POLB WDC Ver 3 0
POLB WDC Ver 3 0
POLB WDC Ver 3 0
02/29/2012
Table of Contents
List of Tables ..................................................................................................................... v
List of Figures ................................................................................................................... vi
List Symbols .................................................................................................................... vii
Acronyms/Definitions ...................................................................................................... xi
1
2.2
2.3
2.4
2.5
2.6
2.7
2.8
2.9
02/29/2012
3.2
3.3
3.4
3.5
3.6
3.7
3.8
3.9
4.2
4.3
4.4
4.5
4.6
02/29/2012
4.7
4.8
4.9
5.2
5.3
5.4
02/29/2012
5.5
6
iv
02/29/2012
List of Tables
Table 2-1:
Table 3-1:
Table 3-2:
Table 3-3:
Table 4-1:
Table 4-2:
Table 5-1:
02/29/2012
List of Figures
Figure 2-1: Design Acceleration Response Spectra for Unimproved Ground
Conditions ....................................................................................................2-2
Figure 2-2: Design Acceleration Response Spectra for Improved Ground Conditions .2-2
Figure 2-3: Axial Soil Springs ........................................................................................2-9
Figure 2-4: Sliding Layer Model ...................................................................................2-12
Figure 3-1: Broken Piles Layout .....................................................................................3-2
Figure 3-2: Container Handling Equipment Design Wheel Load ...................................3-4
Figure 3-3: Vessel Berthing ............................................................................................3-5
Figure 3-4: Mooring Line Force......................................................................................3-6
Figure 4-1: Flow Diagram for Seismic Analysis ............................................................4-6
Figure 4-2: Pile Spacing for Modeling of Typical Wharf Strip ......................................4-7
Figure 4-3: Pile-Deck Structural Model Schematic Showing Strain Penetration
Length ...........................................................................................................4-8
Figure 4-4: Stress-Strain Relationship for Confined and Unconfined Concrete ...........4-10
Figure 4-5: Concrete Strength Ratio versus Confining Steel Ratio ..............................4-11
Figure 4-6: Stress-Strain Relationship for Reinforcing Steel........................................4-12
Figure 4-7: Stress-Strain Relationship for Prestressing Steel .......................................4-13
Figure 4-8: Momentcurvature Curve and Idealization for Method A .........................4-15
Figure 4-9: Moment-curvature Curve and Idealization for Method B ..........................4-16
Figure 4-10: Idealized Moment-rotation Curve ..............................................................4-18
Figure 4-11: Pushover Model with p-y Springs ..............................................................4-19
Figure 4-12: Example of Pushover Curve and Plastic Hinge Sequence .........................4-19
Figure 4-13: Horizontal Marginal Wharf Configurations ...............................................4-20
Figure 4-14: Depth to Point of Fixity ..............................................................................4-21
Figure 4-15: Flow Diagram for the Elastic Stiffness Method .........................................4-23
Figure 4-16: Flow Diagram for Substitute Structure Method .........................................4-24
Figure 4-17: Effective System Stiffness for a Wharf Segment .......................................4-25
Figure 4-18: Elevation View of Transverse Wharf Segment ..........................................4-26
Figure 4-19: Super-pile Locations for a Wharf Segment ................................................4-26
Figure 4-20: Wharf Response due to Longitudinal and Transverse Excitations.............4-28
Figure 4-21: Pile Displacement Capacity........................................................................4-31
Figure 4-22: Curvature Ductility Factor versus Curvature Ductility Demand................4-34
Figure 4-23: Transverse Shear Reinforcement Shear Strength Components ..................4-35
Figure 4-24: Axial Load Shear Strength Components ....................................................4-36
Figure 4-25: Share Key Factor versus Wharf Segment Length ......................................4-37
Figure 4-26: Plastic Hinge Formation due to Kinematic Loads......................................4-38
Figure 4-27: Anchorage Details for Pile Dowels ............................................................4-39
Figure 5-1: Beam on Elastic Foundation.........................................................................5-7
vi
02/29/2012
List Symbols
Agross
Asc
Asp
B
BE
BU
C
D
D
Dp
DMF
E
Ec
Eps
Es
Esh
EQ
F
Fi
Fn
Fp
F
H
H
I
Ieff
Igross
Jeff
Jgross
K
Ke
L
LB
Lc
LL
Lp
Ls
Lu
M
Mn
Mo
02/29/2012
Mp
Pile idealized plastic moment capacity
Mp,in-ground Pile plastic moment capacity at the in-ground plastic hinge including the effect
of axial load due to crane dead load
Pile plastic moment capacity at the top plastic hinge including the effect of axial
Mp, top
load due to crane dead load
My
Moment at first yield
Nu
External axial compression on pile including seismic load
P
Mooring line load
R
Creep loads
RF
Force perpendicular to the fender panel due to berthing load
S
Shrinkage loads
T
Temperature loads
Tcrane
Translational elastic period of the crane mode with the maximum participating
mass
Effective period for iteration n
Tn
Tw
Effective elastic period of the wharf structure based on cracked section
properties
Transverse elastic period of a wharf segment
Twi
U
Total design load in moment, shear forces or axial forces
UB
Upper bound
Va
Shear strength due to axial load
Concrete shear strength
Vc
VF
Fender Shear Force
Vn
Nominal shear strength
Vo
Pile overstrength shear demand
Vp
Pile plastic shear
Vs
Transverse reinforcement shear strength
W
Wind loads on structure
Effective dead load of the wharf strip considered
WDL
WW
Waterside crane wheel load
Landside crane wheel load
WL
X1, X2
Distance from the back of the wharf
c
Depth from the extreme compression fiber to the neutral axis at flexural strength
co
Clear concrete cover plus half the diameter of the transverse reinforcement
dbl
Diameter of dowel reinforcement
dgap
Distance between the top of the pile steel shell and the deck soffit
e
Eccentricity between the wharf center of mass and the center of rigidity
fc
Concrete compression stress
28-day unconfined concrete compressive strength
fc
fcc
Confined concrete compressive strength
fce
Expected compressive strength of concrete
f l
Effective lateral confining stress
Maximum tensile strength of prestressing steel
fpu
Expected maximum tensile strength of prestressing steel
fpue
fpy
Yield strength of prestressing steel
Expected yield strength of prestressing steel
fpye
viii
c
d
p,m
t
t,0
t,n
t,n-1
X1,X2
XL
XT
Y1,Y2
YL
YT
y
ys
02/29/2012
02/29/2012
c
cc
co
cu
p
pue
pye
s
smd
sh
spall
ye
m
p,dem
p,m
u
y
yi
m
p,m
p,dem
u
y
s
eff,n
02/29/2012
Acronyms/Definitions
AASHTO
AC
ACI
AISC
AF&PA
ANSI
AREMA
ASD
ATC
AWS
CALTRANS
CBC
CLE
Cooper E-80
CPT
CQC
c.g.
DCR
DE
DMG
e.g.
FEMA
FHWA
FOS
ft
HL-93
in.
Joint
klf
ksi
LOA
LRFD
MCEER
MHHW
MHW
MLLW
MLW
MSL
mph
M-
NAVD 88
02/29/2012
NAVFAC
NCEER
NCHRP
NDS
NEHRP
NGVD 29
NSF
NTHA
N/A
OLE
PCI
PIANC
PGA
POLB
pcf
psf
p-q
p-y
RO-RO
SDC
SLC
SLD
t-z
UCSD
UFC
USACE
WDC
Wharf exterior unit
Wharf interior unit
xii
02/29/2012
1 Introduction
This document contains design guidelines and criteria for pile supported wharf
construction. It is published by the Port of Long Beach (POLB or Port) to assist
engineering staff of the POLB, as well as consulting firms providing consulting services
related to the design of wharves for the POLB. Any deviation from the criteria listed
herein will require specific prior written approval from the Port.
Design guidelines and reference materials cited throughout this document will be revised
from time to time as required. Updates and revisions occurring during design shall be
followed as directed by the Port.
This document is Version 3.0 of the Port of Long Beach Wharf Design Criteria and it
supersedes the previous Version 2.0 that was published on January 30, 2009 and Version
1.0 that was published in March 2007.
This document was prepared for the POLB under the leadership of Cheng Lai, P.E., S.E.,
Senior Structural Engineer, POLB, and by a team of consultants consisting of Moffatt &
Nichol and Earth Mechanics, Inc. The expert review team included Dr. Nigel Priestley,
Emeritus Professor, Department of Structural Engineering, University of California, San
Diego and Dr. Geoffrey Martin, Emeritus Professor, Department of Civil Engineering,
University of Southern California.
1-1
02/29/2012
1-2
02/29/2012
2 Geotechnical Considerations
Geotechnical evaluations identified in this section shall use methodologies that are
considered acceptable standards of practice in the industry.
For seismic evaluations, ground motion criteria provided in Section 2.1 shall be used.
Ground motions and response spectra are provided in the Port-Wide Ground Motion
Study, Port of Long Beach, California (Ref. 17), Port-wide Ground Motion Study, Port
of Long Beach, California, Addendum to Final Report (Ref. 18), and Addendum No. 2
to Port-wide Ground Motion Study, Port of Long Beach, California (Ref. 19). No
deviation from these ground motions shall be allowed without prior written approval by
the Port.
These guidelines are specific to pile-supported marginal wharves with engineered sloping
ground conditions located under the wharf structure comprising dredged soils or cut
slopes protected or stabilized by quarry run rock material. Applicability of these
guidelines to other structures may be allowed upon written approval by the Port.
2-1
02/29/2012
Recommended design acceleration response spectra for OLE, CLE and DE for different
ground conditions are shown in Figure 2-1 and Figure 2-2. Further details are provided in
References 17 and 18.
