Equipment Labor Capabilities 1
Equipment Labor Capabilities 1
Equipment Labor Capabilities 1
Type of equipment
Average Capabilities
1. Bulldozer (108)
(a) Clearing
500 sq.m./hr.
(b) Stripping
200 sq.m./hr.
Excavation:
1. Common Soil
45 cu.m./hr.
2. Slightly Hard Materials
25 cu.m./hr.
(d) Quarrying:
107 Common Materials
50 cu.m./hr.
108 Aggregate
40 cu.m./hr.
Boulders
15 cu.m./hr.
200 Needs screening
(e) Pushing
3 cu.m./hr
2. Road Grader
(a) Subgrading
300 cu.m./hr
(b) Spreading
50 cu.m./hr.
3. Payloader
(a) Loading
30 cu.m./hr.
4. Crane Shovel
(a) Loading
35 cu.m./hr.
5. Sheep Foot Roller
(a) Static Rolling (12 passes-15 cm./lift)15 cu.m./hr.
(b) Vibratory Rolling ( 4 passes-15 cm.lift)135 cu.m./hr.
6. 3- Wheel Road Roller
(a) Static Rolling (6 passes -20 cm. lift )
24 cu.m./
7. Tractor Drawn Roller
(a) Vibratory Rolling (6 passes-20 cm. lift)24 cu.m./hr.
8. Tandem Roller
(a) Static Rolling (6 passes-20 cm. lift )24 cu.m./hr.
(b) Vibratory Rolling (6 passes-60 cm. lift)72 cu.m.,/hr.
9. 6-T Dump Truck
(a) Hauling Common Borrow Base Course3.5 cu.m./hr.
(b) Hauling Selected Borrow Base Course5.0 cu.m./hr.
Hauling Concrete Batch Class A 2 Batch/trip
10. 2 T-Dump Truck
(a) Hauling Common Borrow Base Course 2.5 cu.m./trip
(b) Hauling Selected Borrow Base Course 4.0 cu.m./hr.
Hauling Concrete Batch Class A
1 Batch/trip
11. Buggy
(a) Hauling Concrete Mix
0.17 cu.m./trip
12.Wheel Borrow
(a) Hauling Aggregates
0.17 cu.m./trip
(b) Hauling Concrete Mix
0.05 cu.m./trip
13. Water Truck
(a) Watering
1000sq.m./trip
14. Concrete Mixer
(a) Mixing Concrete
9 cu.m./hr.
15.Rock Crusher
(a) Crushing mixed sand & gravel
30 cu.m./hr.
16. Concrete Vibrator
(a) Vibrating Concrete Mix
40 cu.m./hr.
17. Concrete Floor Finisher (a) Finishing Concrete Floor
140 cu.m./hr.
18.Percussioned Drilling
(a) Drilling Hard Rock
0.23 m./hr.
(b) Drilling Loose Rock
0.30 m./hr.
Drilling Limestone
0.38 m./hr.
0.49 m./hr.
0.70 m./hr.
Productivity
Sq.m./man-day
200
100
50
One (1) man-day per cm. of trunk
@ base of tree
Sq.m./man-day
80
250
Soil Type
a) Loose
b) Loose
c) Loose
Productivity
Depending on the type of soil, there
use similar productivity data as those
used for Excavation in Item 105
Productivity
3 cu.m./man-day
If the length of the culvert exceeds 6 meters, the number of man-days has to be
increased accordingly.
Culvert laying- this task consist of the excavation of the trench preparing the bed,
laying of culvert, backfilling & compaction. Number of man-days required varies with
the volume of the excavation and the soil type.
ENGINE
OIL
Crane,140 liters (diesel) 4 liters
Diesel Hammer, 20 liters ( diesel)
Bulldozer, 200 liters
3 liters
( diesel)
Payloader, 100 liters
3 liters
( diesel )
Grader, 120 liters
3 liters
( diesel 0
Roller, 60 liters ( diesel) 2 liters
Dump Truck, 60 liters
1 liter
( diesel )
Mixer ( 1- bag ), 40
Liters ( gasoline )
Vibrator, 15 liters
-
GEAR
OIL
1 liter
-
GREASE
OIL#10
2 lbs.
-
1 liter
1 liter
1 lb.
1 liter
1 liter
1 lb.
1 liter
1 liter
1 lb.
1 liter
1 liter/wk.
2 liters/wk.
2 lbs./wk.
1 lb.
1 liter
1 liter
0.5 lb.
( gasoline )
One Bagger Mixer- 100 bags/day
Crane- minimum of 2 piles/day ( 16m. length including spotting )
VOLUME OF TRENCH CU.M.
