Condition Monitoring Documentation
Condition Monitoring Documentation
Condition Monitoring Documentation
CONTENTS
Page No
CHAPTER-I
1.1INTRODUCTION TO APGENCO
CHAPTER-II
TRANSFORMERS
2.1 INTRODUCTION TO TRANSFORMER
12
13
13
20
23
25
CHAPTER-III
27
28
29
30
TRANSFORMER TESTS
4.1 INTRODUCTION
4.2 WINDING RESISTANCE MEASUREMENTS
4.3 CAPACITANCE AND TAN FOR WINDING
4.4 INSULATION RESISTANCE(IR) AND POLARIZATION INDEX
32
32
33
34
CHAPTER-V
DISSOLVED GAS ANALYSIS
5.1 INTRODUCTION
36
CHAPTER VI
TROUBLE SHOOTING CHART FOR ALL TRANSFORMERS
37
CHAPTER VII
CASE STUDIES
43
CONCLUSION
46
BIBOLOGRAPHY
47
CHAPTER.I
BRIEF HISTORY OF KOTHAGUDEM THERMAL
POWER STATION:
1.1 INTRODUCTION TO APGENCO:
Andhra
Pradesh
Power
Generation
Corporation
Limited
of
Andhra
Pradesh.
APGENCO
is
third
largest
power
generating utility in the Country next to NTPC and Maharashtra. It's installed
Hydro capacity of 3703.4 MW is the second highest among the Country.
4382.5 MW
3751.40 MW
2.00 MW
Operat
or
Location
District
Unit
Wise
capacit
y
Installe Plant
d
Coordinates
capacit
y
Ramagund
am
B thermal
Power
Station
APGENC
O
Ramagunda
m
karimnag
ar
162.5
62.5
184331N7930
47E
Kothagud
em
Thermal
Power
Station
APGENC
O
Paloncha
Khamma
m
460,
4120
720
173718N804
1,15E
Kothagud
em
Thermal
Power
Station
V&IV
Stage
APGENC
O
Paloncha
Khamma
m
2250
1500
500
500
173724N804
2060E
Dr Narla
Tatarao
TPS
APGENC
O
Ibrahinpatn
am
Krishna
6210,
1500
1760
163558N8032
12E
Rayalasee
ma
Thermal
Power
Station
APGENC
O
Cuddapah
YSR
4210
840
144214N7827
29E
APGENC
O
Chelpur
Warangal
1500
500
182302N7949
42E
Kothagudem
thermal power station is one of the major power generating stations of the Andhra Pradesh. The main
raw material is coal is supplied by singereni collieries, Kothagudem and a water source is from
kinnerasani project, which is about 12kms. From paloncha.
For the power generation with 2x110 MW and 3x210 MW of K.T.P.S. authorities are
required to be operative to active full operation. The auxiliaries are basically operation either on L.T.
System i.e. 415 V 3 power supply is made available to the system after providing the station
transformer of 3x50 MVA capacity with voltage 220 KV/ 7.2/7.2 KV & different service transformers
of capacity 1.0 MVA, 1.5 MVA, 2.0 MVA, which are located near the load centre as the transformer
having the voltage of 6.6 KV /415 V. The 6.6 KV power is distributed through 6.6 KV interconnected
Bus System for all the five units with a control through DC of 220 V.
The 415 V power supply is done through a L.T. SWGR (Switchgear) which are
located nearby the distribution transformer as well as the load centers. The all in -comers, which are
breaker controlled , are having the control the L.T. SWGR are having the control system on 110/ 220
V AC. The 6.6 KV power supply which are either MOCB (Minimum Oil Circuit Breaker) of JYOTI
MAKE or Air Circuit Breakers.
The 6.6 KV power supply to various draining equipments i.e. more is made through
breakers which are either MOCB of jyothi make air circuit breaker which are either of voltage makers
as well as SF 6 of NGEF make. The LT supply is also controlled through air break circuit breaker
which are either L&T make or English Electric Company of India. The various H.T. motors are
switched on / started through on direct ON line (DOL) in order to inverse the availability of
equipment at full efficiency without time gap.
