6916 Welding Fabrication
6916 Welding Fabrication
6916 Welding Fabrication
ls::6916-1973
( Reaffirmed 1998 )
Indian Standard
C.ODE OF PRACTICE FOR
FABRICATION WELDING OF STEEL CASTINGS
( Second Reprint DECEMBER 1993 )
UDC
BUREAU
MANAK
621791 : 6691414
OF
BHAVAN,
INDIAN
9
NEW
Gr 7
BAHADUR
STANDARDS
SHAH
ZAFAR
MARG
DELHI-110002
December 1973
t8 : 6916- 1973
Indian Standard
CODE OF PRACTICE FOR
FABRICATION WELDING OF STEEL CASTINGS
Welding
General
Sectional
Members
SHRI J. K. AHLIJWALIA
SHRI M. M. GHOSH (Alternate )
SHRI N. C. BAQCHI
SHHI B. C. BISWAS ( Alternata)
SHRI S. BALASUBRAHYANYAY
SHRI D. P. CHATTERJEE
SHRI B. N. DAS
Sam S. P. DASQUPTA
SMDC
14
Represcnhng
Chairman
SHRI R. Glrosri
Committee,
National
Test House,
Calcutta
@ Copyright 1973
BUREAU OF INDIAN STANDARDS
This publication
is protected
under the Indian Copyright Act (XIV
of 1957) and
reproduction in whole or in part by any means except with written permission of the
iublisher shall be deemed to be an infringement
of copyright under the said Act.
IS:6916 - 1973
( Continued from page I )
Represenhg
Members
SRRI $1. v.
1). T(AXIATII
SHKI C. s. KOIIII(AI.
Snc~ A. P. SAHYAL
SHRI S. MAJ~MDA~
Indian
Bharat
(Alternate
Engineering
Heavy Plate
Association,
Calcutta
& Vessels Ltd, Visakhapatnam
Directorate
General
New Delhi
of
Technical
Development,
Those
IS : 6916- 1973
Indian Standard
CODE OF PRACTICE FOR
FABRICATION WELDING OF STEEL CASTINGS
0.
FOREWORD
0.1 This Indian Standard was adopted by the Indian Standards Institution
on 27 February 1973, after the draft finalized by the Welding General
Sectional Committee had been approved by the Structural and Metals
Division Council.
0.2 Repair and rectification of steel castings by metal arc welding processes
This standard has been prepared
have been covered by IS : 5530-1969*.
to specify satisfactory procedures for welding together two or more of steel
castings to produce a larger cast fabrication or to form a part of a complete
welded system. In all such cases the use of welding should be taken into
account at the design and/or casting stages unlike the circumstances when
welding according to IS : 5530-1969 would be required.
0.3 Fabrication welding principles required that proven welding procedures
I are used and although full details on procedure and testing are included,
the requirements have been kept to the minimum necessary to ensure
Manual metal arc and gas-shielded arc and
sound joints are produced.
submerged arc welding processes are covered for the present. Other
fusion welding processes like electro slag welding will be included in due
course after the industry gains experience in adopting them for the
fabrication welding of steel castings.
0.4 The content of the standard follows the general pattern established in
IS : 5530-1969*.
Some typical
weld preparations have been included
but each joint has to be considered in respect of its particular characteristics
and it is for this reason that only guidance has been given in certain
clauses. Similarly, no acceptance levels for welded joints are specified
and these should be the subject of agreement between the contracting
patties if an application standard does not cover them. Care is needed
in the interpretation of the results of non-destructive testing bearing in
mind the allowable defects which may be present in the castings in the
vicinity of the welded joint.
*Code of procedure for repair and rectification of steel castingsby metal arc welding
process.
3
: IS : 6916 - 1973
0.5 This standard
1. SCOPE
1.1 This standard specifies requirements
for the joining together of steel
castings by fusion welding, where the components of the final fabrication
are designed for that purpose or when welding is introduced
at the foundry
planning stage.
1.1.1 It does not cover the welding of steel castings
nor the surface deposition of weld metal for applications,
resistance or hard facing.
to wrought steels,
such as corrosion
2. TERMINOLOGY
assigned
to them
in IS : 812-1957t.
3. CASTINGS
3.1 This
Standards
standard
relates to steel castings
listed in Table 1.
conforming
to the
Indian
CONSUMABLES
TABLE 1 RECOMMENDED
METHODS
OF WELD PREPARATION,
SELECTION
OF WELDING
CONSUMABLES,
PREq AND POST-WELD
TREATMENT
TEMPERATURES
FOR DIFFERENT
INDIAN
STANDARD
GRADES OR STEEL CASTINGS
(C6uuses3.1,5.1.3,
SL
STEEL'~YPE
SPECIFICATION
ANDGRADE
No.
