Sample Test Spring 2014 Final
Sample Test Spring 2014 Final
INSTRUCTIONS!
!
1)
SOLUTION.!
!
!
Problem 1: The following part-incidence matrix has been derived for a particular
manufacturing shop:!
a) Identify modules using the Production Flow Analysis approach of Burbidge (5 points)
b) Perform two iterations of the Rank Order Clustering approach for identifying cells. (5
points) !
c) Defining the similarity coefficient between two parts i and j as N(i,j)/[N(i)+N[(j)]. where
N(i,j) denotes the number of machines that process both parts and N(i) the number of
machines required to process part i, determine the machine that is most similar to
machine A in terms of parts processed. (5 points)!
THE MATRIX IS REPRODUCED BELOW FOR YOUR CONVENIENCE!
Arrival rate
3/hr
0.1 hrs
6/hr
0.05 hrs
1/hr
0.3 hrs
Assume the system is in steady state, that interarrival times are exponentially
distributed and that the variability of the effective service times is negligible. !
a) Compute the probabilities of a randomly selected customer belonging to each class.
!
!
!
!
!
!
!
!
!
!
(5 points)!
!
!
!
c) Compute the expected value and variance of the processing time at the ticket window
!
!
!
!
!
!
!
!
!
!
!
!
!
(Hint: V[X] = E[X2] - E2[X], where E[.] denotes the expected value operator) (5 points)!
d) Now compute the mean and variance of the processing time at this station if the
customers from Class 3 are sent to a separate window, with the arrival rates of
Classes 2 and 3 remaining the same. (5 points)
Depts. Visited
Monthly Volume !
A-C-D-F
500!
B-A-C-D-F
1000!
E-B-C-A-F
300!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
c) Draw the relationship chart for these departments based on the volume of
flow between them.(5 points)!
!
!
!
!
!
!
!
!
!
!
!
d) Draw the Relationship Diagram for this facility based on the REL Chart
from part d). (5 points)!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
e) Assuming that all departments must have the same area, construct a block
diagram of a satisfactory layout for this facility (5 points)
Time
(mins)
4.0
3.4
5.4
7.6
1.8
3.7
2.5
!
a) What is the maximum number of claims that can be processed each hour if
one employee is dedicated to each processing step? (3 points)!
!
!
!
!
!
!
!
b) How many workers are needed to process six claims an hour if a worker is allowed to
process more than one consecutive step of the process, e.g., Worker 1 may perform
processes 1 and 2, but not 1 and 3. Make sure to show a detailed assignments of taks
to workers, and justify that your proposed allocation can in fact meet the production
goal.(5 points) !
!
!
!
!
!
!
!
!
c) What is the minimum number of workers needed to process six claims per hour
under the most idea conditions, assuming tasks can be split between workers with no
loss of efficiency? (2 points)!
!
!
!
!
!
!
!
!
!
!
d) How many workers are needed if the tasks are organized in a U-line, with a separate
station devoted to each process and the employees moving between stations such that
their paths do not cross? (5 points)!
Plant
xi
yi
wi !
10
450!
1200!
300!
16
1500!
!
!
!
!
!
!
!
!
!
!
!
!
!
Problem 7: Consider a production line where a product must be processed through the
following four operations in the order given:!
Operation
Machine
Setup Time
(mins/batch)
Process Time
(mins/part)
Bench
10
VTL
180
17
Deburr
10
VTL
120
26
You are also given the following information on the equipment, based on data collected
over a period of two years:!
Machine
No. of Machines
Mean Time
between Failures
(hrs)
Mean Time to
Repair (hrs)
Bench
160
VTL
160
16
Deburr
80
a) Assuming a batch size of 40 units, calculate the bottleneck rate rb at the VTL station
(You are given that the VTL is the bottleneck!) (5 points)
!
!
!
!
!
!
!
!
!
!
!
!
c) Calculate the worst-case throughput of the line with a batch size of 40 units and a
WIP of 8 batches. (5 points)
Your company has hired a consultant to solve the problem of locating new facilities
to minimize the sum of fixed costs and transportation costs relative to 23 existing
customers. The model does NOT consider capacity limitations at the new facilities.
The consulting firm you have hired has presented you with a solution in which new
facilities are located at candidate locations 3, 4 and 5. In this solution 25% of
customer 3s demand is served from the new facility located at candidate site 3,
and the remainder from the new facility at candidate site 5. Comment on the validity
!
!
!
!
!
!
!
!
!
of this solution. !
c) Is it possible for a cellular layout to require fews machines than a process layout,
assuming the same quantity and mix of parts is to be processed? Explain why or why
not. (4 points)!
!
!
!
!
!
!
!
!
!