1.2
5% Damping
DE Area I
DE Area II
DE Area III
1.0
DE Area IV
CLE
OLE
0.8
0.6
0.4
0.2
0.0
0.0
0.5
1.0
1.5
2.0
2.5
3.0
3.5
4.0
Period (sec.)
5% Damping
DE Area II
DE Area III
1.0
DE Area IV
CLE
OLE
0.8
0.6
0.4
0.2
0.0
0.0
0.5
1.0
1.5
2.0
2.5
3.0
3.5
4.0
Period (sec.)
2-2
02/29/2012
Adequate coverage of subsurface data, both horizontally and vertically, shall be provided
to develop geotechnical parameters that are appropriate for the project. An adequate
number of explorations should extend to depths of at least 20 feet below the deepest
anticipated foundation depths and should be deep enough to characterize subsurface
materials that are affected by embankment behavior. Particular attention should be given
during the field exploration to the presence of continuous low-strength layers or thin soil
layers that could liquefy or weaken during the design earthquake shaking or cause
embankment failure during dredging or other construction activities. Cone penetration
tests (CPT) provide continuous subsurface profile and, therefore, should be used on large
projects to complement exploratory borings. When CPTs are performed, at least one
boring shall be performed next to one of the CPT soundings to check that the CPT-soil
behavior type interpretations are reasonable for the project site. Any differences between
CPT interpretations and subsurface conditions obtained from borings shall be reconciled
prior to developing geotechnical design parameters.
An appropriate and sufficient number of laboratory tests shall be performed to provide
the necessary soil parameters for geotechnical evaluations. Guidelines for site
characterization can be found in Soil Mechanics (Ref. 28) and Design and
Construction of Driven Pile Foundations (Ref. 20) or other appropriate documents.
2-3
02/29/2012
BACKLAND
pp2a
2
p1pa1
WHARF DECK
X2
X
X1
X
p1 a
(psf)
X1
(ft)
p2a
(psf)
X2
(ft)
Min.
FOSb
Static Condition
250
75
1,200
Remaining
Backland
1.5
Temporary Condition
(See Section 2.4.1)
250
Entire
Backland
1.25
250
75
800
Remaining
Backland
-c
Post-earthquake Static
Condition
250
75
800
Remaining
Backland
1.1
Load Condition
Load values may be revised based on project-specific information, upon prior written
approval by the Port.
b
FOS Factor of Safety.
c
Yield acceleration shall be obtained from the analysis to determine lateral deformations per
Section 2.9.2.
2-4
02/29/2012
2-5
02/29/2012
2.5 Settlement
2.5.1 Static Consolidation Settlement
Long-term static consolidation settlement of sites that are underlain by continuous or
large lenses of fine-grained soils shall be evaluated. The long-term static settlement
should be estimated following guidelines outlined in Foundation and Earth Structures
(Ref. 27) or other appropriate documents. If long-term settlement is anticipated, the
resulting design impacts shall be considered, including the potential for development of
downdrag loads on piles (See Section 2.7.1).
2.5.2 Seismically Induced Settlement
Seismically induced settlement shall be evaluated. The seismically induced settlement
should be based on guidelines outlined in Recommended Procedures for Implementation
of DMG Special Publication 117, Guidelines for Analyzing and Mitigating Liquefaction
Hazards in California (Ref. 24) or other appropriate documents. If seismically induced
settlement is anticipated, the resulting design impacts shall be considered, including the
potential development of downdrag loads on piles (See Section 2.7.1).
02/29/2012
02/29/2012
tip resistance of the pile and the side friction resistance below the lowest layer
contributing to the downdrag should be used in the capacity evaluation. The ultimate
axial geotechnical capacity of the pile should not be less than the combination of the
seismically induced downdrag load and the maximum of the service load combinations.
2.7.2 Axial Springs for Piles
The geotechnical engineer shall coordinate with the structural engineer and develop axial
springs (t-z) for piles. The t-z springs may be developed either at the top or at the tip of
the pile, see Figure 2-3. If the springs are developed at the pile tip, the tip should include
both the frictional resistance along the pile (i.e., side springs [t-z]) and tip resistance at
the pile tip (i.e., tip springs [q-w]), as illustrated in Figure 2-3. If t-z springs are
developed at the pile top, the appropriate elastic shortening of the pile should also be
included in the springs. Linear or nonlinear springs may be developed if requested by the
structural engineer.
During development of the axial soil springs, the ultimate capacity of the soil resistance
along the side of the pile and at the tip of the pile should be used. Normally, it is assumed
that the soil resistance along the side of the pile is developed at very small displacement
(e.g., less than 0.5 inches) while the resistance at the tip of the pile will require large
displacements (e.g., 5% of the pile diameter).
2.7.3 Upper and Lower Bound Springs
Due to the uncertainties associated with the development of axial springs (t-z), such as
the axial soil capacity, load distributions along the pile, and the simplified spring
stiffnesses used, both upper bound (UB) and lower bound (LB) limits should be used for
the axial springs. The UB and LB springs should be developed by multiplying the load
values estimated in Section 2.7.2 by 2 and 0.5, respectively, to be used in the structural
analysis. Different values may be acceptable if supported by rational analysis and/or
testing and upon written approval by the Port.
2-8
02/29/2012
P
Applied
Load
P
Applied
Load
Pile
Pile
t-z
(Side Spring)
qw
q-w
(TipSpring)
(Toe Spring)
q
T-z
(Com posite
Spring)
w
Figure 2-3: Axial Soil Springs
02/29/2012
rational analysis and/or testing may be performed to justify the use of different values.
For other wharf slope/embankment/dike types, the UB and LB springs should be
developed on a site-specific basis.
02/29/2012
initial estimate of the free-field dike deformations should be made using the curves
provided in Seismic Analysis and Design of Retaining Walls, Buried Structures, Slopes
and Embankments (Ref. 36) or other appropriate documents as discussed in Section
2.4.4. For the 24-inch octagonal, precast, prestressed concrete piles and pile
configurations that are typically used for Port wharf structures, deformations are
generally considered acceptable in terms of pile strain limits and performance criteria
when the permanent free-field dike deformations are less than about 3 inches for the
OLE, less than about 12 inches for the CLE and less than about 36 inches for DE
conditions. Additional kinematic analysis is not required if the free-field dike
deformations are less than these limits.
In cases where dike deformations estimated using the simplified Newmark sliding block
method exceed the above displacement limits, site-response evaluations may be
necessary to revise the free-field dike deformation analyses. Upon written approval by
the Port, one-dimensional site response analyses may be performed to incorporate local
site effects in developing site-specific acceleration time-histories at the base of the sliding
block (within motions) for Newmark analyses. For the OLE and CLE, the firm-ground
time-histories provided in Port-Wide Ground Motion Study, Port of Long Beach,
California (Ref. 17) should be used as the basis for determining input in the siteresponse evaluations. For the DE, time-histories will be provided by the Port. Sensitivity
analyses should also be performed on factors affecting the results. The site-specific timehistories representing the within motions should then be used in the simplified
Newmark sliding block method to revise the dike deformation estimates. If the revised
dike deformations still exceed the acceptable values, more detailed numerical soilstructure interaction evaluations may be necessary.
A full soil-structure interaction numerical analysis for kinematic loading may not be
required if it can be shown by structural analysis that reduced displacement demands
estimated by simplified Newmark evaluations incorporating pile pinning effects are
structurally acceptable, as discussed in the following publications: Recommended LRFD
Guidelines for the Seismic Design of Highway Bridges (Ref. 8) and Seismic Analysis
and Design of Pile Supported Wharves (Ref. 11). The geotechnical engineer should
provide the structural engineer with level-ground p-y springs for the weak soil layer and
soil layers above and below the weak layer using appropriate overburden pressures for
performing a simplified pushover analysis to estimate the OLE, CLE and DE
displacement capacities and corresponding pile shear within the weak soil zone. For the
pushover analysis, the estimated displacements may be uniformly distributed within the
thickness of the weak soil layer (i.e., zero at and below the bottom of the layer to the
maximum value at and above the top of the weak layer). At some distance above and
below the weak soil layer, see Figure 2-4, the pile should be fixed against rotation, and
also against translation relative to the soil displacement. Between these two points (at
least 10Dp from the soil layer), lateral soil springs are provided, which allow deformation
of the pile relative to the deformed soil profile. The geotechnical engineer should perform
pseudo-static slope stability analysis (Section 2.4.2) with the pinning effects of piles
arising from pile shear in the weak zone incorporated and estimate the displacement
demands using simplified Newmark analysis. If the estimated displacement demands are
less than the displacement capacities as defined by the structural engineer, no further
analysis for kinematic loading will be necessary.
2-11
02/29/2012
10 Dp
10 Dp
Fixed base
2-12
02/29/2012
490 pcf
175 pcf
50 pcf
150 pcf
120 pcf
150 pcf
150 pcf
3-1
02/29/2012
Wharf
Deck
Broken
Pile(s)
Waterside
Crane Beam
3-2
02/29/2012
Flexural
Capacityb
Pile Soil
Capacity
Factor of
Safetyc
Load
Factora
WW
Waterside
WL
Landside
50 klf
50 klf
1.3
Mn
2.0
50 klf
N/A
1.3
1.1Mn
1.5
CL
CL
Truck
Crane
Truck
2'-6"
5'-0" 5'-0" 5'-0"
2'-6"
5'-0" 5'-0" 5'-0"
2'-6"
5'-0" 5'-0" 5'-0"
Truck Truck
Crane
48'-6"
Truck Truck
Crane
48'-6"
CL
Truck Truck
Crane
W
W
2'-6"
5'-0" 5'-0" 5'-0"
Waterside Rail
LL
W
Landside Rail
40'-0"
40'-0"
02/29/2012
Load
Uniform Loads
0%
Truck Loads
10%
10%
20%
3-4
02/29/2012
0.26 foot/second
ft
5
5o
V = 0.425 s
Fender
FenderLine
Line
(3.1)
where:
VF
RF
=
=
02/29/2012
stern breasting line separations as well as distances to possible adjacent vessel breasting
lines. Where applicable, mooring line loads shall also be considered adjacent to
expansion joints and/or the end of the structure.