REC0MbfENDATIONSFOR
METHOD
OF
h_-_----_--r------------_
WELD
Minimum
PREPARATION
Electrodes and Filler Material
_-----h______~
Preheat( seee
7.2 )
Manual
metal arc
-welding
(1)
1.
(2)
Low-carbon
Q\
(3)
(4)
Gas
shielded
welding
Submerged arE
welding
(7)
(6)
(5)
ing Tempeiature
( see 13 )
OC
(8)
G:
---7
Post-Weld
Heat Treatment Temperatu
( see I! I
(:
a, b, c or d
IS : 814,
Groups 1
&2
IS : 6419,
S-l, s-3,
s-4
IS
: 3613
None.
580-650
(Note 1
IS : 814,
Group 2
IS : 6419,
s-2
IS
: 3613
Note 2
600-650
(Note3)
2.
0.25 to
0.35 c
IS : 1030, Grade 2
IS : 2856, Grade
CSW-C25
a, b, c or d
3.
0.35 to
0.45 c
IS
a, b, c or d
IS: 814,
Group 2,
( Note 4 )
IS : 6419,
s-2
( Note 4 )
4.
C-MO
IS : 3038, Grade 2
a, b, c or d
IS
Note 5
5.
1.5 Mn
IS
IS
a, b, c or d
( Note 6 )
IS : 814,
Group 2
IS
: 1030, Grade 1
IS : 4899, Gra.de 1
: 3038, Grade 1
: 2708, Grades 1
&2
FIE
;;,
: 1395
: 6419,
Siote
4)
150
600-650
( Note 3 )
Note 5
150
630-680
(Note 3 )
IS : 3613
( Note 4 )
150
( Note 7 )
IS: 3613
600-650
( Note 8 )
2f
6.
1.6 Mn
IS : 2708, Grade 3
a, b, c or d
( Note 6)
7.
Austenitic
manganese
IS
a, c, or d
8.
High tensile
IS
: 2644, Grades 1
&2
a, b, c or d
(Note 10)
Note 5
9.
1.25 Cr-Mo
IS
: 3038, Grade 5
a, b, c or d
(Note 10)
: 3038, Grade 5
a, b, c or d
(Note 11)
Cr-Mo
IS
: 276
10.
2,25
11.
5 Cr-Mo & 9
12.
9 Cr-Mo
IS
13.
Cr-MO-V
IS: 3038,
14.
13 Cr & 13
Cr-Mo
IS :3444, Grades I,
2&3
IS : 3038, Grades 6
&7
: 3038, Grade 7
Grade 3
a, c or d
(Note 10)
IS: 814,
Group 2
IS : 3613
( Note 4 )
200
600-650
(Note8)
Note 5
Note 9
None
Note 5
Note 5
200
( Note 11 )
600-650
f Notes
& 12)
IS : 1395,
Group C
IS : 6560,
SLA-3
Note 5
250
630-680
IS : 1395,
Group D
I,$ ;:;0,
Note 5
250
680-710
( Note 12 )
IS : 6560,
SLA-5
Note 5
300
650-720
( Note 13
IS : 5856,
S-B02,
MoL,
S-B02 MO
( Note 14 )
Note 5
300
650-720
(Note
IS : 6560
SLA-4
(Note 15 )
Notes 5
Br 15
250
680-7 10
( Notes 15
& 16)
IS : 5856,
S-BOlNb,
S-BO4,
S-B05Nb,
S-B02 MO
( Notes 14
& 17 )
Note 5
300
680-750
( Note 18)
IS :5206 or
any suitable
austenitic
electrode
with
or
without
a
facing
of
austenitic
manganese
steel
IS : 1395.
(Note5)
a, c or d
Kotc 5
( Note 10 )
a or
(Note
c
IO)
a or c
(Note 10)
Not<* 4
Notes 5 Sr
15
Note 5
13)
OI
I
( Contintred
) . ..
J
*
W.
TABLE 1 RECOMMENDED
METHODS
OF WELD PREPARATION,
SELECTION
OF WELDING
CONSUMABLES,
PRE. AND POST-WELD
TREATMENT
TEMPERATURES
FOR DIFFERENT
INDIAN
STANDARD
GRADES OR SIEEL CASTINGS-Confd
SL
No.
STEELTYPE
(1)
(2)
15.
SPECIFIC.~TION
AND GRADE
METROD OF
RECOYYBNDATIONSFOR
_---__
h---_----__----~
WELD
r---PREPARATION
Minimum
Electrodes and Filler Material
~--__-~-_--_-___
Preheat( see 7.2 )
Gas
Submerging TemManual
shielded
metal arc
cd arc
perature
welding
welding
welding
( y$
)
(4)
(3)
18 Cc 8 Ni
Ni/
IS
: 3444, Grade 6
16.
