Project Delivery Methods
Project Delivery Methods
Project Delivery Methods
Traditional
Design / Build
CM Oversight Design/Build
Multiple Primes
Design-Built-Operate-Transfer (BOT)
Turnkey
The contractor is the only one responsible for the execution of work
Handles submittals
Motivations to GC to Subcontract:
No In-house ability
GC overstretched
Poor design
Poor personnel
Contrast
Check billings
C. M. Delivery Method
Tasks
Pre-construction
Constructability, value engineering, estimation, alternatives,
schedule, financing, manage designer, early procurement
Field supervision
QA, Targets met, invoice checking, coordinate work of contractors,
change orders, payments, claims, inspections for design
requirements, sometimes safety
C. M. Delivery Method
Lessens Owners Responsibility
Project control
Job meetings
Management meetings
Administrative tasks
Budgets
Drawing approval
Oversight
Quality assurance
C. M. Delivery Method
Pure (Agency) C.M.
C. M. Delivery Method
Pure (Agency) C.M.
Advantages
Have both
10
C. M. Delivery Method
Pure (Agency) C.M.
Disadvantages
Owner alone takes risk on cost of project (no guarantee from CM)
C.M. @ Risk
11
C.M. @ Risk
Risk-wise, between the DBB and the PCM System (VERY similar to
GC hired early)
C.M. @ Risk
Advantage
Disadvantages
Tension (If CM is hired early: more price risk If CM hired late: less value
during design)
12
Design-Build
Design-Build
This firm can be a design/build firm but also a joint-venture firm for
this specific project
Can be good for complex projects but need phased design to shield
parties from risk
13
Design-Build
Recent drivers
Bridge Designer/Engineer
Design-Build
Advantages
14
Design-Build
Disadvantages
Can be bad for complicated projects (Very important for owner to be closely
involved to specify important aspects of design up-front)
Changes in contract
May take a direction that the owner does not really want
Design-Build
Pricing and Selection
Design/Price/Schedule/Team
Later recruitment: Less benefit from D/B (Limit creativity closer to GC, lower ability to fast track)
15
Modified CM Design/Build:
Design Subcontracted
CM Oversight Design/Build
16
Turnkey
Design-Build-Operate-Transfer (BOT)
17
18