Mooring hardware for container ships shall have a minimum capacity of 200 metric tons.
For other types of vessels, which may require higher mooring hardware capacities, a
more detailed mooring analysis shall be performed. For mooring analysis use 75 mph
design wind speed (30 seconds duration with 25 years return period), for more details
refer to 2010 CBC Section 3103F.5 (Ref. 14).
Face of
Wharf
30 max.
P
Deck
Elevation
Plan
3-6
02/29/2012
02/29/2012
3-8
02/29/2012
L+I
BE
R+S+T
BU
1.20
1.60
1.60
1.60
1.20
1.20
1.20
0.90
1.60
1.60
1.20
1.00
1.20
III
1.20
1.00
1.60
1.60
1.60
1.20
1.20
IV
1.20
1.60
1.60
1.60
1.60
1.20
1.20
II
L+ I
BE
R+S+T
BU
1.00
1.00
1.00
1.00
1.00
1.00
1.00
II
1.00
0.75
1.00
0.75
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
III
a
The Load Resistance Factor Design require the strength reduction factors, as
specified in ACI-318 2008. Strength reduction factors shall follow ACI-318
(Ref. 2) for reinforced concrete design and AISC (Ref. 4) for structural steel
design.
b
For the load factor of crane load case see Table 3-1.
c
Reduce load factor to 0.9 for dead load (D) to check members for minimum axial
load and maximum moment.
d
Increase in allowable stress shall not be used.
3-9
02/29/2012
3-10
02/29/2012
4-1
02/29/2012
Bulkheads
Bulkheads shall be designed for dynamic earth pressures induced during seismic events.
Cut-off wall shall be used to prevent loss of soil from the backland and shall not be
designed to provide seismic lateral resistance.
Slope Stability
A slope stability analysis, including seismic induced movements, shall be performed as
outlined in Section 2.
Utilities & Pipelines
Utilities shall be designed with flexible connections between the backland area and the
wharf capable of sustaining expected wharf movements under CLE response. Flexible
connections shall also be provided across wharf deck expansion joints.
4-2
02/29/2012
Table 4-1: Strain Limits
Component Strain
Solid
Concrete
Pilea
Hollow
Concrete
Pileb
Design Level
OLE
CLE
DE
Top of pile
hinge concrete
strain
c 0.005
No limit
In-ground hinge
concrete strain
c 0.005
c 0.0051.1s 0.012
Deep In-ground
hinge (>10Dp)
concrete strain
c 0.008
c 0.012
No limit
Top of pile
hinge
reinforcing steel
strain
s 0.015
In-ground hinge
prestressing
steel strain
p 0 .015
p 0 .025
p 0 .035
Deep In-ground
hinge (>10Dp)
prestressing
steel strain
p 0 .015
p 0 .025
p 0 . 050
Top of pile
hinge concrete
strain
c 0.004
c 0.006
c 0.008
In-ground hinge
concrete strain
c 0.004
c 0.006
c 0.008
Deep In-ground
hinge (>10Dp)
concrete strain
c 0.004
c 0.006
c 0.008
Top of pile
hinge
reinforcing steel
strain
s 0.015
In-ground hinge
prestressing
steel strain
p 0 .015
p 0.020
p 0 .025
Deep In-ground
hinge (>10Dp)
prestressing
steel strain
p 0 .015
p 0 .025
p 0 . 050
4-3
02/29/2012
Component Strain
Steel
Pipe
Pilesc
OLE
CLE
DE
Top of pile
hinge concrete
strain
c 0.010
c 0.025
No limit
Top of pile
hinge
reinforcing steel
strain
In-ground hinge
hollow pipe
steel strain
s 0.010
s 0.025
s 0.035
In-ground hinge
pipe in-filled
with concrete
steel strain
s 0.010
s 0.035
s 0.050
Deep In-ground
hinge (>10Dp)
hollow pipe
steel strain
s 0.010
s 0.035
s 0.050
02/29/2012
The flow diagram in Figure 4-1 shows the typical steps a designer should follow to
complete the seismic analysis and design for a wharf structure. After the design for
service static loads has been completed, the performance design shall be performed for
OLE, CLE and DE. The seismic design may require additional pile rows or a modified
pile layout. A model including the effective section properties, seismic mass, and soil
springs shall be prepared. An Equivalent Lateral Stiffness method may be used for
preliminary design, if desired. Nonlinear static pushover analysis is always required, and
will provide the displacement capacity based on strain limits for all methods. The
structural analysis shall account for wharf torsional plan eccentricity, soil structure
interaction, multi-directional effects of the ground motion and the interaction between
adjacent wharf segments. Displacement demand for regular wharves shall be estimated
by the Elastic Stiffness method, the Substitute Structure method, or Modal Response
Spectra Analysis. For wharves with irregular geometry, special cases, or when
demand/capacity ratios from Modal Response Spectra Analysis are too high, Nonlinear
Time-History methods may be employed for the global model to verify the analysis
results. Nonlinear Time-History analyses, however, shall not be conducted without prior
written approval from the Port.
The maximum pile displacement shall be determined from the demand analysis, and
compared to the displacement capacity. The demand determined using the Elastic
Stiffness and Substitute Structure methods shall be adjusted for torsional effects using the
Dynamic Magnification Factor. If the demand is greater than the capacity, the design
must be revised. If the demand is less than the capacity, the pile shear, the beam/deck pile
joint and P- effects shall be checked. If the simplified kinematic loading and lateral
spreading analysis performed per Section 2.9.2 requirements indicate that the anticipated
pile strains for the estimated deformations are likely to exceed the strain limits per
Section 4.4, kinematic analysis of the deep in-ground hinge shall be performed in
accordance with Section 4.12.
4.5.2 Earthquake Load Combinations
The following load combinations shall be used to determine seismic moment, shear and
axial demands for wharf deck and pile cap, and seismic shear and axial force demands for
piles:
U = (1K) D + 0.1 L + E + EQ
(4.1)
U = (1K) D + E + EQ
(4.2)
where:
U=
K=
4-5
02/29/2012
S ti
3)
Nonlinear Static
Pushover Analysis
Pile Displacement
Capacity c
(See Section 4.10.1)
Irregular
Structure or
Special Case
Yes
Preliminary Design:
Equivalent Lateral
Stiffness Method
(See Section 4.9.1)
Substitute Structure
Method
Nonlinear Time-History
Analysis
(See Section 4.9.4.3)
d = t x DMF
(See Section 4.9.2)
Displacement Demand, d
c>d
No
Revise Design
Yes
Component Capacities
Kinematic Load
4-6
Seismic Detailing
Requirements
(See Section 4.13)
02/29/2012
CL Waterside
Piles
Strip Width
l sp 0.1 f ye d bl
(4.3)
where,
lsp = Strain penetration length (in.)
dbl = The diameter of the dowel reinforcement (in.)
4-7
02/29/2012
Deck c.g.
Rigid
lsp
16"
Reinforced Concrete
Section Properties
Soffit
Top of Soil
Prestressed Concrete
Section Properties
6"
First Soil Spring
4-8
02/29/2012
The expected compressive strength of concrete, fce, recognizes the typically conservative
nature of concrete batch design, and the expected strength gain with age. The expected
yield strength for reinforcing steel and structural steel, fye, is a characteristic strength
and represents a low estimate of probable strength of the material, which is higher than
the specified minimum strength. Expected material properties shall be used to assess
capacity and demands for earthquake loads. Seismic shear capacity shall not be based on
the expected material strength, see Section 4.10.3. For determining the demand on
capacity-protected members, an additional overstrength factor shall be used on the
capacity of pile plastic hinges as described in Section 4.10. Except for shear, the expected
seismic material strengths shall be:
fce 1.3 fc
(4.4)
f ye 1.1 f y
(4.5)
f yhe 1 .0 f yh
(4.6)
f pye 1 .0 f py
(4.7)
f pue 1 .05 f pu
(4.8)
(4.9)
where,
fc =
28-day unconfined compressive strength
fy =
Yield strength of longitudinal reinforcing steel or structural steel
Yield strength of confining steel
fyh =
fpy =
Yield strength of prestressing steel
fpu =
Maximum tensile strength of prestressing steel
f ce , fye, fyhe, fpye, fpue = Expected material properties
Ec =
The following stress-strain curves may be used to determine the deformation capacity of
the structural members. Alternative stress-strain models are acceptable if adequately
documented and supported by test results.
Concrete
The stress-strain curves for both confined and unconfined concrete are shown in Figure
4-4. This model is based on Manders model for confined and unconfined concrete (Ref.
35).
4-9
02/29/2012
Confined
Concrete
Compression Stress,fc
f cc
Unconfined
Concrete
f ce
co co
spall
cc
cu
Compression Strain,c
Confined Concrete:
For confined concrete, the following are defined:
(4.10)
f cc
1
f ce
cc = co 1 5
(4.11)
7.94 f l
f
2 l
f cc f ce 1.254 2.254 1
f ce
f ce
(4.12)
f l
1
K e s f yh
2
(4.13)
4 Asp
D s
(4.14)
4-10
02/29/2012
cu
cc
f cc
fce
f l
Ke
=
=
=
=
=
=
=
=
s
fyh
Asp
D
s
Figure 4-5 plots the ratio of confined concrete compressive strength to expected
concrete compressive strength ( f cc / f ce ) with varying volumetric transverse steel
ratios (s). This graph may be used to determine the confined concrete strength, f cc
for circular core sections.
