MGN 388 - Fitting of Fall Preventer Devices
MGN 388 - Fitting of Fall Preventer Devices
MGN 388 - Fitting of Fall Preventer Devices
PLEASE NOTE: Where this document provides guidance on the law it should not be regarded as definitive.
The way the law applies to any particular case can vary according to circumstances - for
example, from vessel to vessel and you should consider seeking independent legal advice if
you are unsure of your own legal position.
Summary
Although on load release systems fitted to lifeboats are safe if operated and
maintained properly, there have been a number of accidents during drills and
servicing.
Fall Preventer Devices can be either pins or strops fitted to on-load release hooks to
prevent the lifeboat from falling to the water in the event of an equipment failure.
This notice is only applicable to davit-launched lifeboats fitted with on-load release
hooks.
-1-
1.
Background
1.1
In 1986, on-load release hooks for lifeboats and rescue boats were made mandatory
by SOLAS, in response to Norways worst offshore accident in March 1980. The Alexander
Kielland platform in the North Sea Ekofisk field capsized killing, 123 of the 212 persons on
board. These new SOLAS requirements were considered an important step forward in lifeboat
design.
1.2
Some deaths in this accident were attributed to the fact that the lifeboat had no means
of release when the weight of the lifeboat was on the hooks and falls. Therefore, on-load
release systems were seen to offer benefits.
1.3
Since 1986 when the IMO requirements for all new ships to be fitted with on-load
release systems came into place there have been a number of serious accidents during drills
and servicing.
1.4
Many of these accidents were attributed to lack of maintenance, poor design or
inadequate training. Failures of equipment can result in the premature opening of the on-load
hook mechanism, causing the lifeboat to fall from the davits unexpectedly even with three
safety interlocks provided for in the design arrangements.
1.5
A number of current designs of on-load release hooks can be described as unstable, in
that they are designed to open under the effect of the lifeboats own weight and often need to
be held closed by the operating mechanism. This means that any defects or faults in the
operating mechanism, errors by the crew or incorrect resetting of the hook after being
previously operated can result in premature release.
1.6
A Fall Preventer Device (FPD) can be used to minimise risk of injury or death in the
event of the failure of the on-load hook or its release mechanism, or by accidental release of
the on-load hook.
1.7
The use of FPDs should be considered as an interim measure to allow time for new
hook design criteria to be agreed at IMO.
2.
2.1
Type approval
-2-
MED equipment approved by a Nominated Body or the MSA as detailed in MSN 1735, the
MCA should be contacted for advice.
2.2
2.2.1 The system, including FPD should be verified at the initial survey for a new ship or an
equivalent survey for an existing ship if equipment is changed or modified. This is to ensure
that the installed system with the FPD fitted functions correctly.
2.2.2 The operation and design of FPDs fitted to a ship must be accepted by the MCA or a
Recognised Organisation appointed by them taking into account the guidance provided in this
document.
2.3
Modification of existing type approved on-load hooks already fitted to a ship to
incorporate a FPD
2.3.1 The MCA should be contacted for advice/agreement before any modification is made to
the hook, lifeboat or davit. Any re-testing of any equipment must be agreed and witnessed by
the MCA or a Recognised Organisation appointed by them.
2.3.2 The re-testing of an on-load release hook, where modified to incorporate a pin, should
include a static proof load test of at least 2.2 times the maximum working load to the
satisfaction of the MCA or Recognised Organisation appointed by it. It should be noted that
this test cannot be conducted using the lifeboat and davit as the winch is only designed for a
test load of 1.5 times the SWL for the winch capacity. This test must therefore be conducted
with the lifeboat hooks removed from the lifeboat.
2.3.3 Any fixed structural connections must be designed with a calculated factor of safety of
6 based on the ultimate strength of the materials used, assuming that the mass of the lifeboat
is equally distributed between the falls.
2.3.4 If modifications are made to any type approved component, the system should be
tested by conducting the five yearly lifeboat test contained in SOLAS chapter III Regulation
20.11.
2.4
Replacement of an existing on-load release system with an alternative approved
system that incorporates a FPD
2.4.1 If a ship intends to replace its existing lifeboat release gear with a new system that
incorporates a FPD to provide an enhanced level of safety and that system was not fitted as
original equipment to the lifeboat, the MCA must be contacted for advice/agreement before
any changes are made to the system. The original prototype approval testing of the lifeboat
and the attachment of fitting, such as the on-load hook, are tested as a single unit and
changes to one part may influence the structural integrity or operation of another.
2.4.2 The original lifeboat prototype approval certificate will detail the type of on-load hook
that is fitted. This should not prevent the hook being changed for an on-load hook that has fall
prevention or fail safe capability provided it can be demonstrated to the MCA or Recognised
Organisation that the arrangements are equivalent.