18 Cr8
Nb/Ti
17.
18 Cr 8 Ni
MO
18.
18 Cr 1ONi
2.5 MO
19.
18 Cr 10 Ni
2.5 Mo-Nb
IS
20.
18Cr 10Ni
3.5 MO
IS : 3444, Grade 10
IS
: 3444, Grades G,
7,8 & 9
(6)
a,cor
d
( Note 6 )
IS : 5206
(Note 14)
MAOl,
MBOlL
Ij ~$56,
a, c or d
( Note 6 )
IS : 5206
MB01 Nb
IS : 5856,
S-BOlNb
S:BOli
S-B0 1tib
(Note 19 )
(7)
Kores 5
& 19
(8)
IJone
(9)
1000-l 100
( Note 20 )
Note 5
None
Note 16
Note 5
IS : 5856,
IS : 5206,
S-BO2MoNb
MBO2Mo.
MB02MoL.
S-B02MoL
MB02MoNb
None
Note 16
Note 5
I
IS
(5)
Post-Weld
Heat Treatmen t Tcmperature
( sez;S )
I
: 3444, Grade 11 1 a, c or d
:
( Note 6 )
: 3444, Grades
12 & 13
I
J
a, cord
( Note 6 )
IS : 5206,
MB03Mo
IS : 5856.
S-B02Mo
S-B02MoL
Note 5
None
1000-1 150
!El,
p i d
;I,
y
o\
g
;:
TABLE f RECOMMENDED
METHODS
OF WELD-PREPARATION,
SELECTION
OF WELDING
CONSUMABLES,
PRE- AND POST-WELD
TREATMENT
TEMPERATURES
FOR DIFFERENT
INDIAN
STANDARD
GRADES OR STEEL CASTINGS - Contd
tf
*
$
s
1.
CI
3
w
is rather
low compared
NOTE 5 -No
suitable electrode or fill& wire complying with an Indian
types are manufactured and marketed under various trade names.
NOTE 6 -
Standard
is available,
although
suitable
Depends on composition
(a) is used,
the casting
shall
be preheated
and the
preparation
shall
be
may be necessary.
For heavy sections and steels of certain compositions Note 13 may apply.
NOTE 13 - Extreme care is needed when weldmg these steels which require immediate
to minimize the risk of cracking.
NOTE 14 -These
NOTE 15 -Welds
NOTE 16-Welds
to carbide
embrittlement.
in this material shall be ground at the toes, before post-weld heat treatment,
if any.
NOTE 17 - In the case of steel castings to IS : 3038-1965, Grade 3 and IS : 3444-1966, Grade 1, the filler wires
In the case of these the following consideraspecified are not suitable for those parts of castings subject to abrasion.
tions also apply:
a) In all cases, particularly when it is intended to use austenitic filler wires to minimize the risk of cracking,
reference should first be made to the service requirements of the casting for hardness, corrosion and
abrasion resistance, fatigue and tensile properties and appearance.
b) A 13.percent chromium filler wire may be used provided a satisfactory weld can he made.
NOTE 18 - Extreme care is needed when welding this steel which requires immediate post-weld heaf treatment to
avoid cracking.
When certain austenitic steel electrodes or fi!lcr metals have been used it may not be essential to
apply any post-weld heat treatment.
NOTE 19 -
Weld
before
with columbium
or titanium
should be cooled through the range of ( 920-540 ) in not more than three minutes.
The
rapid-cooling
should be continued
to below 425C.
Slower cooling rates may- be just as satisfactory
for some comp&
tion of the matciial
and conditions
of service.
NOT= 21 -
z
^
Should
subject
to abrasion.
: 2856-1964
Specification
for carbon steel castings suitable for high temperature
service ( fusion welding quality )
( Since revised ) .
IS : 2985-1964 Specification for steel castinga for ships structure
( Since revised ).
IS : 2986-1964 Specification
for steel castingr for marine engines and boilers
IS : 3038-1965 S ccification
for alloy steel castings for pressure containing
parts suitable for high temperature
service
(!LHAd).
IS : 3444-1966 Specification
for corrosion resistant steel castings
IS :,3613-1966
Specification
for acceptance
tests for wire flux combinations
for submerged-arc
welding equipment
( Since revised ).
IS: 4491-1968 Specification
for steel castings of high magnetic
permeability
IS : 4522-1966 Spccificarion
for heat resistant alloy steel castings
IS : 4898-1968 Specification
for steel castings for case carburizing
IS : 4899-1968 Specification
for ferritic steel castings for use at low temperatures
IS : 5206-1969 Specification
for corrosion-resisting
chromium
and chromium-nicklc
steel covered electrodes
for manual
metal arc welding.
