0% found this document useful (1 vote)
497 views4 pages

CHP 4 Project MGT Problems Questions

This document contains 9 problems involving scheduling projects using critical path method (CPM). The problems involve drawing network diagrams, finding critical paths, calculating project duration, analyzing time/cost tradeoffs of crashing activities, and calculating probability of on-time completion. Activities include R&D of a new communications system, construction projects, and general projects broken down into tasks.

Uploaded by

Sunil Shaw
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (1 vote)
497 views4 pages

CHP 4 Project MGT Problems Questions

This document contains 9 problems involving scheduling projects using critical path method (CPM). The problems involve drawing network diagrams, finding critical paths, calculating project duration, analyzing time/cost tradeoffs of crashing activities, and calculating probability of on-time completion. Activities include R&D of a new communications system, construction projects, and general projects broken down into tasks.

Uploaded by

Sunil Shaw
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 4

CHAPTER 3

PROJECT MANAGEMENT
Problems:
1. The following activities are part of a project to be scheduled using CPM:

a.
b.
c.
d.

Draw the network.


What is the critical path?
How many weeks will it take to complete the project?
How much slack does activity B have?

2. Schedule the following activities using CPM:

a. Draw the network path.


b. What is the critical path?
c. How many weeks will it take to complete the project?
d. Which activities have slack, and how much?
3. The R&D department is planning to bid on a large project for the development of
a new communications system for commercial planes. The accompanying table
shows the activities, times, and sequences required:

a. Draw the network diagram.


b. What is the critical path?

c. Suppose you want to shorten the completion time as much as possible, and
you have the option of shortening any or all of B, C, D, and G each one week.
Which would you shorten?
d. What is the new critical path and earliest completion time?
4. A construction project is broken down into the following 10 activities:

a. Draw the network diagram.


b. Find the critical path.
c. If activities 1 and 10 cannot be shortened, but activities 2 and 9 can be
shortened to a minimum of one week each at a cost of $10,000 per week,
which activities would you shorten to cut the project by four weeks?
5. The following represents a project that should be scheduled using CPM:

a.
b.
c.
d.

Draw
What
What
What

the network.
is the critical path?
is the expected project completion time?
is the probability of completing this project within 16 days?

6. There is an 82 percent chance the project below can be completed in X weeks or


less. What is X?

7. Here is a CPM network with activity times in weeks:

a. Determine the critical path.


b. How many weeks will the project take to complete?
26 weeks
c. Suppose F could be shortened by two weeks and B by one week. How would
this affect the completion date?
8. The following table represents a plan for a project:

a. Construct the appropriate network diagram.


b. Indicate the critical path.

c. What is the expected completion time for the project?


d. You can accomplish any one of the following at an additional cost of $1,500:
(1)Reduce job 5 by two days.
(2) Reduce job 3 by two days.
(3) Reduce job 7 by two days.
If you save $1,000 for each day that the earliest completion time is reduced,
which action, if any, would you choose?
e. What is the possibility that the project will take more than 30 days to
complete?
9. Here is a network with the activity times shown in days:

a. Find the critical path.


b. The following table shows the normal times and the crash times, along with
the associated costs for each activity.

If the project is to be shortened by four days, show which activities, in order of


reduction would be shortened and the resulting cost.

You might also like