Training Getting Started - Modeler - Din: RM Bridge V8i September 2010
Training Getting Started - Modeler - Din: RM Bridge V8i September 2010
RM Bridge V8i
September 2010
RM Bridge
Training Getting Started Modeler DIN
Contents
1
1.2
4.1
4.2
4.3
4.4
5.3
5.4
6.2
6.3
Bentley Systems
Austria
RM Bridge
Training Getting Started Modeler DIN
6.4
7
II
7.2
Bentley Systems
Austria
RM Bridge
General
1-1
1 General
In this example, the necessary definitions for modeling the bridge structure will be shown
step by step. The subprogram Modeler is a geometry-preprocessor. The following geometric data should be defined:
Axes
Cross-section
Segment
The different structure parts are assigned to a segment.(i.e. segment for main girder, pier, link segment).
The segments will be closed to each other according to
the static connection after the assignment.
Static system
The start point of one axis should be located in the global-coordination system in groundplan(X and Z-coordination) or in elevation plan (the desired position and the height) at first.
The segment is created by assigning cross-section to one section of an axis. Use the axis
station to define the start point and the end point of a section.
The segment is subdivided into segment points. The cross-sections are assigned to these
points. In the segment point list (in Modeler), each segment point has its own station and is
defined with certain distance to the next one. After the export to RMBridge, the stations will
be converted into structure nodes. The distance between the segment points will be the
length of element. They are used for static analyze in RMBridge.
Bentley Systems
Austria
RM Bridge
General
1-2
30m
A2
10x3m
30m
A3
10x3m
Axis in plan:
Part 1: straight line:
Axis in elevation:
Part 1.: straight line:
The numbering:
Node numbers (span wise):
Element numbers (span wise):
Support (spring) elements:
Bentley Systems
Station: 0-60 m
Station: 0-60 m
101-111-121
101-110,111-120
1100, 1200, 1300
Austria
RM Bridge
General
1-3
A2
A3
1100
1200
1300
101-110
111-120
Z
X
1.2.2 Cross-Section
1.65 m
2.00 m
0.10 m
0.25 m
8.00 m
0.10 m
3.50 m
3.40 m
1.00 m
Fig. 4: T-Beam Cross-section
Bentley Systems
Austria
RM Bridge
Program Start
2-1
2 Program Start
After the program installation, you can find the RM-Icon on the desktop.
The program can be started by double-clicking this symbol or selection in the windowstartmenu.
Bentley Systems
Austria
RM Bridge
3-1
First level
If the program starts for the first time, RM-Default database(material, tables and variables
which are depend on different standards) and cross-section catalog will be loaded, the project
starts in the installation directory. The program starts always in the last work directory. The
complete pad is shown on the top of main window.
Bentley Systems
Austria
RM Bridge
Bentley Systems
3-2
Use File change
work directory in main
menu to change the
project into the desired
directory.
The project should be
initialized. In the setting window, you can
set some general options (i.e. Standard,
material group).
After the initialization,
the modelling-process
can begin.
Austria
RM Bridge
Construction of Axis
4-3
4 Construction of Axis
Axis elements are used to define the axis in plan. For this example the axis is straight.
Click Modeler in the navigation to start Modeler. Use Modeler to prepare the geometry of
the bridge. The project is shown in the ground plan (empty yet).
Navigation menu
The input window changes according to the selected geometric definition (navigation
menu). Modeler can be closed by pressing Esc-button or click the close icon x. It is
also possible to exit Modeler that if you switch to another function, which could be found in
the navigation menu and not a sub-function of Modeler.
In helpbrief help for Icons you can find the description for different functions.
Note: Recalc-function in Modeler(GP) and Analyzer(RM) are not the same. In Modeler, the Recalcfunction is used to export the Modeler data to Analyzer. But in Analyzer, the Recalc
function is used to start the calculation. The calculation options can also be set in the Recalc-function.
The import and export function for Tcl-file works in the same manner. The import and export
process is executed in the Modeler database (if Modeler is active) or in the Analyzer database
(if Analyzer is active).
Bentley Systems
Austria
RM Bridge
Construction of Axis
4-4
There is a detailed description about data management and backup in RmBridge, see
chapter 1010.
Define an Axis
Confirm
If there are more axes existing, double-click the desired axis to select it.