3
w
IS
6916 - 1973
5.2 Storage and Handling - E?lectrodes, tiller wires and rods, and fluxes
shall be stored, handled and used in accordance
with the manufacturers
recommendations.
In certain cases re-drying or re-baking of electrodes
above the minimum temperature
recommended
by the manufacturer
may
be advantageous,
but the maximum
permissible temperature
for a particular electrode should be ascertained
from the manufacturer.
Electrodes,
filler wires and rods, and fluxes that show signs of damage or deterioration
shall not be used.
5.3 Shielding
is used
of IS : 5760-
Argon -
bl
1970*.
c>
content
shall
correspond
to a dew
point of - 30C or
lower.
6. EQ,UIPMENT
6.1 Welding plant, instruments, cables and accessories shall comply with
the requirements of the appropriate Indian Standard where available.
Their capacity shall be acje uate for the welding procedure proposed and
subsequently to .be qualifi 4 . The contractor shall maintain all welding
plant and ancillary equipmentin
good working order.
6.1.1 All electrical equipment used in connection
operation shall ,bc adequately earthed.
with
the welding
welding
process, means
of measuring
the
IS t 6916- 1973
6.4 Where necessary, staging and protection from the weather shall be
provided to enable the welding operation to be performed properly. This
is particularly necessary when using a gas-shielded welding process.
7. PREPARATION
FOR WELDING
(a)
b)
NoTII-T~~
dimension for the gap depends
on the welding
process
being
used and
whether a fusible insert is to be employed.
/-lOoMIN 7
3MIN
--+
lO*MIN
IOMIN
(4
FIG. 1 TYPICAL
URCW
Om
Snm.
U:6916-1973,
( b)
(d)
NOTE - Certain
welding
procedures
achirve
full penetration
without
back
gouging, but where this cannot be proved, the back of the first run shouid be gouged
out by suitable means to clean sound metal before welding is started on the gouged
outside.
All dimensions
Fm. 2
in millimetres.
15
1s 16916 - 1973
8.2 Metal Backing Bars ( Temporary) - When a metal backing bar is
used it shall be of similar chemical composition
to that of the casting or
it shall be a carbon steel up to 026 percent
carbon provided that the
sulphur and phosphorus contents do not exceed O-04 percent each. Backing
bars shall not be welded all round their perimeter in order to minimize
the risk of basal cracking.
8.3 Copper Backing Bars - Copper backing bars shall only be used by
agreement
between
the contracting
parties since there is a danger of
copper pick-up in the weld metal ( see Appendix A ).
backing
bars shall be of
8.4 Non-ametal Backing Bars - Non-metal
non-combustible
materials and shall be completely
removed after completion of welding.
9. ASSEMBLY
9.1 To maintain
the required
alignment
and gap where used, during
welding,
the parts to be welded shall be securely
held in position
by
mechanical
means, welded-on
bridge pieces, or by tack welding. When
sufficient weld metal has been deposited
to make the fabrication
selfsupporting,
bridge pieces or mechanical
clamps shall be removed and
potential
distortion
controlled
by welding
sequence
rather
than
by
mechanical
restraint.
NOTE-Cracking
can result if bridge-pieces or mechanical
position during completion of the weld.
clamps remain in
9.2 Preheating,
as required by 13, shall be applied and maintained
during
tack welding and the welding-on
of bridge pieces or other attachments.
9.3 Electrodes, filler rods or filler wires used for tack welding shall be of
the same type and class and of a size not larger than those used for
completing
the first run of weld metal.
9.4 Particular
attention
shall be paid to the quality of tack welds which
shall be made by qualified welders. The throat thickness of tack welds
made with filler metal shall be similar to that of the initial root run.
Where necessary,
the extremities
of these tack welds shall be dressed by
grinding or chipping to facilitate proper fusion when they are incorporated
in the root run. Any cracked tack weld made with or without filler metal
shall be completely
removed and retack-welded.
9.5 Care shall be taken when removing welded-on bridge pieces. Under no
circumstances shall they be knocked of, but removed by hack saw as disc grind=
at a point close to the surface of the casting. The remnants of the bridge
pieces and attaching
weld shall be removed by grinding or filing until the
surface contour of the casting is restored. The area embracing that exposed
16
IS : 6916 - 1993
by the welds that attached
the bridge pieces shall be examined
by nondestructive
means to determine
whether
rectification
is required
by
All welded-on
bridge pieces shall be removed
grinding
or by welding.
before applying
any post-weld heat treatment,
which shall include
the
area occupied by the bridge pieces,
10. DISTORTION
CLEANING
13.1 Defidtions
13.1.1Preheating temperature
is the temperature
of the parent metal
in the welding region immediateIy
prior to. the absorption
of any heat
from the welding process and is anDlicable
to the first and all subsequent
runs.
