Detergent Flushing of Pre Boiler System-Procedure 250
Detergent Flushing of Pre Boiler System-Procedure 250
Detergent Flushing of Pre Boiler System-Procedure 250
(4X250 MW)
Page 1 of 11
CONTENTS
1.
GENERAL
2.
PREPARATION
3.
PROCEDURE
4.
5.
6.
7.
COMPLITION CRITERIA
8.
Signatures
JPL
BHEL
JPL RAIGARH
(4X250 MW)
Page 2 of 11
1.0.0.
GENERAL
In order to achieve trouble free, continuous operation of the power
plant and also to maintain the water quality during the initial operation
of the plant, it is very important that all the systems carrying DM
water from condenser to boiler drum, must be cleaned thoroughly to
remove dirt, oil, grease etc. or else presence of these undesirable
matter will contaminate the system. For achieving the cleanliness, the
detergent flushing by using the chemical EXTRAN MA01 is carried
out in the pre boiler system consisting of Feed water system,
Condensate system and the Heaters drip system.
2.0.0.
PREPARATIONS
Prier to starting the detergent cleaning, the pre-boiler system , i.e.
feed water system, condensate system and drip system is prepared
for its completeness and temporary lines/looping connections etc. as
described in the following manner;
2.1.0.
2.2.0.
Signatures
JPL
BHEL
JPL RAIGARH
(4X250 MW)
Page 3 of 11
2.3.0.
Remove all safety valves and provide blanks on the stubs on the
following;
2.3.1.
2.3.2.
2.3.3.
Deaerator.
2.4.0.
2.5.0.
2.6.0.
2.7.0.
2.8.0.
Close tight all the gate valves of the steam extraction lines to heaters.
Ensure that all the NRVs in these lines are also closed. Open the
drains before these NRVs in atmosphere and observe for any
passing (during flushing operation ) . it should be ensured that
detergent solution does not enter the turbine, condenser, heaters,
3
Signatures
JPL
BHEL
JPL RAIGARH
(4X250 MW)
Page 4 of 11
2.9.1
2.9.2
2.9.3
2.9.4
2.10.0
Make sure that all the chemicals and laboratory reagents and
apparatus for testing the samples, are available.
2.11.0
2.12.0
2.13.0
2.14.0
Signatures
JPL
BHEL
JPL RAIGARH
(4X250 MW)
Page 5 of 11
2.15.0
2.16.0
2.17.0
2.18.0
2.19.0
3.0.0.
PROCEDURE
3.1.0.
Signatures
JPL
BHEL
JPL RAIGARH
(4X250 MW)
Page 6 of 11
3.2.0.
MASS FLUSHING.
3.2.1.
3.2.2.
Again fill the system with DM water and establish the circulation.
Samples at inlet & outlet may be taken and compared visually and
analyzed. The process of mass flushing is deemed to be complete
when the turbidity and conductivity of water at system inlet and
system return are same. Drain the complete system.
3.3.0.
DETERGENT FLUSHING:
3.3.1 Fill the system completely with DM water. Keep the system on
circulation and add the alkaline detergent (EXTRAN MA 01) to
obtain the concentration of 0.5%. Circulation is continued and all the
loops are included in the circulation one by one suitably operating
the respective valves. During the process, the samples may be
analyzed for oil content and pH only which should get stabilized at
system inlet and system outlet by the time detergent flushing is
declared completed. The detergent flushing is, in fact, time bound
process. The duration of circulation in each circuit can be from half
to one and half hours depending upon the length of the circuit. After
the detergent flushing is completed, drain the system completely. For
6
Signatures
JPL
BHEL
JPL RAIGARH
(4X250 MW)
Page 7 of 11
the disposal of the detergent, only the dilution with water is required.
As such, the detergent is bio-degradable.
3.4.0.
RINSING OPERATION
Fill the mixing tank with DM water. Start the flushing pumps and fill
the system, keep the loop on circulation for 15 to 20 min. Then open
the drain by a little amount. Make up the level in the mixing tank by
DM water. Try to drain max. Qty. of water from the system
continuously throughout the operation. The samples are taken at
outlet and inlet at the interval of hour, and analyzed for pH. The
rinsing process is deemed to be complete when the pH values are
same at outlet and at the inlet. Drain the complete system.
3.5.0 All the drain valves in the system stand pipes etc should be opened for a
while during and after each flushing to ensure removal of any
blockage.
3.5.1.
3.5.2.
4.0.0.
10.1.0.
Signatures
JPL
BHEL
JPL RAIGARH
(4X250 MW)
Page 8 of 11
Mixing tank, mixing pump-point near Eco NRV- feed control station
(one
line at a time) bypass of HP heater 6-bypass of HP heater
5 BFP discharge line, suction line- booster pump, suction line-FST,
second BFPSuction line through its BP suction line. Back to mixing tank.
Afterwards through recirculation and through HP heater coil side to
be included.
4.2.2.
4.2.3.
4.2.4.
Signatures
JPL
BHEL
JPL RAIGARH
(4X250 MW)
Page 9 of 11
5.1.0.
5.2.0.
Remove the temporary lines of the system with the mixing tank and
mixing pumps.
5.3.0.
Make and check that all the pipelines and connections are normalized
as per the final scheme of the normal operation.
5.4.0.
Open the manhole of deaerator / FST and inspect it from inside for
foreign substance and clean thoroughly. Box up after inspection.
6.0.0.
SAFETY PRECAUTIONS
6.1.0.
Ensure that the safety procedures for Alkaline flushing of the Preboiler System are followed.
6.2.0.
Signatures
JPL
BHEL
JPL RAIGARH
(4X250 MW)
Page 10 of 11
6.3.0.
6.4.0.
7.0.0.
COMPLITION CRITERIA
7.1.0.
Samples at inlet & outlet are compared visually before declaring the
Mass flushing complete. Turbidity of the samples should be the
same.
7.2.0.
7.3.0.
10
Signatures
JPL
BHEL
JPL RAIGARH
(4X250 MW)
Page 11 of 11
8.0.0.
REQUREMENTS OF MATERIALS
1.
D. M. Water
3000 MT
2.
Detergent EXTRAN MA 01
2000 Lits
3.
4.
2 Nos.
5.
7 Nos.
6.
Sampling Bottles
12 Nos.
7.
Mixing Tank
20 T capacity.
8.
As per schematic
requirement.
11
Signatures
JPL
BHEL