Active
Axis in plan:
straight line:
Station: 0-60 m
Bentley Systems
Austria
RM Bridge
Construction of Axis
4-5
Select P0 in order to
define the starting point
of the axis in the
ground
plan.
The coordinates for the
starting points (X =
east, Y = north).
Confirm
Keep the default set for this example (P0 (0.0/0.0).). The new axis goes along the Xdirection, no angle needs to be defined. After input confirmation the point with the specified direction are visible on the screen. Please use the Zoom functions at the left vertical
tool bar (or use Free hand symbols, see next page) to view.
Select Append straight
line to axis from the
tool-bar.
The length of the
straight line is 60.0 m.
Confirm
The axis is now defined in the ground plan and is displayed on the screen.
Bentley Systems
Austria
RM Bridge
Construction of Axis
4-6
Alternatively to the zooming facilities, the so called free hand symbols can be used. Such
a free hand symbol is executed with the left mouse button and simultaneously pressing
[Ctrl]-key on the keyboard. The free hand symbolV creates a full view of the currently available items.
The other free hand symbols can be viewed by clicking the explanation button on top
of the screen.
Bentley Systems
Austria
RM Bridge
Construction of Axis
4-7
Station: 0-60 m
Confirm
Select the button append straight line by
station and set Station
Difference to 60 m..
Confirm
Now the axis definition is finish. You can use the zoom-function as explained above to
check the axis.
Bentley Systems
Austria
RM Bridge
Construction of Axis
Elevation of Axis
4-8
Bentley Systems
Austria
RM Bridge
Construction of Axis
4-9
4.4 Modify
The Delet last axis element button allows to delete the last input.
Modifications to the axis
definition in plan and
elevation can be done in
the ground plan list or
elevation list.
Modifications
Bentley Systems
Austria
RM Bridge
Construction of Cross-Section
5-1
5 Construction of Cross-Section
1.65 m
2.00 m
0.10 m
0.25 m
8.00 m
0.10 m
3.50 m
3.40 m
1.00 m
Fig. 5: Cross Section
Define Cross-Section
Click cross-section in the navigation-menu with the right mouse-button. Select New
Cross Section in the context.
The basic definitions
for the cross-section
name can be used, confirm with <OK>.
Confirm
Bentley Systems
Austria
RM Bridge
Construction of Cross-Section
5-2
Aktive CS
Bentley Systems
Austria
RM Bridge
Construction of Cross-Section
5-3
CS Window
Direction
Different viewzoom functions
and
Bentley Systems
Austria
RM Bridge
Construction of Cross-Section
5-4
5.1 Definitions
5.1.1 Construction Lines
The construction line (CL) is needed for locating the intersection points, which are used to
draw a FE-element. The FE-elements construct the cross-section network. Use the drawfunctions to create the construction lines. The construction lines are referenced on each
other (i.e. parallel to). All the construction lines are depends on CL1 (horizontal) or CL2
(vertical).
Note: Different dependencies of construction lines on each other are important for defining construction lines
with variables. The assigned variables are given in Tables and formulas. The influence of variables on the
other construction lines should be considered.
Use Offset-option can move cross-section position (CL1, CL2) relate to the Axes.
5.1.3 Cross-section
In order to create a cross-section, the elements are required, which defined by intersection
point of construction lines. Every element is a build-part of the cross-section.
Note:
Bentley Systems
Parts can also be used to assign the different static length system of one cross-section into
different part. (i.e. Doppel-T cross-section prepared as Grillage, that means instead of two
single cross-section (each -T)to two different segments, you just need one cross-section
and one segment, the cross-section consists of two parts for two separate longitudinal element series ),
Austria
RM Bridge
Construction of Cross-Section
5-5
Reference Points
The intersection of CL1 and CL2 represents the axis of the bridge and acts as a reference
point for the position of the cross-section in the overall 3D geometry.
5.1.7
Reference Sets
In addition to the cross-section geometry information for the structural analysis such as
temperature points, reinforcement layers, stress points and others are defined in so called
reference sets. Properties (e.g. material) of a Reference Set can be defined and grouped in
so called Attribute Sets.
5.1.8
Layer Management
Each object of the cross-section can exist in all, one or several graphical layers.