Further , the 6.6 KV system which is normally in delta configuration and terms as an
unearthed system so also to keep the running motor complete in operating condition in case of any
one .phase of motor winding is earthed due to any one reason. Earthling is detected by an protection
system with alarm facility to take remedial measures immediately and at the same time to maintain
DEPARTMENT OF ELECTRICAL AND ELECTRONICS ENGINEERING
ANNAMACHARYA INSTITUTE OF TECHNOLOGY & SCIENCES
page 5
NOOF UNITS
Individual capacity
Total capacity
Station A
60 MW
240 MW
Station B
120 MW
240 MW
Station C
120 MW
240 MW
Stage V
250 MW
500 MW
Stage VI
500 MW
500 MW
TOTAL
1720 MW
Objectives
DEPARTMENT OF ELECTRICAL AND ELECTRONICS ENGINEERING
ANNAMACHARYA INSTITUTE OF TECHNOLOGY & SCIENCES
page 8
LOCATION:
The Kota Thermal Power Station is ideally on the left bank of Chambal River
at Up Stream of Kota Barrage. The large expanse of water reached by the
barrage provides an efficient direct circulation of cooling system for the power
station. The 220 KV GSS is within km \ from the power station.
LAND:
Land measuring approx. 250 hectares was required for the project in 1976, For disposal of
ash tank very near to power station is acquired which the ash in slurry form is disposed off through
ash and slurry disposal plants.
The very first thing we need to provide is a conductor cutting magnetic flux.
So this can be done in two basic ways i.e. either the conductor can be moved in
the magnetic field or the field can be varied according to the required emf that is
to be generated. The process we follow here is we rotate the rotor of a generator
in the magnetic field and emf is generator at the stator and this generated emf is
further utilized according to the purpose.
To meet the purpose of rotating the rotor of a generator, the rotating shaft
is in turn connected to a turbine which is made to rotate at a rated speed by an
external energy source. So we need an energy source to rotate the turbine. To
rotate the turbine energy must be transferred from a medium to the turbine so
DEPARTMENT OF ELECTRICAL AND ELECTRONICS ENGINEERING
ANNAMACHARYA INSTITUTE OF TECHNOLOGY & SCIENCES
page 10
Fuel
Water
Heating system
Steam circuit
Regenerating system
Steam turbine
Generator
Transformer
COAL:
Coal India limited owns and operates all the major coal fields in India through its coal
producing subsidiary companies viz. Eastern Coal Fields Limited, Western Coal Fields Limited/Coal
India limited is supply coal from its coal mines of coal producing subsidiaries BCCL, SECL & ECL
to Kota Thermal Power Station through railway wagons. The average distances of SECL, ECL &
BCCL are 800, 950 and 1350 Kms. respectively.
DEPARTMENT OF ELECTRICAL AND ELECTRONICS ENGINEERING
ANNAMACHARYA INSTITUTE OF TECHNOLOGY & SCIENCES
page 11
The source of water for power station is reservoir formed by Kota Barrage on the
Chambal River. In case of large capacity plants huge quantities of coal and water is required. The
cost of transporting coal and water is particularly high. Therefore, as far as possible, the plant must be
located near the pit rather than at load centre for load above 200 MW and 375 MW. The
transportation of electrical energy is more economical as compared to the transportation of coal.
The design of steam power station requires wide experience as the subsequent
operation and maintenance are greatly affected by its design. The most efficient design consist of
properly sized component designed to operate safely and conveniently along with its auxiliaries and
installation.
HEATING SYSTEM:
REGENERATIVE SYSTEM:
STEAM TURBINE:
rotated which in turn is operated by a shaft which is rotated with the help of
three turbines.
GENERATOR:
have discussed the 3 turbines rotate a single shaft at a rated speed of 3000 RPM.
DEPARTMENT OF ELECTRICAL AND ELECTRONICS ENGINEERING
ANNAMACHARYA INSTITUTE OF TECHNOLOGY & SCIENCES
page 12
TRANSFORMER:
1.
2.
3.