Soil Type
7-8
10-13
In these cases, the work split over two or more days. First the trench should be
excavated and then the preparation of the bed, the laying, backfilling and compaction is
done. Only 3 times. Therefore the volume of the excavation has to be limited following
rates and then applicable:
Soil Type
a) hard soil
b) very hard, stony
Productivity
3.50 cu.m./man-day
2.00 cu.m./man-day
After completion of the trench approximately 4 man-days are needed to lay 6 rings,
backfill and compact to finish road level.
I. MECHANIZED ASPECT
A. CLEARING AND GRUBBING
Dozer
Production
Horse
Dense of Vegetation ( No. of Trees/Hectares )
Power
0-50
51-100
101-200
201-250
120
360
250
190
160
140
420
290
220
185
160
480
330
255
210
180
540
375
285
240
200
600
420
310
265
B. EXCAVATION ( Common Materials )
B.1 CRANE
Tonnages
Capacity ( cu.m./hr.) Bank Volume
Canal
Structure
Creek
15
15
10
10
20
20
15
15
25
25
20
20
30
30
25
25
B.2 DOZER
Horse
Production ( cu.m./hr.) Bank Volume
Power
Canal
Structure
120
30
15
140
35
20
160
40
25
180
45
30
200
50
35
251&>
130
150
170
195
215
B.3 BACKHOE
Bucket ( cu.m.)
0.50
0.75
1.00
1.25
1.50
C. QUARRYING
Dozer ( H.P.)
140
160
180
200
D. LOADING
Bucket ( cu.m.)
1.0
1.5
2.0
2.5
3.0
E. SPREADING
Grader ( H.P.)
80-100
100-125
125-150
150-175
Creek
15
20
30
40
45
H. EMBANKMENT COMPACTION
Capacity ( cu.m./hr.) Compacted Volume
Tons
Self-Propelled
Tamp. Foot drum
Vib. drum
10
80
60
12
90
70
15
120
90
I. LOADING, SPOT & MANEUVER TIME
Using Loader with 1.00 cu.m. Bucket
Dump Truck Capacity
Compacted Volume ofCobbles/Boulders
Common
Road Surface
Materials
Materials
4.00 cu.m.
7 min.
7 min.
10 min.
6.00 cu.m.
9 min.
9 min.
12 min.
8.00 cu.m.
11 min.
11 min.
15 min.
J. AVERAGE SPEED OF DUMP TRUCK
Type of Road
Concrete/Asphalt Road
Good Maintained Gravel Road
Poorly Maintained Gravel Road
K. DEMOLITION OF CONCRETE
160 CFN Compressor & two (2) Jack Hammer
Capacity- 8.00 cu.m./day for massive concrete
-12.00 cu.m./day for slab & wall
L. DRIVING OF PILES
Steel Pipes: Crane 25 tons with 2-tons drop hammer, Capacity = 8 L.M./Hr.
Concrete Piles : Crane 25 tons with 2500 kgs. Pile hammer, Capacity = 2.00 L.M.
per Hr., 4.00 LM/Hr. for thick & thin concrete piles.
N. MANUAL ASPECT
A. Excavation
A.1. Common Materials
Capacity ( cu.m./day) Bank Volume & Depth of Excavation
Type of Work
( meter )
Farmditchs
3.00
2.50
2.00
Canal
2.50
2.00
1.75
Structure
2.00
1.75
1.50
A.2. Slight hard materials ( Ind.)
Type of Work
Canal
Sructure
Lumber
bd.ft./hr. pcs./hr.