Bentley Systems
Austria
RM Bridge
Construction of Cross-Section
5-6
Constants
Six vertical and four horizontal lines are needed for the following cross-section. First parallel and vertical lines with a distance of 4.0m to the centre are defined.
Set the constant to 4.0
in
the
variables/constants-input
field.
Press the icon Parallel Line to activate this function. The graphic cursor is then displayed
as continuous line indicating a function being active.
During the execution of this action the following information is displayed in the status
line:
Click to the right side of the selected line to create a new construction line. This new CL
has a distance of 4.0m to the centre.
Create the second line on the other side in the same way:
Select the vertical basic line.
Click to the left side of the selected basic line (CL_2) to create a new CL. This new CL
has a distance of 4.0m to the centre.
Bentley Systems
Austria
RM Bridge
Construction of Cross-Section
CS window
5-7
The next figure shows the rest of the needed CLs with the corresponding distances . The
procedure is the same as explained above. Click at the vertical or horizontal basic line and
set the constant to the appropriate value.
Bentley Systems
Austria
RM Bridge
Construction of Cross-Section
5-8
The following overview shows all necessary construction lines for this example:
0.35
0.25
4.00
2.00
CS Window
4.00
0.6
Bentley Systems
Austria
RM Bridge
Construction of Cross-Section
5-9
CS Window
Click at the intersection points of the construction lines to create the corner nodes 1, 2, 3
and 4 of the new element (see picture below). The new element is automatically assign
to part 1, thus the number 1 appears in the middle of the element. (Different parts are
needed in composite constructions, see next training)
Bentley Systems
Austria
RM Bridge
Construction of Cross-Section
5-10
All other elements are generated in the same way. Please make use of the zoom functions
to properly select the intersection points. A wrong definition can be interrupted by hitting
the <Esc> key (or right mouse button). A wrongly defined element can be selected (element line changes colour) and deleted with the delete icon.
Elements can be copied and mirrored to speed up the input. These icons can be found with
right click above the icon Linear 4-Point-Element.
CS Window
The cross-section of this example consist of 4 elements only, see picture below:
Bentley Systems
Austria
RM Bridge
Construction of Cross-Section
5-11
Reference-Sets
Connection points
Confirm
This new reference set
is inserted in the table
of existing reference
sets. Several sets can be
defined in one project.
Select the wanted set
and hit <OK> to change
the active set
Active
Insert
Bentley Systems
RM Bridge
Construction of Cross-Section
5-12
Single Point
Connection point
Bentley Systems
Confirm
Austria
RM Bridge
Construction of Cross-Section
5-13
Stress Points
Open the reference set input window by clicking the arrow key next to it.
Reference-Sets
Insert
Stress Points
Confirm
Active
The newly defined reference set is inserted in the table of available reference sets.
Select the new set and hit <OK> to activate the reference set.
Bentley Systems
Austria
RM Bridge
Construction of Cross-Section
5-14
Select the icon for the
stress point definition.
The intersection point
is selected by clicking
it with the cursor in
order to define the
wanted position of the
reference
point.
The upcoming window
asks for the definition
of the point name for
the
selected
point
(SP_TOP in this case).
Confirm
Confirm
Bentley Systems
Austria
RM Bridge
Construction of Cross-Section
5-15
Reference-Sets
Insert
Reinforcement Top
Confirm
The newly defined reference set is inserted in the table of available reference sets.
Select the new set and hit <OK> to activate the reference set.
Bentley Systems
Austria
RM Bridge
Construction of Cross-Section
5-16
Select the appropriate
icon for the reinforcement
definition.
Select the element corner to which the reference point is relative to
using the mouse cursor.
The upcoming window
requires data for point
type, point name and
offset to the selected
element corner. The
new point will be the
start of the reinforcement polygon.
Confirm
After the reinforcement definition at the top layer is defined the bottom reinforcement will
following as next:
Bentley Systems
Austria
RM Bridge
Construction of Cross-Section
5-17
Open the reference set input window by clicking the arrow key next to it.
Reference-Sets
Insert
Reinforcement Bottom
Confirm
The newly defined reference set is inserted in the table of available reference sets.
Select the new set and hit <OK> to activate the reference set.
Bentley Systems
Austria
RM Bridge
Training Getting Started Modeler DIN
Construction of Cross-Section
5-18
Select the appropriate
icon for the reinforcement
definition.