GENERATOR TRANSFORMER
UNIT AUXILIARY TRANSFORMER
STATION TRANSFORMER
CHAPTER.II
Transformers
DEPARTMENT OF ELECTRICAL AND ELECTRONICS ENGINEERING
ANNAMACHARYA INSTITUTE OF TECHNOLOGY & SCIENCES
page 13
lower capacity ranges, while an efficiency of 95% is achievable in high capacity ranges.
Theoretically, there is no upper limit to the power handling capacity; transport constraints,
handling facilities, etc. being the limiting factors. The lower limit is governed by the
allowable no-load losses.
The physical basis of a transformer is mutual induction between two circuits linked by
a common magnetic field. The primary circuit carrying a current has associated with it, as a
manifestation of electrical phenomenon of current flow, a magnetic field in its immediate
vicinity. When the circuit is alternating, the magnetic field at any point in the surrounding
medium will vary in both magnitude and direction I accordance with the change of current
with time. The secondary being in the vicinity the primary circuit will link with some of the
primary magnetic flux produced. With an alternating primary current, and therefore flux, the
changing linkages will produce in secondary winding an emf. The more closely the primary
and the secondary circuits are mutually linked, the more direct becomes the change of energy
between them. Major electrical parameters of a transformer are iron and copper losses,
hysteresis losses, efficiency, regulation. Essentially the chief elements of construction of a
transformer comprise materials for magnetic circuit, terminals, tapping switches, oil as well
as cooling devices.
E=M*(di/dt)
Where E=induced emf,
M=mutual inductance.
EMF induced in a transformer is given by
the equation
E=4.44 m f N volts, m=BmA
If second circuit is closed, a current flow in it and so electrical energy is transferred entirely
magnetically from the first coil to the second coil.
Insulating oil:
Insulating oil forms a very significant parts of a transformer insulation system and has the
important function of acting as an electrical insulation as well as coolant to the dissipate heat losses.
This basic raw material for the production of transformer oil is a low viscosity lube termed as
TRANSFORMER OIL BASE STOCK (TOBS) which is normally obtained by fractional distillation
and subsequent treatment of crude petroleum. TOBS is further refined by acid treatment process to
yield transformer oil.
Chemical Properties:
Transformer oil consist of four major generic classes of organic compounds, namely
paraffins, naphthenes, aromatics and olefins. All these are hydrocarbons and hence insulating oil is
called a pure hydrocarbon mineral oil. For good fresh insulating oil, it is desirable to have more of
saturated paraffin, less of aromatic or naphthenes and none of olefins. However, for better stability of
properties, it is necessary to have optimum aromatic or naphthenes hydrocarbons. Such as optimum
balance is carefully struck by a carefully controlled refining process. Depending upon the
predominance, oil is usually termed as of paraffinic base or naphthenic base.
Electrical properties:
Electric strength (Breakdown voltage): BDV is the voltage at which breakdown occurs
between two electrodes when oil is subjected to an electric field under prescribed conditions.
Electric strength is the basic parameter for insulation system design of a transformer. It serves
to indicate the presence of contaminating agents like moisture, fibrous material, carbon
Winding:
The transformer consists of two coils called WINDINGS which are wrapped around a core.
The transformer operates when a source of ac voltage is connected to one of the windings and a load
device is connected to the other. The winding that is connected to the source is called the PRIMARY
WINDING. The winding that is connected to the load is called the SECONDARY WINDING.
Tap-Changing: There is considerable voltage drop between generating sources and consumers in
modern electricity supply. So transformers provided with number of taps at the ends of the lowcurrent winding i.e. H.V side so that the voltage ratio can be adjusted to suit loading conditions. There
are two types of tap-changers, they are
Off-load Tap-changer: The transformer is normally fitted with a off-load tap changing to obtain
required tap voltage. It can be hand operated by a switch handle mounted in tank. Locking device is
fitted to handle to padlock it on any tap position and also to prevent any unauthorized operation of
switch. The switch mechanism is such that it can be locked only when it is bridging two contacts on
any particular tapping position and cannot be locked in any intermediate position.
It
is important that the transformer should be isolated from the live line before moving the switch.
