight manner.
Containment Area Access A vertical cut in the containment side wall must provide access into the
containment area. This vertical cut must begin no less than 6 inches (15.2 centimeters) from the floor
and must be at least 5 feet (1.5 meters) long. The entrance must be entirely covered by two flaps (one on
each side of the polyethylene).
Negative Pressure The containment area should be kept under negative pressure at all times to the
degree feasible. Negative pressure must be sufficient to prevent migration of particulate material out of
the containment area. Exhaust from the device providing negative pressure must be HEPA filtered. If
this device does not exhaust directly outdoors, it must be possible to verify that there is no leakage
through or around the HEPA filter.
Dismantling Interior surfaces of the containment enclosure must be wet-wiped or HEPA vacuumed
before moving or dismantling the containment enclosure.
Level 3 Containment - Work Area Containment with Single Chamber Decontamination Unit
Level 3 Containment may be applicable to HVAC system cleaning in buildings where severe cases of microbial
amplification or hazardous substances are known to exist within the HVAC system or indoor environment.
Level 3 Containment is commonly the level of containment appropriate to healthcare facility cleaning projects,
including those where microbial contamination may not exist. All of the Level 1 Containment and Level 2
Containment requirements apply to Level 3 Containment areas. In addition, the following protection actions are
required under Level 3 Containment strategies:
Page 31
the top and one side. The decontamination chamber must utilize double flaps for its opening to the nonwork area.
Monitoring Requirements Level 3 containment areas must be monitored for negative pressure on a
continuous basis by using an instrument sensitive enough to detect a loss of negative pressure.
Background monitoring for total particulate must be performed prior to set-up of containment to
establish baseline airborne total particulate concentrations. It is recommended that monitoring also be
conducted during set-up of containment. Real time monitoring for total particulate must be conducted
on a regular basis to ensure that particulate is not escaping the containment. If airborne particulate
levels exceed background levels, work must cease until airborne particulate levels are reduced to
background levels and the cause of problem is found and corrected.
Decontamination Facility A decontamination facility as described for a Level 3 Containment area must
be utilized, except that the decontamination facility must consist of two chambers. Each chamber must
be constructed according to the requirements described for a Level 3 Containment area.
Monitoring Requirements Monitoring requirements described for a Level 3 Containment area must
apply. In addition, the containment must have a constant recording pressurization monitor with an
alarm.
Equipment Redundancy
Loss of containment caused by equipment failure can be avoided or minimized by providing redundant
equipment. Equipment redundancy is required on projects taking place within healthcare facilities as well as on
projects where severe mold or biological growth or hazardous substances are known to exist within the HVAC
system. When equipment redundancy is specified by the project plan, the following criteria must apply:
Secondary equipment, which is equal or greater in capability, is to be staged on the production site
creating redundant operations to meet the engineering, safety and containment minimum requirements.
It is highly recommended that all secondary equipment meet or exceed the same requirements as the
primary equipment. All equipment specified for redundancy purposes will be in the same location as the
primary equipment and pre-tested for operation. Redundant equipment must be specified as either
concurrent operation or non-concurrent operation.
Under concurrent operation, the redundant equipment must be fully operational while the primary
equipment is functioning. Loss of either piece of equipment should not alter the containment,
engineering controls or safety protocols of the project to a point less than the minimum requirements.
Under non-concurrent operation, the redundant equipment is not required to be operational while the
primary equipment is functioning. The secondary equipment must be wired, contained, isolated, vented,
secured, and fully prepared for immediate operation if failure of the primary equipment occurs.
In cases where the redundant equipment is connected to an emergency power source, the building owner or
representative must approve the use of that power source.
Page 33
Chapter 2
Visual Observations of the HVAC system: The technician performing the procedure must observe the
air-conditioning system interior for settled debris, air by-pass at the air filter bank and air by-pass in the
return duct or equipment cabinet. The observations must be documented with notes and/or photo
images.
Particle Measurements: Particle measurements must be taken at the return air and supply air registers.
A laser particle counter that has the ability to enumerate individual particle sizes and show a printout of
the results must be used. The measurements must be plotted on a filter chart, which may be found in
applicable ASHRAE documents (i.e., MERV test or dust spot tests).
Page 34
Air Sampling: Air samples using a fungal spore trap must be taken from the ambient air (inside and
outside the building) and from the supply air. The fungal spore trap needs to be analyzed by a qualified
laboratory. The analysis should include, at minimum, the type and quantity of fungal spores, man-made
vitreous fibers (fibrous glass), and opaque particles.
Surface Sampling: Surface samples using sticky tape must be procured from locations inside the
HVAC system. A laboratory must determine if fungal germination is or has occurred by analyzing the
samples.
Air Temperature and Relative Humidity Readings: Temperature and humidity measurements must
be obtained indoors and compared to requirements set forth in ASHRAE Standard 55.
Location of the outdoor air ventilation must be properly accounted for when using the procedure. Detailed
requirements for the analytical procedures listed above are contained in the following sections.
