Cost Management Plan Template (4306)
Cost Management Plan Template (4306)
<Month, Year>
<Project Name>
Office of System Integration
<Project Name>
Office of System Integration
Revision History
REVISION HISTORY
REVISION/WORKSITE
#
Initial Draft SIDdocs
DATE OF
OWNER
RELEASE
06/30/2004 SID - PMO
SUMMARY OF CHANGES
Initial Release
ROLE
DATE
<Project Name>
Office of System Integration
toolbar. The File Download dialog box will open. Click on Open to return to
this document.
<OSIAdmin #4306>
ii
<Project Name>
Office of System Integration
Table of Contents
1. INTRODUCTION.....................................................................................................1
1.1 PURPOSE.........................................................................................................1
1.2 SCOPE.............................................................................................................1
1.3 REFERENCES...................................................................................................2
1.3.1 Best Practices Website..............................................................................2
1.3.2 Project Document Repository....................................................................2
1.3.3 Project Cost Database and Tool................................................................3
1.4
1.5
ACRONYMS......................................................................................................3
DOCUMENT MAINTENANCE................................................................................3
iii
<Project Name>
Office of System Integration
iv
<Project Name>
Office of System Integration
5.5
RECONCILIATION.............................................................................................18
List of Tables
TABLE 1. LEVELS OF COST MANAGEMENT.......................................................................1
List of Figures
FIGURE 1. RELATIONSHIP OF BUDGET/ACCOUNTING PROCESSES TO COST MANAGEMENT
PROCESSES............................................................................................................2
<OSIAdmin #4306>
<Project Name>
Office of System Integration
1. INTRODUCTION
1.1
Purpose
The purpose of cost management is to ensure the project and its contractors will
complete the project within budget. This Cost Management Plan identifies the
processes and procedures used to manage costs throughout the projects life cycle.
The plan covers the cost management approach, expenditure tracking, variance
analysis, oversight of contractor costs, and reconciliation between the State budget,
accounting, and project management cost processes.
Additionally, the plan covers who is responsible for tracking expenditures, how
variances will be addressed, and the cost tracking and reconciliation between the
State and project management cost processes. This plan also describes the cost
management tool that will be used.
1.2
Scope
The scope encompasses the two levels of cost management for OSI projects. One
level is the detailed accounting level of tracking budget, expenditures, salary and
benefits, and overhead costs in accordance with the normal State of California
budget process. The second level is the project management level of tracking costs
against work performed in accordance with the OSI Best Practices standards
derived from the Project Management Institutes Project Management Body of
Knowledge (PMBOK). Table 1 shows the differences in terminology that will be used
in this plan when discussing the two different levels.
Table 1. Levels of Cost Management
STATE BUDGETING/ACCOUNTING
Budget Planning
Accounting/Expenditure
Tracking
Changes to the Budget
Reconciliation
Adding to the complexity is the interaction of the budget and cost management
processes with the contract management (acquisitions and invoicing) and time
reporting (attendance and timesheet tracking) processes. All of these processes
must interact and reconcile with each other.
In the figure below, the items toward the left hand side of the chart represent the
state budget, accounting and contract management processes (lightly shaded
bubbles). The items towards the right hand side of the chart represent the project
cost management processes (white bubbles). The two processes must reconcile at
the Initial Baseline, (after the Budget Act is signed) in the monthly attendance and
<Project Name>
Office of System Integration
time reporting processes, in the monthly expenditure and cost update processes,
and whenever there is a re-plan and a new baseline established.