Operating the switch when the transformer is energized, will damage the switch contacts due to serve
arching between the contacts, and may damage the winding also.
On-load Tap-changer: On-load tap changers are employed to change turn ratio of transformer to
regulate system voltage while the transformer is delivering normal load. With the introduction of onload tap changer , the operating efficiency of electrical system has considerably improved. Now-adays, almost all large transformers are fitted with on-load tap changer. All forms of on-load tap
changing circuit posses impedance, which is introduced to prevent short circuiting of tapping section
DEPARTMENT OF ELECTRICAL AND ELECTRONICS ENGINEERING
ANNAMACHARYA INSTITUTE OF TECHNOLOGY & SCIENCES
page 18
Conservator:
Breather:
The breather is a box containing calcium chloride or silica gell to absorb moisture of air entering the
conservator as it is a will known fact that the insulating property of the transformer oil is lost if a
small amount of moisture enters in it, so dry air is allowed to pass in through this breather.
valves:
Transformer is equipped with drain cum filter valve at the bottom of the tank and filter
valve at the top of the tank. Valves are fitted with plug/blanking plates to stop the dirt or moisture
entering inside the valve and avoid the contamination of the transformer oil.
Plug type
Wheel valve with female screw threads
Wheel valve with flanges
Buchholz relay: This relay gas actuated relay which is meant for the protection of oil immersed
transformer from insulation failure, core heating or any type of internal fault which may cause the
heating of coil beyond the specified temperature.
Due to any internal fault, oil is heated up and oil vapour so formed causes either the alarm circuit(for
less fault) or the trip circuit (for severe faults). The relay is situated in the pipe connected between the
transformer and the conservator.
Explosion Vent:
from the gases induced by any type of short circuit in the transformer.
Temperature gauge:
It is also a
Radiators: Radiators are commonly used for cooling. ONAN, ONAF and OFAF are the types of
cooling. Radiators consist of elements joined to top and bottom headers.
Bushings:
Porcelain insulators and connectors should be
To reduce losses here the winding is done in PANCAKES-primary, secondary windings are
on the central limb.
Depending upon the cooling medium. The transformers are classified into two types. They are Dry type transformers
Oil filled transformers
Oil filled transformer: in general transformers are of oil-immersed type. The oil used for this
purpose is mineral one which provides better insulation in addition to cooling. These transformers are
further classified as oil immersed natural cooled, oil immersed forced air cooled, oil immersed water
cooled, oil immersed forced oil cooled transformers.
Depending upon the power rating, the transformers are classified into two categories,
they are Distribution Transformers
Power Transformers
Distribution Transformers:
distribution voltage to a standard service voltage are known as distribution transformers. They are
kept in operation all the 24 hours a day whether they are carrying any load or not. They are of the self
cooling type and are almost invariably oil-immersed. Energy is lost in iron losses throughout the day
while the copper losses account for ioss in energy when the transformer is loaded. Therefore
distribution transformers should have their iron losses small as compared to full load(about 50%).
Owing to low iron loss, the distribution transformers have good all-day efficiency. These transformers
should have a good voltage regulation.
Power transformers: The transformers of rating above 200KVA used in generating station and
substations at each end of a power transmission line for stepping up or stepping down the voltage are
known as power transformers. They are put in operation during load hours and disconnected during
light load hours. Therefore, power transformers should be designed to have maximum efficiency at or
near full load. Power transformers are designed to have considerably greater leakage reactance than is
permissible in distribution transformers because in the case of power transformers, voltage regulation
is less important than the current limiting effect of higher leakage reactance. They may be self oil
cooled, forced air cooled or forced water cooled.
circuit.
Poor welding, leaky fittings cause leakage of oil resulting in overheating.
Improper ventilation causes overheating of oil.
provided, at the time of filling the oil in the tank and close the same during operation.
Clean the oil conservator thoroughly before erecting.
Check the pointers of all gauges for their free movement before erection.
Inspect the painting and if necessary do retouching.
If inspection covers are opened or any gasket joint is tightened, tighten the bolts evenly
position.
Do not leave off-circuit tap switch handle unlocked.