13.13 Interpass tem+rature,
in a multi-run
weld, is the temperature
of a section of deposited
weld metal and adjacent
parent metal immediately prior to welding again at that section.
17
IS : 6916 - 1973
13.2 Preheating - No thermal
cutting or welding shall be carried out
when the temperature
of the castings is below 15C. Recommendations
for preheating
are given in Table 1 and during cutting or welding the
actual
preheating
temperature
prescribed
shall be maintained
in the
region of the weld.
13.2.1 If it is not possible to preheat the entire fabrication, either because
of its size or because the extent of the welding required is such that the
fabrication
will fall below the appropriate
temperature
specified in Table 1
before the completion of welding then local preheating
shall be used over
an area on each side of the weld having a width of at least three times
the thickness of the material.
Whichever method is used, it is preferable
to preheat
the fabrication
to a temperature
slightly higher than the
minimum
given in Table 1 so that either the weld is completed
before the
temperature
falls below the value stated or the number of reheatings
required is kept to a minimum.
14. COOLING AFTER WELDING
14.1 In general, low carbon steel and austenitic
cooled naturally
without precautions.
In the
shall be taken to ensure slow even cooling.
steel fabrications
may bc
case of other steels care
IS I 6916 - 1973
15.4 Heat treatment shall be carried out by one of the following methods,
care being taken to ensure that the minimum stipulated temperature is
achieved uniformly through the thickness of the fabrication:
a) Heating in a stationary industrial furnace; and
b) Local heating using a portable muffle furnace, or induction coils,
or resistance heaters.
15.4.1
Manually-operated
15.5 Where other methods of heating are the accepted practice in certain
industries these may be used by agreement between the contracting parties
but consideration should be given to the metalhtrgical effects of such
methods. The foregoing methods are, however, preferable ( JCGAppendix A).
15.6 The heatiug and cooling rates shall be appropriate to the material,
geometry and thickness which would be verified by the welding procedure
tests.
16. MEASUREMENT
OF TEMPERATURE
19
ts I 6916- 19?3
17. ALTERNATIVE
METHODS
OF STRESS
RELIEF
18. DRESSING
18.1 Dressing
reasons:
a) To facilitate
may
non-destructive
be necesrary
testing;
OF FAULTY
WELDS
20.1 When welds fail to comply wholly or partly with the standard of
acceptance
derived in accordance
with 19, all unacceptable
defects shall
Preparation
and re-welding
shall be in accordance
with the
be removed.
requirements
of IS : 5530-1969*.
20.2 A repaired
weld shall be subjected,
as a minimum
requirement,
to
the same testing and inspection requirements
as the original weld.
2 1. PROCEDURE
QUALIFICATION
21.1 General
-The
object of procedure qualification
tests. is to prove the
feasibility
of a manufacturers
particular
welding
procedure
as distinct
from the ability of an individual
welder to deposit sound weld metal.
*Code
procclkr.
of procedure
for repair
and rectification
20
of steel carting
IS : 6916 - 1973
21.X.1 A manufacturer shall be exempt from making procedure qualification tests in accordance with this clause when he can show that for the
previous three years he has successfully undertaken welding in the fabrication of steel castings in compliance with satisfactcry welding procedures
in respect of welding process, type of steel, filler metal and approximate
thickness.
A manufacturer shall also be exempt when he can show that
he has previously made successful procedure tests of the type required.
21.1.2 In other cases, welding procedure qualification tests shall be
carried out before a manufacturer can be permitted to weld castings in
For each of the steels in Table 1 for
accordance with this standard.
which approval is required, the welding procedures shall specify the
details given in 21.2, including the operational ranges for each relevant
feature.
These welding procedures shall be submitted for approval by
the purchaser if requested.
21.1.3 Separate procedure qualification tests are not necessarily required
for each type of steel where proof of satisfactory performance does not
exist. Where welding procedures are similar with respect to welding
process, welding position, preheating, post-weld heat treatment, electrodes,
filler material, flux or shielding gas, then one welding procedure qualmfication test may be sufficient. When separate procedure tests are required
this shall be stated in the enquiry and/or order.