State/Fed
Approvals
APD
Planning
And/Or
Master Project
Cost
(to the WBS Level)
FSR
Hearings
Readiness
Resource
Planning
BCC
BCP
Cost
Estimating
Budget
Act
Initial Baseline
Re-Baseline
Re-Baseline
Re-Baseline
Rev 1
Encumbrances
Amendments
POs/
Contracts
TAP
Work
Authorizations
Reconciliation
Cost
Budgeting
Tracking &
Change Control
Expenditures
Lessons
Learned &
Closeout
Time Reporting
(against WBS)
Attendance
Tracking
Reconciliation
Incorporate
Lessons
Learned
Analyze
Lessons
Learned
Cost Tracking
Re-Planning
Variance Analysis
(monthly)
Unacceptable
Acceptable
Variance
Change Control Variance
Board
Invoices
Archive
Cost Data
DESCRIPTION
Project Cost Management
Budget Baseline w/possible
revisions
Funding and Expenditure
Documentation
Contracts and Invoices
References
<Project Name>
Office of System Integration
Acronyms
List only acronyms applicable to this document. If the list becomes longer than one
page, move the acronym list to the Appendix.
APD
APDU
BCC
BCP
BPWeb
CALSTARS
CM
DGS
DOF
FSR
IPOC
IPOR
IV&V
M&O
OSI
PCA
PIER
PMBOK
SCO
SOW
SPI
SPR
TA
TAP
WBS
<Project Name>
Office of System Integration
1.5
Document Maintenance
This document will be reviewed annually and updated as needed, as the project
proceeds through each phase of the system development life cycle. If the document
is written in an older format, the document should be revised into the latest OSI
template format at the next annual review. This document contains a revision
history log. When changes occur, the documents revision history log will reflect an
updated version number as well as the date, the owner making the change, and
change description will be recorded in the revision history log of the document.
2. PARTICIPANT ROLES AND RESPONSIBILITIES
This section describes the roles and responsibilities of the <Project Name> staff with
regard to cost management. The following are the primary participants in the budget,
accounting, and cost management processes from the projects perspective. In
some cases, one individual may perform multiple roles in the process.
2.1
The Office of Systems Integration (OSI) is responsible for coordinating the state
budget and accounting processes with the projects in OSI and the appropriate
control agencies.
2.1.1 OSI Director
The OSI Director is responsible for approval of funding documents and representing
<Project Name> at the budget hearings.
2.1.2 OSI Chief Deputy Director
The OSI Chief Deputy Director is responsible for review of project funding
documents, and for representing the projects at budget hearings, as necessary.
2.1.3 OSI Budget Office
The OSI Budget Office is responsible for coordinating the review and submission of
approval documents (e.g., Feasibility Study Reports (FSRs) and Advance Planning
Document (APDs), Budget Change Concepts (BCCs), and Budget Change
Proposals (BCPs)) to the appropriate state control agencies for all OSI projects. The
Budget Office coordinates responses to questions from the control agencies and,
creates and distributes the Governors Budget. They are the single point of contact
for state communications (Control Agencies, Project Sponsors, and other State
Agencies). The OSI Budget Office also coordinates the development of the
departments travel budget which includes estimates for project travel.
2.1.4 OSI Accounting Office
The Accounting Office is responsible for coordinating the accounting, customer
billing, invoice approval processes, travel advances, and travel claims for all projects
in OSI. The Accounting Office works with the OSI Budget Office to reconcile the
budget to the expenditures.
<Project Name>
Office of System Integration
The Project Director is responsible for approval of the Project Cost Management
Plan and is ultimately responsible for the allocation and expenditure of the project
budget.
2.1.7 <Project Name> Project Manager
The Project Manager is responsible for managing and reviewing project costs from a
project management perspective to ensure appropriate progress is being made for
the funds being expended. The Project Manager works with the financial staff to
reconcile the cost management data to the current accounting data.
2.1.8 <Project Name> Project Financial Manager
The Financial Manager is responsible for leading the cost management effort,
sponsoring cost budgeting and tracking activities, facilitating communication on fiscal
status, and ensuring the project cost tool is maintained and supporting
documentation is maintained. The Financial Manager is responsible for providing the
Project Manager with recommendations and status on the project budget and
expenditures. This role must be performed by a state employee. If the Project
Manager is a state employee they may assume this role.
