Gorgon Project
Downstream Execution Overview
W. Scott Young
Gorgon Development Director
25 September 2012
2012 Chevron
Gorgon Project Downstream Overview
Gorgon Project Barrow Island
Infrastructure Scope
Shore Crossing
Logistics base
Materials
Offloading Facility
Operations
Facilities
LNG Jetty
LNG Plant Site
Construction
Village
Airport
2012 Chevron
Gorgon Project Downstream Overview
Gorgon Project
Scope
3 x 5.2 million tons per annum (MTPA)
LNG processing trains
20,000 barrels per day condensate
Domestic gas plant with
capacity of 275 mmscf/d
2 x 180,000 m3 LNG tanks
4 x 240,000 barrels condensate tanks
5 x 118 MW gas turbine
power generation units
5,500 bed construction accommodation
2012 Chevron
Gorgon Project Downstream Overview
Gorgon Project
LNG Plant Technology and Design
Technology proven and reliable
Air Products and Chemicals Incorporated (APCI) liquefaction technology selected
BASF was selected for Acid Gas Removal technology
Aker Process Systems was selected to provide MEG system for hydrate inhibition
Design and constructability
Designed for long term reliability, availability, operability and safety
Modularization approach was taken to minimise on-island work, reduce construction footprint and to
move work to a world class fabrication facility
Train Capacity
Engineering models using data from actual purchased equipment and string testing of selected major
elements has confirmed throughput of 5.2 MTPA per train
2012 Chevron
Gorgon Project Downstream Overview
Gorgon Project
LNG Loading Terminal
1.8 miles of shipping channel
(46 feet depth, 210 million feet3 of material dredged)
1.3 miles long Materials Offloading Facility (MOF)
and Causeway
1.3 miles long LNG Jetty, with two loading berths
LNG jetty
2012 Chevron
Gorgon Project Downstream Overview
Gorgon Project Downstream
Engineering, Procurement and Construction Management
Kellogg Joint Venture Gorgon (KJVG) selected as
Engineering, Procurement and Construction Management
contractor
KJVG was formed in consortium with KBR, Japan Gas
Corporation, Hatch Engineering and Clough
- Bringing local and global expertise
- Proven track record
- Demonstrated ability to attract and retain the right people
with the right skill sets
- Proven track record in their areas of specialization
Design and engineering completed in London
and high value engineering centers in Asia
Procurement managed from London
Construction contracts managed from Perth
2012 Chevron
Gorgon Project Downstream Overview
Gorgon Project
Proven Downstream Construction Contractors
Overall scope too large for any single contractor
strategy to divide into manageable scope
Extensive contractor pre-qualification exercise:
- Financial capability
- Demonstrated track record in safe and predictable performance
- Local content
Develop work scopes to:
- Reduce contractor interfaces
- Target top performing contractors
- Allow consortium and joint ventures
Leverage Chevron International Master Agreements
2012 Chevron
Gorgon Project Downstream Overview
Gorgon Project
Construction Contractor Selection
Sample of major contracting entities delivering Gorgons Downstream scope
2012 Chevron
Gorgon Project Downstream Overview
Gorgon Project
Modularization Downstream Fabrication Status
2012 Chevron
Gorgon Project Downstream Overview
Gorgon Project
Modularization Equipment Modules Fabrication, South Korea
Total Weight =
200,000 tons
Total of 51 equipment based
modules
First two modules delivered to Barrow Island
Remaining 49 to arrive over next 18 months
Range in size from
1,000 to 7,000 tons
2012 Chevron
LNG process module
Gorgon Project Downstream Overview
10
Gorgon Project
Modularization Pipe Racks Pre-Assembled, China and Indonesia
Total of 40 pre-assembled pipe rack modules delivered
196 remaining to be delivered
Total of 236 pre-assembled pipe
rack modules, 71,000 tons
In transit to Barrow Island
2012 Chevron
Gorgon Project Downstream Overview
11
Gorgon Project Barrow Island
Preparing the Site
LNG plant site looking towards jetty
Plant site equal to length of 65 football
fields from inlet to jetty head (4.5 miles)
Design concept utilized cut and fill process
Volume of Excavations (173 million cubic
feet)
Remainder for roads and Materials
Offloading Facility
Site preparation complete
2012 Chevron
Gorgon Project Downstream Overview
12
Gorgon Project Barrow Island
Installation and Integration
2012 Chevron
Gorgon Project Downstream Overview
13
Gorgon Project
Downstream Achievements
Completed dredging program
Completed dredging program
plant
preparation
Foundation
Foundation plant
sitesite
preparation
Expansion of marine logistic bases
Expansion of marine logistic bases
Engineering complete and all major equipment ordered
Engineering complete and all major equipment ordered
Successful dredging program
2012 Chevron
Gorgon Project Downstream Overview
14
Gorgon Project
Year-to-date Milestones
Materials offloading facility fully
operational
Five pre-assembled rack (PAR)
module shipments delivered to
Barrow Island
-
40 of 236 PARs on-site
Raised first LNG tank roof
First process module shipment
delivered to Barrow Island
First LNG process module delivered to Barrow Island
2012 Chevron
Gorgon Project Downstream Overview
15
Gorgon Project
Update Video
2012 Chevron
Gorgon Project Downstream Overview
16
Gorgon Project
Implementing Lessons Learned
Lessons learned highlights:
Last Planner process to achieve
maximum productivity during construction,
testing and commissioning (Escravos GTL)
Pre-commissioning - Onshore Pipeline
Systems to avoid substantial delays in the
pre-commissioning of hydraulic power
systems (Sakhalin LNG)
Gorgons Fault-free Start-up Initiative
ensures cleanliness, tightness and integrity
of pipes (Pearl GTL)
2012 Chevron
Gorgon Project Downstream Overview
Escravos Gas to Liquids plant site, Nigeria
17
Gorgon Project
Future Milestones
Gas Turbine Generator fabrication in Avenza, Italy
2012 (Oct - Dec)
Roof raising on second LNG tank
Arrival of first gas turbine generator
module
Start mixed refrigerant compressor
installation
2013
All Train 1 modules on site
LNG jetty ready for commissioning
Domestic gas pipeline complete
2012 Chevron
Gorgon Project Downstream Overview
18
2012 Chevron
Gorgon Project Downstream Overview
19