2.2
f ce = 5 ksi
fyh = 70 ksi
Ke = 0.95
f ce = 7 ksi
1.8
1.6
f ce = 9 ksi
f ce = 8.45 ksi
1.4
1.2
1
0
0.005
0.01
0.015
0.02
0.025
0.03
0.035
4-11
0.04
02/29/2012
For pile sections with different transverse reinforcement strengths or shapes (i.e.
rectangular stirrups), the confined concrete strength f cc may be approximated by 1.5 f ce
or calculated according to Manders model (Ref. 35).
Steel
The stress-strain curve for reinforcing steel is shown in Figure 4-6. The strain-hardening
equation for this curve is available in References 15, 32 and 33. To control the tensile
properties, A706 reinforcing steel is preferred for pile dowels. The stress-strain curve for
structural steel is similar to this curve (Ref. 15).
fue
fye
Es
ye
sh
smd
sh =
smd =
0.0150
#8 bars
0.0125
#9 bars
0.0115
0.0075
#14 bars
0.0050
#18 bars
0.120
0.090
f ue 1 .4 f ye
02/29/2012
Prestressing Steel
fpue
Prestressing Steel
Tensile Stress, fps
fpye
Eps
pye
pue
Elastic analysis assumes a linear relationship between stiffness and strength of structural
members. Concrete members display nonlinear response before reaching their idealized
yield limit state. Section properties shall reflect the cracking that occurs before the yield
limit state is reached. The effective section properties shall be used to determine realistic
values for the structures elastic period and seismic demands.
The effective moment of inertia, Ieff shall be used for the structural model. Ieff can be
determined based on the value of the secant slope of the moment-curvature curve
between the origin and the point of first yield:
E c I eff
My
(4.15)
yi
where:
Ec = Modulus of elasticity of concrete
4-13
02/29/2012
The seismic mass for the seismic analysis shall include the mass of the wharf deck,
permanently attached equipment, and 10% of the design uniform live loads or 100 psf. In
addition, 1/3 of the pile mass between the deck soffit and 5Dp below the dike surface
shall be considered additional mass lumped at the deck. Hydrodynamic mass associated
with piles, where significant, should be considered. For 24-inch diameter piles or less,
hydrodynamic mass may be ignored.
The seismic mass shall also include the larger of: 1) part of the crane mass positioned
within 10 feet above the wharf deck or 2) 5% of the crane mass.
4.6.5 Lateral Soil Springs
Upper and lower bound (UB and LB) lateral soil springs (p-y) shall be used to create two
distinct models to determine the seismic demands and the corresponding capacities. This
recognizes the inherent uncertainties associated with soil-structure interaction. The higher
of the two demand-to-capacity ratios will provide a conservative estimate of compliance
for displacement response. See Section 2 for further discussion on soil spring values.
4.6.6 Pile Nonlinear Properties
4.6.6.1 Moment-curvature Analysis
The plastic moment capacity of the piles shall be calculated by Moment-curvature (M-
analysis using expected material properties. The analysis must be modeling the core and
cover concrete separately, and must model the enhanced concrete strength of the core
concrete. The pile in-ground hinge section shall be analyzed as a fully confined section
due to the soil confinement. Reinforcement and prestressing steel nonlinearity must also
be modeled using material properties as specified in Section 4.6.2. Moment-curvature
analysis provides a curve showing the moments associated with a range of curvatures for
a cross-section based on the principles of strain compatibility and equilibrium of forces.
The analysis shall include the pile axial load and the effective prestressing force.
4-14
02/29/2012
The idealized plastic moment capacity, Mp, for typical concrete pile at the POLB
corresponds to the moment associated with an extreme concrete strain of 0.004, as shown
in Figure 4-8. Typically, the M- curve peaks around an extreme concrete strain of 0.004,
has a reduction in moment, and peaks again, depending on confinement, spalling of
concrete cover and strain-hardening of reinforcement. If the second peak on the curve is
less than the Mp value, the moment at the lower second peak should be taken as Mp.
However, for capacity protection analysis, the moment at the higher peak shall be used
for Mp. The elastic portion of the idealized M- curve passes through the curvature at first
reinforcing bar yield of the section or when concrete strain equals 0.002, whichever
occurs first (yi, My), and extends to meet Mp. The idealized yield curvature, y, is
determined as the curvature corresponding to the plastic moment value.
Moment-curvature Curve Idealization - Method B:
For other M- curves of concrete piles different than the typical POLB piles, the momentcurvature relationship may not exhibit the dramatic reduction in section moment capacity
near the cover spalling strain. This may occur for larger diameter concrete piles,
concrete-filled steel pipe piles with concrete plug connections, and hollow steel piles. For
these types, an equal area approach to determine the idealized M- curve is more
appropriate. For this approach, the elastic portion of the idealized M- curve should pass
through the point marking the first reinforcing bar yield or when c = 0.002, whichever
comes first (yi, My). The idealized plastic moment capacity is obtained by balancing the
areas between the actual and the idealized M- curves beyond the first yield point (Figure
4-9).
Actual Moment-curvature
Curve
Moment taken at
c = 0.004
Moment
Mp
Idealized Moment-curvature
Curve
My
Note: Mp is defined as
moment @ c = 0.004 or
moment at second peak,
whichever is lower, except for
capacity protection design, Mp
is defined as moment @ c =
0.004 or moment at second
peak, whichever is higher
p,m
yi y
Curvature
4-15
02/29/2012
Actual Moment-curvature
Curve
Mp
Equal Areas
Moment
My
p,m
yi y
Curvature
where:
My
yi
y
m
p,m
u
The plastic hinge length is needed to convert the moment-curvature relationship into a
force-displacement or moment-rotation relationship for the nonlinear static pushover
analysis. Table 4-2 cross references the equations that should be used to determine pile
plastic hinge lengths for different pile sections.
Table 4-2: Plastic Hinge Length Equations
Section
Top
In-ground
Concrete Pile
4.16
4.18
4.16
4.18
4.17
4.18
4.17
4.18
4-16
02/29/2012
For concrete pile dowel connections, the piles plastic hinge length, Lp (above ground),
when the plastic hinge forms against a supporting member, at deck soffits may be taken
as:
L p 0.08 Lc 0.1 f ye d bl 0.2 f ye d bl
(4.16)
where,
Lc
dbl
fye
= The distance from the center of the pile top plastic hinge to the point of
contraflexure in the pile (in.)
= Diameter of dowel reinforcement (in.)
= Expected yield strength dowel reinforcement (ksi)
For steel pipe sections connected to the deck by a concrete plug with dowels, the plastic
hinge length for the top of pile hinge may be taken as:
(4.17)
L p 0 .3 f ye d bl d gap
where,
dgap =
The distance between the top of the pile steel shell and the deck soffit
The plastic hinge length for in-ground hinges may be calculated as defined in equation
4.18 for piles with 18 to 30 inches in diameter. For piles with larger diameter, reduced
plastic hinge length for in-ground hinges may be used.
Lp 2Dp
(4.18)
where,
Dp
= Pile diameter
(4.19)
where,
4-17
02/29/2012
Mp
Moment
p,m
Rotation
u
y
m
= Ultimate rotation
= Idealized yield rotation (y = y Lp)
= Total rotation at the OLE, CLE or DE strain limits
4-18
02/29/2012
Deck
Dike
Piles
Soil Springs
(p-y)
Deck
Total Shear
2
5
Plastic Hinge
Plastic
3 Hinges
Dike
4
Piles
Displacement
b) Plastic Hinge Sequence
a) Pushover Curve
Horizontal irregularity occurs when wharves have unsymmetrical pile and/or dike
layouts, and when wharves have an angle point; see Figure 4-13. Figure 4-13 a) shows a
regular marginal wharf structure. The wharf in Figure 4-13 b) shows an irregular
marginal wharf constructed with a partial dike. Figure 4-13 c) shows two adjacent
wharves with large differences in stiffness, which may occur between two adjacent
wharves with different pile or soil stiffnesses. Figure 4-13 d) shows an irregular wharf
with an angle point.
4-19
02/29/2012
b) Irregular Wharf
with Partial Dike
a) Regular Wharf
k1
k2
d) Irregular Wharf
with Angle Point
Vertical irregularity occurs when soil profiles below the wharf have sharp variations in
lateral soil deformation over short vertical distances under seismic response.
4.8.2 Special Cases
4.8.2.1 Crane-wharf Interaction Analysis
A special case for crane-wharf interaction analysis shall be considered if the crane mass
impacts the wharf behavior as follows:
Tcrane 2Tw
(4.20)
where:
Tcrane = Translational elastic period of the crane mode with the maximum
participating mass
Tw =
Effective elastic period of the wharf structure based on cracked section
properties
For crane-wharf interaction analysis, the displacement demand, d of the wharf shall be
determined using Nonlinear Time-history Analysis per Section 4.9.4.3. This analysis
requires prior written approval by the Port.
4.8.2.2 Linked-wharf Interaction Analysis
A special case for linked-wharf interaction analysis shall be considered for wharf
structures if one of the following requirements is met:
1. LL < 400 feet or LL > 800 feet
2. B < 100 feet or B > 120 feet
3. More than 20% variation in the initial elastic stiffness of the wharf structure along the
wharf length
4-20
02/29/2012
where:
LL = length of the shortest exterior wharf unit
B = width of a wharf unit
For linked-wharf interaction analysis, the displacement demand, d of the wharf shall be
determined using Nonlinear Time-history Analysis per Section 4.9.4.3. This analysis
requires prior written approval by the Port.