2.1.9 <Project Name> Project Financial Analyst(s)
The Financial Analyst(s) are responsible for coordinating and developing project
funding and approval documents and expenditure tracking and reconciliation in
accordance with state processes. The analysts also work with the Financial Manager
to reconcile the cost management and accounting data.
2.1.10
The Functional Manager(s) are responsible for identifying funding needs and for
assisting with the tracking of expenditures, including tracking of staff effort and costs.
2.2
Section 2.2 should be updated to reflect the name of the sponsor organization.
IV&V/IPOC may be removed if the project is not required to have this function.
2.2.1 Sponsor Financial Staff
The sponsors financial staff works with the project financial staff to develop the
sponsors budget in coordination with the projects budget. The sponsor financial
staff is also responsible for authorizing payment for project services.
<Project Name>
Office of System Integration
Section 2.3 should be updated to reflect the name of the federal partner, if
applicable. Add any additional information regarding federal participation, reporting
or required approvals, as appropriate.
The projects federal partner is responsible for review and approval of project
funding documents.
2.4
Contractors
If the project has a prime contractor, indicate how the prime participates in the
projects budgeting, including coordination of planned costs for the next fiscal year
(particularly during M&O) and reporting of cost data for inclusion in project cost
management processes.
The Contractor is responsible for reporting appropriate costs to the project and to
their efforts as described in their contract. The contractor is responsible for
managing costs internal to their activities. The contractor should report their costs in
their monthly status reports and raise potential or actual cost variances or problems
to the project team at appropriate status meetings.
2.5
Counties/Local Offices
<Project Name>
Office of System Integration
Budget Planning
This section is intended to be written generically enough to describe both the Fall
and Spring Budget Processes.
The state budget is established on a yearly basis, the funding for the project is only
secured for one year at a time (although requests for future year funding may be
reviewed, but not guaranteed).
3.1.1 Project Concept Approval
Describe how the initial project approval and approximate budget was
established/received and what might cause a new concept (e.g., welfare reform, new
M&O initiatives, etc.). Discuss where the funding is coming from: grants, general
fund, bonds, federal funding, etc. and any restrictions on the money that was/may be
received.
Describe who is responsible for the development of any new BCCs. If appropriate,
discuss the annual Interagency Agreement updates and how that affects the budget
and new concepts. Describe the organizational coordination required to establish the
BCC and, if companion BCCs must be used (e.g., one BCC for OSI and one BCC
for the Sponsor which are dependent on each other), who is responsible for what
types of activities, etc.
When appropriate, new project concepts or staffing requests are proposed through
the development of a Budget Change Concept (BCC) and high-level cost estimates
(refer to Section 4.1 for more on developing cost estimates). The project financial
staff prepares the BCCs in accordance with instructions provided by the OSI Budget
Office. The OSI Budget Office coordinates the review of BCCs with the OSI Director
and Agency.
3.1.2 Project Document (< FSR/SPR or APD>) Development
Based on the specific project, describe the project document development process.
<Project Name>
Office of System Integration
<Project Name>
Office of System Integration
The Budget Office coordinates any questions regarding the budget proposals, and
assists with the budget hearings. Once the Budget Act is signed, the project financial
staff reviews the final Budget Act for any change to the requested amounts.
The Project Manager and Project Financial staff reviews the budget against the cost
estimates, and adjust the cost baseline, if necessary.
3.1.6 Responding to Budget Drills and Analyses
If the project responds to budget drills, it may be useful to include this section.
Discuss the approach to budget drills: who coordinates the response, who reviews
the information, who must approve the response, and how responses are
coordinated with the sponsor (and when coordination is appropriate). Also discuss
other budget analyses and reviews that may be required to support budget
reductions, changes in project approach or scope, changes in rates, analysis of
proposed contractor work orders or amendments, etc. This section should discuss
only the analysis of proposed changes. Refer to the Changing the Project Budget
section (below) to describe the specific processes to enact a change.