Select the element corner to which the reference point is relative to
using the mouse cursor.
The upcoming window
requires data for point
type, point name and
offset to the selected
element corner. The
new point will be the
start of the reinforcement polygon. Define
the polygon end point
in the same way.
Bentley Systems
Austria
RM Bridge
Segment Definition
6-1
6 Segment Definition
The structural system consists of 2 span girders with a constant T-shaped cross-section.
Only one Segment is needed for this project.
Click Segment in the navigation-menu with the right mouse-button. Select New segment in the contex.
Define Segment
Bentley Systems
Austria
RM Bridge
Segment Definition
6-2
Define new segment points by clicking the "Insert after" - button (at the left of the general screen).
The structural system shall start at 0 and shall end at Station 60.0 m.
All elements will have a length of 3.0m, 20 elements will finally compose the girder. 10
elements for the left span and 10 elements for the right span.
Bentley Systems
Austria
RM Bridge
Segment Definition
6-3
Confirm
Segment Points
Austria
RM Bridge
Segment Definition
6-4
Element numbering
The element numbering should start at segment point 1, the first element and node-number
should be 101. At the end of the first element (101) the nodenumber is 102. The increment is definition by 1.
The properties of the material is:C_35/45 (DIN 1045-1) will be applied.
All elements are grouped with the name MG (main girder).
Activate the 'Modify' - Function at the left of the table to open the input pad.
Bentley Systems
Austria
RM Bridge
Segment Definition
6-5
Element numbering
Confirm
Any modification after this initial definition can be done, but <recalculate> must be executed in MODELER before export the project to ANALYZER .
Bentley Systems
Austria
RM Bridge
Segment Definition
6-6
The cross-section 'cross1' is locked after this initial assignment. Any modification to the
cross-section requires to unlock the cross-section (program asks for it). Again <recalculate> must be executed in MODELER before the export to ANALYZER starts.
Bentley Systems
Austria
RM Bridge
Definition of Supports
7-1
7 Definition of Supports
The following definitions are required:
A connection point is required for the support. It should be defined in the crosssection (see Definition of Reference-Sets).
Create the connection between sub- and superstructure with spring elements- see below:
Bentley Systems
Austria
RM Bridge
Definition of Supports
7-2
Bentley Systems
Austria
RM Bridge
Definition of Supports
7-3
Support Definition
Spring Constants
Confirm
The newly defined spring element will be displayed in the table for support definitions.
Bentley Systems
Austria
RM Bridge
Definition of Supports
7-4
Support Definition
The same procedure is repeated for the other two connections (segment point 11 und 21).
The element numbers shall be 1200 and 1300.
The table below shows the sprig constants for the spring elements.
Element
Spring constants
CX
CY
CZ
CMX
CMY
CMZ
Bentley Systems
1100
KN/M
1e8
0
1e8
0
0
0
1200
KN/M
1e8
1e8
1e8
0
1e8
0
1300
KN/M
1e8
0
1e8
0
0
0
Austria
RM Bridge
3D - View
8-1
8 3D - View
The completed girder can be viewed in 3D now.
3D - View
Bentley Systems
Austria
RM Bridge
Export to Analyzer
9-1
9 Export to Analyzer
9.1 Export to Analyzer
The completed structural system can be transformed into a structural model for further use
in Analyzer.
Export
Export to Analyzer
Select 'Recalc'-Icon to start the calculation and export the Modeler data to Analyzer .
Recalc:
Some sub-functions are provided in the Recalc window for Modeler. They are separate
calculation parts. For complex project, sometimes the evaluate formulas check box
will not be selected to reduce the calculation time.
The Evaluate formulas has to be selected for further calculation options. Hamblyis
a special algorithm to find the common gravity line of several different cross-section
areas. Precast segmentation is used in RMCast.
Check numbering of
elements and nodes:
To check if any element or node-number is used for more times. This option will be
set automatically, if the Create model is set.
Create model:
Export the Modeler data to Analyzer. There are three sub-options can be set.
(1)Keep the original model data in Analyzer, only the new data will be added into the
database. (2) initialize the model structure in analyzer or (3) initialize the whole analyzer data (include the input data in Analyzer).
Bentley Systems
Austria
RM Bridge
10-2
Bentley Systems
Austria