Do not leave tertiary terminals unprotected outside the tank.
Do not leave any connection loose.
Do not meddle with the protection circuit.
Do not leave maximum temperature indicating pointer behind the other pointer in OTI
and WTI.
10. Do not change the setting of WTI and OTI alarm and trip frequently.
11. Do not allow oil level in bushings to fall, they must immediately top up.
12. Do not allow conservator oil level to fall below one-fourth level.
13. Do not leave secondary terminals on an unloaded CT open.
Core losses:
Core losses are caused by alternating flux in the core. These are also called as iron
losses. The iron losses are constant on every load. These losses can be found out by open circuit test
on the transformer. It consist of
Hysteresis losses
Eddy current losses
Hysteresis losses: Each time the magnetic field is reversed, a small amount of energy is lost due the
hysteresis within the core. For a given core material, the loss is proportional to the frequency, and is a
function of the peak flux density to which it is subjected.
Eddy current losses: due to variation in magnetic flux eddy currents are induced on the surface of
iron core which in turn produce heating and therefore reduce the amount of power to the secondary
coil. In order to avoid eddy currents, the core is laminated, made of thin sheets of soft iron. Each sheet
is separated from the next by a layer of insulating varnish.
Copper losses:
These losses are due to resistance of winding and are proportional to (current)^2
CHAPTER.III
Condition monitoring
3.1 Introduction:
Reliable and quality power is need of the hour for the economic
development of a country. For providing reliable electrical energy, it is very
necessary
to
have
highly
reliable
associated
electrical
equipment.
The
The article, being submitted, shall present a survey of new monitoring and diagnostic
technologies in power transformer for the purpose of condition assessment. Also, life assessment and
extension program for transformer in service will be highlighted. Case studies citing site experiences
of problem faced on transformer in service and various diagnostic tools employed for finding
solutions will be cited.
an important role in
the life expectancy of the transformer. Transformer life known to us is based on the designed
parameter with respect to normal operation and climate conditions. To determine the performance and
aging of the asset, insulation behavior is a main indicator [1]. Most of the transformers in a system,
around the world are exceeding their designed life. In the absence of insulation assessment, good
number of transformer failed due to insulation problems, before reaching to their designed technical
life.
It is important to investigate the cause(s) of the insulation degradation with respect to age.
Average age of the transformers that failed due to insulation deterioration during the last ten years was
17.8 years [2]. A good number of aged transformers are still performing well, it is vital to monitor the
insulation behavior rather than replacing with new one. Transformer insulation behavior is different
with respect to operation mode, climate (ambient condition) and frequency of subjected faults. Load
growth has influence on the insulation degradation. The insulation degradation trend needs regular
assessment.
An accurate analysis of the insulation can suggest operating condition, de-rating of the
transformer will increase the life expectancy [3, 4]. The unit can be proposed for relocation, subjected
to less stress. Cost effective maintenance strategies can be developed. Insulation aging in transformer
is a complex and irreversible phenomena. To ensure higher reliability and safety, insulation condition
monitoring and trend analysis are of major concern. Insulation trend analysis will conclude type of
failure as well as severity of the fault. This will make easy to understand type of maintenance
required, loading constraints and future management required. The analysis will predict the life
expectancy of the asset. It is significant to recommend insulation assessment for the aged and
suspicious behavior transformers. The overall integrity of the asset can be assessed, with minimum
risk of sudden failure. The environmental risk can be reduced. Effect of aging rate on the life
expectancy can be established. Condition monitoring provides information on the developing
insulation problems and incipient faults [5, 6]. Thus early warning of any abnormality can avert the
catastrophic failure.
Simple
Low cost
Without disruption of power
Prevent problems
Define the severity of a problem
Provide information to take action
Provide on-line and off-line diagnostics
Enable trending of data
Avoid intrusive maintenance
3.3 Critical Components: Core, windings, insulation oil, bushing and on-load tap-changer
are the main active parts of the transformer insulation chain . The degradation of insulation systems is
accompanied by phenomenon of changing physical parameters or the behavior of insulation systems.