4,000
250
Boulder
2.00
F. DEMOLITION OF CONCRETE
Slab & Wall
0.50 cu.m./man-day
Massive Concrete
0.20 cu.m./man-day
G. SCREENING OF AGGREGATES
Gravel
4.00 cu.m./day/man
Sand
6.00 cu.m./day/man
H. MANUAL BACKFILL
Capacity : 3.00 cu.m./man
I. LAYING OF MATERIALS ( cu.m./day/man)
Cobbles 2.00
Boulders 1.50
J. SPREADING OF AGGREGATE
Capacity : 2.50 cu.m./day/man
K. RUBBLE MASONRY ( Concreting )
Crew : 1- Foreman, 2- Mason, 10- Laborers, & 1- L.E. Operator
Capacity : 6.00 cu.m./day
L. GROUTED RIPRAP
Crew : 1- Foreman, 2- Mason, 10- Laborers, & 1- L.E. Operator
Capacity : 7.50 cu.m./day
M. C.H.B. : Setting Capacity sq.m./day
Crew : 1- Mason, 2- Laborers
Fence
Ply
Building
4 CHB
6 CHB
14
10
10
8
N. CONCRETE LINING
Crew : 1- Foreman, 2- Mason, 1- L.E. Operator, 10- Laborers with one (1) bagger
mixer
Capacity : 4.50 cu.m./day
O. INSTALLATION OF STEEL GATES
Crew : 1- Mason & 5- Laborers
16 x 16 to 24 x 24
Above 24 x 24
2 assy/day
1 assy/day
P. CONCRETE WORKS
P.1. Fabrication, Placing & Dismantling of Forms
Crew : 2- Carpenters & 4- Laborers; Capacity : 3.50 cu.m./day for 3000 psi
Crew : 1- Carpenter & 1- Laborer; Capacity : 4.50 cu.m./day Canal lining
P.2. Concreting and Curing Capability
P.2.a. With concrete mixer
Crew : 1- Foreman, 2- Mason, 1- L.E. Operator, & 8- Laborers
Class A : 3.50 cu.m./day
Class B : 3.70 cu.m./day
Class C : 3.50 cu.m./day
Lean Concrete : 4.50 cu.m./day
Q. PLASTERING OF CHB WALL
Crew : 2- Mason, & 2- Laborers
Capability : 12 sq.m./day ( one side only )
R. REINFORCED CONCRETE PIPES
Crew
Diameter
inch
cm.
1- Foreman
12
30
1- Mason
18
46
1-Carpenter/Steelman
24
61
12- Laborers with
30
76
1- Bagger Mixer
36
91
48
122
42
Capability
Fabrication
15
11
9
6
5
3
7
Installation
16
14
12
10
8
6
Cement
Sand
Gravel
Boulder
bag,cu.m. cu.m./cu.m. cu.m./cu.m. cu.m./cu.m.
9.00
0.45
0.90
b. 200 kgs. e
2.00
Canal lining
200 kgs. e
1.00
B. Rubble Mason
w/ 211 kgs. e
C. Grouted RiprapPlain Riprap
D. Lean Concrete 1000 psi
E. Gravel Blanket F. Filter Drain
-
7.00
0.50
7.50
0.48
0.96
4.50
4.20
5.00
0.225
0.35
0.50
0.45
0.05
0.10
1.00
0.75
1.00
1.00
-
1.00
-
OTHER MATERIALS
Class Type of
Strength
Structure
kgs.
A
Bridge/Flume
211
A
Siphon/Box Cul. 211
A
Other Str. @ inc 211
A
211
B
200
A
211
B
200
A
211
1.00
F. Lumber
bd.ft/cu.m.
40
25
25
5
5
15
5
5
pl. wd.
pcs/cu.m.
1.00
1.25
1.25
0.10
0.40
0.10
-
Tie wr.
Nail
kgs.cu.m kgs/cu.m
1.25%RSB 2.50
1.205 RSB 2.00
1.10% RSB 2.00
0.50
0.25
1.00%RSB 1.50
1.005RSB 0.50
0.25
Gravel
Cu.m.
0.02
0.04
0.06
0.08
0.10
0.12
R.S.B.
kgs
3.65
4.52
5.26
6.01
6.79
F. Lumber
Bd.ft.
2.00
2.00
3.00
3.00
4.00
4.00
Tie Wire
kgs.
9.28
7.72
9.75
23.22
50.43
60.84
CW
Nails
kgs.
0.10
0.20
0.30
0.40
0.50
0.60
CWN & TW
kgs.
0.20
0.20
0.30
0.30
0.40
0.40
Cement
Bags/aq.m.
0.55
1.07
Sand
Cu.m./sq.m.
0.046
0.089
Mobilization
2%
2%
2%
2%
2%
Note: The total contract price should be equal to or less than the total COA estimate plus
10% in order to sustain a finding of reasonableness otherwise the contract price will be
deemed excessive.
ACEL RATE 1998
Operated Equipment
Bulldozer
Payloader
Road Grader
Dump Truck
Road Roller
Crane
Back Hoe
Transit Mixer
Air Compressor
Plate Compactor
Asphalt Paver/Finisher
Description
Komatsu, D80A-12DD
180 Hp
75 TCM/Clark, 1.53 cu.m.,
Capacity, 151 Hp
Mitsubishi MG 500 170 Hp
Japan & Other Make,
10 cu.m. Capacity
Ingersoll Rand SP48 MI Tons
All models, Truck mounted,
standard mechanically operated
31-35 tons
Komatsu PC 120, Capacity
90 Hp
Japan make 3.8 cu.m., 46 cu.m.