3.2
Acquisitions Tracking
Who does the product research (e.g., IT, functional manager, requestor, etc.)
<Project Name>
Office of System Integration
How are the equipment costs tracked/depreciated and who is responsible for
tracking depreciation (project vs. OSI)
The project Administrative and IT staff work with the OSI Acquisition Center to
identify and document specific requirements for equipment. The OSI Acquisition
Center solicits vendors to obtain the desired equipment at the best price from the
various DGS supplier lists. The project notifies OSI Acquisition Center and the
Accounting Office when the equipment is received and if it meets the stated
requirements. Upon approval by the project office, the Accounting Office coordinates
payment to the vendor.
3.2.2 Acquisitions for Services
Discuss briefly how project contracts are procured and how contract expenditures
are handled. If contract withholds, liquidated damages, etc. are used, describe the
processes to track and invoke these refer to the appropriate contract management
processes for additional information. Discuss any coordination performed with the
Acquisitions and Contract Manager for tracking deliverables, services, invoices,
withholds, and liquidated damages.
The project Procurement and Contract Management staff work with the OSI
Acquisition Center to identify and document specific requirements for the desired
services. The OSI Acquisition Center solicits offers/proposals from qualified bidders,
coordinates questions/answers to the requirements and oversees with the review
and evaluation of offers/proposals. The project works with OSI Acquisition Center to
conduct interviews, if appropriate, and selects the winning bidder. The OSI
Acquisition Center creates and issues the contract documents.
Depending on the contract amount, either the OSI Director or Agency Secretary is
the final approver of consultant contracts. The Project Manager is the approver of
the Task Accomplishment Plans (TAPs), and consultant invoices. The Project
Functional Manager tracks the contractor day-to-day tasking, performs review of
consultant work products, and assists with invoice review and approvals.
The project has three to five working days to respond to contractor invoices, in
accordance with Government Code Section 927 (California Prompt Payment Act).
The contractor submits official invoices to OSI Accounting. OSI Accounting Office
sends the Project a copy of the invoice for review and approval. The project financial
staff reviews the invoice against the deliverable tracking log and the attached
timesheets to validate the information. The Project Manager reviews the invoice and
Project Financial Analysts comments and recommendations, and makes the final
decision to approve or reject an invoice. The approval or rejection notice is faxed to
the OSI Accounting Office who coordinates payment with the State Controllers
Office. Refer also to the Contract Management Plan for more on invoice processing
and review.
10
<Project Name>
Office of System Integration
Discuss where actual expenditure data comes from, how the expenditures are
validated for accuracy, and how they are coded and posted to the project
expenditure tracking tools.
Discuss if there is any coordination with the sponsor regarding monthly or quarterly
expenditures. Discuss any coordination with county/local offices for their
expenditures.
The project tracks all contract, personnel and operations expenditures in <Insert
Expenditure Tool>. At the close of each month, the project receives expenditure
reports from the Accounting Office showing the funds that were expended according
to California State Accounting and Reporting System (CALSTARS). The project
reviews and validates the expenditures match with their records of expenditure
approvals and works with the Accounting Office to resolve any discrepancies.
3.3
11
<Project Name>
Office of System Integration
3.4
Describe the process used to review and approve a project budget change. This
section should discuss the typical reasons and types of changes such as moving
dollars between fiscal years, addressing changes in project approach (usually
requiring an SPR), addressing minor changes such as coding/category changes,
etc. Describe the approvals required for each type of change and the archiving of the
prior cost baseline/budget and establishment of the new cost baseline/budget.
Discuss supporting materials that must be kept and/or generated to support the
approval process.
Discuss required approvals include a reference to the Budget Development section
of the plan for the procedures to enact a change, as appropriate. Include a reference
to the contract management processes for changing a contract dollar amount.
If the project budget needs to be adjusted, the Project Manager determines if an
approval document (e.g., APD or FSR) and/or BCP/SPI needs to be written to
address the change. If a change is deemed necessary, the financial staff develops
the approval document and/or BCP/SPI. The OSI Budget Office coordinates the
submission and approvals of the document(s) in accordance with the state budget
cycle.