Particle Measurements
Particle measurements should be taken using a 6-channel laser particle counter operating at a flow rate of 0.1
CFM.
Three (3) samples must be taken at the return air entering the air-handling unit. Samples must also be taken at
approximately 50% of the supply air outlets. For more aggressive sampling, one (1) sample should be procured
at a supply outlet during start up of the indoor fan, and one (1) sample should be taken while lightly tapping on
the side of the duct.
The particle size range to be studied includes the following: 0.3, 0.5, 0.7, 1.0, 2.0, and 5.0 micrometers (m).
The coincidence error is less than 5% at 2 x 106 particles/cu. ft.
The particle counter must be properly prepared before sampling occurs. The following actions must be
performed:
1.
2.
3.
4.
Check battery level to ensure unit does not become non-operational during sampling.
Program time and date to current settings.
Turn printer option on.
Turn machine on, attach purge filter, and run in concentration (CONCEN) mode for 1 minute. At
the end of 1 minute, print the particle count taken with the purge filter on and stop the unit.
5. Replace the purge filter with the sampling probe.
The laser particle counter should be zero counted and purged each day prior to use (the manufacturers
instructions should be followed for this procedure. The laser particle counter should be factory calibrated and
serviced in accordance with the manufacturers recommendations (once a year).
When performing the sampling, the following procedures must be followed in sequence:
1. Set unit to desired number of samples (enough for a representative sample).
Page 35
Supply Air
-1
Return Air
Once the calculations are completed, the data should be plotted on a modified ASHRAE filter efficiency
performance chart.
Air Sampling
Air sampling for fungal spores must be performed using spore trap sampling procedures and a fungal spore trap.
The pump used in this procedure must be operated at a properly calibrated flow rate as recommended by the
cassette manufacturer.
Prior to sampling, a field calibration should be performed using a standard calibrated rotometer (with a cassette
attached).
One (1) sample must be taken of the ambient indoor air. One (1) sample must be taken of the supply air. One
(1) sample must be taken of the return air.
The following sampling procedure must be followed:
1. The fungal spore trap should be attached to the pump and the inlet cover or seal tape removed.
2. The sampling pump/cassette should be placed in the appropriate location at the return air, supply
air and in the ambient air and operated for a period of time as recommended by the cassette
manufacturer or as required to obtain the necessary results. Supply air samples should be
obtained underneath a supply air vent in a manner that prevents mixing with ambient air, and
should be located in an air stream that is operating at the same approximate static pressure as the
pump discharge. Return samples should be obtained with the outside air accounted for in order to
provide a true representation of filter performance.
Page 36
Spores will be identified and enumerated within analytical limitations. Concentrations are reported in spores
per cubic meter. Analysis shall be by direct microscopic analysis by a qualified laboratory.
Surface Sampling
Surface samples must be taken to determine if fungal amplification is occurring within the HVAC system.
Samples must be taken using sticky tape mounted to a slide.
One (1) must be taken from the return duct. Two (2) samples must be taken from the air-handling unit. Two
(2) samples must be taken from the supply plenum, or supply duct (depending upon accessibility).
The following procedures must be followed when performing the sampling:
1. Technician should wear clean examination gloves during the handling of all components (slides and
tape).
2. The sticky tape should be impinged on the area to be sampled.
3. The tape should then be placed on a slide, properly labeled, and stored as not to cross-contaminate
the samples.
The presence of spores and/or hyphal elements will be identified by direct microscopic analysis by a qualified
laboratory.
Conclusions
The observations and data collected must be reviewed to determine if significant debris is present in the HVAC
system, or if a fungal reservoir or other undesired contaminant (which can significantly affect the quality of the
indoor air) exists in the HVAC system. Positive determinations indicate a need for cleaning. Likewise, if the
analytical data demonstrates the HVAC system is introducing unwanted contaminants at undesired or
unacceptable levels, then cleaning is necessary.
If temperature and humidity conditions exceed the ASHRAE acceptable range, this indicates the need for an
engineering study to correct deficiencies.
Page 37
Chapter 3
Page 38
Apply a bead of sealant or mastic around the opening and mechanically fasten the closure panel to the duct wall
with screws 4" O.C. Ensure that there are no breaks in the sealant. If an approved tape is to be used to seal the
closure panel, rather than a sealant, the tape should be applied after the installation of the mechanical fasteners.
Drilled 1" service openings shall be closed with materials having a flame-spread rating of not over 25 without
evidence of continued progressive combustion and a smoke-developed rating of not over 50. Any exposed
fibrous glass edges within the duct should be sealed with no breaks or gaps in the insulation.
Opening and Closing Fibrous Glass Ducts
If the opening is to be less than the full height of the duct, the service openings should be made using either a
straight knife or a shiplap tool to cut a converging 45 degree angle on all four sides. If the opening is to be full
height, determine which of the longitudinal joints (top or bottom) will serve as the hinge for the opening.
Make converging 45 degree cuts along the remaining three sides. This section of the duct can either be lifted up
or dropped down out of the way, dependent on the location of the cut. Along the corners of the duct the cuts
should only be made through the facing of the duct.