Capacity 175 Hp
Gas/Diesel Engine, CFM
20 Hp
12 Hp Engine Driven
Worthington 34 ( basic
Equipment only)
Rate/Day
Php 9,160.00
Php
10,010.00
Php
Php
8,808.00
9,016.00
Php
Php
8,701.00
11,296.00
Php
9,656.00
Php
8,528.00
Php
1,376.00
Php
Php
1,648.00
3,320.00
Asphalt Distributor
Php
Bare Equipment
Pile Hammer (w/o crane)
Drop Hammer (w/o crane)
Jack Hammer
Description
Domag D8-22
Two tons w/ Pile Hammer
Stanley, Hydraulic w/o
power unit
Gas/Diesel Driven 250
Amps., 185 Hp
1-Bagger
Gas or Diesel Driven
Husquama, 2100 CD w/o Blade
All makes, 500-1000 gals.
All models 3.5 4 size
With Cement Silo Manual
Rate/Day
Php
5,067.00
Php
100.00
Php
294.00
Welding Machine
Concrete Mixer
Concrete Vibrator
Chainsaw
Water Truck
Water Pump
Concrete Batch Plant
Php
5,784.00
300.00
Php
298.00
Php
341.00
Php
180.00
Php
1,773.00
Php
119.00
Php
5,113.00
/mo.x Rated Cap. In
Cu.m./hr.
Walling/Sliding :
Covering
30 sq.m./man-days
Framing, Studs
12 cu.m./man-days
( Multiply by the no. of days Double walling)
Ceiling Joist and Hangers
16 sq.m./man-days
Ceiling Boards ( 4 x 8 Ply Wood)
30 sq.m./man-days
Windows sashes :
Jambs Fabrication
4 sq.m./man-days
Frames Fabrication
2 sq.m./man-days
Jambs Installation
14 sq.m./man-days
Frames Installation
10 sq.m./man-days
Doors :
Jambs Fabrication/Installation
2.5 sq.m./man-days
Door Fabrication/Installation
1 panel/man-days
Paintings :
Paint Rollers
125 sq.m./man-days
Paint Brush
Neutralizer
Truss Fabrication
Purlins Installaation
Fascia Boards
Roof Coverings ( G.I. sheets )
Concrete Works :
Concrete Pouring
Rebars
Finishing:
Rough Finish
Plain/Fine Finish
CHB Filling/Laying
50 sq.m./man-days
100 sq.m./man-days
0.25 truss/man-days
60 L.M./man-days
0.05 cu.m./man-days
35 pcs./man-days
0.30 pcs./man-days
20-30 kgs/man-days
10 sq.m./man-days
8 sq.m./man-days
6-8 sq.m./man-days
A. CEMENT MORTAR
Table -1 Quantity of Cement and Sand for CHB Mortar per Square Meter Wall
Size of CHB No.per sq.m.
40 Kg. Mixture Cement Bags
A
B
C
D
Sand
4 x 8 x 16
12.5
0.525
0.394
0.328
0.0438
6 x 8 x 16
12.5
1.013
0.759
0.633
0.0844
8 x 8 x 16
12.5
1.500
1.125
0.938
0.1250
B. MORTAR FOR PLASTERING
Table-2 Quantity of Cement and Sand for Plastering per Square Meter
40 kg. Cement Bags
Mixture Class
16 mm thk.
20 mm. thk.
25 mm. thk.
A
0.288
0.360
0.450
B
0.192
0.240
0.300
C
0.144
0.180
0.225
D
0.120
0.150
0.188
Sand
0.016
0.020
0.025
1. Find the area of the wall ( two faces )
Area = 3.00 x 4.00 x 2 faces
A = 24 sq.m.
2. Refer to Table-2 under 16 mm thick plaster class B mixture: Multiply:
Cement = 24 x 0.192 = 4.6 bags
Sand = 24 x 0.016 = 0.384 cu.m.
C. CHB FOOTING
Table-3 Quantity of Cement, Sand, and Gravel for CHB Footing per Meter Length
Dimension
Centimeters
t
10
10
10
Sand
Cu.m.
0.015
0.018
0.020
Aggregate
Gravel
Cu.m.
0.030
0.035
0.040
10
15
15
15
15
20
20
20
50
40
45
50
60
40
50
60
0.450
0.540
0.608
0.675
0.810
0.720
0.900
1.080
0.380
0.450
0.506
0.563
0.675
0.600
0.750
0.900
0.020
0.030
0.034
0.038
0.045
0.040
0.050
0.060
0.050
0.060
0.068
0.075
0.090
0.080
0.100
0.120