The Equivalent Lateral Stiffness method uses a wharf model with piles fixed at the
bottom without p-y lateral springs. In this method, the equivalent depth to point of fixity,
Ls, is determined as the depth that produces the same top of pile displacement as that
given by an individual lateral analysis for a given lateral load applied at top of pile. The
equivalent pile length has all soil and associated lateral stiffness removed above its
supported base, as shown in Figure 4-14. For different assumed displacements, different
pile head conditions, free-head or fixed-head, and different subsurface conditions, Ls is
expected to vary from approximately two times pile diameter to approximately fifteen
times pile diameter.
Deck
Dike
Piles
Ls
Point of Fixity
This method may not accurately predict pile top and in-ground hinge forces; therefore
this method should only be used for preliminary design.
4.9.2 Dynamic Magnification Factor (DMF)
Most of the seismic lateral resistance of marginal wharves is provided by landward piles
due to long embedment in soil. The seaward piles are mainly used for gravity loads and
might provide about 10% of the overall seismic lateral resistance. This configuration
creates eccentricity between the center of mass and the effective center of rigidity for the
wharf, which will induce torsional response in the structure under longitudinal excitation.
4-21
02/29/2012
Displacement demand of the critical piles at the end of a segment can be determined by
multiplying the displacement demand calculated under pure transverse excitation by
Dynamic Magnification Factor, which accounts for torsional response and simultaneous
longitudinal and transverse excitations, and interaction across expansion joints. An
analytical study utilizing nonlinear time-history analysis was performed to calculate the
DMF (Ref 11) using OLE and CLE ground motions with lower and upper bound soil
springs conditions. The study was performed on 110-ft wide wharf with single segment,
two linked segments and three linked segments. Segment lengths varied between 400
feet, 600 feet, and 800 feet. The study results show that DMF for CLE is always lower
than DMF for OLE. Therefore, DMF for DE may conservatively be assumed to be equal
to DMF for CLE.
Based on the study results, the DMF may be calculated as follows:
Single Wharf Unit:
(4.21)
(4.22)
(4.23)
(4.24)
(4.25)
(4.26)
DMF = 1.10
(4.27)
where:
LL = length of the shortest exterior wharf unit
B = width of a wharf unit
LB = lower bound
UB = upper bound
Wharf Exterior Unit = a wharf structure with an expansion joint at one end
Wharf Interior Unit = a wharf structure with expansion joints at both ends
The DMF values shall be used for straight wharf units only if all the following conditions
are met, otherwise refer to Section 4.8.2.2 for the requirements of special case analysis:
1. 400 feet < LL < 800 feet
2. 100 feet < B < 120 feet
3. Less than 20% variation in the initial elastic stiffness of the wharf structure along the
wharf length
4. Crane-wharf interaction analysis is not required per Section 4.8.2.1
4-22
02/29/2012
The Elastic Stiffness Method is a single-mode pure transverse analysis of a typical wharf
strip, refer to Figure 4-2. This method uses the transverse elastic stiffness, ki, of wharf
segment determined from the pushover curve to calculate the pure transverse
displacement demand For this method, the damping ratio shall be 5%.
The pure transverse displacement demand shall then be modified with the DMF to
include the influence of simultaneous longitudinal response, interaction across expansion
joints, and torsional effects, to calculate the displacement demand d. The flow chart
shown in Figure 4-15 demonstrates the analysis steps for the Elastic Stiffness Method.
Calculate transverse elastic
stiffness from pushover curve for
a wharf segment, ki
Calculate seismic mass of a wharf
segment, m
Twi 2
m
ki
ki =
m=
Twi =
t =
Displacement demand
d t DMF
Figure 4-15: Flow Diagram for the Elastic Stiffness Method
4-23
02/29/2012
The Substitute Structure Method is a single-mode pure transverse analysis, modified for
simultaneous transverse and longitudinal response interaction across expansion joints and
torsional effects by the DMF to calculate the displacement demand. Figure 4-16
demonstrates the analysis steps to calculate the displacement demand using the Substitute
Structure Method.
This method is an iterative process that uses the effective secant stiffness, ke, of a wharf
segment at the demand displacement determined from the pushover curve, and an
equivalent elastic damping representing the combined effects of elastic and hysteretic
damping to determine the pure transverse displacement demand for each iteration, see
Figure 4-17.
Assume an initial value for pure
transverse displacement demand
t,o ,n = 1
Calculate effective secant stiffness
from pushover curve
for a wharf segment
ke,n=Fn/t,n-1
Calculate seismic mass of a wharf
segment, m
Tn 2
m
k e ,n
t ,n 1
n=
ke,n =
Fn =
Tn =
m=
t ,n
t,o =
d =
Displacement demand
100 % 3 %
Calculate DMF for the
wharf segment based on
Section 4.9.2
Yes
No
d t ,n DMF
t ,n t ,n 1 , n n 1
4-24
02/29/2012
Pushover Curve Bilinear Approximation
Pushover Curve
Total Shear
ke,n
ke,n-1
ke
t,n-2
ys
t,n-1
Displacement
The effective secant stiffness, ke is the slope of the line that starts from the pushover
curve origin point to the point of the first plastic hinge formed in a pile, refer to Figure
4-17. The system yield displacement, ys, is determined from the intersection of the
elastic and post-yield branches of the bilinear approximation. The Equal Energy
approach should be used to estimate the bilinear approximation of the system pushover
curve. The bilinear curve should be determined at an estimated displacement demand,
t,n-1, for CLE. The system yield displacement will always be larger than the
displacement at first yield of piles. The system displacement ductility demand at iteration
n, n, is determined as follows:
n t , n
(4.28)
ys
n 1
(4.29)
The wharf transverse displacement demand based on pure transverse excitation may be
Three dimensional demand analyses include Modal Response Spectra Analysis and
Nonlinear Time-History Analysis. A typical wharf segment between expansion joints has
a large number of piles, which may result in unacceptable matrix sizes for analysis. As an
alternative, the structural characteristics of a wharf segment may be modeled by using the
Super-Pile concept, as explained below.
4-25
02/29/2012
Four super-piles may be used to represent the combined properties and stiffness of piles
in the model for a regular wharf segment between expansion joints. For the analysis of an
irregular wharf, the super-pile concept should be used with special consideration of the
irregular elements.
The super-pile locations are determined based on the locations of the gravity piles and the
seismic piles, as shown in Figure 4-18. The gravity piles mainly carry vertical loads,
usually carrying less than 10% of the total lateral seismic load, and have less stringent
detailing requirements. Seismic piles also carry vertical loads and provide most of the
lateral seismic resistance with stringent detailing requirements.
Approximate location of
waterside super-pile
Approximate location of
landside super-pile
Deck
G3
G2
S2
Dike
G1
Gravity
(G) Piles
S1
Super-pile
Seismic
(S) Piles
G3
G2
G1
S2
S1
LL
CL Waterside
Piles
Row G3
Row G2
Row G1
yW
Row S2
yL
Row S1
C
L Landside Piles
LL
Center of Gravity (CG)
12
LL
12
Super-Pile
4-26
02/29/2012
The super-piles shown in Figure 4-19 are located at distances yL and yW from the center
line of landside pile row S1:
S2
yL
ni Fi yi
iS 1
S2
n F
i S 1
G3
and yW
n F y
i G1
G3
(4.30)
n F
i G1
where:
Distance of landside super-pile from centerline of landside pile row S1
Pile row (i.e. S1, S2, G1-G3 as shown in Figure 4-19 and Figure 4-18)
Total number of piles in row i for length LL
Lateral force per pile in row i from pushover analysis when seismic pile
yield reach displacement
yi = Distance of row i from the landside pile row S1
yW = Distance of waterside super-pile from centerline of waterside pile row S1
yL
i
ni
Fi
=
=
=
=
The super-pile stiffness is calculated from the pushover curve for the piles represented.
The location of the super-pile should be determined based on the elastic response when
the seismic piles reach yield displacement. For compatibility reasons, the gravity piles
should have their stiffness determined at the same displacement. The landside super-pile
stiffness is equal to the stiffness of all piles on the landside of the dike. The remainder of
the total pile stiffness goes to the waterside super-piles. For a regular structure, the two
landside super-piles should have equal stiffness, and the two waterside super-piles should
have equal stiffness. In order to ensure the correct torsional stiffness under longitudinal
response, the super-piles must be located at the center of gyration of the wharf segment.
For a regular wharf segment the super-piles must be located at a distance of L L / 12
from the segment centroid, as shown in Figure 4-19.
The simplified model described above is suitable for both Modal Response Spectral
Analysis and Nonlinear Time-History Analysis.
4.9.4.2 Modal Response Spectra Analysis
This method is essentially a linear response spectrum analysis for a stand-alone wharf
segment. When wharf segments are linked by shear keys at movement joints, Modal
Response Spectral Analysis will not provide adequate representation of shear key forces
or displacement of the movement joint. A three dimensional linear elastic modal response
analysis shall be used with effective section properties to determine lateral displacement
demands.
Sufficient modes shall be included in the analysis such that 90% of the participating mass
is captured in each of the structures principal horizontal directions. For modal
combinations, the Complete Quadratic Combination (CQC) rule shall be used. A
damping ratio of 5% for spectral analysis shall be used unless a higher ratio can be
justified.