2.4.3 Where the on-load hook system is replaced it must be verified to the satisfaction of the
MCA or a Recognised Organisation appointed by it that the structural attachment points to the
lifeboat are of an equivalent strength and the system functions correctly. The type and level of
verification will depend on the replacement hook, its associated control mechanism and the
number and type of modifications made to the lifeboat.
-3-
2.4.4 If a type approved component is changed the system should be tested by conducting
the five yearly lifeboat test contained in SOLAS chapter III Regulation 20.11.
2.4.5 It should be noted that under both SOLAS and the MED, the lifeboat, release gear and
davit are type approved separately and each part of the system will have its own type approval
certificate before it is installed in the lifeboat. Replacement equipment must be MED/SOLAS
approved.
2.4.6 Designs of on-load release mechanisms fitted with pins acting as a FPDs that are
already type approved under the MED do not require re-testing. However, any operational
procedures should be agreed by the MCA, or a Recognised Organisation appointed by them,
and included in the ships ISM documentation.
3.
3.1
The following points should be considered when utilising locking pins as FPDs;
.1
Existing on-load release hooks fitted to ships must not be modified by drilling to
provide a locking pin insertion point as this may significantly reduce the strength
of the hook. Any modifications must be agreed as detailed in section 2 above,
.2
locking pins should have clear operational instructions located nearby the
insertion point of the locking pin and be colour coded so that it is clear where
the pins are to be inserted,
.3
.4
a strict procedure for removal of the locking pin must be in place to prevent the
locking pin being left in the hook before the boat is released in an on-load
condition. If the hooks are operated in an on-load condition, with the pins still
in, it will not be possible to release the boat until there is no weight on the falls
thereby losing on-load release capability,
.5
the removal of the pin should be achievable quickly and easily without posing
any risk to the seafarer designated to carry out the task once the lifeboat has
reached the water,
.6
if the removal of the pins requires opening of the lifeboat hatch it should be
readily achievable by a person at each device from within the craft,
3.2
The following points should be considered when synthetic strops or slings are used as FPDs;
.1
Where FPDs are synthetic strops or slings and no modifications are required to
the lifeboat, the on-load release hook or launching equipment, a functional test
should be carried out. The functional test should demonstrate to the MCA or the
Recognised Organisation appointed by it that the equipment performs without
interfering in the operation of the lifeboat or launching equipment. Once the
functional test has been conducted to verify that the system works and a snatch
load has been applied to the strops, they should be replaced with new strops or
slings. Strops or slings should be resilient fibre in construction. Wires or chains
are unacceptable, as they do not absorb shock loads.
-4-
3.3
.2
.3
.4
The release of the strops or slings should be achievable quickly and easily
without posing any risk to the seaman designated to carry out the task once the
lifeboat has reached the water. If the release of the strops or slings requires
opening of the lifeboat hatch it should be readily achievable by a person at each
device from within the craft. Once detached the strops or slings must not
interfere with the operation of the on-load release gear or the propeller.
.5
Once the recovery stage of the operation is underway and the on-load release
hooks are connected to the lifeboat, the strops or slings must be reattached to
the lifeboat before the boat is hoisted clear of the water. The strops or slings
must be designed so that they do not interfere with either the lifting or restowing of the lifeboat into the davits.
.6
A strop or sling used as a FPD should be arranged to allow the transfer of load
from the hook mechanism to the strop with minimal movement (drop) of the
boat in the event of a release mechanism failure. Should a fall preventer strop
or sling be subject to an unintentional dynamic shock loading then the strop or
sling should be replaced and the associated attachment points inspected. In
such cases, the MCA must be informed as soon as possible and the Master
should provide a full report of the circumstances of the incident.
.7
Fall preventer strops or sling must not be used for any other purpose and
should be fitted to the lifeboat at all times or stowed so that they are readily
accessible.
Lifeboat and hook design to incorporate FPD
Lifeboat and release gear manufacturers and designers are encouraged to consider the design
of both the lifeboat and hook so that FPDs can be released from inside the boat. The
possibility of modifying existing boats and hooks so that FPDs can be released from within
the boat should be considered. This is particularly relevant to FPDs fitted to oil, gas and
chemical tankers. A pragmatic approach should be taken by all stakeholders to allow
equipment to be upgraded so that FPDs can be fitted to existing equipment.
4.
4.1
The ships Master or the officer in charge of any lifeboat lowering or lifting operation
should ensure that the lifeboat FPD are fitted before commencing any drill, testing,
inspection or maintenance where persons are in the lifeboat, unless the lifeboat has
either an off-load hook system or has been approved to be used without a FPD.