Once the change is approved and included in the appropriate fiscal year budget, the
Project Manager works with the financial analyst to re-baseline the cost data and
estimates.
3.5
Budget Reconciliation
12
<Project Name>
Office of System Integration
The following section summarizes the project management processes for managing
costs on the project as tailored from the PMBOK 1.
Communication is a key part of the cost management process and occurs at every
step of the process among the project team, project stakeholders and consultant
team.
4.1
Cost Planning
The project has chosen to tailor the PMBOK guidance on Cost as follows: The planning processes
of Cost (Resource Planning, Cost Estimating, and Cost Budgeting) have been consolidated into a
section called Cost Planning. The PMBOK Controlling processes (Cost Control) have been expanded
into four sections called Cost Tracking, Cost Reporting and Metrics, Cost Control and Changes, and
Cost Closeout.
13
<Project Name>
Office of System Integration
Discuss the inputs used to establish the resource estimates. Indicate where the
resources estimates and supporting information is located/stored.
Cost estimation begins upon completion of the project WBS2. Resource skills are
determined based on the needs of the project and the products being produced. The
project uses and tailors the personnel resource information from the <Project Name>
Staff Management Plan and <Project Name> Responsibility Assignment Matrix for
determining needed resource skills.
4.1.2 Cost Estimating
Describe any specific cost methods used to validate or confirm the costs estimates
for the various tasks. Refer to PMBOK, regarding Cost Estimating for more info.
Discuss correlation of cost allocations to the project budget (chart of accounts) or put
this information in Section 5 on Reconciling the Accounting/PM Perspectives.
Hour estimates are created for each WBS item. The necessary skill sets and staff
labor categories are identified for each WBS element. Approximate costs are
estimated based on the anticipated classification of staff assigned to the work.
The anticipated costs are allocated to each WBS item and totaled. Resource/labor
costs are allocated by resource category and total.
The estimates are then used to request funding or funding adjustments for the
project (refer to Section 3.1 on state budget requests). Risks associated with the
cost estimates are documented and included in the risk management database.
4.1.3 Establishing the Cost Baseline
Describe how the cost baseline is set and what approvals are required. Indicate if
the baseline is set manually (by saving a clean copy to fall back to, or a new
version in WorkSite) or what specific tool feature is used to establish the cost
baseline.
Once the Budget Act is signed, the Project Manager and Project Financial Analyst
review the cost allocation (of funding per WBS item) against the approved budget,
and adjust the allocations, if necessary, to reflect the approved funding for the year.
Upon approval by the Project Manager, the cost allocations are baselined. For more
information on the current cost allocations to WBS items, refer to the projects
Master Project Plan.
4.2
Cost Tracking
Actual hours expended are recorded and validated against attendance records and
contractor monthly reports. The hours are converted to costs for tracking the cost of
current progress to determine if the project is staying within and expected to
complete within budget.
Refer to the project Master Project Plan to obtain the projects WBS and refer to the project
Schedule Management Plan for a description of how the WBS was established.
14
<Project Name>
Office of System Integration
Who ensures the sheets are setup and ready for use
To assist with tracking actual costs against the baseline, the following charts/reports
are used. The charts are available in the <Insert reporting tool such as CalSTARS,
Excel, etc>, and are updated as described below.
15
<Project Name>
Office of System Integration
Spending Plan (by fiscal year) a run chart showing the actual costs against
the baseline by month for the fiscal year and the cumulative total to date for
the fiscal year.
Cost by WBS Item - a bar chart showing the labor costs by Level 1 WBS items
by month for the fiscal year and the cumulative total to date for the fiscal year.
Cost Variance by WBS Item a bar chart showing the actual costs against the
baseline to date.
Labor Hours by WBS Deliverable Item a bar chart showing the amount of
effort expended towards the Level 1 WBS items by month for the fiscal year
and the cumulative total (to date) for the fiscal year.