4-27
02/29/2012
X
YT
YL
XT
Node
XL
Longitudinal
Excitation
Transverse
Excitation
Input response spectra shall be applied separately along two orthogonal global axes
(longitudinal and transverse), see Figure 4-20. Spectral displacement demand shall be
obtained by the maximum of the following two load cases:
Case 1: Combine the displacement demand resulting from 100% of the
longitudinal load with the corresponding displacement demand
from 30% of the transverse load:
X 1 XL 0.3 XT
Y 1 YL 0.3 YT
Case 2: Combine the displacement demand resulting from 100% of the
transverse load with the corresponding displacement demand from
30% of the longitudinal load:
X 2 0.3 XL XT
Y 2 0.3 YL YT
where,
XL =
4-28
02/29/2012
2
2
X 2 Y 2
(4.31)
Nonlinear time-history analysis has shown that the 100% + 30% spectral combination
rule to be non-conservative for wharf structures (Ref. 11). If Modal Response Spectra
Analysis method is used for the wharf design with soil initial lateral stiffness, the
displacement demand to capacity ratio (DCR) shall be less than or equal to 0.85. If the
DCR is larger than 0.85 other analysis methods shall be used.
4.9.4.3 Nonlinear Time-History Analysis
Nonlinear Time-History Analysis (NTHA) is the most accurate method for determining
displacement demand. Since the inelastic characteristics of the piles can be directly
incorporated in the response, the longitudinal and transverse excitation can be
simultaneously applied, and the complexities of the movement joints can be directly
modeled. NTHA must always be used in conjunction with another simplified analysis
approach to verify results. The NTHA results should be within 20% of the results
obtained from another simplified approach such as response spectral analysis. When
modeling reinforced or prestressed concrete piles or steel piles with concrete plugs,
degrading stiffness models such as the Modified Takeda rule (Ref. 35) should be adopted
with =0.3 and =0.5. Elastic damping should be represented by tangent stiffness
damping equivalent to 10% critical damping.
Displacement demands from NTHA shall be based on simultaneous orthogonal
horizontal input motions, as defined in Section 2.1. Multiple time-history records will be
required to achieve a representative displacement demand for the global model.
When three sets of spectrum-compatible time-history records are used, the envelope
value of each response parameter shall be used in the design. When seven sets or more of
spectrum-compatible time-history records are used, the average value of each response
parameter shall be used.
When NTHA methods are used, a peer review shall be conducted per Section 4.14.
(4.32)
where
Mo =
Mp =
Vo =
Vp =
02/29/2012
Deck beam and deck slab design moment and shear forces shall be in equilibrium with
pile overstrength moment and shear demands.
The wharf structural elements shall be designed for the induced forces due to the lateral
seismic deformations. For wharf deck, beam and deck slab, and pile beam/deck joint, the
moment, shear and axial demands shall be determined using the load combinations per
Section 4.5.2. Any moment demand caused by dead load and 10% live load need to be
distributed to the entire frame. The pile earthquake moment represents the amount of
moment induced by an earthquake, when coupled with the existing pile dead load
moment and pile 10% live load moment, will equal the piles overstrength moment
capacity.
4.10.1 Pile Displacement Capacity
Pile displacement capacity, c, shall be determined at OLE, CLE and DE using strain
limits provided in Table 4-1 for upper bound and lower bound soil conditions. The
displacement capacity shall be the lesser of displacement capacity at pile top plastic hinge
or at in-ground hinge, determined as follows:
c y p ,m
(4.33)
p ,m p ,m H
(4.34)
where:
c
y
p,m
p,m
H
= Displacement capacity
= Pile yield displacement, determined from pile initial position to the
formation of the plastic hinge being considered (i.e. top hinge or inground hinge)
= Pile plastic displacement capacity due to rotation of the plastic hinge at
the OLE, CLE or DE strain limits
= Plastic rotation at LE, CLE, or DE strain limits, determined per equation
4.19
= The distance between the center of pile top plastic hinge and the center
of pile in-ground plastic hinge
The pile yield displacements, y, of the top and in-ground hinges are obtained from the
pushover analysis. Figure 4-21 shows a graphical representation of the displacement
capacity calculation for a top plastic hinge. The concept is similar for an in-ground plastic
hinge.
For piles with a large unsupported length, Lu and in-ground and top plastic hinges with a
ratio Mp, in-ground /Mp, top > 1.25, the distance from the top and in-ground plastic hinges to
the point of contraflexure becomes uneven. Therefore, the displacement capacity
calculation becomes more complex, and the procedure used above will not provide
accurate results. Thus, a detailed pushover analysis with proper definition of plastic
curvature or rotation limits should be used to determine the displacement capacity.
4-30
02/29/2012
c
Deck Soffit
y p,m
Mp, top
Top of
Soil
Top Plastic
Hinge
Lu
Lp/2
Lc
Point of
Contra-flexure
p,m
Pile
In-ground
Plastic Hinge
p,m
Mp, in-ground
b) Displacement Profile
As previously stated, wharves are designed with weak column (pile), strong beam (deck
beam or deck slab) concept. In this capacity, weak column (pile) is required to form
plastic hinges and experience permanent deformation due to seismic load. The nominal
strength capacity of the beam or deck shall be sufficient to ensure the piles have reached
their plastic limit prior to the beam or deck reaching its expected nominal strength. The
beam or deck shear and flexural capacities shall be determined based on ACI-318 using
strength reduction factors. The superstructure flexural capacity shall be greater than the
largest combination of deck dead load moment, deck moment due to 10% of live load,
and pile overstrength moment distributed on each side of the pile beam/deck joint (joint).
Any distribution factors shall be based on cracked section properties.
For the pile beam/deck joint details shown in Figure 4-27, joint shear requirements are
satisfied by providing adequate confinement. The required effective volumetric ratio of
confining steel, s, around the pile dowels anchored in the joint shall be:
0.46 Asc
Dla
s max of
f ye
or 0.016
0.0015 Esh
where:
Asc = Total cross-section area of dowels in the joint
4-31
(4.35)
02/29/2012
(4.36)
where
Mp, top =
Pile plastic moment capacity at the top plastic hinge including the
effect of axial load due to crane dead load
Mp, in-ground = Pile plastic moment capacity at the in-ground plastic hinge
including the effect of axial load due to crane dead load
H
= The distance between the center of pile top plastic hinge and the
center of pile in-ground plastic hinge
The shear capacity of steel piles shall be determined according to AISC-LRFD or API
provisions, where applicable.
Concrete Piles Shear Capacity
The following applies to concrete piles and steel pipe piles with concrete plug and dowels
connections to the deck. The shear capacity, Vn , shall be calculated using the method
described below.
This method is based on the modified UCSD three-parameter model (Ref. 33) with
separate contributions to shear strength from concrete, transverse reinforcement and axial
load:
Vn (Vc Vs Va ) 0.2 f ce Ae
(4.37)
where,
=
Vn =
Vc =
Strength reduction factor for shear, equal to 0.85 for OLE and CLE and
equal to 1.0 for DE
Nominal shear strength
Concrete shear strength
4-32
=
=
=
=
02/29/2012
(4.38)
where:
k
fc
Ae
The curvature ductility demand, shall be calculated at the demand displacement, and
can be found using the formula below:
P ,dem
1 P ,dem
y
L p y
(4.39)
where:
4-33
02/29/2012
3.5
3
2.5
2
1.5
1
0.5
0
0
10
12
14
16
18
20
22
24
26
28
30
Asp f yh ( D p c co ) cot( )
2
(4.40)
where:
Asp =
fyh =
Dp =
c =
co =
=
s
4-34
02/29/2012
Vs
Pile
co
Neutral
Axis
Dp
(4.41)
where:
Nu =
Fp =
=
4-35
02/29/2012
Deck Soffit
Deck
Compression
Zone
Vp = (Nu + Fp)tan()
Pile
Top of Soil
In-ground
Plastic Hinge
Compression Zone
Alternatively, for piles with curvature ductility, < 2, the pile shear strength may be
calculated according to ACI-318 provisions.
4.10.4 P- Effects
Additional secondary forces due to the effect of dead load and lateral seismic
displacement demand (P- shall be included in the analysis for OLE, CLE and DE. The
P- effects may be ignored when:
F
4 d
WDL
H
(4.42)
where:
F
WDL =
d =
H =
02/29/2012
part of a research study (Ref. 11) to obtain shear key forces for different wharf
configurations, soil properties and ground motion intensities. The results of the study are
based on a 110-ft wide wharf section with wharf segment length combinations that varied
from 400 feet, 600 feet, and 800 feet. The analysis was conducted using both lower and
upper bound soil conditions and OLE and CLE ground motions.
The study results show that for two linked wharf units, the shear key should be designed
for a seismic shear key force demand, Vsk, as shown below:
F e
Vsk sk
LL
(4.43)
where,
F
=
=
sk =
e
LL
4-37
02/29/2012
Inertial loading
Rock dike
Weak clay or
liquefaction
Weak
zone clay or
liquefaction
zone
Pile
Kinematic load
4-38
02/29/2012
Beam/Deck
24 to 48
spirals
2 embedment
Cut pile to expose 1 turns
of spiral and embed in deck
concrete
Cut pile prestressing strands
and remove
24 precast
pile
Dowels with
bulb ends
4 maximum
Beam/Deck
48
spirals
2 embedment
24 precast
pile
Dowels without
bulb ends
4-39
02/29/2012
5 Structural Considerations
5.1 Design Standards
Wharf analysis and design shall comply with the provisions of POLB Wharf Design
Criteria and the following codes and standards as applicable. The provisions of POLB
Wharf Design Criteria shall supersede the requirements of all other documents if there
are disagreements.
1. California Building Code (CBC), California Code of Regulations, Title 24,
(Ref. 13).
2. American Concrete Institute (ACI), Building Code Requirements for Structural
Concrete and Commentary, ACI-318, (Ref. 2).
3. ASCE 7-05, Standard, Minimum Design Loads for Buildings and Other
Structures, (Ref. 9).