21.1.4 It is recommended that welding procedure qualification tests
carried out in accordance with this standard and witnessed by an independent inspecting authority should be accepted by other inspecting authorities
provided that all the provisions have been fulfilled.
records of the procedure
21.2 Procedkre
Test Records -The
fication tests shall specifically include the following details:
quali-
4 Type of steel;
b) Welding process;
cl Joint preparation;
4 Method of preparation;
e>Welding
f)
g)
position;
Preheating;
Welding technique and sequence;
J4 Electrodes,
j) Electrodes,
both;
J4 Electrical
filler materials,
or filler material
characteristics
size, or interpass,
21
temperature
or
iS I 6916 - 1973
4
4
( temperature,
time
at
temperature,
P) Identification
of inspecting
authority.
21.3 Requalification
of Procedure - A new procedure
qualification
test is required consequent
upon a change in any of the following:
4
b)
Type
of steel, subject
to relaxation
Welding process;
A change from a backed
c>
given in 21.1;
weld to an unbacked
weld;
21.3.2 In the absence of a change in any of the above items, the qualification of a procedure shall remain in force indefinitely.
21.4 Types of Test Joint - The joint used for a procedure qualification
test shall be representative
of that to be employed in production.
As it is
normally impracticable
to use actual production
castings for this purpose,
the test joint may be made between two cast p!ates or two cast pipes
according
to which are most representative
of the production
work to
which the procedure
being qualified is to relate. In all cases the material
for the test pieces shall be made by the same casting process and be of the
same type of steel as those used for production
work (see also 21.1 and
Appendix A ) .
21.4.1 For procedure
qualification
purposes, a test joint shall be made
for one or more of the following types of joint or weld, as stated in the
enquiry and/or as agreed to at the time of the order:
a) A butt joint ( plate and/or pipe ),
b) A fillet weld ( plate ), and
c) A branch connection
(pipes).
22
IS I 6916 - 1973
21.5 Position
21.5.1 Butt Joint or Fillet Weld Bttwetn Platts - A test joint shall be
made in each of the following welding positions that is to be used in
production:
a) Flat,
b) Horizontal-vertical,
c) Vertical,
and
d) Overhead.
Qualification
under (c) includes qualification
under (a) and qualification under (d) qualifies the procedure for use in all positions.
NOTE- Welding position is not an essential variable for branch connections.
21.5.2 Butt joint Bctwcrn Pipes - A test joint shall be made with the
pipes in one or more of the following positions according to which is most
representative
of production conditions:
a) Horizontal
rdtating,
b) Vertical fixed,
c) Horizontal fixed, and
d) 45 to horizontal tixcd.
cation
Qualification
under (c) includes
under (d) includes qualification
qualification
under (a) and qualifiunder (a) and (b).
Tests
21.7.1
shall be visually
If found to be acceptable and if radiography is to be used for
examined.
the examination
of.production
work, the test joints shall then be radiographed before the cutting of test specimens. Radiography
shall be carried
out in accordance
with the requirements
of either IS : 118%1967*
or
IS :4853-1368t
using the same technique as that to be used for production
work.
The-standard
of acceptance for each method of examination shall be
that determined in accordance with the riquirements
of 19.
-*Recommended practice for radiographic examination of fusion welded butt jointr in
steel plates (Jirsf rcuki~n ).
tRecommended
practice for radiographic
joints in steel pipes.
examination
23
of fusion wddcd
circumferential
__I_*
--.......__
..__~__.l_,I..
IS : 6916 - 1973
21.7.1.2
Transverse
be machine
cut
IS : 3600-1966*.
various thickness
has been used, it
The tensile
requirements
of
minimum
tensile
:, or
TEST PLATE OR
PIPEAS WELDED
mm
1.5 to 10 including
Over 10, under 20
20 and over
OP THI~X~~E~~ES
TYPB AND Nvxsmt op T~CET
QUALIFIED
&!XJVIRED*
A---p-A------.
r-FaCe
MitB
MO%
Side
Root
ywdgd
mm
mm
Bend
Bend
Bend
Tension
2
2
1.5
2
2tt
5
2t
2
2
2
5
20
4
2
RANQE
*Either the face and root bend tests or the side bend tcrtr may be used for thicknroa
from 10 to 20 mm.
tThe maximum thickness qualified with pipe amaIler than 125 mm ir two timo the
thicknaa of the pipe brit not more than 20 nun.
IS t 6916 - 1973
specimen. If a recess strip is used, this surface of the specimen may be
machined to a depth not exceeding the depth of the recess to remove the
strip. The specimen shall be bent with a jig in accordance with IS :36001966*. Face bend specimens shall be placed such that the face surface
becomes the convex side of the bend specimen. In the case of the root
bend test the specimens shall be placed such that the root of the weld
becomes the convex side of the bend specimen. The specimen shall be
bent until the curvature of the specimen is such that 0.8 mm diameter
wire cannot be passed between the curved portion of the male member of
the jig and the specimen. The diameter of the former shall be equal to
four times the thickness of the specimen.