The Project Manager and Project Financial Manager will compile the reports and
submit the reports to the Project Director and if needed, Project Executive Steering
committee consistent with the Communication Management Plan reporting
requirements.
4.4
If the overall cost baseline is affected, the variance is documented and reported to
the Project Director and, subsequently, the <Project Name> Executive Steering
Committee. The Project Director and the <Project Name> Executive Steering
Committee review the rationale and discuss the options and mitigations for dealing
with the variance, and determine if a re-plan, is necessary. If so, the issue and
recommendation is presented to the <Project Name> Executive Committee for
review and approval. The <Project Name> Executive Steering Committee makes the
policy decision to amend the projects cost, scope, schedule, or quality.
4.4.3 Cost Re-Planning
If a re-plan is deemed necessary by the <Project Name> Executive Steering
Committee, the project prepares documents to address the re-plan. The state
funding documents are included in the next budget cycle and are subject to the
normal review and approval processes.
4.4.4 Cost Re-Baselining
Once the re-plan is approved, the Project Manager works with the Project Financial
Manager to re-baseline the cost data and estimates based on the approved funding.
16
<Project Name>
Office of System Integration
The project works with the OSI Accounting Office to adjust their encumbrances and
accounting tools to reflect the re-plan.
4.5
Cost Closeout
At the end of the project, the cost historical information is completed by the Project
Financial Manager, reviewed by the Project Manager, submitted to OSI Budget
Office for review and then forwarded to TA.
4.5.1 Annual Cost Summary
At the end of the fiscal year, the Project Manager and Project Financial Manager
summarize the actual hours and costs expended against the baseline for the fiscal
year. The annual summary is archived for historical purposes.
4.5.2 Lessons Learned on Cost Management
Lessons learned related to costs and cost estimation are used in the development of
the subsequent fiscal years cost baseline.
5. RECONCILING THE STATE PROCESS TO THE PROJECT PROCESS
As discussed previously, the State budgeting and accounting processes operate
separately from the project cost management processes, though they are related.
This section discusses the relationships and where these processes must interact
and synchronize.
5.1
Once the project management baseline (or revised) budgets have been finalized, the
<Project Name> team must determine if future Annual budget demands require
adjustments to OSIs base spending authority. If additional spending authority is
required, a BCP must be prepared. If additional spending authority is not required,
the project adjusts the cost baseline to reflect the actual approved budget for the
fiscal year.
5.2
Specifically discuss how the attendance tracking and time reporting processes relate
and reconcile to each other as part of the cost tracking process. Who is responsible
for the coordination and reconciling? What happens when there is a discrepancy?
Do not repeat information that has been discussed in prior sections, but summarize
or refer to the appropriate section, as applicable.
State staff submits monthly attendance reports at the end of the month. These
reports are used by OSI Accounting to bill the project for state staff salary and
benefits.
17
<Project Name>
Office of System Integration
5.3
Invoice Processing
Invoices must clearly identify the products (deliverables) and service period for
which the invoice is requesting payment. The prime contractor and nonprime
contractors must adhere to specific invoice requirements set forth in the contract.
All contractor invoices are sent directly to OSIs Accounting Office. This office logs
the invoice, begins the processing cycle and coordinates the actual payment with the
SCO once all the appropriate approvals have been received. The Accounting Office
retains the original invoice.
The California Prompt Payment Act (Government Code Section 927, et seq.)
established a 45-day turnaround time for payment of undisputed invoices. The 45day period begins when the invoice is received at OSI and ends when the check is
sent from the SCO to the contractor. OSI has only 30 days to process the invoice
and route it to SCO for payment. Within these 30 days, the <Project Name> project
has only five business days to process the invoice and fax the response back to
the Accounting Office. (Projects that exceed their allotted five-business day review
will incur the late penalty fees should payment not be issued within the 45-day time
frame allowed.) The SCO has 15 days to process the check request.