4. American Institute of Steel Constructions (AISC), Code of Standard Practice for
Steel Buildings and Bridges, (Ref. 4).
5. ANSI/AWS D1.1, Structural Welding Code Steel, (Ref. 7).
6. California Building Code Chapter 31F [For SLC], Marine Oil Terminals, also
known as Marine Oil Terminal Engineering Standards (MOTEMS), (Ref. 14).
7. American Petroleum Institute (API), Recommended Practice for Planning,
Designing and Constructing Fixed Offshore Platforms Working Stress Design,
(Ref. 5).
8. American Forest and Paper Association (AF&PA), National Design
Specifications for Wood Construction and Supplement LRFD/ASD, (Ref. 3).
The wharf controls shall refer to the Control Section of the Design Criteria and
Standard Plans under General Criteria, (Ref. 29) for specific instructions as to survey
controls.
Vertical Datum
The vertical datum for the POLB is based on NGVD 29 (National Geodetic vertical
Datum of 1929), with MLLW elevation = 0.0 feet. The City of Long Beach uses
NGVD 29 with MSL elevation = 0.0 feet. As a reference, tidal elevations are provided in
Table 5-1 for NAVD 88 (North American Vertical Datum of 1988) and NGVD 29.
Monuments
The Project Plans shall show the location and type for installation of baseline
monuments. The Port survey section shall provide the required locations and type of
monuments.
5-1
02/29/2012
Abbreviation
Elevation (ft)
Description
NGVD 29
a
NAVD 88
---
+7.54
+7.16
MHHW
+5.43
+5.05
MHW
+4.71
+4.33
MSL
+2.80
+2.42
MLW
+0.95
+0.57
MLLW
0.00
-0.38
---
-2.56
-2.94
Wharf Elevations
Wharf elevations shall be determined to maintain facility operations under all tidal
conditions. Where applicable, the wharf elevation shall also match that of adjacent
facilities, unless directed otherwise by project-specific criteria. Wharf elevations for RORO, barge loading and unloading, and special purpose docks are to be determined by
project-specific criteria.
Crane Rail Elevations
The top of crane rails (except for wheel flange notches) shall be level with the adjacent
deck surface. The top of rail elevation is dictated by drainage conditions for the wharf.
This normally results in a relative elevation difference between the waterside and
landside crane rails, due to deck transverse cross-slope. If cross-section elevations differ,
crane design shall accommodate elevations differential by specifying crane legs to match.
The longitudinal elevation of a crane rail shall be constant.
Typical rail elevations are at +15.0 feet for the waterside crane rail. The landside crane
rail elevation is based on minimum grade requirements, typically 0.75%.
The allowable tolerances for the top of crane rail elevation shall be 1/8 inch, and 1/16
inch for any 10 feet along the rail length.
Grade 60 reinforcing steel shall be used. Epoxy coating is not permitted without prior
written approval by the Port.
5-2
02/29/2012
Prestressing Steel
Precast prestressed concrete piles strength ( f c ) shall be a minimum of 6,500 psi at time
of driving, and 4,500 psi at time of prestressing steel stress transfer. Minimum concrete
cover over transverse reinforcing steel shall be 2 inches.
Prestressed Precast Concrete (other than piles)
The flat slab system consists of a cast-in-place concrete deck supported by piles. The
thickness of the deck slab is normally controlled by slab punching shear capacity to resist
pile reactions. The slab depth in this case can be reduced by the use of capitals or shear
caps under the deck at pile locations.
Flat slab system may have larger seismic mass when compared to a beam/slab system.
Precast Slab Panels
This system consists of precast deck slab panels placed on top of cast-in-place bent caps
supported by piles. The entire system can also be covered with a reinforced cast-in-place
5-3
02/29/2012
topping slab for continuity. Precast deck slabs have the advantage of reducing the amount
of required falsework, which lowers both the construction cost and construction duration.
However, the bent cap beams reduce the construction tolerance of the pile placement (i.e.
misalignment). This can be an important factor in locations of construction nearby or
replacing existing structures, where submerged obstacles can be expected during pile
driving. Additionally, the depth of the bent cap beams with this type of deck can become
relatively large as the pile spacing is increased. This can place portions of the beam in the
tidal zone, potentially increasing the corrosion potential of the superstructure.
Ballasted Decks
Ballasted decks are normally not a preferred system due to their high seismic mass and
associated higher seismic demands. However, this type of system works well when deck
accessories such as railroad tracks are necessary, and a large number of utilities and
pipelines are required. A dropped deck or ballasted section is necessary in utility
corridors, and can be combined with any of the above systems. Ballasted decks are also
useful for non-container and general cargo (break-bulk) wharves where point loads from
odd shaped equipment and freight are operated.
5.4.2 Expansion Joints
Expansion joints are joints between two wharf units with a shear key that allows relative
longitudinal movement (movement parallel to shore) but restricts relative transverse
movement (movement perpendicular to shore). Expansion joints locations are determined
by thermal forces, and are typically placed at a maximum of approximately 800 feet
along the wharf.
The wharf expansion joints shall be designed for the combined effect of seismic
deformation, seismic forces and thermal expansion.
5.4.3 Cut-off Wall
Crane rails shall be supported by a continuous weight distributing sole plate with attached
rail clips, a continuous flexible impact pad, and the appropriate crane rail. The assembly
shall be galvanized and installed in a recessed pocket with an epoxy fill under the sole
plate and asphalt concrete (AC) fill around the rail assembly to match the finished grade
of the wharf deck, with block-outs for wheel flanges. Crane rails shall be continuously
welded at expansion joint.
5-4
02/29/2012
Crane Stops
Crane stops are provided at the ends of the wharf to restrict crane motion beyond their
intended travel limits. The crane stop bumpers shall be positioned per crane
manufacturers recommendation. See Section 3.3.3 for further discussion on crane stops.
Crane stowage pins
The number of crane stowage pins and their location shall be based on operational
considerations. They are typically placed at ends of wharf, and at intermediate points for
long wharves. Consideration should be given to the number of cranes, length of wharf,
location of power source, and distance between stowage pins.
5.4.5 Fenders and Mooring Hardware
Safety ladders shall be provided at a maximum spacing of 400 feet along the face of the
wharf.
5.4.7 Piling
Clearance
An approximate minimum of 4 feet clearance shall be used between the deck/ beam soffit
and top of dike to allow for adequate post-earthquake inspection and repairs.
Concrete Piles
The Ports standard pile is a 24-inch octagonal precast prestressed concrete pile. Larger
size solid or hollow piles may be proposed for situations where the 24-inch octagonal pile
is not a cost effective solution. The Port prefers to use only one size pile for the entire
structure, varying only the length and prestress level, unless project conditions and/or
cost savings prove otherwise. The use of piles other than the standard 24-inch octagonal
precast prestressed piles is not permitted without a prior written approval by the Port.
5-5
02/29/2012
Steel Piles
The use of steel piles is strongly discouraged due to the corrosion potential and associated
higher maintenance cost. Additionally, corrosion barrier coating systems and
encasements impede routine visual pile inspections. Steel piles should only be used when
project-specific criteria and site circumstances dictate.
Battered Piles
The use of battered piles is not permitted without a prior written approval by the Port.
However, battered piles may be used for isolated structures with low seismic mass, such
as landside anchors, mooring and breasting dolphins.
5.4.8 Guard Timber
On the waterside edges of the wharf deck, a curb or chemically treated guard timber 10inch high by 12-inch wide shall be used. Notches shall be provided on the underside of
the guard timber to permit drainage. The guard timber shall be anchored to the deck slab
using recessed bolts or pins, and should include vessels net anchor rings.
5.4.9 Trench Cover Plates
Galvanized steel checker plate shall be used for trench covers. Special consideration
should be given to the hinge design due to the weight of the plates. The preferred location
of the power trench is on the waterside of the waterside crane rail. The trench cover
plates shall be designed using the applicable load specified in Section 3.
5.4.10 Cable Trench
Trench for crane power cables shall be covered with a continuous flexible material,
fabricated from rubber with inlaid steel reinforcement. The trench shall be a minimum
width and depth to accommodate the crane power cables anticipated at the facility.
5.4.11 Inclinometer Tubes/ Motion Instrumentation
The decision to install inclinometer tubes/ motion instrumentation in the wharf structure
should be made during design, and should be coordinated with other instrumentations
functioning within the Port.
5.4.12 Dike Scour
Submerged slopes shall be protected to withstand the effects of ocean waves, tidal
currents, propeller wash, and vessels wakes. At a minimum, the slope protection shall
consist of an under layer of quarry run rock and an armor layer consisting of nominal 500
pounds armor stone. The submerged slope protection shall at a minimum extend above
all expected water levels and wave run-up elevations. Other approaches to slope
protection shall require prior written approval by the Port.
Design current speed, wave height and other coastal hydrodynamic processes shall be
defined and approved by the Port. Armor design and analysis shall consider the design
water level including sea level rise, design wave conditions, design current speeds, design
currents from propeller and bow thruster wash, design ship wake and any other potential
5-6
02/29/2012
sources of currents and waves such as tsunami (Ref. 37). The design vessel, for vessel
related factors, is provided in Section 3.6. An approach for addressing sea level rise is
given in Ref. 38.
For service load analysis such as dead loads, live loads, and wind loads, the material
properties shall be based on the relevant design code, see Section 5.1.
Section Properties
For temperature or creep loads, the effective moment of inertia (Ieff) should be used for
piles, see Section 4.6.3. For all other service loads, gross moment of inertia (Igross) shall
be used.
Beam on Elastic Foundation Model
For modeling the wharf structure frame as beams on elastic foundation, UB and LB t-z
springs shall be used for the analysis including the pile elastic shortening, see Section 2.