The degradation of insulation systems is a complex physical process. Many parameters act at the
same time thus making the interpretation extremely difficult. The aging process in the oil/cellulose
insulation system under thermal stress and their measurable effects are due to chemical reactions in
the dielectric. The temperature of the oil/paper dielectric is the critical aging parameter to cause
enough change in the mechanical and electrical properties of the material. Apart from high
temperatures, other important parameters affecting the aging of the solid and liquid insulation include
the presence of water and oxygen in the system . The monitoring and assessment of such components
is vital to achieve better reliability of the system. By implementing correct operational and
maintenance strategies the insulation aging/ degradation process can be controlled and the asset life
can be extended effectively. Assets critical component monitoring (strict) is required for the technical
assessment (normal to end of life) to ensure economical and safe operation. Also better asset
management policies can be implemented .
Tap chargers,
Core:
Breakdown in core bolt insulation, core plate insulation or insulation between core and core clamps
leads to circulating currents and usually sparking at the fault. Gases are evolved, which dissolve in oil.
These can be monitored by Dissolved Gas Analysis (DGA).
Bushings:
Ingress of moisture, loosed/bad joints may lead to failure of bushings.
Operating Time
Time in service and time under abnormal conditions or extreme condition (load variation,
change in thermal stresses).
Vibration Effect
Sound and material fatigue.
Contaminants
Moisture (water content in oil), presence of oxygen and particles in oil.
CHAPTER.IV
TRANSFORMER TESTS
4.1 INTRODUCTION:
A Transformer is very vital equipment in a power system & its availability, reliability is very
important. The transformer primarily comprises of core, winding, and insulation. The insulation
comprises of solid, liquid and combination of oil and cellulose paper. The condition monitoring of oil
is performed by prescribed tests as below-
Things to be monitored:
PURPOSE OF TESTING:
Winding resistance measurements in transformers are of fundamental importance for the following
purposes:
Loose joints- leads to local hot spots and eventual melting of joints.
Worn out contacts- leads to contact erosion.
Measure capacitance and tan of each pair of windings and windings with respect to earth.
Compare with factory results
It indicates healthiness of insulation system-paper, press-board and oil.
Measure the insulation resistance values of each pair and with respect to earth.
Compare with factory results.
To determine gradual decrease in insulation resistance. This provides a means for predicting
PI: It is ratio of insulation resistance (IR )for 10 minutes to insulation resistance for 1 minute.
condition
Dangerous
poor
Questionable
fair
CHAPTER.V
DISSOLVED GAS ANALYSIS
5.1 INTRODUCTION: Transformers are vital components in both the transmission and
distribution of electrical power. The early detection of incipient faults in transformers is extremely
cost effective by reducing unplanned outages. The most sensitive and reliable technique used for
evaluating the health of oil filled electrical equipment is dissolved gas analysis (DGA). Insulating oils
under abnormal electrical or thermal stresses break down to liberate small quantities of gases. The
qualitative composition of the breakdown gases is dependent upon the type of fault. By means of
dissolved gas analysis (DGA), it is possible to distinguish faults such as partial discharge (corona),
overheating (pyrolysis) and arcing in a great variety of oil-filled equipment. Information from the
analysis of gasses dissolved in insulating oils is valuable in a preventative maintenance program. A
number of
Samples must be taken over a period of time for developing trends.
CHAPTER.VI
TROUBLE SHOOTING CHART FOR ALL TRANSFORMERS
DEPARTMENT OF ELECTRICAL AND ELECTRONICS ENGINEERING
ANNAMACHARYA INSTITUTE OF TECHNOLOGY & SCIENCES
page 38
Trouble
(1)
Cause
(2)
Remedy
(3)
Over voltage
Rise in
Temperature
High Temperatures
Over current
High ambient
temperatures
Insufficient Cooling
Short-circuited core
Electrical
Troubles
Winding failure
Lightning, short-circuit.
Directive Foreign
Material
of
fuse.