Before re-installing the original section of duct, apply an approved ductliner adhesive meeting ASTM C 916
requirements to all cut edges of the section and the opening. Re-install the section to its original position. Seal
all sides of the original cuts with approved closure methods and materials. If tape is to be used it shall meet the
criteria of UL181A, part I or II, for fiber glass ductboard. The ductboard surfaces to which the tape will be
applied must be clean and dry. Dust, dirt, oil, grease, and moisture may result in bonding failure. Follow the
tape manufacturers recommendations.
Opening & Closing Flexible Ducts
Due to the nature of flexible ducting it is not possible or feasible to install service openings in it. The
recommended methods of accessing flexible ducts are as follows:
(1) Disconnect either or both ends of the flexible duct from the duct plenum or trunklines, the
equipment, the grilles, or the registers. Upon completion of the cleaning/inspection, re-connect the flex
duct to the metal collar with plastic closure straps or metal hose clamps. Seal the connection with tape
compliant with UL 181B, Part I, or mastic compliant with UL 181B, Part II. Check for local compliance
as codes vary from state-to-state.
(2) Cut cleanly through the flexible duct to produce two separate openings for inspection/cleaning.
Upon completion, insert the properly sized sheet metal connecting sleeve and reconnect the two ends.
Complete the closure as in (1) above.
(3) When replacing flexible ductwork, it is required that contractors follow all manufacturers
instructions for proper installation.
Page 39
Important Information
The guidelines shown above are not necessarily inclusive of all methods of service opening construction. The
provisions of this Standard are not intended to prevent the use of any material, method or system not
specifically addressed herein, provided that such material, method, or system meets the flame and smoke
criteria of this Standard and all other criteria of locally adopted codes.
No matter the type of duct construction, it is important that service openings be constructed in a manner that
facilitates a proper closure that meets the requirements set forth in the above Standard.
Contractors inexperienced in the actual physical creation of service openings are recommended to seek
professional training prior to attempting any procedures described herein.
Page 40
Chapter 4
Japan
Japan Air Duct Cleaners Association (JADCA)
JADCA Publications
The Actual State and the Cleaning Management of the Duct System, 1992.
The Guide to Cleaning and Management of the Kitchen Exhaust Duct System, 1995.
JADCA-04 Field Investigation on the Effects of Duct Cleaning on Indoor Air Quality with Measured
Results of TVOC and Perceived Air Quality, 1997.
Related Laws in Japan
Ministry of Health and Welfare, The Laws for Maintenance of Sanitation in Buildings, 1970.
Sweden
Checking the Performance of Ventilation Systems, The Swedish National Board of Housing, Building
and Planning. General Guidelines 1992:3E.
United Kingdom
Page 41
Page 42
DISCLAIMER
The Standards Committee of the National Air Duct Cleaners Association (NADCA) developed NADCA ACR 2006. It is
intended to establish the minimally acceptable criteria for Heating, Ventilation and Air Conditioning (HVAC) hygiene
assessments, project design, cleaning, and verification. This standard is based on the collective experience of members
of the industry, but is not intended to be either exhaustive or inclusive of all pertinent requirements. The information
provided in this standard is offered in good faith and believed to be reliable, but is made WITHOUT WARRANTY,
EXPRESSED OR IMPLIED, AS TO THE MERCHANTABILITY, FITNESS FOR A PARTICULAR PURPOSE, OR ANY
OTHER MATTER.
The provisions are not intended to be directed to any particular product or contractor, nor are they claimed to satisfy all
current legal, health and safety, or performance requirements related to contractual relationships for Heating, Ventilation
and Air Conditioning (HVAC) system cleaning projects. Following this standard does not guarantee compliance with any
regulation, nor safe, satisfactory, or complete performance of HVAC system cleaning. Users are cautioned that the
existing HVAC system design, installation, maintenance history, building design, occupancy and maintenance play a
significant role in managing indoor air quality. Thus, users of this document should understand the limitations with use of
this document in an attempt to mitigate indoor environmental problems. The information upon which this standard is
based is subject to change, which may invalidate any or all of the information contained herein.
NADCA, its members and contributors do not assume any responsibility for the users compliance with any applicable
laws and regulations, nor for any persons relying on the information contained in this standard. NADCA does not endorse
proprietary products, methods, or individual HVAC system cleaning companies.
It should be noted that this standard does not specifically address the protocols for service when potentially hazardous,
regulated materials are likely to be present in HVAC systems. Such potentially hazardous, regulated materials include, but
are not limited to, asbestos, lead and other chemical and biological contaminants. This standard does not address such
situations for two reasons. First, the worker safety and public safety aspects of operations involving hazardous materials
are, in many cases, governed by legal requirements imposed by the Occupational Safety and Health Administration, the
United States Environmental Protection Agency and various state and local agencies. Second, unless HVAC system
cleaners are engaged specifically to perform hazardous material decontamination, the building owner and/or occupant
should bear responsibility for any consequences of encountering unexpected hazardous materials.
Page 43
____________________________________________
Signature (required)
Page 44