-5-
4.2
The ships crew must be fully trained in the operation of the FPD fitted to the lifeboat
on their ship. The procedure to be followed should be contained in ISM documentation
and ships training manual.
4.3
It should be taken into account that with certain types of ship such as oil, gas or
chemical tankers it may not be possible to use a FPD in an abandon ship situation
where the release mechanism of the device is not inside the lifeboat. Those conducting
training drills and drafting ISM procedures must consider this. Where a different
procedure is followed during routine drills compared with an abandon ship situation this
should be clearly described in the ISM documentation and training manual.
4.4
SOLAS Chapter III Regulation 20.6.3 requires that at sea, lifeboats, except freefall
lifeboats, on cargo ships shall be moved from their stowed position, without any
persons on-board, to the extent necessary to demonstrate satisfactory operation of the
launching appliances, if weather and sea conditions allow.
4.5
The use of a FPD is currently not mandatory in SOLAS, however this document must
be taken into account before a lifeboat is used for training, maintenance or servicing.
Reference should also be made to SOLAS Chapter III regulation 19 and MSC.1/Circ.
1206 Annex 2.
4.6
If any on-load release hook is subject to a premature or unintentional release, the MCA
must be informed as soon as possible and the Master should provide a full report of the
circumstances of the incident.
4.7
The following points should be considered when conducting drills, testing, inspections,
or maintenance of lifeboats and launching appliances:
.1
the officer in charge of the lowering operations should verify the correct fitting of
the FPDs before the lifeboat is boarded and any davit harbour pins or gripes
are removed. Where possible the FPDs should be readily visible by the officer
in charge, persons inside the lifeboat and the person at the winch controls;
.2
.3
before removing any securing devices the on-load release systems should be
inspected to ensure that the hooks are properly locked;
.4
there should be clear visual indication to the coxswain of the lifeboat that the
FPD is fitted, this may be achieved by the use of placards at the coxswains
position and/or hook;
.5
.6
on recovery, the lifeboat should be re-connected to the falls and the FPD reconnected. The lifeboat should then be lifted just clear of the water and the onload release mechanism checked paying particular attention to ensure that the
interlock has reset and the hooks are properly locked. Once confirmed,
recovery to embarkation deck or stowage position can be continued. When the
lifeboat is recovered it should be stowed and checked that all is ready for
emergency operation.
-6-
5.
5.1
6.
.1
where the lifeboat is lowered to the water without persons onboard for drills,
testing inspections or maintenance the lifeboat should not be boarded by the
shipside embarkation ladder. In exceptional circumstances where this cannot
be avoided, adequate measures must be been taken to ensure that persons
boarding the lifeboat cannot fall from the ladder;
.2
if there is any doubt as to the safety of boarding by a ship-side ladder and the
lifeboat can not be boarded as described below, then the drill or inspection
should continue as far as practicable so that the davit sheaves, winches and
brakes can be examined to verify that the equipment is operating correctly. If
the drill cannot be completed the ships Master should make an appropriate
entry in the official logbook;
.3
where a FPD is not fitted consideration should be given to the use of shoreside facilities such as a hired boat to board the lifeboat safely once it is afloat;
.4
6.1
Shore-based training that includes a practical abandon ship exercise and the
participation of students to demonstrate the use and operation of on-load release systems
should use FPDs for such training exercises. In comparison with the industry, shore based
training establishments have a good record of minimal accident statistics when launching and
recovering survival craft, due to enhanced training, maintenance and procedural control. As
there is now a clear recognition that FPDs are routinely used at sea, then it is important that
they are included during shore-based survival craft training.
6.2
Shore based practical training should, as is currently the case, simulate an abandon
ship scenario as closely as possible. Historically, training establishments have delivered
training that followed equipment manufacturers guidelines. This training has replicated the
simple procedure required to effectively and safely abandon ship using on-load survival craft
release mechanisms. In reflection of the growing accident statistics, it is now recognised that
there are inherent issues with some on-load release systems. In the interest of best practice,
and to accommodate a higher level of safety, it is considered beneficial that FPDs are
included in the training and assessment process for all lifeboats. Therefore, training
establishments should provide training in the principles of FPDs detailed in this guidance.
6.3
As survival craft on-load release systems used in training establishments will be
operated frequently, the maintenance and testing regime of the training establishment for this
equipment should be designed to take account of frequent use to ensure an enhanced level of
safety.
-7-
More Information
Marine Technology Branch
Maritime and Coastguard Agency
Bay 2/29
Spring Place
105 Commercial Road
Southampton
SO15 1EG
Tel :
Fax :
e-mail:
MS003/007/0150
Published:
February 2009
Please note that all addresses and
telephone numbers are correct at time of publishing
-8-