Project Delivery Methods

Download as pdf or txt
Download as pdf or txt
You are on page 1of 18

Project Delivery Methods

Project Delivery Systems




Traditional

Pure Construction Management

Construction Management at risk

Design / Build

Modified CM Design/Build: Design Subcontracted

CM Oversight Design/Build

Multiple Primes

Design-Built-Operate-Transfer (BOT)

Turnkey

Most Common Delivery Methods

Traditional Delivery Method

Traditional Delivery Method




Design professional in charge of the preparation of design and


contract documents

Competitive bid or negotiation with contractors after design


complete

Contractor in charge of the delivery of the completed project (may


decide to subcontract)

The contractor is the only one responsible for the execution of work

Sequential Construction Process

Collaborative relationship between A/E (Chosen on Qualification


Basis) and Owner

Lump-sum bids commonly adopted.

Traditional Delivery Method


Different participants with different Interests:


Owner: Quality and value product, delivery schedule, site


safety

Contractor: Profit, construction time, relationships,


reputation

A/E: Profit, aesthetics, relationships, quality, recognition

Traditional Delivery Method


General Contractor Responsibilities


Still responsible for a large portion of work (particularly public jobs


with bidding)

For larger jobs, GC doesnt do much of work (sometimes <10%)

Contractor designs temporary structures (Engineer needs to stamp)

Traditional Delivery Method


Subcontracting
GC manages most subcontractors


Exceptions: Tenant subcontractors

Overhead at each level

Handles submittals

Get bids from subcontractors (bid shopping a danger; no formal


guarantee of award of contract)

Bidding here is typical

Can be large number of subcontractors

Responsible for failure

Shop drawings typically produced by subcontractors

Problem: Things can fall through the cracks

Traditional Delivery Method


Subcontracting


Motivations to GC to Subcontract:


No In-house ability

GC overstretched

GC lacks familiarity with local conditions

Need to get warrantees

Laws and regulations (assign subs to contractor)

Due to specialization, more efficient, cheaper

Sometimes GC provides equipment to subs

Tensions (e.g. how quickly, many subs on site)

Subcontractor management very important for productivity

Traditional Delivery Method


Role of Architect/Engineer


Typically negotiated contract




Recruited on service rather than commodity basis

Financial stability, other factors critical

Sometimes have design competition

Dont want to push too low:

Poor design

Poor personnel

No time for double-check

Contrast


Price of design has small impact on overall price

Quality of design has big impact on overall price

Traditional Delivery Method


Role of Architect/Engineer II


Sometimes do own value engineering (dangerous)

If estimates off, may be required to redo design at own expense

Carry errors and omissions experience

Limited participation in construction process

Typically observes construction

Review shop drawings with disclaimers

Do not want to direct construction methods




May put suggestion in contract documents

Traditional Delivery Method


Advantages


Well known method (courts, companies)

Flexibility during design (vs. design-build)

Cost defined early (when bidding)

Good contractual protection for the owner

Open bidding procedure very easy

Owner not too involved in the construction process

Trusting relationship between A/E & Owner

Good if uncertainty exists, primarily in design

Traditional Delivery Method


Disadvantages
Design not reviewed before construction

Miss opportunities for major time/cost savings

May yield changes due to constructability problems

Sequential and linear process preventing from overlapping of


tasks and money saving

Few interactions among the participants

Construction cant start until design is complete

Difficult for complex projects

Traditional Delivery Method


Changes Difficult


Owner can be at contractor's mercy


(Role of on-call contractor)

Design Fixed after construction starts

Sometimes contractors seek changes to make $

C.M. Delivery Method

C. M. Delivery Method (Pure Agency)




The Owner hires both a design firm and a construction management


firm before the beginning of the construction of the project

Typically CM selected based on quality

Many variations are possible in the delivery method depending


mostly on when the management team is hired and its skills

Started in late 1960s




World Trade Center

Madison Square Garden

May recommend A/E

Check billings

C. M. Delivery Method
Tasks
Pre-construction
Constructability, value engineering, estimation, alternatives,
schedule, financing, manage designer, early procurement

Field supervision
QA, Targets met, invoice checking, coordinate work of contractors,
change orders, payments, claims, inspections for design
requirements, sometimes safety

C. M. Delivery Method
Lessens Owners Responsibility


Project control

Job meetings

Management meetings

Reports (operational and annual)