After logging the invoice, the Accounting Office routes a copy of the invoice to the
project for review and approval. Upon receipt of the invoice at the project, it is routed
to the Project Financial Analyst who verifies that the personnel, classifications, and
rates in the invoice correspond to the terms in the contract. The Project Financial
Analyst also verifies the PCA codes are correct, if applicable. If travel expenses have
been included, the Financial Analyst verifies the contractor is authorized to bill for
travel expenses, the necessary receipts are present and under no circumstances will
claim exceed the states allowable travel rates. The invoice is then routed to the
Contract Manager (CM).
If the invoice is from a nonprime contractor, the CM will verify that all deliverables for
that billing month have been received and approved. If the deliverable(s) has not
been approved, the invoice will not be approved for payment. If the invoice is from
the prime contractor, the CM will verify that all issues relating to withholds and
liquidated damages have been reviewed and addressed.
If all the information is acceptable, the invoice is passed to the Project Manager for
final review and signature. If the Project Manager approves the invoice, the
approved paperwork is sent back to the OSI Accounting Unit, who will then send a
payment request to the SCO.
If some or all of the deliverables or services were unacceptable, the CM notifies the
Accounting Office that the invoice is unacceptable and indicates why the invoice is
being disputed. The OSI Accounting Office sends a notice of invoice dispute (Form
209) to the contractor indicating why the invoice cannot be paid and what must be
done or corrected. The 45-day processing clock stops when the Accounting Office
sends the notice of invoice dispute to the contractor. After addressing the problems,
the contractor re-submits an invoice for payment to OSIs Accounting Office and the
processing clock is reset and restarted.
18
<Project Name>
Office of System Integration
5.4
Changes to the annual OSI budget and spending plan may be required by the
project to support a re-plan. The Project Manager and Project Financial Manager will
partner to ensure that the State budget and the project management baseline
estimates match. Corrective actions or change requests will follow the appropriate
project change or budget change processes.
5.5
Reconciliation
At the end of the fiscal year and at the end of the project, a reconciliation must be
completed using both the project cost management and project accounting
processes. The expenditures must reconcile to the approved budget and also to the
OSI accounting system.
6. COUNTY BUDGET MANAGEMENT
If the project is reimbursing counties/local offices for costs, this section is
mandatory.
If the project involves payment of county costs or reimbursements to counties or
local offices, this section is considered mandatory. For projects not dealing with
county/local office funding, this section should be marked as not applicable.
Complete this section by discussing budget planning, cost allocations, spending
authorities, expenditure approvals, expenditure tracking and receipts, and
reconciliation.
Additional procedures for the county/local office should be developed and
referenced in this plan which describes how to request state funding for county
activities; how the request is reviewed, approved and included in the project/sponsor
budget; and how the actual funding is provided/reimbursed to the county.
7. PROJECT COST TOOL
If the project is using a database tool (MS Access) or other software package (other
than MS Excel) for tracking costs and budget information, this section should be
included.
If the project only uses MS Excel spreadsheets, then indicate this and list the names
and WorkSite numbers (or location) of the spreadsheets and their purpose.
7.1
Identify and discuss the primary features of the tool/database. Indicate the
manufacturer/developer and who is responsible for maintenance and upgrades of
the tool. Indicate the platform and version of the tool. Indicate why the tool was
selected. Indicate any interfaces or dependencies to other tools.
19
<Project Name>
Office of System Integration
Discuss security and user accounts. Indicate if the data is considered sensitive and if
there are any special approvals for data updates or major changes. Indicate if there
was any customization done for the project that is different from the standard
version.
Indicate where the user manual and/or training materials are located or accessed.
7.2
Discuss the specifics about using a tool including the primary features and reports
used by the project. Refer to the specific procedures available and any tips/tricks for
using the tool. If appropriate, attach supporting information in an appendix or refer to
where it may be found.
APPENDICES
20
<Project Name>
Office of System Integration
21