Trouble
(1)
Cause
(2)
Remedy
(3)
Core insulation
breakdown
between laminations)
Short-circulated core
Test core loss. If high, it is probably due to a shortcircuited core. Test core insulation. Repair if
damaged. If laminations are welded together, refer
Trouble
(1)
Cause
(2)
Remedy
(3)
Incorrect voltage
Improper ratio
Audible internal
arching
Supply voltage
abnormal
Isolated metallic part
Loose connection
Same as above. Tighten all connections.
Mechanical
Troubles.
Lightning
Dirty bushings
Foreign materials in
Leakage through
screw
Joints
Filler. Improper
assembly
Trouble
(1)
Cause
(2)
Remedy
(3)
Leakage at gaskets
Insufficient or uneven
Compression improper
Preparation of gaskets
and
Gasket surfaces
Leakage in welds
Shipping strains,
imperfect
Weld
Pressure-relief
Improper assembly.
diaphragm
Mechanical damage
Pressure-relief
Internal fault in
diaphragm
conservator transformer
not blocked.
breathing.
In gas-seal transformer
obstructed pressure
values in discharge
relief value.
In sealed transformer
liquid level
too high.
Trouble
(1)
Moisture
Cause
(2)
Improper or insufficient
Remedy
(3)
Make sure that all ventilator openings are free .
ventilators
Moisture
Cracked diaphragm.
condensation in
sealed transformers
moisture in oil
Filter oil.
Audio noise
Rusting and
deterioration of paint
weathering.
with grease.
porcelain parts of
on terminal connection.
finish
bushings
Trouble
(1)
Cause
(2)
Remedy
(3)
Oil troubles
Condensation in open
Low dielectric
unobstructed.
strength
improper ventilation.
Broken relief diaphragm
Replace diaphragms.
Leaks around cover
Replace gaskets if necessary.
Leaky cooling oil
Test cooling and repair.
Contaminated by
Varnishes Carbonized
oil due to switching
winding or core failure.
Oxidation (sludge of
Exposure to air
acidity)
High operating
temperature
CHAPTER.VII
CASE STUDIES
CASE STUDY 1:
1. 125MVA, 11kv/ 220 kv , 50Hz, 3 generator transformer:
Sl . No.
: 6002681
Year of manufacture
: 1973
Oil Temp.
: 28C
Winding Temp.
: 28C
Ambient Temp.
: 28C
Date of test
ANALYSIS:
HV& LV Windings:
Results of IR,PI and Tan test obtained on the generator transformer are presented below;
Table 6.1: case study of generator transformer:
Insulation section
Insulation resistance
60 sec (G)
Polarization index
Tan (%)
@10 KV
HV vs LV connected to
grounded tank
1.72
2.24
0.249
HV vs LV ungrounded
1.76
2.83
0.243
LV vs HV connected to
grounded tank
1.19
3.23
0.248
The IR and PI values obtained are in the normal acceptable range. The PI is regarded as index of
dryness of the insulation system. For a good, healthy and dry paper-oil insulation system the PI
shall be higher than 1.5.
The Tan test values obtained on three insulation sections of the transformer are low and lie in
the normal permissible range. These results indicated low dielectric losses in the transformer
insulation system. Typical values of Tan for a new transformer are 0.5%. the maximum
permissible value of Tan for an in-service and aged transformer is 2%.
3.11.1999
TGC
8.45
CH4
237
C2H6
54
C2H4
588
C2H2
2961
H2
1982
CO2
1548
Observation:
DGA indicates that the failure was due to severe arcing in the transformer.
CASE STUDY 3:
3. 20MVA POWER TRNASFORMER
ROUTINE MAINTAINCE
TGC
6.90
53
C2H6
C2H4
28
C2H2
437
H2
140
CO2
1125
Observation: Rogerss ratio (0011) indicates arc with persistent sparking, IEC ratio (202) indicates
continuous sparking in oil.
CONCLUSION
In the conditional monitoring, we test the transformer for reliability of the equipment and also to
avoid the forced outage. If faults are found to be occurring outages can be planned and the fault can
be rectified before major occur. With strict monitoring, accurate diagnostics interpretations and
realistic operational/ maintenance
Strategies implementation the following would be achieved effectively:
BIBOLOGRAPHY