When the parent metal is incapable of withstanding this; test, the
former diameter and the angle of bend shall be modified accordingly.
After bending the specimen shall be examined for the appearance of
opened out defects. Any specimen having any such open defects exceeding
3 mm measured in any direction shall be considered as having failed.
Cracks occurring on the corners of the specimen during bending shall be
disregarded.
21.7.1.5 Macro-examination
-Each
test joint shall be sectioned at
These sections shall be prepared for
three places for macro-examination.
macro-etching and etched to give a clear indication of the weld structure.
The standard of acceptance shall be determined in accordance with the
requirements of 19.
21.7.2 Fillet Welds Between Plates and Branch Connections Between Pipes
21.7.2.1
Visual examination-All
21.7.2.2 Macro-examination
- Each test joint shall be sectioned at
These sections shall be prepared for
three places for macro-examination.
macro-etching and etched to give a clear indication of the weld structure.
The standard of acceptance shall be that determined in accordance with
the requirements of 19.
23.7.3 Hardness survey for All Test Joints - A hardness survey shall be
conducted across a cross section of the test weld and the results shall be
recorded for comparison with results of hardness surveys on production
welds when required.
The method of hardness testing shall be in accordance with IS : 1Sol-19687.
21.7.4 Imfiact Test -When
relevant from the point of view of service
conditions, impact tests shall be included in the assessment of the welding
*Code of procedure for testing of fusion weldedjoints and weld metal in steel. (Since
revised and split into variour parts ) .
tMethod for Vickera hardnesstest for steel (first rcuisron ).
25
21.7.5Repeat Tests - If any of the above tests show that the welds do
not meet the required standard,
two further test joints shall be made and
the tests repeated.
If either of these additional
test joints does not meet
the required standard,
the welding procedure
shall not be regarded as
capable of meeting the requirements
of this standard without modification.
22. WELDER QUALIFICATION
22.1 General - Welders employed on welding castings in accordance
with this standard shall have been successfully tested by the manufacturer
to the satisfaction
of an inspecting
authority
which shall be given the
opportunity
of witnessing the tests. In all cBses, complete records of such
tests- shall be available for inspection.
22.1.1 The welder who satisfactorily
completes the procedure
fication tests is thereby exempt from undergoing
separate welder
fication tests involving the same range of procedures.
qualiquali-
26
connection
Qualification
22.3
( pipes ).
qualification
under (b).
Position
22.3.1 ButtJoint or Fillet Weld Behem Plates - A test joint shall be made
for each welding position that is to be used in production (flat, horizontalvertical, vertical or overhead ).
Qualification
in the horizontal-vertical
and vertical positions also
Qualification
in the vertical and
qualifies for welding in the flat position.
overhead
positions also qualifies for welding in the flat and horizontalvertical positions.
22.3.2 Butt Joint Between Pipes- A test joint shall be made with the
pipes in one or more of the following positions according to which is most
representative
of production conditions:
a) Horizontal
bj
Vertical
c) Horizontal
rotating,
fixed,
fixed, and
d) 45 to horizontal
fixed.
22.3.2.1
Qualification
under (c) includes qualification
qualification
under (d) qualifies for welding in all positions.
22.3.2.2
Qualification
on a butt joint between pipes also qualifies
for welding butt joints and fillet welds between plates for the same welding position.
22.3.2.3
connections.
Welding
position
is not an essential
variable
for branch
18 : 6916- 1973
22.5 Tests
22.5.1
shall
22.5.1.2 Side bend test - Side bend test specimens shall be machine
cut from each test joint to the dimensions specified in IS : 3600-1966$.
The number of tests required to qualify a procedure for various thickness
ranges shall be as given in Table 3. If a backing strip has been used, it
shall be removed prior to testing.
3 TYPE AND NUMBER
OF TEST SPECIMENS
AND RANGE
THICKNESSES
QUALIFIED
( WELDERS PERFORMANCES
)
TABLE
THICKNESS
t. OF
RANGE
PIPEAS
bk.DED
mm
OF Tmc$mces
TYPE
QUALIBIED
TEST PLATE OR
Min
REQUIRED*
~--_--h-__--~
#-------_h----~
Ma.%
mm
OF
mm
1.5 to 10 including
1.5
2t
21
2r
20 and over
Mwa&t:dbe
Side
Bend
Face
Bend
Root
Bend
1
examination
IS t 6916- 1973
parent metal is incapable
and angle of bend should
of withstanding
this test, the former diameter
be modified accordingly.
and etched
Fillet
22.5.2.1
the standard
requirements
shall be that
of acceptance
of 19.
being
determined
in accordance
*Code of procedure for testing of fusion welded joints and weld metal in steel. ( Since
mvbal and split into variow parts ).