Administrative tasks

Budgets

Drawing approval

Oversight

Quality assurance

C. M. Delivery Method
Pure (Agency) C.M.

Great flexibility in the schedule and for changes

Market competition for subcontracts

Trust relationship with the Contractor

Small financial risks of PCM and high risk of loss of reputation

PCM Generally paid a Fixed Fee (professional)

Take over work of designer, GC, owner

PCM as facilitator/mediator in conflicts

C. M. Delivery Method
Pure (Agency) C.M.
Advantages


Great Flexibility for Changes

CM more objective, less partial

Less conflict between owner and CM

Small Financial Risks of PCM

Have both


Cost competition (for subcontractors - often 5-8% savings for


dealing directly with subs)

Fiduciary relationship with CM

One common reference point: The CM

Owner can get rid of particular subcontractor

Lessens owners responsibilities

10

C. M. Delivery Method
Pure (Agency) C.M.

Disadvantages


Lower incentive for CM to reduce price, time

Owner alone takes risk on cost of project (no guarantee from CM)

Participants must all be cooperative and well communicating

High Risk of Loss of Reputation

C.M. @ Risk

11

C.M. @ Risk


CM usually Guaranteeing Maximum Price: GMP to give the owner


security that the project will be built within budget


This is a big difference from pure CM

Fee typically 10-15%

Reduced Owner Risk

Risk-wise, between the DBB and the PCM System (VERY similar to
GC hired early)

Contractual Relationships between. CM & Subs

Performance bonds typical

C.M. @ Risk
Advantage


Reduces Owners Risk

CM at risk usually goes with Guaranteed Maximum Price (GMP)

Contractual Relationships between CM and Trade Contractors

Disadvantages


The GMP is a defined price for an undefined product

Bad during design: Design pressure

Tension (If CM is hired early: more price risk If CM hired late: less value
during design)

CM is no longer impartial (may argue against changes for own interest)

Risk of adversarial relationship with the A/E

12

Design-Build

Design-Build


The Owner develops 20-30% design and hires a design/build firm


that will complete both design and construction

This firm can be a design/build firm but also a joint-venture firm for
this specific project

Possibility for the design/build company to hire subcontractors

Solicit work with RFP

Can be good for complex projects but need phased design to shield
parties from risk

One contractual team responsible for design and construction


functions

Owners with more emphasis on schedule despite less control and


more uncertainty of cost

Loss of control over design and flexibility in changes

Owner with enough knowledge about design/construction to


establish initial parameters, review proposals & monitor process

13

Design-Build


Dominant method early in US history

Recent drivers


Downsizing of US corporations (outsourcing design)

Desire for single source of responsibility

Time pressure (desire to fast track)

Shortcomings of tightly defined architect role (constructability


issues, limited A/E oversight of construction)

Bridge Designer/Engineer

Serves as bridge between Owner and Design-build team

Preliminary design before DB team hired (Maybe up to 30%


design)

Monitors development of design and construction (Fiduciary with


owner)

Design-Build
Advantages


Allows Fast Tracking

May be good for some complex projects

Close coordination within team

Good interactions among participants

Single source of accountability and

Designer/contractor conflicts not exposed to owner

Easier incorporation of changes caused by field conditions

14

Design-Build
Disadvantages


Pricing isnt possible at the beginning

Can be bad for complicated projects (Very important for owner to be closely
involved to specify important aspects of design up-front)

Fewer checks and balances




Changes in contract

Problems may be hidden until late (no A/E to watch)

May take a direction that the owner does not really want

Design-build firm can give high quote for changes

Fast tracked: Changes can lead to (Rework, Iteration, delay)

Owner responsible for Quality assurance

Package: Can not pick or get rid of individual team members

Design-Build
Pricing and Selection


More comprehensive selection process typical




Design/Price/Schedule/Team

Design competitions undertaken

Timing tension for when to recruit DB firm




Earlier recruitment: Greater risk and Risk premium (hard to


judge on qualification of D/B team)

Later recruitment: Less benefit from D/B (Limit creativity closer to GC, lower ability to fast track)

Often have segmented pricing (cost-plus design, fixed price or GMP


build)

15

Modified CM Design/Build:
Design Subcontracted

CM Oversight Design/Build

16

Other Delivery Methods


Multiple Primes


Allows owner time to raise money

Turnkey


Like DB but Contractor Financed (Very common in residential


housing)

Design-Build-Operate-Transfer (BOT)


Long-term financing (vs. DBO)

Can compete on size, transfer time, etc.

Owner/Agent (Owner does part of design)

Type of Relationships Among


Participants

17

Advantages of Common Delivery


Methods

Disadvantages of Common Delivery


Methods

18

You might also like