Cram Quizzes and Answers
Cram Quizzes and Answers
qxd
11/2/09
10:39 AM
Page 1
Cram Quizzes
and Answers
Cram Quizzes
Chapter 1
1. You are a project manager working for a large utility company. You have
been assigned the responsibility to manage a project that performs
monthly security vulnerability assessments and addresses any identified vulnerabilities. You question the assignment because
A. Security vulnerability assessments do not materially contribute to your organizations products and should not be
considered important enough to be classified as a project.
13_9780789742230_cram_quiz.qxd
11/2/09
10:39 AM
Page 2
D. Although your training looks like it is behind schedule, you wisely built
in enough slack time to cover such a problem. You simply find
replacement trainers and continue the training.
Chapter 2
1. You are a project manager newly assigned to a project to implement new manufacturing management software. The project sponsor tells you he has chosen
you because he is impressed with your record of completing projects. He tells
you that work must start immediately and there is not enough time to go through
all the formal documentation process. He asks for a quick list of tasks to start
now. What do you do?
A. Put a quick list of the most important tasks together, per the sponsors request.
C. Refuse to start on the project until you develop a project charter and
get it approved.
D. Explain the need for a project charter and project plan to the sponsor.
2. Which of the following statements does NOT apply to the project charter?
Chapter 3
1. You are a project manager newly assigned to a large project for your organization.
The project charter has been signed and the stakeholders have been identified.
What should you do next?
13_9780789742230_cram_quiz.qxd
11/2/09
10:39 AM
Page 3
Chapter 5
A. Bottom-up estimating
B. Decomposed estimating
C. Should-cost estimating
D. Three-point estimating
Chapter 4
1. What is the primary purpose of the human resource plan?
B. Describing a potential risk and the most likely choice and outcome
associated with the risk
C. Describing a potential risk and the least likely choice and outcome
associated with the risk
Chapter 5
1. What does crashing a project imply?
A. Project cost and project schedule tradeoffs occur to achieve the maximum schedule compression for the least cost to the project without
compromising the intended scope of the project.
B. Project cost and project schedule overruns resulting in a project coming in over budget and over time but within the original defined project scope.
13_9780789742230_cram_quiz.qxd
11/2/09
10:39 AM
Page 4
A. Weighting system
B. Expert judgment
C. Seller rating system
D. Screening system
Chapter 6
1. Youre managing a project using the earned value technique (EVT) for cost management. The project planned value (PV) is $200,000. The project earned value
(EV) is $100,000. The actual value (AV) is $150,000. What is the cost variance
(CV) for the project?
A. 100,000
B. 100,000
C. 50,000
D. 50,000
Chapter 7
1. The primary output of the close project or phase process is
13_9780789742230_cram_quiz.qxd
11/2/09
10:39 AM
Page 5
Chapter 8
Chapter 8
1. You have access to proprietary information a vendor included as part of a bid
proposal. The information was marked confidential and was included to show
the vendor would be issued a patent by the end of the month, which makes this
companys bid the best candidate for your company and significantly improves
the market share of the vendor. What do you do with this information?
A. Do nothing. File a complaint with the managers boss after the meeting.
B. Use your authority as the meeting leader to take control of the discussion and present your rebuttal.
D. Bring the managers boss into the meeting and ask for assistance in
addressing his comments.
13_9780789742230_cram_quiz.qxd
11/2/09
10:39 AM
Page 6
Answers
Chapter 1
1. Answer C is the best answer. As explained in this question, recurring security
vulnerability assessments with no ending date cannot be considered a project.
Projects must have time boundaries. Answer A is incorrect because the project
product does not have to be directly related to an organizations main product(s).
Answer B is incorrect because the lack of a specific start date in the question
description would not automatically disqualify the assessment as a project.
Answer D is incorrect because a security vulnerability assessment does create at
least one productthe vulnerability assessment report.
2. Answer B is correct. The question states that training is not meeting the schedule and the result is that the training is not getting people properly trained. That
means both schedule and quality are suffering. Of all the solutions, Answer B
provides the best description of the effects on your project. Answer A is incorrect because it does not mention the impact on project quality. Answer C is
incorrect for several reasons. The problem might be the responsibility of the
organization that supplied the trainers, but the responsibility of the impact on the
project is the project managers. Answer C also ignores the quality issue. Answer
D is incorrect because is implies that the project manager padded the schedule.