29
IS t 6916- 1973
22.5.2.2 Macro-examination -Each
test joint shall be sectioned at
These sections shall be prepared for
three places for macro-examination.
macro-etching and etched to give a clear indication of the weld structure.
in accordance
22.5.3 Repeat Test - If any of the above tests show that the welds do
not meet the required standard, two further test joints shall be made and
the tests repeated.
If either of these additional test joints does not meet
the required standard, the welder shall not be regarded as capable of meeting the requirements of this standard without further training.
APPENDIX
A
(Clauses5.1.4, 7.3, 8.1, 8.3,15.5, 17.1, 19.1, 21.4and22.2)
ITEMS
FOR AGREEMENT
CONTRACTING
BETWEEN
PARTIES
are
THE
agreement
a>Flux/electrode
b)
wire combinations
for subinerged-arc welding
( 5.1.4 ).
Acceptability
of fusion faces when non-destructive testing is
used ( 7.3 ).
Sealing-off of filamentary shrinkage ( 7.3 ).
Type of backing strip ( 8.1).
4
4
4 Use
f-1 Use
30
1 t 6916 - 1973
( Continuedfrom
pugs 2 )
Members
S~sr D. P. CEATTEWJEE
SHRI l-3.HILL
SHEI H. S. RAO ( Al&mats )
SERI V. G. JAOANNATH
SHRX R. VISVANATHAN (Al&m&
SSSI S. V. NADKA~NI
SHRI K. RAMA RAO
REPRESENTATIVE
REPRESENTATIVB
Rapresenting
Directorate
General
of Supplies
&
New Delhi
Lloyds Register of Shipping, Calcutta
&-Is,
31
BUREAU
OF
INDIAN
STANDARDS
Headquarters;
Manak Bhavan, 9 Bahadur Shah Zafar Marg, NEW DELHI 110002
Talephones : 331 01 31, 331 13 75
Telegrams : Manaksanrtha
( Common to all offices )
Regional
Offlces:
Telephones
Central
: Manak Bhavan, 9 Behadur Shah Zafar Marg,
331 01 31
[ 3311375
NEW DELHI-1 10002
*Eastern : 1114 C.I.T. Scheme VII M, V. I. P. Road,
36 24 99
Maniktols, CALCUTTA 700054
Northorn : SC0 445-446, Sector 35-C,
21643
[ 31641
CHANDIGARH
160036
41 24 42
Southern : C. I. 1. Campus, MADRAS 600113
412519
{ 412916
tWostern : Manakalaya, E9 MIDC, Marol, Andheri (East),
6329296
BoMBAY 400093
Branch
Oflees:
Pushpak Nurmohamed Shaikh Marg, Khanpur,
26348
[ 2 63 49
AH M EDABAD 380001
SPeenya Industrial Area, 1 st Stage, Bangalore Tumkur Road
38 49 55
I 38 49 56
BANGALORE 560058
Gangotri Complex, 5th Floor, Bhadbhada Road, 1. T. Nager,
66716
BHOPAL 462003
Plot Ne. 82/83, Lowis Road, BHUBANESHWAR
751002
6 36 27
53/5, Ward No. 29, R. 6. Barua Road, 5th Byelane,
33177
GUWAHATI 781003
5-8-56C L.. N. Gupta Marg ( Nampally Station Road ),
23 1083
HYDERABAD 500001
63471
R14 Yudhleter Marg, C Scheme, JAIPUR 302005
[ 6 98 32
21 68 76
117/41 B B Sarvodaya Nagar, KANPUR 268005
[ 218292
62305
Patllputra Industrial Estate, PATNA 800013
6 21 04
T.C. No. 14/1421, University P.O., Palayam
[ 621 17
TRIVANDRUM
695035
lnspecflon
Oflce
(With Sale Point) :
Pushprnjali, 1st Floor, 205-A West High Court Road,
Shankar Nagar Square, NAGPUR 440010
Institution of Engineers ( India) Building. 1332 Shivaii Nager,
PUNE 411005
2 51 71
52436
27
lSalee Office in Calcutta la at 5 Chowrlnghro Approach, P.O. Prlncep
Sttaet, Calcutta 700072
89
tSalea ORICe In Bombay la at Novelty Chamber&
Grant Road,
Bombay 400007
22
$Salet ORiCe In Bangalore IO at Unity Bulldlng, Nararlmharaja
Square
Bengalore 560002
Prlntrd rt Slmso Printing Prom. Dolhl.
66 00
65 28
36 71
India