To calculate moments in the beam and axial force in the piles, the t-z springs may replace
modeling the piles, as shown in Figure 5-1-a). The piles should be included in the model
to determine moments and shear in the piles, as in Figure 5-1-b).
Beam
t-z Spring
Piles
t-z Spring
5-7
02/29/2012
5-8
02/29/2012
6 References
1. American Association of State Highway and Transportation Officials (AASHTO),
LRFD Bridge Design Specifications, 2007.
2. American Concrete Institute (ACI), Building Code Requirements for Structural
Concrete and Commentary, ACI 318, 2008.
3. American Forest and Paper Association (AF&PA), National Design
Specifications for Wood Construction and Supplement LRFD/ASD, ANSI/
AF&PA NDS 2005, AF&PA, Washington DC, 2005.
4. American Institute of Steel Construction (AISC), Manual of Steel Construction,
13th Edition, 2005.
5. American Petroleum, Institute, Recommended Practice for Planning, Designing
and Constructing Fixed Offshore Platforms Working Stress Design, API
Recommended Practice 2A-WSD (RP2-WSD), 21st Edition, December 2000.
6. American Railway Engineering and Maintenance-of-Way Association (AREMA),
Manual for Railway Engineering, 2011.
7. ANSI/AWS, D1.1, Structural Welding Code, Steel 2008 Edition.
8. Applied Technology Council/Multidisciplinary Center for Earthquake
Engineering Research, Recommended LRFD Guidelines for the Seismic Design
of Highway Bridges, MCEER/ATC-49, Based on NCHRP 12-49, 2003.
9. ANSI/ASCE 7, Standard, Minimum Design Loads for Buildings and Other
Structures, 2005.
10. Blake, T. F., R. A. Hollingsworth, and J. P. Stewart, J. P. (eds.), Recommended
Procedures for Implementation of DMG Special Publication 117, Guidelines for
Analyzing and Mitigating Landslide Hazards in California, Southern California
Earthquake Center, University of Southern California, February 2002.
11. Blandon, C. A., Seismic Analysis and Design of Pile Supported Wharves, Ph.
D. Dissertation, Rose School, Pavia, Italy, October 2007.
12. Boulanger, R. W. and I. M. Idriss, Liquefaction Susceptibility Criteria for Silts
and Clays, ASCE: Journal of Geotechnical and Geoenvironmental Engineering
Vol. 132, No. 11, November 2006.
13. California Building Code (CBC) (2010), California Code of Regulations, Title
24, January 2011.
14. California Building Code (CBC) (2010) Chapter 31F [For SLC], Marine Oil
Terminals, January 2011.
15. California Department of Transportation, Guide Specifications for Seismic
Design of Steel Bridges, First Edition, December 2001.
16. California Department of Transportation, Seismic Design Criteria, Version 1.6,
November 2010.
6-1
02/29/2012
17. Earth Mechanics, Inc., Port-Wide Ground Motion Study, Port of Long Beach,
California, Prepared for the Port of Long Beach, August 7, 2006.
18. Earth Mechanics, Inc., Port-Wide Ground Motion Study, Port of Long Beach,
California, Addendum to Final Report, Prepared for the Port of Long Beach,
August 15, 2008.
19. Earth Mechanics, Inc., Addendum No. 2 to Port-Wide Ground Motion Study
Report, Port of Long Beach, California, Prepared for the Port of Long Beach,
April 11, 2011.
20. FHWA, Design and Construction of Driven Pile Foundations, US Department
of Transportation, Federal Highway Administration, Publication No. FHWANHI05-042, April 2006.
21. Hart, E. W. and Bryant, W. A., Fault Rupture Hazard Zones in California,
California Geological Survey Special Publication SP-042, 1992. Revised 1997
(Supplements 1 and 2 Added 1999).
22. International Navigation Association [PIANC], Guidelines for the Design of
Fender Systems: 2002, Working Group No. 33 of the Maritime Navigation
Commission, 2002.
23. Mander, J.P., Priestley, M.J.N, and Park, R., Theoretical Stress-Strain Model for
Confined Concrete, ASCE: Journal of Structural Engineering, Vol. 114, No. 8,
August 1988.
24. Martin, G.R., and Lew, M. (eds.), Recommended Procedures for Implementation
of DMG Special Publication 117, Guidelines for Analyzing and Mitigating
Liquefaction Hazards in California, Southern California Earthquake Center,
University of Southern California, March 1999.
25. Moffatt & Nichol et al., Alameda Corridor Currents and Tracer Study Revised
Final Report, Prepared for Alameda Corridor Transportation Authority, May 31,
2001.
26. Moffatt & Nichol, Tsunami Hazard Assessment for the Ports of Long Beach and
Los Angeles, Final Report, Prepared for the Port of Long Beach and the Port of
Los Angeles, April, 2007.
27. NAVFAC, Foundation and Earth Structures, Design Manual 7.02, Department
of the Navy, Naval Facilities Engineering Command, Alexandria, VA, September
1986.
28. NAVFAC, Soil Mechanics, Design Manual 7.01, Department of the Navy,
Naval Facilities Engineering Command, Alexandria, VA, September 1986.
29. Port of Long Beach, Design Criteria and Standard Plans.
30. Port of Los Angeles, Draft Commentary to the Code for Seismic Design,
Upgrade, and Repair of Container Wharves, July 2004.
31. Prestressed Concrete Institute, PCI Design Handbook, Precast and Prestressed
Concrete, 6th Edition, January 2004.
6-2
02/29/2012
32. Priestley, M.J.N., Seible, F., and Calvi, G.M., Seismic Design and Retrofit of
Bridges, John Wiley & Sons, 1996.
33. Priestley, M.J.N., Calvi G.M., and Kowalski M.J., Displacement-Based Seismic
Design of Structures, IUSS Press, Pavia, ITALY, 2007.
34. Seed, R. B. et al., Recent Advances in Soil Liquefaction Engineering: A Unified
and Consistent Framework, 26th Annual ASCE Los Angeles Section, Spring
Seminar, Long Beach, California, April 2003.
35. Takeda, T., Sozen, M., and Nielsen, N., Reinforced Concrete Response to
Simulated Earthquakes, Journal of the Structural Division, Proceedings of the
American Society of Civil Engineers, Vol. 96, No. 12, December 1970.
36. Transportation Research Board, National Cooperative Highway Research
Program, Seismic Analysis and Design of Retaining Walls, Buried Structures,
Slopes, and Embankments, NCHRP Report 611, 2008.
37. U.S. Army Corps of Engineers, Coastal Engineering Manual, USACE EM1110-2-1100 (6 volumes), Washington, D.C., 2008.
38. U.S. Army Corps of Engineers, Water Resource Policies and Authorities
Incorporating Sea-Level Change Considerations in Civil Works Programs,
USACE Guidance EC 1165-2-211, Washington, D.C., 2009.
39. Youd, T.L. et al., Liquefaction Resistance of Soils: Summary Report from the
1996 NCEER and 1998 NCEER/NSF Workshops on Evaluation of Liquefaction
Resistance of Soils, ASCE, Journal of Geotechnical and Geoenvironmental
Engineering, Vol. 127, No. 10, October 2001.
6-3
02/29/2012
Bibliography
American Concrete Institute, Guide for the Design and Construction of Fixed
Offshore Concrete Structures, ACI- 357R-84, Reapproved 1997.
American Concrete Institute, Design, Manufacture, and Installation of Concrete
Piles, ACI 543R-00, 2000.
American Institute of Steel Construction (AISC 303-05), Code of Standard Practice
for Steel Buildings and Bridges, 2005.
American Society for Testing and Materials, American Society for Testing and
Materials (ASTM) Standards in Building Codes, 2007.
American Petroleum Institute (API), Recommended Practices 2A RP 2A-LRFD,
1997.
ANSI/AWS, D1.4, Structural Welding Code, Reinforcing Steel 2005 Edition.
Bell J., C. Blandon, and J. Restrepo, Seismic Testing of Existing Full-Scale Pile to
Deck Connections: Precast Prestressed and Steel Pile, Structural Systems Research
Project, UCSD, January 2008.
Blake, T. F., R. A. Hollingsworth, and J. P. Stewart, J. P. (eds.), Recommended
Procedures for Implementation of DMG Special Publication 117, Guidelines for
Analyzing and Mitigating Landslide Hazards in California, Southern California
Earthquake Center, University of Southern California, February 2002.
Blakely, J.P. and R. Park, Prestressed Concrete Sections with Cyclic Flexure,
Journal of the Structural Division, ASCE, 1973.
California Department of Transportation (CALTRANS), Seismic Design Criteria
(SDC), Version 1.6, 2010.
Department of Defense, Unified Facilities Criteria (UFC), Design: Piers and
Wharves, UFC 4-152-01, July 2005.
FEMA 4500-1, National Earthquake Hazards Reduction Program, NEHRP
Recommended Provisions for Seismic Regulations for New Buildings and Other
Structures, 2003.
Ferritto, J., Dickenson, S., Priestley N., Werner, S., Taylor, C., Burke D., Seelig W.,
and Kelly, S., Seismic Criteria for California Marine Oil Terminals, Vol.1 and
Vol.2, Technical Report TR-2103-SHR, Naval Facilities Engineering Service Center,
Port Hueneme, CA, July 1999.
International Navigation Association [PIANC], Seismic Design Guidelines for Port
Structures, Working Group No. 34 of the Maritime Navigation Commission, A. A.
Balkema Publishers, 2001.
Joen, P. and Park, R., Flexural Strength and Ductility Analysis of Spirally
Reinforced Prestressed Concrete Piles, PCI Journal, July-August 1990.
6-4
02/29/2012
6-5
02/29/2012
6-6