This is not an ethical practice. Your estimates should be realistic. If you expect
such problems to occur, you should address them in the beginning of the project, along with appropriate recovery methods. By padding the schedule, you
hide a real risk to the project.
Chapter 2
1. Answer D is correct. Answers A and B ignore the PMBOK requirement that a
project manager insist on proper project management techniques. It is crucial
that a PMP candidate understand the need for properly obtaining authorization
for a project (initiating) and then planning a project before starting actual work.
Answer C is too extreme for the initial response. The sponsor might have made
the request to immediately begin work out of a lack of understanding of project
management. Always start by getting as much information as you can and educating others on the benefits of good project management.
2. Answer D is the correct response. A work breakdown structure (WBS) is not a
component of the project charter. Answers A, B, and C are all components of the
project charter.
13_9780789742230_cram_quiz.qxd
11/2/09
10:39 AM
Page 7
Chapter 5
Chapter 3
1. Answer C is correct. The first process in the planning group is develop project
management plan. Answers A, B, and D skip the first process and start subsequent processes prematurely.
2. Answer A is the correct response. Bottom-up estimating is a technique for estimating cost through decomposition. The bottom-up estimate is based on the
cost requirements for each lower work package and then is combined to estimate cost of the entire component of work. Answer B is incorrect because there
is no technique called decomposed estimating. Answer C is incorrect because
should-cost estimating is an activity duration estimating technique. Answer D is
incorrect because three-point estimating does not incorporate decomposition.
Chapter 4
1. Answer A is correct. Answers B, C, and D describe other processes in the executing process group.
2. Answer A is the correct response. A decision tree diagram can be used to consider potential risks and all the implications associated with the risk. You can
include every conceivable choice and outcome. Every option is considered.
Answer B is incorrect because choice and outcome are limited to the most probable scenario. Answer C is incorrect because choice and outcome are limited to
the least probable scenario. Answer D is incorrect.
Chapter 5
1. Answer A is the correct response. Crashing is a schedule compression technique
whereby the project cost and project schedule are optimized to obtain the highest degree of schedule compression for the least cost to the project. Crashing
does not always result in a viable project solution and can increase the overall
cost of your project. Answer B is incorrect because crashing is not a term used
for a project that is over time and over budget. Answer C is incorrect because
crashing does not necessarily allow you to meet the planned project end date.
Answer D is incorrect because fast tracking is another schedule compression
tool used to perform multiple phases of project development in parallel.
2. Answer D is correct. A screening system rejects sellers that dont meet minimum
requirements.
13_9780789742230_cram_quiz.qxd
11/2/09
10:39 AM
Page 8
Chapter 6
1. Answer D is the correct response. Cost variance (CV) is calculated by subtracting
the actual cost (AC) from the earned value (EV). CV=EVAV. In the example
given, the AC is $150,000 and the EV is $100,000. $100,000$150,000=-$50,000.
Answer A is incorrect. Answer B is the schedule variance (SV), not the CV, so it is
incorrect. Answer C is incorrect.
2. Answer B is correct. Before risks can be mitigated, you need to know how
probable is it that they will occur and what their triggering events are.
Chapter 7
1. Answer A is correct. The primary output of the project closing process is to formalize and distribute all the information pertaining to the closing of the project.
This coordinated message is distributed by administrative closure, contract closure procedure, final product, service, or result and organizational process
assets (updates).
2. Answer E is correct. Lessons learned are used to collect information pertaining
to good and bad outcomes throughout the project execution. If you look at the
output sections of the PMI methodology, lessons learned are virtually a part of all
the execution processes.
Chapter 8
1. Answer C is the best response. You have a responsibility to maintain and respect
the confidentiality of sensitive information obtained in the course of professional
activities. This responsibility makes Answers A and B incorrect. You have a
responsibility to recognize and respect intellectual property developed and
owned by others, which makes Answer D an incorrect choice.
2. Answer C is the correct answer. The PMI Code of Ethics and Professional
Conduct requires that you act in a professional manner even when others do
not. Answer A is incorrect because doing nothing solves nothing. Going to the
managers boss is likely to make the situation worse, not better. Answer B is
incorrect because it is an emotional response, not a professional one. Answer D
is incorrect because you should always first attempt to solve differences one-onone.